CN109544660B - Data processing method based on field mapping automatic data processing system - Google Patents

Data processing method based on field mapping automatic data processing system Download PDF

Info

Publication number
CN109544660B
CN109544660B CN201811431396.XA CN201811431396A CN109544660B CN 109544660 B CN109544660 B CN 109544660B CN 201811431396 A CN201811431396 A CN 201811431396A CN 109544660 B CN109544660 B CN 109544660B
Authority
CN
China
Prior art keywords
data
error
data processing
calculation
mapping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811431396.XA
Other languages
Chinese (zh)
Other versions
CN109544660A (en
Inventor
丁文利
王良民
吴芳
李保平
葛俊涛
陈小乐
张永杰
张雨沛
赵俊俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811431396.XA priority Critical patent/CN109544660B/en
Publication of CN109544660A publication Critical patent/CN109544660A/en
Application granted granted Critical
Publication of CN109544660B publication Critical patent/CN109544660B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T11/002D [Two Dimensional] image generation
    • G06T11/20Drawing from basic elements, e.g. lines or circles
    • G06T11/206Drawing of charts or graphs
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F13/00Interconnection of, or transfer of information or other signals between, memories, input/output devices or central processing units
    • G06F13/38Information transfer, e.g. on bus
    • G06F13/42Bus transfer protocol, e.g. handshake; Synchronisation
    • G06F13/4282Bus transfer protocol, e.g. handshake; Synchronisation on a serial bus, e.g. I2C bus, SPI bus

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The invention relates to a data processing method based on an automatic data processing system for field surveying and mapping, which comprises six modules of a wire and level recording module, a data communication module, an adjustment calculation module, a broken part measurement coordinate calculation module, a broken part measurement data automatic connection module and a measurement tool. The system reduces the number of workers, improves the working efficiency and the accuracy of mapping, and can obtain the mapping graph with small error and high accuracy by using the data processing method of the system.

Description

Data processing method based on field mapping automatic data processing system
Technical Field
The invention relates to a data processing method, in particular to a data processing method based on an automatic data processing system for field surveying and mapping.
Background
With the application and popularization of computer technology in the surveying and mapping industry, various original measurement data are converted from original manual acquisition to automatic acquisition, and meanwhile, the mapping method is also converted from traditional manual flat plate mapping to digital mapping. The digitalized mapping can be divided into three parts according to the operation flow: collecting and processing original data (or coordinates), editing internal work charts and managing data. Despite improvements in surveying and instrumentation, total stations do not allow for automatic connections from the survey of the drawing until the management of three parts, for most production units, to at least three people: respectively running a ruler, observing an instrument and drawing a sketch. Only dense points exist after the original data are uploaded to relevant software, and a plotter can compile the data only by contrasting sketches; the surveyor must take the generated point file to plot the graph on site in the area which the sketch cannot mark. In addition, part of the procedures of the surveying and mapping work flow are still manually or semi-manually recorded and processed, so that the work efficiency is influenced, the result quality cannot be guaranteed, and the storage and management of a user are inconvenient; in addition, data among all links cannot be shared, each working step needs manual data linkage, and mechanical complicated working procedures bring disasters to convenient digitization. Therefore, a system that overcomes the above-described deficiencies is urgently needed.
Disclosure of Invention
Aiming at the technical problems of low efficiency, personnel waste, inaccurate mapping, incapability of realizing comprehensive digitization of the process and incapability of realizing convenient data sharing of the existing system, the invention provides a novel automatic data processing system for field surveying and mapping and a working method for automatically processing data by using the system.
The invention provides an automatic data processing system for field surveying and mapping, which comprises the following six modules: conducting wire and level recording, data communication, adjustment calculation, broken part measurement coordinate calculation, broken part measurement data automatic connection and measuring tool; the wire and level recording module comprises field data acquisition, observation limit difference setting, error prompting and exceeding, error data elimination and data processing, and the module generates an electronic handbook from the acquired data; the data communication module automatically converts the data format and transmits the data of the electronic handbook to the computer; the adjustment calculation module automatically generates a control point result table and automatically generates an adjustment data into a control network diagram; a broken part measurement coordinate calculation module performs coordinate calculation on broken part point original data observed by the total station; the broken part connecting code module generates connecting code data for broken part points according to codes input during mapping, and then automatically generates a graph after spreading the points; the measuring tool module realizes data conversion, coordinate conversion, intersection calculation and distance azimuth calculation.
The invention also provides an automatic data processing method for field mapping, which utilizes an automatic data processing system for field mapping to carry out full automation of field mapping and comprises the following steps: defining a brevity code file required to be used in the acquisition of the fragment by user; step two: the conducting wire and level recording module is used for carrying out field data acquisition and inputting set brevity codes and connection relations according to the attributes of acquisition points; step three: the data error judgment module automatically detects original data, analyzes the type of data error, prompts the position of the error and error type information by a dialog box, if the error relates to the error with the principle and not meeting the requirement, requires the user to perform data retest to perform subsequent processing, if the error relates to neutral data and data which is considered by the system to possibly have problems, the dialog box is prompted, the user judges whether the result is influenced or not, and the user can directly confirm the subsequent processing when the influence is not formed; step four: transmitting the original data acquired by the surveying and mapping equipment to a computer by utilizing an MSComm control, wherein the control realizes communication by adopting a serial port to transmit and receive data; step five: automatically calling Qinghuashan dimension intelligent image-text network software to perform manual book processing and adjustment calculation, automatically generating a control point result table and automatically generating a control network diagram according to Qinghuashan dimension intelligent image-text network adjustment data; step six: the method comprises the steps that the broken part calculation calculates collected original observation data according to a control result of adjustment calculation to obtain coordinates of broken part points; step seven: the broken part connecting code module converts the broken part points according to the brevity codes and the connection relation, generates a measuring point file and a connecting code file which can be identified by the graph editing software, and can automatically generate the graph by directly calling the two files in the graph editing software.
Preferably, the data collected in the field data collection in the second step includes wire data, level observation data and broken data.
Preferably, the types of errors detected by the data error determination module in step three include: data format, data type, calculation error, and out-of-tolerance.
Preferably, in the sixth step, the broken part calculation module may perform coordinate calculation on the original data of the broken part point observed by the total station, and may check the orientation point and the branch station data.
The invention has the following beneficial effects:
(1) The method comprises the steps that the fragment part calculation calculates collected original observation data according to a control result of adjustment calculation to obtain coordinates of a fragment part point, then the link code function is utilized to directly carry out link code, and then automatic mapping is carried out in mapping software, so that manual intervention is reduced, and errors are avoided;
(2) The automatic network diagram generation function in the system can automatically perform corresponding connection according to the mutual connection relation among the observation data, and the whole processing process is completely automatic;
(3) The system can convert the collected data into the measuring point file and the link code file which can be identified by the graph editing software according to the user-defined brevity code file, and the graph can be automatically generated by directly calling the two files in the graph editing software, so that the workload of editing is reduced.
Drawings
FIG. 1 is a block diagram of an automatic data processing system for field mapping,
FIG. 2 is a flow chart of the field mapping automatic data processing system
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings. Other embodiments, which can be derived by one of ordinary skill in the art without making any creative effort, are within the scope of the present invention given the embodiments of the present invention.
The automatic data processing system for field surveying and mapping as shown in the attached figure 1 comprises the following six modules: the method comprises the following steps of wire and level recording, data communication, adjustment calculation, measurement coordinate calculation of a fragment part, automatic connection of measurement data of the fragment part and a measuring tool.
The wire and level recording module can collect field data, set observation limit difference, prompt error overrun, reject error data and process data. The data collected by the field data comprise wire data, level observation data and broken part data.
The data processing system comprises a data error judgment module at each link of data processing, and the data error judgment module is used for automatically detecting data formats, data types, calculation errors and exceeding tolerance; and analyzing the type of the data error, prompting the error position and the error type information, and respectively prompting the error position and the error type information in a dialog box mode, wherein for some errors which are principle and not in accordance with requirements, a user is required to perform subsequent processing after data modification, for some neutral data and data which are considered by a system to possibly have problems, the system prompts the user by using the dialog box, the user judges that the user can directly confirm that the result is not influenced, and the subsequent processing is performed. The system ensures the quality of data processing by such strong error judgment capability.
The wire recording module comprises two implementation modes, wherein one mode is an electronic handbook generated by writing software, and the other mode is that the electronic handbook is directly recorded by using a total station memory and then data processing is carried out through a computer.
Both modes have the following characteristics: 1. the design is carried out according to the requirements of urban survey Specification (CJJ 8-99), and the observation requirements of four and below leads can be met; 2. the observation grade can be set, and the tolerance requirement can be modified; 3. the elevation of the observation triangle can be selected according to the requirement; 4. the observation data can be transmitted to a computer for post-mathematical processing.
The two ways differ: 1. the electronic handbook mode can support manual and automatic modes, and different types of total stations can be selected in the automatic observation mode; the total station records cannot be selected by directly using the memory records; 2. after observation data of each station is qualified in the electronic manual book mode, recording and prompting a transfer station; the total station records the original observation to the memory, does not judge the tolerance, and carries out the inspection when processing the data.
The lead recording module adopts an electronic handbook mode, and has the following advantages: the wire data recorded by the total station can be automatically processed, and the limit difference specified by the regulation is checked; the data recorded by the electronic handbook can be processed; generating a standard handbook according to the requirements of the regulations; adjustment data required by adjustment software such as Qinghuashan Wei can be generated.
The level recording module also runs in an electronic handbook mode and has the following characteristics: according to the requirement design of leveling measurement specification, recording of external levels such as second, third, fourth and the like can be carried out; the limit difference judgment of the difference between the sight distance difference, the sight distance cumulative difference, the base auxiliary difference and the height difference can be automatically carried out, the station measurement is limited, and the station can be moved; only the original observation is reserved, and the intermediate calculation result is not reserved, so that the memory space is saved; for observed data, a random storage mode is adopted to ensure that the data cannot be lost; the observation data can be transmitted to a computer for post-processing, and the electronic handbook is only used as a carrier.
The data communication module selects MSComm control which adopts serial port to transmit and receive data. The universal communication total station is adopted for communication, can be communicated with total stations of different types and can perform data conversion, and can be directly converted into a calculation format, and has prompt information of data format errors; in addition, the system can also be communicated and exchanged with an electronic handbook machine, a PDA and various data acquisition handbooks; the data transmitted by the random software of the topotecan and the Nikon can be converted. In addition, the first and second substrates are,
the adjustment calculation module can automatically call Qinghuashan dimensional intelligent image-text network software to perform the handbook processing and the adjustment calculation; automatically generating a control point result table according to the data result; and automatically generating a control network diagram according to the adjustment data of the Qinghuashan dimension intelligent image-text network.
When surveying and mapping work is carried out, each level control point must have an expansion point network map, and therefore encryption and data acquisition can be carried out step by step according to needs when subsequent work is carried out. The automatic generation network diagram function in the system carries out data processing analysis on the adjustment file obtained by adjustment calculation, automatically carries out point location mapping according to the coordinates in the adjustment file, configures corresponding symbols according to the grade of the set control point, and automatically carries out corresponding connection according to the interconnection relation between observation data after the point location mapping, and the whole processing process is completely realized automatically, thereby improving the efficiency by dozens of times compared with the original manual processing.
The broken part calculation module can perform coordinate calculation on the original data of the broken part point observed by the total station, and can check orientation and branch stations to ensure the accuracy of the data. The broken part connecting code module can generate the broken part points according to codes input during mapping and connecting code data required by software according to different software, and the graphs can be automatically generated after the points are displayed by the software.
The invention realizes automatic continuous coding, wherein the automatic continuous coding is to convert the fragment point coordinate coding data into a measuring point file and a continuous coding file which can be identified by a mapping system, thereby realizing automatic mapping and improving the mapping efficiency. In addition, although the system comprises a plurality of data formats of mapping software, an expansion interface is reserved, and data expansion of other software in the future is facilitated. In addition, the system does not embed codes, but sets the codes in a mode of a code comparison table, manages the codes in an open mode, and a user can modify and expand the code table according to needs, so that the system can better accord with own operation habits.
Fig. 2 shows a flow chart of an automatic data processing method for field mapping, which utilizes the automatic data processing system for field mapping to perform full automation of field mapping.
The method comprises the following steps: the method comprises the following steps of 1, customizing a brevity code file required to be used in the collection of the fragment: when mapping, firstly, user-defined brevity code files to be used in the collection of the fragment part are defined, brevity codes can be set according to respective habit characteristics (generally, for convenience of memory, the first letter of Chinese pinyin of a ground object is taken, for example, a house is F), and the brevity codes can be used for a long time after being set.
Step two: the conducting wire and level recording module is used for carrying out field data acquisition and inputting set brevity codes and connection relations according to the attributes of acquisition points; the data collected in the field data collection includes wire data, level observation data, and data of a broken part.
Step three: the data error judging module automatically detects original data, analyzes the type of data error, prompts the position of the error and error type information by a dialog box, if the error relates to the error with the principle and not meeting the requirement, requires the user to perform data retest to perform subsequent processing, if the error relates to neutral data and data which is considered by the system to be possibly problematic, the prompting dialog box appears, and the user judges whether the result is influenced or not, and can directly confirm the subsequent processing when the influence is not formed. In addition, the types of errors detected by the data error judgment module include: data format, data type, calculation error, and out-of-tolerance.
Step four: transmitting the original data acquired by the mapping equipment to a computer by utilizing an MSComm control, wherein the control realizes communication by adopting a serial port to transmit and receive data;
step five: and automatically calling Qinghuashan dimensional intelligent image-text network software to perform hand book processing and adjustment calculation, automatically generating a control point result table and automatically generating a control network diagram according to Qinghuashan dimensional intelligent image-text network adjustment data.
Step six: the method comprises the steps that the broken part calculation calculates collected original observation data according to a control result of adjustment calculation to obtain coordinates of broken part points; the broken part calculation module can perform coordinate calculation on original data of a broken part point observed by the total station, and can check the data of the orientation point and the branch station point.
Step seven: the fragment joint code module converts the fragment points according to the brevity codes and the connection relation to generate a measuring point file and a joint code file which can be identified by the graph editing software, and the two files are directly called in the graph editing software to automatically generate the graph, so that the workload of editing is reduced, and errors are effectively avoided.
The data acquisition system is simple to operate, has higher reliability, convenience and automation degree in data recording and processing, and can analyze and report errors; the electronic handbook is used as a transitional carrier and adopts a real-time recording mode, so that data can not be lost due to dead halt or program interruption; the operation habit and the flow of field work are fully considered, a set of brevity codes can be used for generating various receivable data, and the problem of data interface is effectively solved; the operation method is changed from the original three-person operation to the current two-person operation, thereby greatly reducing the labor intensity of field operation and improving the production efficiency.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. A data processing method based on an automatic data processing system for field mapping comprises the following six modules: the method comprises the following steps of conducting wire and level recording, data communication, adjustment calculation, measurement coordinate calculation of a fragment part, automatic connection of measurement data of the fragment part and a measuring tool; the method realizes the full automation of the field mapping by utilizing the field mapping automatic data processing system, and is characterized by comprising the following steps: the method comprises the following steps: defining a brevity code file required to be used in the acquisition of the user-defined fragment; step two: the conducting wire and the level recording module are used for acquiring field data, and inputting set brevity codes and connection relations according to the attributes of acquisition points; step three: the data error judging module automatically detects original data, analyzes the type of the data error, prompts the position of the error and error type information by a dialog box, if the error relates to the error with the principle and the non-conformity, the user is required to perform data retesting to perform subsequent processing, if the error relates to neutral data and data which is considered by the system to have problems, the dialog box is prompted, the user judges whether the result is influenced or not, and the user can directly confirm to perform the subsequent processing when the influence is not formed; step four: transmitting the original data acquired by the mapping equipment to a computer by utilizing an MSComm control, wherein the control realizes communication by adopting a serial port to transmit and receive data; step five: automatically calling Qinghuashan dimensional intelligent image-text network software to perform hand book processing and adjustment calculation, automatically generating a control point result table and automatically generating a control network diagram according to Qinghuashan dimensional intelligent image-text network adjustment data; step six: the method comprises the steps that the broken part calculation calculates collected original observation data according to a control result of adjustment calculation to obtain coordinates of broken part points; step seven: the broken part connecting code module converts the broken part points according to the brevity codes and the connection relation, generates a measuring point file and a connecting code file which can be identified by the graph editing software, and can automatically generate the graph by directly calling the two files in the graph editing software.
2. The data processing method of claim 1, wherein: and in the second step, the data collected in the field data collection comprises wire data, level observation data and broken data.
3. The data processing method of claim 1, wherein: the error types detected by the data error judgment module in the third step include: data format, data type, calculation error, and out-of-tolerance.
4. The data processing method of claim 1, wherein: in the sixth step, the broken part calculation module may perform coordinate calculation on the original data of the broken part observed by the total station, and may check the data of the orientation point and the branch station.
CN201811431396.XA 2018-11-28 2018-11-28 Data processing method based on field mapping automatic data processing system Active CN109544660B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811431396.XA CN109544660B (en) 2018-11-28 2018-11-28 Data processing method based on field mapping automatic data processing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811431396.XA CN109544660B (en) 2018-11-28 2018-11-28 Data processing method based on field mapping automatic data processing system

Publications (2)

Publication Number Publication Date
CN109544660A CN109544660A (en) 2019-03-29
CN109544660B true CN109544660B (en) 2022-12-16

Family

ID=65850564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811431396.XA Active CN109544660B (en) 2018-11-28 2018-11-28 Data processing method based on field mapping automatic data processing system

Country Status (1)

Country Link
CN (1) CN109544660B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113450076B (en) * 2021-07-06 2024-02-09 河南省水利勘测设计研究有限公司 Hydraulic engineering measures integrated intelligent processing service platform
CN115242769B (en) * 2022-07-18 2023-11-14 吉林省国土资源调查规划研究院 Remote field quality inspection system
CN117113012A (en) * 2023-06-15 2023-11-24 中国水利水电第十二工程局有限公司 Adjustment data preprocessing system based on level control

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1281188A (en) * 2000-08-12 2001-01-24 南宁市天测科技有限责任公司 Real-time processing system of surveyed data and graphics for palm computer
CN103617035A (en) * 2013-11-27 2014-03-05 东北林业大学 Sight distance measurement processing method based on smart phone
CN103711050A (en) * 2013-12-31 2014-04-09 中交第二公路勘察设计研究院有限公司 Laser radar road reconstruction and expansion exploratory survey design method
CN203550955U (en) * 2013-10-11 2014-04-16 广州南方测绘仪器有限公司 Detail survey system
CN104931987A (en) * 2015-06-11 2015-09-23 上海同想文化传播有限公司 Golf terminal equipment course navigation method
CN104931990A (en) * 2015-06-11 2015-09-23 上海同想文化传播有限公司 Golf course navigation map surveying and mapping method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1281188A (en) * 2000-08-12 2001-01-24 南宁市天测科技有限责任公司 Real-time processing system of surveyed data and graphics for palm computer
CN203550955U (en) * 2013-10-11 2014-04-16 广州南方测绘仪器有限公司 Detail survey system
CN103617035A (en) * 2013-11-27 2014-03-05 东北林业大学 Sight distance measurement processing method based on smart phone
CN103711050A (en) * 2013-12-31 2014-04-09 中交第二公路勘察设计研究院有限公司 Laser radar road reconstruction and expansion exploratory survey design method
CN104931987A (en) * 2015-06-11 2015-09-23 上海同想文化传播有限公司 Golf terminal equipment course navigation method
CN104931990A (en) * 2015-06-11 2015-09-23 上海同想文化传播有限公司 Golf course navigation map surveying and mapping method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BIM技术在地图测绘中的应用研究;王伟;《北京测绘》;20180430;第32卷(第4期);第877-880页 *
数字化地形图更新的测绘技术探析;张园园等;《河南建材》;20180620(第3期);第299-300页 *

Also Published As

Publication number Publication date
CN109544660A (en) 2019-03-29

Similar Documents

Publication Publication Date Title
CN109544660B (en) Data processing method based on field mapping automatic data processing system
CN104850596B (en) A kind of distribution data processing method based on mobile GIS and RTK positioning
CN102750413B (en) Data processing and mapping method of topographic surveying of electric transmission line tower positions
CN112282847B (en) Deformation monitoring method for underground coal mine roadway
CN109471142B (en) Working track identification method based on RTK differential positioning
CN104135521A (en) Method and system of identifying data abnormal values of environment automatic monitoring network
CN109959345A (en) The contactless actual measurement actual quantities method and system of cable laying based on 3-D scanning
CN102200436B (en) Real-time kinematic GPS (RTK-GRS) total station integrated topographic surveying method and system with encoded data
CN111275580A (en) Power distribution network cable positioning monitoring method
CN114111706A (en) Leveling method integrating interior and exterior industry and quality inspection and data acquisition system
CN111460623A (en) Real-time collection and processing method and system for surveying and mapping operation data
CN111309791A (en) Automatic data acquisition method for detection instrument
CN109541644B (en) A kind of RTK field operation synchronization skeletonizing method
CN113450076B (en) Hydraulic engineering measures integrated intelligent processing service platform
CN111641960B (en) Base station monitoring system
CN112785706B (en) Method, system, equipment and medium for dynamically analyzing reserves of multi-type ore storage yard
CN102346019A (en) Laser measuring system employing GPS positioning and method thereof
CN115310107A (en) Internet of things data secure storage method and system based on cloud computing
CN111551145A (en) Urban and rural planning inspection surveying and mapping data acquisition method
CN112883447A (en) Method for rapidly generating drawing based on-site survey data
CN202074961U (en) Monitoring and measuring integrated machine for nailed pile layouting and project construction planning
CN113704944A (en) Design method based on mobile terminal power transmission line
CN106504496A (en) A kind of intelligent work piece measurement data wireless acquisition system
CN202799168U (en) High-precision rapid measurement system based on continuous operating reference system (CORS)
CN112504243A (en) Communication engineering investigation method and system based on VR technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant