CN109530461A - Method and device for controlling length of high-speed wire water-cooling uncooled section - Google Patents

Method and device for controlling length of high-speed wire water-cooling uncooled section Download PDF

Info

Publication number
CN109530461A
CN109530461A CN201811277441.0A CN201811277441A CN109530461A CN 109530461 A CN109530461 A CN 109530461A CN 201811277441 A CN201811277441 A CN 201811277441A CN 109530461 A CN109530461 A CN 109530461A
Authority
CN
China
Prior art keywords
finishing mill
mill unit
water
rolling
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811277441.0A
Other languages
Chinese (zh)
Other versions
CN109530461B (en
Inventor
潘巍
王云波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ceristar Electric Co ltd
Capital Engineering & Research Inc Ltd
Original Assignee
Ceristar Electric Co ltd
Capital Engineering & Research Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ceristar Electric Co ltd, Capital Engineering & Research Inc Ltd filed Critical Ceristar Electric Co ltd
Priority to CN201811277441.0A priority Critical patent/CN109530461B/en
Publication of CN109530461A publication Critical patent/CN109530461A/en
Application granted granted Critical
Publication of CN109530461B publication Critical patent/CN109530461B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B45/00Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills
    • B21B45/02Devices for surface or other treatment of work, specially combined with or arranged in, or specially adapted for use in connection with, metal-rolling mills for lubricating, cooling, or cleaning
    • B21B45/0203Cooling
    • B21B45/0209Cooling devices, e.g. using gaseous coolants
    • B21B45/0215Cooling devices, e.g. using gaseous coolants using liquid coolants, e.g. for sections, for tubes
    • B21B45/0233Spray nozzles, Nozzle headers; Spray systems
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B37/00Control devices or methods specially adapted for metal-rolling mills or the work produced thereby

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Control Of Metal Rolling (AREA)

Abstract

The embodiment of the invention provides a method and a device for controlling the length of a water-cooling uncooled section of a high-speed wire, wherein the method comprises the following steps: converting the physical length of the finishing mill group into an equivalent length when the finishing mill group rolls the rolled piece according to the rolling specification of the rolled piece; calculating the opening and closing delay time of the valve of each water cooling nozzle in each water-through cold water tank at the rear section of the finishing mill group by taking the moment when the head of the rolled piece passes through the inlet thermal detection position of the finishing mill as an initial moment according to the equivalent length, the preset length of the non-cooled section of the rolled piece and the outlet speed of the finishing mill group; and sequentially controlling the opening and closing of the valve of each water-cooling nozzle in each section of water-passing cold water tank according to the calculated delay time. According to the scheme, the length of the head non-cold section and the length of the tail non-cold section which are actually generated are not consistent with the preset length of the head non-cold section and the preset length of the tail non-cold section, so that the phenomena of shortening and increasing the length of the head non-cold section and the tail non-cold section in actual production are reduced, the yield is improved, and the rolling benefit is improved.

Description

The not cold segment length control method and device of high line Water cooling
Technical field
The present invention relates to rolling technical field, in particular to the not cold segment length control method of a kind of high line Water cooling and dress It sets.
Background technique
The core of Controlled Rolling And Controlled Cooling is during the rolling process by control heating temperature, the operation of rolling, cooling condition etc. Technological parameter further increases the obdurability of steel and obtains reasonable comprehensive performance, and can reduce alloying element content and Carbon content saves valuable alloying element, reduces production cost, at home using extremely wide in major iron and steel enterprise.
In the rolling of high line, it is cooling to wear by force water quenching for big cooling more than water spray, water drenching of the intensity of cooling of Water cooling Ensured the wire rod inlet and outlet temperatures required when different units roll, be obtain high-intensitive tissue (for example, martensite or Bainite) effective means, directly determine the processing quality and performance of product, especially closed in rolling high-strength degree and special steel Key.
High-intensitive cooling can roll rolled piece and generate both sides adverse effect.First is that the extrusion effect with milling train is common Effect, causes workpiece front end inhomogeneous cooling even, generates blackhead, elbow, certain specification products are easy to produce dehiscence in the head, and then lead It causes downstream rack can not be successfully and bites rolled piece, generate piling of steel accident.Second is that high pressure water flow is to the rolled piece (most high speed in high-speed cruising Degree can arrive 110m/s) strong impact, especially small dimension rolled piece are generated, lead to the violent shake of rolled piece, easily induction piling of steel Accident.Therefore, in strong Water cooling, it is necessary to ensure that after workpiece front end passes through, can boiled water, namely must assure that rolled piece has foot Not cold section of enough heads, it is ensured that workpiece front end reliably passes through and enters downstream rack.
The not cold Duan Taichang in tail portion, rolled piece tail temperature is high, is easy to appear whipping;Tail portion is not cold section too short, and rolled piece tail portion is cold But resistance is big, and tail portion is easy to appear ringlet, to ensure that rolled piece tail portion passes through downstream rack, according to the process specification of rolling, Need to guarantee that the length of not cold section of tail portion is controllable.
For wearing water cooling water tank after finishing mill, the first scheme in the prior art is to detect wire rod head signal Afterwards, be delayed by one section, it is ensured that the head of rolled piece gone out it is all wear water cooling water tank or workpiece front end bite Laying head before pinch After roller, boiled water, detecting element are generally hot metal detector, water cooling water are worn after finishing mill 4 sections of water tanks simultaneously after finishing mill Before the outlet of case final stage or Laying head at pinch roller.
Above-mentioned control program may insure rolled piece by rear boiled water, ensure that stable rolling, but general water tank length About 6 meters, for wearing water chiller and configure 4 sections of water tanks, there are about 40 meters for the recover section total length between water tank and water tank, if to Just boiled water after pinch roller bites before Laying head, then about 60 meters of the not cold segment length of rolled piece (about 20 circle), the not cold segment length in this part by It is not up to standard that all inspections is useless in performance, so that having seriously affected lumber recovery, reduce rolling benefit.
Second scheme is delayed by one section, it is ensured that the head of rolled piece after detecting wire rod head signal in the prior art Water cooling water tank paragraph 1 is worn after having gone out finishing mill by portion, then paragraph 1 wears water cooling water tank boiled water, and subsequent each water cooling water tank of wearing successively is opened Water.
It is useless this technique avoids largely being examined caused by the first technical solution, shorten not cold section end to end of length.But Since rolling specs are different, mill speed is different, cause the delay time for wearing water cooling water tank paragraph 1 after finishing mill different, and it is smart Milling train muzzle velocity is more than 100m/s, once delay time is on the low side, will result in the water slug that is cooled when rolled piece not yet passes, produces Raw shake, easily causes piling of steel accident.Operative employee is not only unable to judge accurately delay time, but also is difficult the variation with rolling parameter It goes to adjust delay time repeatedly, to guarantee stable rolling, operative employee tends to that longer delay is arranged, so that head is not cold Section is partially long, has seriously affected lumber recovery, has reduced rolling benefit, final result and the first technical solution are very nearly the same.
Summary of the invention
The embodiment of the invention provides a kind of not cold segment length control methods of high line Water cooling, to solve the prior art The technical problem that lumber recovery existing for middle high line Water cooling is low, rolling benefit is low.This method comprises:
It is equivalent when the physical length of mm finishing mill unit is converted as mm finishing mill unit rolling rolling stock according to the rolling specs of rolled piece Length;
According to the equivalent length, the preset not cold segment length of rolled piece and the muzzle velocity of mm finishing mill unit, with rolled piece Head by the heat inspection of finishing mill entrance at the time of be initial time, calculate each section of mm finishing mill unit rear wear it is each in water cooling water tank The valve opening of water-cooled nozzle and the delay time of closing;
According to the delay time being calculated successively control each section wear in water cooling water tank the valve opening of each water-cooled nozzle and It closes.
The embodiment of the invention also provides a kind of not cold segment length control devices of high line Water cooling, to solve the prior art The technical problem that lumber recovery existing for middle high line Water cooling is low, rolling benefit is low.The device includes:
The physical length conversion of mm finishing mill unit is essence for the rolling specs according to rolled piece by equivalent length computing module Equivalent length when milling train group rolling rolling stock;
Delay time computing module, for the preset not cold segment length and finish rolling according to the equivalent length, rolled piece The muzzle velocity of unit calculates mm finishing mill unit as initial time at the time of using the head of rolled piece by the heat inspection of finishing mill entrance Wear the delay time of the valve opening of each water-cooled nozzle and closing in water cooling water tank in each section of rear;
Control module wears each water-cooled nozzle in water cooling water tank for successively controlling each section according to the delay time being calculated Valve opening and closing.
The embodiment of the invention also provides a kind of computer equipments, including memory, processor and storage are on a memory And the computer program that can be run on a processor, the processor are realized above-mentioned arbitrary when executing the computer program The not cold segment length control method of high line Water cooling.To solve existing for high line Water cooling in the prior art, lumber recovery is low, rolls The low technical problem of benefit processed.
The embodiment of the invention also provides a kind of computer readable storage medium, the computer-readable recording medium storage There is the computer program for executing the not cold segment length control method of above-mentioned arbitrary high line Water cooling.It is high in the prior art to solve The technical problem that lumber recovery existing for line Water cooling is low, rolling benefit is low.
In embodiments of the present invention, realize successively respectively control each section of mm finishing mill unit rear wear each water cooling in water cooling water tank The valve opening of nozzle and closing, meanwhile, it is essence by the physical length conversion of mm finishing mill unit based on the rolling specs of different rolled pieces Equivalent length when milling train group rolling rolling stock, and then equivalent length when based on mm finishing mill unit rolling rolling stock, rolled piece is preset The muzzle velocity of not cold segment length and mm finishing mill unit is starting at the time of with the head of rolled piece by the heat inspection of finishing mill entrance Moment, when wearing the delay of the valve opening of each water-cooled nozzle and closing in water cooling water tank to calculate separately each section of mm finishing mill unit rear Between, that is, realize rolling specs, the preset not cold segment length of rolled piece and the outlet speed of mm finishing mill unit based on different rolled pieces Degree, to calculate the delay time that the valve opening of each water-cooled nozzle and closing in water cooling water tank are worn in each section of mm finishing mill unit rear, most Each section is successively controlled according to the delay time being calculated afterwards and wears the valve opening of each water-cooled nozzle and closing in water cooling water tank, is made It must be furthermore achieved and be worn based on the preset not cold segment length of the rolling specs of different rolled pieces, rolled piece to be accurately controlled each section The valve opening of each water-cooled nozzle and closing in water cooling water tank.Compared with prior art, the application is realized based on different rolled pieces Rolling specs, rolled piece preset not cold segment length be accurately controlled each section of valve for wearing each water-cooled nozzle in water cooling water tank It opens and closes, delay time is set without operative employee, it is advantageously ensured that the accurate control of not cold segment length (is normally controlled in 3 ~4 circle left and right), it is advantageously ensured that head-tail avoids cooling water slug, avoid when rolling different rolled pieces using unified delay It is cooling that time controls each section of water tank boiled water, and then avoids the not cold segment length in the head actually generated, the not cold segment length in tail portion Be not inconsistent with the not cold segment length in preset head, the not cold segment length in tail portion, reduce in actual production shorten, to increase head, tail not cold The phenomenon that segment length, is conducive to improve lumber recovery, improves rolling benefit.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, not Constitute limitation of the invention.In the accompanying drawings:
Fig. 1 is a kind of flow chart of the not cold segment length control method of high line Water cooling provided in an embodiment of the present invention;
Fig. 2 is a kind of high line Water cooling system exemplary apparatus configuration schematic diagram provided in an embodiment of the present invention;
Fig. 3 is a kind of mm finishing mill unit physical length schematic diagram provided in an embodiment of the present invention;
Fig. 4 is a kind of multiple angle pedestal valves provided in an embodiment of the present invention successively cooling schematic diagram of boiled water;
Fig. 5 is a kind of structural block diagram of the not cold segment length control device of high line Water cooling provided in an embodiment of the present invention.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, right below with reference to embodiment and attached drawing The present invention is described in further details.Here, exemplary embodiment and its explanation of the invention is used to explain the present invention, but simultaneously It is not as a limitation of the invention.
In embodiments of the present invention, a kind of not cold segment length control method of high line Water cooling is provided, as shown in Figure 1, This method comprises:
Step 102: according to the rolling specs of rolled piece, the physical length of mm finishing mill unit being converted as mm finishing mill unit rolling rolling stock When equivalent length;
Step 104: according to the outlet of the equivalent length, the preset not cold segment length of rolled piece and mm finishing mill unit speed Degree calculates each section of mm finishing mill unit rear and wears water as initial time at the time of using the head of rolled piece by the heat inspection of finishing mill entrance The delay time of the valve opening of each water-cooled nozzle and closing in cold water storage cistern;
Step 106: each section of valve for wearing each water-cooled nozzle in water cooling water tank is successively controlled according to the delay time being calculated Door opens and closes.
Process as shown in Figure 1 realizes successively that control mm finishing mill unit rear is each respectively it is found that in embodiments of the present invention Section wears the valve opening of each water-cooled nozzle and closing in water cooling water tank, meanwhile, based on the rolling specs of different rolled pieces, by finishing mill Equivalent length when the physical length conversion of group is mm finishing mill unit rolling rolling stock, and then when based on mm finishing mill unit rolling rolling stock etc. Length, the preset not cold segment length of rolled piece and the muzzle velocity of mm finishing mill unit are imitated, is entered with the head of rolled piece by finishing mill It is initial time at the time of at the hot inspection of mouth, to calculate separately the valve that each water-cooled nozzle in water cooling water tank is worn at each section of mm finishing mill unit rear The delay time that door opens and closes realizes the preset not cold segment length of rolling specs based on different rolled pieces, rolled piece And the muzzle velocity of mm finishing mill unit, to calculate the valve opening that each water-cooled nozzle in water cooling water tank is worn at each section of mm finishing mill unit rear With the delay time of closing, the delay time that last basis is calculated successively controls each section and wears each water-cooled nozzle in water cooling water tank Valve opening and closing so that the preset not cold segment length of the rolling specs based on different rolled pieces, rolled piece is furthermore achieved Degree wears the valve opening of each water-cooled nozzle and closing in water cooling water tank to be accurately controlled each section.Compared with prior art, this Shen It please realize and water cooling water is worn to be accurately controlled each section based on the preset not cold segment length of the rolling specs of different rolled pieces, rolled piece Delay time is arranged without operative employee in the valve opening of each water-cooled nozzle and closing in case, it is advantageously ensured that not cold segment length Accurate control (being normally controlled in 3~4 circle left and right), it is advantageously ensured that head-tail avoids cooling water slug, it is different to avoid rolling It is cooling that each section of water tank boiled water is controlled when rolled piece using unified delay time, and then avoids not cold section of the head actually generated The not cold segment length in length, tail portion is not inconsistent with the not cold segment length in preset head, the not cold segment length in tail portion, reduces in actual production Shorten, increase head, tail not cold segment length the phenomenon that, be conducive to improve lumber recovery, improve rolling benefit.
When it is implemented, as shown in Fig. 2, high line wears the process orientation of water-cooling system as by the side of 18# milling train to Laying head To, for not cold section of the head control to wear water cooling water tank (control of not cold section of tail portion is similar), mm finishing mill unit is 10 roller tandem mills, Its muzzle velocity is more than 100m/s, that is to say, that the valve event time every variation 10ms for wearing the cold nozzle of water cooling Water in Water Tanks rolls Part changes 1m not cold segment length, therefore, to accurately control not cold segment length, just must accurately control water-cooled nozzle valve Action delay.
It is found by Fig. 2 present inventor, the head of rolled piece is detected by finishing mill entrance heat, the detection signal It is reliable and stable, but rolled piece is when by mm finishing mill unit, roll quantity, drafts as used by different size kind Etc. differing greatly, cause to be all different from the valve event delay that " inspection of finishing mill entrance heat " is starting point, it can be in order to realize For the rolling specs of different rolled pieces, the preset not cold segment length of rolled piece and the muzzle velocity of mm finishing mill unit, calculate separately Each section of delay time for wearing the valve opening of each water-cooled nozzle and closing in water cooling water tank out, present inventor proposes will be smart Equivalent length when the physical length conversion of milling train group is mm finishing mill unit rolling rolling stock.
When it is implemented, in actual production, present inventor's discovery, mm finishing mill unit when rolling different size rolled piece The elongation percentage of each roll is different in the service condition and mm finishing mill unit of each roll, but is rolled for one specification of rolling The elongation percentage of each roll is fixed value in the service condition and mm finishing mill unit of each roll of mm finishing mill unit when part, is not to implement The value of variation, and mm finishing mill unit, as outlet rack, speed remains unchanged, and therefore, mm finishing mill unit equivalent length can basis The come into operation elongation percentage of situation and each roll of the roll of mm finishing mill unit calculates when rolling different size.Do not changing existing equipment knot Structure, in the case where not increasing detecting element, for the rolling specs of different rolled pieces, present inventor is proposed by the following method The equivalent length when physical length of mm finishing mill unit is converted as mm finishing mill unit rolling rolling stock:
According in the rolling specs of rolled piece use roll the case where and each roll elongation percentage, respectively will be in mm finishing mill unit Equivalent length when length conversion is rolling rolling stock between the rolling centerline of two neighboring roll;
Equivalent length when by each rolling rolling stock is added, and obtains equivalent length when mm finishing mill unit rolling rolling stock.
Specifically, when length between the rolling centerline of two neighboring roll being converted as rolling rolling stock by following formula Equivalent length:
L2i1=L2i×Ei+1×Ei+2×Ei+3......×En;(1)
Wherein, L2i1For i-th in mm finishing mill unit and i+1 roll rolling rolling stock when equivalent length;L2iFor finish rolling Length between the rolling centerline of i-th and i+1 roll in unit;Ei+1For the extension of i+1 roll in mm finishing mill unit Rate;Ei+2For the elongation percentage of the i-th+2 rolls in mm finishing mill unit;Ei+3For the elongation percentage of the i-th+3 rolls in mm finishing mill unit;EnFor The elongation percentage of n-th of roll in mm finishing mill unit;N is the sum of roll in mm finishing mill unit;Wherein, when mm finishing mill unit rolling rolling stock not The elongation percentage of the roll used is 1, and the ordinal number of roll is arranged according to the direction by entrance to outlet in mm finishing mill unit.
For example, as shown in figure 3, the physical length of mm finishing mill unit is L2 so that mm finishing mill unit includes 10 rolls as an example, according to The roll quantity that mm finishing mill unit includes divides the physical length of mm finishing mill unit, and the roll of each adjacent two roll is rolled Centreline space length is divided into a physical length, for example, be divided into L21, L22, L23, L24, L25, L26, L27, L28, L29, and then equivalent length when length between the roll rolling centerline of each adjacent two roll is converted as rolling rolling stock.
Specifically, the corresponding equivalent length of L21 is L211 according to above-mentioned formula (1), the corresponding equivalent length of L22 is The corresponding equivalent length of L221, L23 is L231, and so on, the corresponding equivalent length of L29 is L291, then L291=L29×E10; L281=L28×E9×E10;L271=L27×E8×E9×E10;And so on, L211=L21×E2×E3×E4×E5×E6×E7× E8×E9×E10;And then equivalent length L when mm finishing mill unit rolling rolling stockIt is equivalent=L211+L221+L231+L241+L251=L261+L271+ L281+L291
When it is implemented, after equivalent length when calculating mm finishing mill unit rolling rolling stock, in order to be rolled for different size The not cold segment length of the not cold segment length in the tail portion of part and head calculates separately the valve that each section is worn each water-cooled nozzle in water cooling water tank and closes The delay time that closing and opening opens is calculated by the following formula each section of mm finishing mill unit rear and wears in water cooling water tank in the present embodiment The delay time of the valve opening of each water-cooled nozzle:
Wherein, TdabFor wear water cooling water tank a b-th of water-cooled nozzle of section valve opening delay time;L1For thermometal The distance of detector first roll into mm finishing mill unit;V1For mm finishing mill unit upstream rack (for example, the 18# in Fig. 2, Fig. 3 Milling train) outlet linear velocity m/s;VfmFor the outlet linear velocity of mm finishing mill unit;LIt is equivalentEquivalent length when for mm finishing mill unit rolling rolling stock Degree;L3For the last one roll of mm finishing mill unit to the distance for wearing the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4To wear water cooling water tank The 1st water-cooled nozzle of paragraph 1 is to the distance for wearing water cooling water tank a b-th of water-cooled nozzle of section;L5For the not cold segment length in preset head Degree;Thd1For the synthesis opening time-delaying time of the valve of water-cooled nozzle.
When it is implemented, in the present embodiment, being calculated by the following formula each section of mm finishing mill unit rear and wearing in water cooling water tank The delay time that the valve of each water-cooled nozzle is closed:
Wherein, TdcdTo wear the delay time that the valve of water cooling water tank c d-th of water-cooled nozzle of section is closed;L1For thermometal The distance of detector first roll into mm finishing mill unit;VfmFor the outlet linear velocity of mm finishing mill unit;LIt is equivalentFor mm finishing mill unit rolling Equivalent length when rolled piece;L3For the last one roll of mm finishing mill unit to wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 away from From;L4To wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 to the distance for wearing water cooling water tank c d-th of water-cooled nozzle of section;L5It is pre- If the not cold segment length in tail portion;Thd2Delay time is closed for the comprehensive of valve of water-cooled nozzle.
When it is implemented, by calculating each section of delay for wearing the valve opening of each water-cooled nozzle and closing in water cooling water tank After time, as shown in Figure 4 (grey line segment be not cold section, black is cooling section), for the control of the not cold segment length in head, according to Process orientation successively controls the valve opening of water-cooled nozzle according to delay time from front to back, it is ensured that the not cold segment length in head is always Outside cooling range, not only reduce the impact to rolled piece, and the control effect of the not cold segment length in head is more excellent.Together Reason successively controls water-cooled nozzle according to delay time from front to back according to process orientation for the control of the not cold segment length in tail portion Valve close.
When it is implemented, the above-mentioned not cold segment length control method of high line Water cooling can integrate in the cold basis of wire rod control certainly In dynamicization PLC control system, as versatility control method, it can be applied to multiple scenes (for example, a surname high line of steel two, splendid steel High line etc.) in, in practice it has proved that this method is succinctly effective, widely applicable (distinct device type, transformation project are equally applicable), by To will be widely welcomed for user.
When it is implemented, the valve of above-mentioned water-cooled nozzle can be electronic valve, controlled out by electronic activation signal It opens and closes, when reaching delay time, send electronic signal to trigger valve opening or the closing of water-cooled nozzle.
Based on the same inventive concept, a kind of not cold segment length control of high line Water cooling is additionally provided in the embodiment of the present invention Device, as described in the following examples.The principle and height solved the problems, such as due to the not cold segment length control device of high line Water cooling The not cold segment length control method of line Water cooling is similar, therefore the implementation of the not cold segment length control device of high line Water cooling can be with Referring to the implementation of the not cold segment length control method of high line Water cooling, overlaps will not be repeated.It is used below, term The combination of the software and/or hardware of predetermined function may be implemented in " unit " or " module ".Although described in following embodiment Device is preferably realized with software, but the realization of the combination of hardware or software and hardware is also that may and be contemplated.
Fig. 5 is a kind of structural block diagram of the not cold segment length control device of high line Water cooling of the embodiment of the present invention, such as Fig. 5 Shown, which includes:
The physical length conversion of mm finishing mill unit is by equivalent length computing module 502 for the rolling specs according to rolled piece Equivalent length when mm finishing mill unit rolling rolling stock;
Delay time computing module 504, for the preset not cold segment length and essence according to the equivalent length, rolled piece The muzzle velocity of milling train group calculates finishing mill as initial time at the time of using the head of rolled piece by the heat inspection of finishing mill entrance Wear the delay time of the valve opening of each water-cooled nozzle and closing in water cooling water tank in each section of rear of group;
Control module 506 wears each water cooling in water cooling water tank for successively controlling each section according to the delay time being calculated The valve opening of nozzle and closing.
In one embodiment, the equivalent length computing module, for using roll in the rolling specs according to rolled piece The case where and each roll elongation percentage, respectively by between the rolling centerline of roll two neighboring in mm finishing mill unit length conversion be Equivalent length when rolling rolling stock;Equivalent length when by each rolling rolling stock is added, when obtaining mm finishing mill unit rolling rolling stock etc. Imitate length.
In one embodiment, the equivalent length computing module is by following formula by the rolling of two neighboring roll The equivalent length when conversion of centreline space length is rolling rolling stock:
L2i1=L2i×Ei+1×Ei+2×Ei+3......×En
Wherein, L2i1For i-th in mm finishing mill unit and i+1 roll rolling rolling stock when equivalent length;L2iFor finish rolling Length between the rolling centerline of i-th and i+1 roll in unit;Ei+1For the extension of i+1 roll in mm finishing mill unit Rate;Ei+2For the elongation percentage of the i-th+2 rolls in mm finishing mill unit;Ei+3For the elongation percentage of the i-th+3 rolls in mm finishing mill unit;EnFor The elongation percentage of n-th of roll in mm finishing mill unit;N is the sum of roll in mm finishing mill unit;Wherein, when mm finishing mill unit rolling rolling stock not The elongation percentage of the roll used is 1, and the ordinal number of roll is arranged according to the direction by entrance to outlet in mm finishing mill unit.
In one embodiment, the delay time computing module, for according to the equivalent length, rolled piece it is preset The muzzle velocity of the not cold segment length in head and mm finishing mill unit is calculated by the following formula each section of mm finishing mill unit rear and wears water cooling water The delay time of the valve opening of each water-cooled nozzle in case:
Wherein, TdabFor wear water cooling water tank a b-th of water-cooled nozzle of section valve opening delay time;L1For thermometal The distance of detector first roll into mm finishing mill unit;V1For the outlet linear velocity m/s of the rack of mm finishing mill unit upstream;VfmFor The outlet linear velocity of mm finishing mill unit;LIt is equivalentEquivalent length when for mm finishing mill unit rolling rolling stock;L3For mm finishing mill unit, the last one is rolled Roller is to the distance for wearing the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4To wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 to wearing water The distance of cold water storage cistern a b-th of water-cooled nozzle of section;L5For the not cold segment length in preset head;Thd1For the valve of water-cooled nozzle The comprehensive opening time-delaying time.
In one embodiment, the delay time computing module, be also used to according to the equivalent length, rolled piece it is default The not cold segment length in tail portion and mm finishing mill unit muzzle velocity, be calculated by the following formula each section of mm finishing mill unit rear and wear water cooling The delay time that the valve of each water-cooled nozzle is closed in water tank:
Wherein, TdcdTo wear the delay time that the valve of water cooling water tank c d-th of water-cooled nozzle of section is closed;L1For thermometal The distance of detector first roll into mm finishing mill unit;VfmFor the outlet linear velocity of mm finishing mill unit;LIt is equivalentFor mm finishing mill unit rolling Equivalent length when rolled piece;L3For the last one roll of mm finishing mill unit to wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 away from From;L4To wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 to the distance for wearing water cooling water tank c d-th of water-cooled nozzle of section;L5It is pre- If the not cold segment length in tail portion;Thd2Delay time is closed for the comprehensive of valve of water-cooled nozzle.
In another embodiment, a kind of software is additionally provided, the software is for executing above-described embodiment and preferred reality Apply technical solution described in mode.
In another embodiment, a kind of storage medium is additionally provided, above-mentioned software is stored in the storage medium, it should Storage medium includes but is not limited to: CD, floppy disk, hard disk, scratch pad memory etc..
The embodiment of the present invention realizes following technical effect: realize successively respectively control each section of mm finishing mill unit rear wear water The valve opening of each water-cooled nozzle and closing in cold water storage cistern, meanwhile, based on the rolling specs of different rolled pieces, by the object of mm finishing mill unit Manage equivalent length when length conversion is mm finishing mill unit rolling rolling stock, and then equivalent length when based on mm finishing mill unit rolling rolling stock Degree, the preset not cold segment length of rolled piece and the muzzle velocity of mm finishing mill unit pass through finishing mill entrance heat with the head of rolled piece It is initial time at the time of at inspection, is opened to calculate separately each section of the mm finishing mill unit rear valve for wearing each water-cooled nozzle in water cooling water tank The delay time for opening and closing, that is, realize rolling specs based on different rolled pieces, rolled piece preset not cold segment length and The muzzle velocity of mm finishing mill unit wears the valve opening of each water-cooled nozzle and pass in water cooling water tank to calculate each section of mm finishing mill unit rear The delay time closed, it is last that each section of valve for wearing each water-cooled nozzle in water cooling water tank is successively controlled according to the delay time being calculated Door open and close so that be furthermore achieved the rolling specs based on different rolled pieces, rolled piece preset not cold segment length come It is accurately controlled each section and wears the valve opening of each water-cooled nozzle and closing in water cooling water tank.Compared with prior art, the application is real Show and has been worn in water cooling water tank based on the preset not cold segment length of the rolling specs of different rolled pieces, rolled piece to be accurately controlled each section Delay time is arranged without operative employee, it is advantageously ensured that not cold segment length is accurate in the valve opening of each water-cooled nozzle and closing Control (is normally controlled in 3~4 circle left and right), it is advantageously ensured that head-tail avoids cooling water slug, avoids the different rolled pieces of rolling Shi Caiyong unified delay time is cooling to control each section of water tank boiled water, and then avoids the not cold segment length in the head actually generated Degree, the not cold segment length in tail portion are not inconsistent with the not cold segment length in preset head, the not cold segment length in tail portion, reduce in actual production and contract It is short, increase head, tail not cold segment length the phenomenon that, be conducive to improve lumber recovery, improve rolling benefit.
Obviously, those skilled in the art should be understood that each module of the above-mentioned embodiment of the present invention or each step can be with It is realized with general computing device, they can be concentrated on a single computing device, or be distributed in multiple computing devices On composed network, optionally, they can be realized with the program code that computing device can perform, it is thus possible to by it Store and be performed by computing device in the storage device, and in some cases, can be held with the sequence for being different from herein The shown or described step of row, perhaps they are fabricated to each integrated circuit modules or will be multiple in them Module or step are fabricated to single integrated circuit module to realize.In this way, the embodiment of the present invention be not limited to it is any specific hard Part and software combine.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the embodiment of the present invention can have various modifications and variations.All within the spirits and principles of the present invention, made Any modification, equivalent substitution, improvement and etc. should all be included in the protection scope of the present invention.

Claims (12)

1. a kind of not cold segment length control method of high line Water cooling characterized by comprising
Equivalent length according to the rolling specs of rolled piece, when the physical length of mm finishing mill unit is converted as mm finishing mill unit rolling rolling stock Degree;
According to the equivalent length, the preset not cold segment length of rolled piece and the muzzle velocity of mm finishing mill unit, with the head of rolled piece It is initial time at the time of portion is by the heat inspection of finishing mill entrance, calculates each section of mm finishing mill unit rear and wear each water cooling in water cooling water tank The valve opening of nozzle and the delay time of closing;
Each section, which is successively controlled, according to the delay time being calculated wears the valve opening of each water-cooled nozzle and closing in water cooling water tank.
2. the not cold segment length control method of high line Water cooling as described in claim 1, which is characterized in that according to rolling for rolled piece Specification processed, the equivalent length when physical length of mm finishing mill unit is converted as mm finishing mill unit rolling rolling stock, comprising:
According in the rolling specs of rolled piece use roll the case where and each roll elongation percentage, respectively will be adjacent in mm finishing mill unit Equivalent length when length conversion is rolling rolling stock between the rolling centerline of two rolls;
Equivalent length when by each rolling rolling stock is added, and obtains equivalent length when mm finishing mill unit rolling rolling stock.
3. the not cold segment length control method of high line Water cooling as claimed in claim 2, which is characterized in that pass through following formula Equivalent length when length between the rolling centerline of two neighboring roll is converted as rolling rolling stock:
L2i1=L2i×Ei+1×Ei+2×Ei+3......×En
Wherein, L2i1For i-th in mm finishing mill unit and i+1 roll rolling rolling stock when equivalent length;L2iFor mm finishing mill unit In i-th and i+1 roll rolling centerline between length;Ei+1For the elongation percentage of i+1 roll in mm finishing mill unit;Ei+2 For the elongation percentage of the i-th+2 rolls in mm finishing mill unit;Ei+3For the elongation percentage of the i-th+3 rolls in mm finishing mill unit;EnFor finishing mill The elongation percentage of n-th of roll in group;N is the sum of roll in mm finishing mill unit;Wherein, not used when mm finishing mill unit rolling rolling stock The elongation percentage of roll is 1, and the ordinal number of roll is arranged according to the direction by entrance to outlet in mm finishing mill unit.
4. the not cold segment length control method of high line Water cooling as claimed any one in claims 1 to 3, which is characterized in that Calculate the delay time that the valve opening of each water-cooled nozzle in water cooling water tank is worn at each section of mm finishing mill unit rear, comprising:
According to the not cold segment length in the preset head of the equivalent length, rolled piece and the muzzle velocity of mm finishing mill unit, by with Lower formula calculates the delay time that the valve opening of each water-cooled nozzle in water cooling water tank is worn at each section of mm finishing mill unit rear:
Wherein, TdabFor wear water cooling water tank a b-th of water-cooled nozzle of section valve opening delay time;L1For thermometal detection The distance of device first roll into mm finishing mill unit;V1For the outlet linear velocity m/s of the rack of mm finishing mill unit upstream;VfmFor finish rolling The outlet linear velocity of unit;LIt is equivalentEquivalent length when for mm finishing mill unit rolling rolling stock;L3Extremely for mm finishing mill unit the last one roll Wear the distance of the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4To wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 to wearing water cooling water The distance of case a b-th of water-cooled nozzle of section;L5For the not cold segment length in preset head;Thd1For the synthesis of the valve of water-cooled nozzle The opening time-delaying time.
5. the not cold segment length control method of high line Water cooling as claimed any one in claims 1 to 3, which is characterized in that It calculates each section of mm finishing mill unit rear and wears the delay time that the valve of each water-cooled nozzle in water cooling water tank is closed, comprising:
According to the not cold segment length in the preset tail portion of the equivalent length, rolled piece and the muzzle velocity of mm finishing mill unit, by with Lower formula calculates each section of mm finishing mill unit rear and wears the delay time that the valve of each water-cooled nozzle in water cooling water tank is closed:
Wherein, TdcdTo wear the delay time that the valve of water cooling water tank c d-th of water-cooled nozzle of section is closed;L1For thermometal detection The distance of device first roll into mm finishing mill unit;VfmFor the outlet linear velocity of mm finishing mill unit;LIt is equivalentFor mm finishing mill unit rolling rolling stock When equivalent length;L3For the last one roll of mm finishing mill unit to the distance for wearing the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4For The 1st water-cooled nozzle of water cooling water tank paragraph 1 is worn to the distance for wearing water cooling water tank c d-th of water-cooled nozzle of section;L5For preset tail The not cold segment length in portion;Thd2Delay time is closed for the comprehensive of valve of water-cooled nozzle.
6. a kind of not cold segment length control device of high line Water cooling characterized by comprising
Equivalent length computing module converts the physical length of mm finishing mill unit for finishing mill for the rolling specs according to rolled piece Equivalent length when group rolling rolling stock;
Delay time computing module, for the preset not cold segment length and mm finishing mill unit according to the equivalent length, rolled piece Muzzle velocity calculate mm finishing mill unit rear as initial time at the time of using the head of rolled piece by the heat inspection of finishing mill entrance Each section of delay time for wearing the valve opening of each water-cooled nozzle and closing in water cooling water tank;
Control module, for successively controlling each section of valve for wearing each water-cooled nozzle in water cooling water tank according to the delay time being calculated Door opens and closes.
7. the not cold segment length control device of high line Water cooling as claimed in claim 6, which is characterized in that the equivalent length Computing module, in the rolling specs according to rolled piece use roll the case where and each roll elongation percentage, respectively by finish rolling Equivalent length when length conversion is rolling rolling stock between the rolling centerline of two neighboring roll in unit;When by each rolling rolling stock Equivalent length be added, obtain equivalent length when mm finishing mill unit rolling rolling stock.
8. the not cold segment length control device of high line Water cooling as claimed in claim 7, which is characterized in that the equivalent length It is equivalent when computing module is converted length between the rolling centerline of two neighboring roll for rolling rolling stock by following formula Length:
L2i1=L2i×Ei+1×Ei+2×Ei+3......×En
Wherein, L2i1For i-th in mm finishing mill unit and i+1 roll rolling rolling stock when equivalent length;L2iFor mm finishing mill unit In i-th and i+1 roll rolling centerline between length;Ei+1For the elongation percentage of i+1 roll in mm finishing mill unit;Ei+2 For the elongation percentage of the i-th+2 rolls in mm finishing mill unit;Ei+3For the elongation percentage of the i-th+3 rolls in mm finishing mill unit;EnFor finishing mill The elongation percentage of n-th of roll in group;N is the sum of roll in mm finishing mill unit;Wherein, not used when mm finishing mill unit rolling rolling stock The elongation percentage of roll is 1, and the ordinal number of roll is arranged according to the direction by entrance to outlet in mm finishing mill unit.
9. the not cold segment length control device of high line Water cooling as described in any one of claim 6 to 8, which is characterized in that The delay time computing module, for the not cold segment length in preset head and finish rolling according to the equivalent length, rolled piece The muzzle velocity of unit is calculated by the following formula each section of the mm finishing mill unit rear valve for wearing each water-cooled nozzle in water cooling water tank and opens The delay time opened:
Wherein, TdabFor wear water cooling water tank a b-th of water-cooled nozzle of section valve opening delay time;L1For thermometal detection The distance of device first roll into mm finishing mill unit;V1For the outlet linear velocity m/s of the rack of mm finishing mill unit upstream;VfmFor finish rolling The outlet linear velocity of unit;LIt is equivalentEquivalent length when for mm finishing mill unit rolling rolling stock;L3Extremely for mm finishing mill unit the last one roll Wear the distance of the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4To wear the 1st water-cooled nozzle of water cooling water tank paragraph 1 to wearing water cooling water The distance of case a b-th of water-cooled nozzle of section;L5For the not cold segment length in preset head;Thd1For the synthesis of the valve of water-cooled nozzle The opening time-delaying time.
10. the not cold segment length control device of high line Water cooling as described in any one of claim 6 to 8, which is characterized in that The delay time computing module is also used to the not cold segment length in preset tail portion and essence according to the equivalent length, rolled piece The muzzle velocity of milling train group is calculated by the following formula the valve that each water-cooled nozzle in water cooling water tank is worn at each section of mm finishing mill unit rear The delay time of closing:
Wherein, TdcdTo wear the delay time that the valve of water cooling water tank c d-th of water-cooled nozzle of section is closed;L1For thermometal detection The distance of device first roll into mm finishing mill unit;VfmFor the outlet linear velocity of mm finishing mill unit;LIt is equivalentFor mm finishing mill unit rolling rolling stock When equivalent length;L3For the last one roll of mm finishing mill unit to the distance for wearing the 1st water-cooled nozzle of water cooling water tank paragraph 1;L4For The 1st water-cooled nozzle of water cooling water tank paragraph 1 is worn to the distance for wearing water cooling water tank c d-th of water-cooled nozzle of section;L5For preset tail The not cold segment length in portion;Thd2Delay time is closed for the comprehensive of valve of water-cooled nozzle.
11. a kind of computer equipment including memory, processor and stores the meter that can be run on a memory and on a processor Calculation machine program, which is characterized in that the processor is realized described in any one of claim 1 to 5 when executing the computer program The not cold segment length control method of high line Water cooling.
12. a kind of computer readable storage medium, which is characterized in that the computer-readable recording medium storage has perform claim It is required that the computer program of 1 to 5 described in any item not cold segment length control methods of high line Water cooling.
CN201811277441.0A 2018-10-30 2018-10-30 Method and device for controlling length of high-speed wire water-cooling uncooled section Active CN109530461B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811277441.0A CN109530461B (en) 2018-10-30 2018-10-30 Method and device for controlling length of high-speed wire water-cooling uncooled section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811277441.0A CN109530461B (en) 2018-10-30 2018-10-30 Method and device for controlling length of high-speed wire water-cooling uncooled section

Publications (2)

Publication Number Publication Date
CN109530461A true CN109530461A (en) 2019-03-29
CN109530461B CN109530461B (en) 2020-09-11

Family

ID=65845495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811277441.0A Active CN109530461B (en) 2018-10-30 2018-10-30 Method and device for controlling length of high-speed wire water-cooling uncooled section

Country Status (1)

Country Link
CN (1) CN109530461B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112090969A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Through water cooling control method and system for long material rolling
CN112090970A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112090968A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112756404A (en) * 2020-11-23 2021-05-07 阳春新钢铁有限责任公司 Precise and quantitative automatic control system and control method for non-cold section of production head of high-speed wire rod
CN112823873A (en) * 2019-11-21 2021-05-21 杉杉能源(宁夏)有限公司 Method and device for accurately controlling feeding of reaction kettle
CN113500101A (en) * 2021-06-22 2021-10-15 山东莱钢永锋钢铁有限公司 High-precision shearing control system for multi-length shear
CN113522990A (en) * 2021-06-25 2021-10-22 武汉钢铁有限公司 Method for accurately regulating and controlling spinning temperature of 70-grade cord steel
CN114951307A (en) * 2022-05-20 2022-08-30 广西钢铁集团有限公司 Hot-rolled ribbed steel bar direct-rolling sectional control cooling method
CN117399438A (en) * 2023-11-03 2024-01-16 中天钢铁集团(南通)有限公司 Method for stabilizing head and tail performance in English standard rolling process

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113604655A (en) * 2021-08-09 2021-11-05 宝武集团鄂城钢铁有限公司 Fog cold blowing control equipment, method and device and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6044122A (en) * 1983-08-19 1985-03-09 Kawasaki Steel Corp Method and apparatus for cooling hot rolled steel plate
CN102371283A (en) * 2011-10-14 2012-03-14 东北大学 Method for improving ultra-fast cooling uniformity of medium and heavy plate after rolling
CN102601134A (en) * 2011-12-09 2012-07-25 秦皇岛首秦金属材料有限公司 Method for controlling thin pipeline steel cooling uniformity in ultrafast cooling process
CN104511485A (en) * 2013-09-30 2015-04-15 株式会社日立制作所 Rolling member coiling temperature control device and rolling member coiling temperature control method
CN105268750A (en) * 2015-11-23 2016-01-27 东北大学 Head and tail rapid shielding device, system and method for moderate-thickness plate cooling system
CN106391727A (en) * 2016-06-28 2017-02-15 东北大学 Head no-cooling control method for hot rolled strip steel in ultra-rapid cooling area

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6044122A (en) * 1983-08-19 1985-03-09 Kawasaki Steel Corp Method and apparatus for cooling hot rolled steel plate
CN102371283A (en) * 2011-10-14 2012-03-14 东北大学 Method for improving ultra-fast cooling uniformity of medium and heavy plate after rolling
CN102601134A (en) * 2011-12-09 2012-07-25 秦皇岛首秦金属材料有限公司 Method for controlling thin pipeline steel cooling uniformity in ultrafast cooling process
CN104511485A (en) * 2013-09-30 2015-04-15 株式会社日立制作所 Rolling member coiling temperature control device and rolling member coiling temperature control method
CN105268750A (en) * 2015-11-23 2016-01-27 东北大学 Head and tail rapid shielding device, system and method for moderate-thickness plate cooling system
CN106391727A (en) * 2016-06-28 2017-02-15 东北大学 Head no-cooling control method for hot rolled strip steel in ultra-rapid cooling area

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112823873A (en) * 2019-11-21 2021-05-21 杉杉能源(宁夏)有限公司 Method and device for accurately controlling feeding of reaction kettle
CN112090968B (en) * 2020-08-28 2022-03-25 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112090970A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112090968A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112090969A (en) * 2020-08-28 2020-12-18 中冶华天工程技术有限公司 Through water cooling control method and system for long material rolling
CN112090970B (en) * 2020-08-28 2022-04-22 中冶华天工程技术有限公司 Water cooling control system and control method for long material rolling
CN112090969B (en) * 2020-08-28 2022-04-22 中冶华天工程技术有限公司 Through water cooling control method and system for long material rolling
CN112756404A (en) * 2020-11-23 2021-05-07 阳春新钢铁有限责任公司 Precise and quantitative automatic control system and control method for non-cold section of production head of high-speed wire rod
CN112756404B (en) * 2020-11-23 2022-04-01 阳春新钢铁有限责任公司 Precise and quantitative automatic control system and control method for non-cold section of production head of high-speed wire rod
CN113500101A (en) * 2021-06-22 2021-10-15 山东莱钢永锋钢铁有限公司 High-precision shearing control system for multi-length shear
CN113522990A (en) * 2021-06-25 2021-10-22 武汉钢铁有限公司 Method for accurately regulating and controlling spinning temperature of 70-grade cord steel
CN114951307A (en) * 2022-05-20 2022-08-30 广西钢铁集团有限公司 Hot-rolled ribbed steel bar direct-rolling sectional control cooling method
CN114951307B (en) * 2022-05-20 2024-05-28 广西钢铁集团有限公司 Direct rolling sectional control cooling method for hot rolled ribbed steel bar
CN117399438A (en) * 2023-11-03 2024-01-16 中天钢铁集团(南通)有限公司 Method for stabilizing head and tail performance in English standard rolling process

Also Published As

Publication number Publication date
CN109530461B (en) 2020-09-11

Similar Documents

Publication Publication Date Title
CN109530461A (en) Method and device for controlling length of high-speed wire water-cooling uncooled section
CN105817489B (en) A kind of TEMPERATURE FOR HOT STRIP LAMINAR cooling technique
CN103372572B (en) Control method for improving rolling pace of roughing mill
CN102179406B (en) Method for rolling thin high-strength steel plate of single-frame steckel mill
CN103934278B (en) A kind of hot fine rolling band steel method for controlling thickness
CN208628122U (en) A kind of microgap rolling system
CN106480306B (en) The control method of second segment cooling precision in laminar flow sub-sectional cooling technique
CN102266866A (en) Technology for producing hot-rolled pipeline steel of roll mill with single frame furnace
CN102974623B (en) Pre-straightening method for realizing plate shape control on medium and thick plates
CN105057364B (en) Magnesium alloy sheet rolling edge crack pre-judgment and control method
CN102225432B (en) Control process for performances of steel plate during hot rolling and flat rolling process of single-stand steckel mill
CN106914495B (en) A kind of hot-strip camber control method and system
CN103722009A (en) Bar continuous rolling production line
CN103079719A (en) Method for producing steel strips by continuous rolling or semi-continuous rolling
CN211413168U (en) Screw-thread steel rolling production line
CN108856303A (en) Reliable hot-rolling finishing mill frame stings steel signal control method
CN109550810A (en) Straightening method for improving shape of thin-specification cold-control steel plate
CN110355221A (en) A kind of hot-rolled strip production line essence de-scaling pinch roller adjustment system and method
CN103128099B (en) A kind of hot rolling system and method
US20080135203A1 (en) Continuous Casting and Rolling Installation For Producing a Steel Strip
CN103586294A (en) Laminar cooling method, hot continuous rolling production line and production line laminar cooling system for thick plates
CN103521554A (en) Method for preventing tail part of band steel from loop rising in front of coiling machine
CN108580559A (en) A kind of control method for material tracking
JP2016209897A (en) Cooling control method for thick steel plate, cooling control apparatus, manufacturing method, and manufacturing apparatus
US3553997A (en) Method of rolling bars cast in continuous casting plants

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant