CN109537598A - Control excavation of foundation pit deformation method - Google Patents

Control excavation of foundation pit deformation method Download PDF

Info

Publication number
CN109537598A
CN109537598A CN201811481134.4A CN201811481134A CN109537598A CN 109537598 A CN109537598 A CN 109537598A CN 201811481134 A CN201811481134 A CN 201811481134A CN 109537598 A CN109537598 A CN 109537598A
Authority
CN
China
Prior art keywords
foundation pit
deformation
underground installation
excavation
stabilization zone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201811481134.4A
Other languages
Chinese (zh)
Inventor
陶利
付武荣
周彪
何拥军
贾尚华
陈冠良
徐杰
陈辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Road and Bridge Group Co Ltd
Original Assignee
Shanghai Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Road and Bridge Group Co Ltd filed Critical Shanghai Road and Bridge Group Co Ltd
Priority to CN201811481134.4A priority Critical patent/CN109537598A/en
Publication of CN109537598A publication Critical patent/CN109537598A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of control excavation of foundation pit deformation methods comprising following steps: S1, excavating to the earthwork in foundation pit, while detecting the deformation of the underground installation below the foundation pit;S2, the deformation data of the underground installation is obtained to determine whether to generate excessive deformation, when the underground installation determines that deformation values are more than permissible value, grouting equipment carries out slip casting to stabilization zone, and the stabilization zone is between the foundation pit and the underground installation;When the underground installation determines that deformation values are no more than permissible value, then continue to excavate the earthwork in the foundation pit, until the earth excavation in the foundation pit is completed.Based on the principle of severe compensation, so that the promotion of slip casting severe compensates soil body off-load amount caused by excavation of foundation pit, to prevent the floating of underground installation from deforming, it is ensured that the safety of underground installation.In digging process grouting cost can be advantageously reduced while control underground installation is safe according to deformation monitoring value dynamic adjustment grouting equipment.

Description

Control excavation of foundation pit deformation method
Technical field
The present invention relates to a kind of civil construction field, in particular to a kind of control excavation of foundation pit deformation method.
Background technique
Construction of future cities will develop towards compact and intensive, efficient green direction, need to reinforce the space multistory to city, put down The planning and control of face harmony etc., adhere to Compact development, establish " shrewdness increases ", " Compact plasma toroid " theory.In underground It needs to focus on intensive use potentials in terms of space utilization, thus generates above the underground installations such as a large amount of existing tunnels and side carries out foundation pit and opens The case of digging, special when hole bottom is closer apart from tunnel, big off-load amount caused after a large amount of soil excavations will cause inside foundation pit The underground installations such as existing tunnel generate deformation of floating, to cause structural joint to open, cracking even damages.
Current control method is to be subtracted by the cement injection in the soil body after waiting cement slurries to harden with promoting soil body rigidity The floating deformation of few underground installation, but effect is unobvious, underground installation still can generate after a large amount of soil excavations inside foundation pit It floats and deforms, cause structural joint to open, cracking even damages.
Summary of the invention
The technical problem to be solved by the present invention is in order to overcome underground installation in the prior art can generate floating deformation etc. Defect provides a kind of control excavation of foundation pit deformation method.
The present invention is to solve above-mentioned technical problem by following technical proposals:
A kind of control excavation of foundation pit deformation method, it is characterized in that comprising following steps:
S1, the earthwork in foundation pit is excavated, while detects the deformation of the underground installation below the foundation pit;
S2, the deformation data of the underground installation is obtained to determine whether to generate excessive deformation, when the underground installation is sentenced When determining deformation values more than permissible value, grouting equipment carries out slip casting to stabilization zone, and the stabilization zone is located at the foundation pit with described Between lower facility;
When the underground installation determines that deformation values are no more than permissible value, then continue to open the earthwork in the foundation pit It digs, until the earth excavation in the foundation pit is completed.
Preferably, when the underground installation determines that deformation values are more than permissible value, stopping excavation in the step S2 and setting It is standby that the earthwork in the foundation pit is excavated, start the grouting equipment and slip casting is carried out to the stabilization zone;
When the underground installation determine deformation values be no more than permissible value when, stop the grouting equipment to the stabilization zone into Row slip casting starts the excavation equipment and excavates to the earthwork in the foundation pit.
Preferably, in the step S1, deformation monitoring device, the deformation monitoring dress are equipped in the underground installation Set the deformation for monitoring the underground installation.
Preferably, the quantity of the grouting equipment and the stabilization zone is two, and two stabilization zones are located at describedly The two sides of lower facility.
Preferably, being comprised the following steps that before the step S1
S1.0, building enclosure is built in the two sides of the foundation pit.
Preferably, being comprised the following steps that before the step S1, after the step S1.0
S1.1, the surface for setting up the grouting equipment to the stabilization zone, the Grouting Pipe on the grouting equipment is inserted Enter to the stabilization zone.
It is moved preferably, the Grouting Pipe is inserted into the stabilization zone and can go up and down along the length direction of the Grouting Pipe It is dynamic.
Preferably, the stabilization zone is located in the building enclosure.
On the basis of common knowledge of the art, above-mentioned each optimum condition, can any combination to get each preferable reality of the present invention Example.
The positive effect of the present invention is that:
Control excavation of foundation pit deformation method of the invention, in Excavation Process by detect underground installation deformation come Regulate and control slip casting, based on the principle of severe compensation, so that the promotion of slip casting severe compensates soil body off-load amount caused by excavation of foundation pit, To prevent the floating of underground installation from deforming, it is ensured that the safety of underground installation.Meanwhile it can be according to deformation monitoring in digging process Value dynamic adjustment grouting equipment, advantageously reduces grouting cost while control underground installation is safe.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the control excavation of foundation pit deformation of the embodiment of the present invention.
Fig. 2 is the flow chart of the control excavation of foundation pit deformation method of the embodiment of the present invention.
Description of symbols:
Foundation pit 1
Underground installation 2
Grouting equipment 3
Grouting Pipe 31
Stabilization zone 4
Deformation monitoring device 5
Building enclosure 6
Specific embodiment
Illustrate below by the mode of embodiment and completely the present invention in conjunction with attached drawing to become apparent from, but therefore not incite somebody to action this It invents among the scope of embodiments being limited in.
As depicted in figs. 1 and 2, the control excavation of foundation pit deformation method of the embodiment of the present invention comprising following steps:
Step S1, the earthwork in foundation pit 1 is excavated, while detects the deformation of the underground installation 2 of 1 lower section of foundation pit.
In this step, the earthwork in foundation pit 1 is excavated out, and the lower section of foundation pit 1 is neighbouring to have underground installation 2.Work as the earthwork After excavating, soil body weight will be reduced in foundation pit 1, can cause soil layer around and the underground installation of lower section 2 and neighbouring underground Facility 2 generates floating, damages more than will cause underground installation 2 after certain magnitude.So being needed simultaneously during foundation pit 1 excavates The deformation for detecting underground installation 2 avoids damaging to underground installation 2.
Step S2, the deformation data of underground installation 2 is obtained to determine whether to generate excessive deformation, when underground installation 2 determines When deformation values are more than permissible value, grouting equipment 3 carries out slip casting to stabilization zone 4, stabilization zone 4 be located at foundation pit 1 and underground installation 2 it Between;When underground installation 2 determines that deformation values are no more than permissible value, then continue to excavate the earthwork in foundation pit 1, until foundation pit Earth excavation in 1 is completed.
In this step, the deformation data of real-time detection underground installation 2 determines whether to generate excessive deformation, avoids over the ground Lower facility 2 damages.If underground installation 2 determines that always deformation values are no more than permissible value, and the excavation of foundation pit 1 is shown in Bottom, then earth excavation terminates, and does not damage to underground installation 2.If underground installation 2 determines that deformation values are more than permissible value, Then start grouting equipment 3 and slip casting is carried out to stabilization zone 4, i.e., carry out slip casting operation in underground installation 2, until underground installation 2 determines When deformation values are no more than permissible value, stop grouting equipment 3 and slip casting operation is carried out to stabilization zone 4.
Regulate and control slip casting by detecting the deformation of underground installation 2 in 1 digging process of foundation pit, the original based on severe compensation Reason so that the promotion of slip casting severe come compensate foundation pit 1 excavate caused by soil body off-load amount, to prevent the floating of underground installation 2 Deformation, it is ensured that the safety of underground installation 2.Meanwhile grouting equipment 3 can be adjusted according to deformation monitoring value dynamic in digging process, Grouting cost is advantageously reduced while control underground installation 2 is safe.
In step sl, deformation monitoring device 5 can be equipped in underground installation 2, deformation monitoring device 5 is for monitoring ground The deformation of lower facility 2.It is mounted in underground installation 2 by deformation monitoring device 5, it is dynamic by the monitor value of deformation monitoring device 5 State adjustment grouting equipment 3 cut-off and watt level.
In step s 2, when underground installation 2 determines that deformation values are more than permissible value, stop excavation equipment in foundation pit 1 The earthwork is excavated, and starting grouting equipment 3 carries out slip casting to stabilization zone 4;When underground installation 2 determines that deformation values are no more than permissible value When, stop grouting equipment 3 and slip casting is carried out to stabilization zone 4, starting excavation equipment excavates the earthwork in foundation pit 1.If underground When facility 2 determines that deformation values are more than permissible value, stops excavation equipment immediately and the earthwork in foundation pit 1 is excavated, effectively avoid Underground installation 2 further generates deformation of floating, and carries out slip casting to stabilization zone 4 by starting grouting equipment 3, passes through injecting paste material The soil body off-load amount caused by excavating in the compensation foundation pit 1 of weight, effectively avoids damaging to underground installation 2.Until ground When lower facility 2 determines that deformation values are no more than permissible value, then stops grouting equipment 3 and slip casting is carried out to stabilization zone 4, start excavation equipment Continue to excavate the earthwork in foundation pit 1.
Wherein, injecting paste material can be high specific gravity injecting paste material, and the severe of high specific gravity injecting paste material is natural earth severe It 1.1~1.5 times, can be produced by the way that the high specific gravity materials such as steel-making slag powder are added in conventional injecting paste material.
The main body of 4 range of stabilization zone is located at foundation pit 1 and excavates in range in the soil body, most of soil after the completion of foundation pit 1 excavates Body is removed, and will not be runed the later period and be had an impact.The quantity of grouting equipment 3 and stabilization zone 4 all can be two, and two add Gu the two sides of the facility 2 located underground of area 4.The range determination of stabilization zone 4 should comprehensively consider 1 discharging quantity of foundation pit and later period structure is returned and built Anti-floating requires comprehensive determination afterwards, can be according to the monitor value for the deformation monitoring device 5 being installed in underground installation 2 in digging process Dynamic adjusts.
Include step S1.0 before step S1: step S1.0 is to build building enclosure 6 in the two sides of foundation pit 1.At this In step, building enclosure 6 is built in the two sides of foundation pit 1 before the excavation of foundation pit 1, protective action is played, effectively prevents the soil body Phenomena such as collapsing.Wherein, stabilization zone 4 is located in building enclosure 6, injects injecting paste material in stabilization zone 4, the soil in foundation pit 1 Body can play the role of bracing against during being excavated to building enclosure 6, strengthen the structural strength of building enclosure 6, keep away Exempt from building enclosure 6 to collapse phenomenon.
Before step S1, include step S1.1 after step S1.0: step S1.1 be set up grouting equipment 3 to reinforcing Grouting Pipe 31 on grouting equipment 3 is inserted into stabilization zone 4 by the surface in area 4.Grouting equipment 3 will be infused by Grouting Pipe 31 Pulp material is injected into stabilization zone 4, is realized by grouting equipment 3 to slip casting in stabilization zone 4.
Grouting Pipe 31 is inserted into stabilization zone 4 and can be along the length direction lifting moving of Grouting Pipe 31.Pass through Grouting Pipe 31 Lifting moving adjust the height of injection, to realize that the range of stabilization zone 4 is bigger, and significantly facilitate in grouting equipment 3 Slip casting.
Although specific embodiments of the present invention have been described above, it will be appreciated by those of skill in the art that this is only For example, protection scope of the present invention is to be defined by the appended claims.Those skilled in the art without departing substantially from Under the premise of the principle and substance of the present invention, many changes and modifications may be made, but these change and Modification each falls within protection scope of the present invention.

Claims (8)

1. a kind of control excavation of foundation pit deformation method, which is characterized in that itself the following steps are included:
S1, the earthwork in foundation pit is excavated, while detects the deformation of the underground installation below the foundation pit;
S2, the deformation data of the underground installation is obtained to determine whether to generate excessive deformation, when the underground installation determines to become When shape value is more than permissible value, grouting equipment carries out slip casting to stabilization zone, and the stabilization zone is located at the foundation pit and with described divides into Between applying;
When the underground installation determines that deformation values are no more than permissible value, then continue to excavate the earthwork in the foundation pit, Until the earth excavation in the foundation pit is completed.
2. control excavation of foundation pit deformation method as described in claim 1, which is characterized in that in the step S2, when described When underground installation determines that deformation values are more than permissible value, stops excavation equipment and the earthwork in the foundation pit is excavated, start institute It states grouting equipment and slip casting is carried out to the stabilization zone;
When the underground installation determines that deformation values are no more than permissible value, stops the grouting equipment and the stabilization zone is infused Slurry, starts the excavation equipment and excavates to the earthwork in the foundation pit.
3. control excavation of foundation pit deformation method as described in claim 1, which is characterized in that in the step S1, described Deformation monitoring device is equipped in underground installation, the deformation monitoring device is used to monitor the deformation of the underground installation.
4. control excavation of foundation pit deformation method as described in claim 1, which is characterized in that the grouting equipment and the reinforcing The quantity in area is two, and two stabilization zones are located at the two sides of the underground installation.
5. control excavation of foundation pit deformation method as described in claim 1, which is characterized in that include before the step S1 Following steps:
S1.0, building enclosure is built in the two sides of the foundation pit.
6. control excavation of foundation pit deformation method as claimed in claim 5, which is characterized in that before the step S1, described It is comprised the following steps that after step S1.0
S1.1, the surface for setting up the grouting equipment to the stabilization zone, the Grouting Pipe on the grouting equipment is inserted into In the stabilization zone.
7. control excavation of foundation pit deformation method as claimed in claim 6, which is characterized in that the Grouting Pipe is inserted into described add Gu Qu simultaneously can be along the length direction lifting moving of the Grouting Pipe.
8. control excavation of foundation pit deformation method as claimed in claim 5, which is characterized in that the stabilization zone is located at described go along with sb. to guard him In structure.
CN201811481134.4A 2018-12-05 2018-12-05 Control excavation of foundation pit deformation method Withdrawn CN109537598A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811481134.4A CN109537598A (en) 2018-12-05 2018-12-05 Control excavation of foundation pit deformation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811481134.4A CN109537598A (en) 2018-12-05 2018-12-05 Control excavation of foundation pit deformation method

Publications (1)

Publication Number Publication Date
CN109537598A true CN109537598A (en) 2019-03-29

Family

ID=65852813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811481134.4A Withdrawn CN109537598A (en) 2018-12-05 2018-12-05 Control excavation of foundation pit deformation method

Country Status (1)

Country Link
CN (1) CN109537598A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775687A (en) * 2022-05-23 2022-07-22 中铁上海设计院集团有限公司 Compensation type construction structure for underground engineering construction and construction method thereof
KR102476570B1 (en) * 2022-05-26 2022-12-13 주식회사 대한측량기술 Underground facilities detection system for constructing database of geographic information system using mms

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061923A (en) * 2010-11-28 2011-05-18 山东科技大学 Tunnel construction method capable of protecting existing building
CN102828517A (en) * 2012-08-30 2012-12-19 中铁十三局集团第三工程有限公司 Hierarchical control construction method of foundation pit excavation at entrance and exit of station
CN103758133A (en) * 2014-01-13 2014-04-30 河海大学 Deep soft soil foundation pit reinforcement method
CN105926633A (en) * 2016-03-25 2016-09-07 曹信江 Method for protecting surrounding soil or building in foundation pit construction
CN108755699A (en) * 2018-06-07 2018-11-06 上海勘察设计研究院(集团)有限公司 The deformation control method and device of a kind of foundation pit periphery soil body

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061923A (en) * 2010-11-28 2011-05-18 山东科技大学 Tunnel construction method capable of protecting existing building
CN102828517A (en) * 2012-08-30 2012-12-19 中铁十三局集团第三工程有限公司 Hierarchical control construction method of foundation pit excavation at entrance and exit of station
CN103758133A (en) * 2014-01-13 2014-04-30 河海大学 Deep soft soil foundation pit reinforcement method
CN105926633A (en) * 2016-03-25 2016-09-07 曹信江 Method for protecting surrounding soil or building in foundation pit construction
CN108755699A (en) * 2018-06-07 2018-11-06 上海勘察设计研究院(集团)有限公司 The deformation control method and device of a kind of foundation pit periphery soil body

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775687A (en) * 2022-05-23 2022-07-22 中铁上海设计院集团有限公司 Compensation type construction structure for underground engineering construction and construction method thereof
CN114775687B (en) * 2022-05-23 2024-08-09 中铁上海设计院集团有限公司 Compensation type construction structure for underground engineering construction and construction method thereof
KR102476570B1 (en) * 2022-05-26 2022-12-13 주식회사 대한측량기술 Underground facilities detection system for constructing database of geographic information system using mms

Similar Documents

Publication Publication Date Title
CN105715296B (en) Sand blowing, backfilling and grouting construction method for tunnel to penetrate through coal mine goaf
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN102277898B (en) Drain pipe jacking construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
AU2020286274B2 (en) Aquifer connection method for inner dump in open-pit mine
CN108035335A (en) A kind of construction freezing method well shaft type underground parking garage method
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN102733816B (en) Deformation control method when shield traverse building within short distance
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN109882182A (en) A kind of extra small clear distance construction method in tunnel
CN108412503A (en) Bias shallow-buried tunnel portal construction protection structure and construction method thereof
CN110864162B (en) Construction process of argillaceous sandstone geological pipe jacking
CN105041322A (en) Method and system for reinforcing hole for push bench to go in and out
CN110259490B (en) Subway underground excavation station construction method
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN108951641A (en) It is a kind of for the compound support method of ultra-deep pipe gallery foundation trench in water river
CN109537598A (en) Control excavation of foundation pit deformation method
CN112900468A (en) Bridge foundation construction method suitable for complex geological conditions
KR101746654B1 (en) Method for constructing pile for reinforce of mine hole
CN103628507A (en) Anti-floating construction method for passing through seabed shallow buried soil for pipe jacking
CN101509258B (en) Method for precontrolling subsidence slant of sinking well
CN115370376A (en) Collapse treatment construction method suitable for large-span expanded tunnel
CN208039234U (en) Engineering pile in karst cave geology
CN106759526A (en) Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
CN106013238B (en) A kind of big earthing open trench tunnel subsidence control method of soft stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190329