CN109487748A - Nearby Structure depth riverbed quaywall supporting construction and construction method - Google Patents

Nearby Structure depth riverbed quaywall supporting construction and construction method Download PDF

Info

Publication number
CN109487748A
CN109487748A CN201810559976.0A CN201810559976A CN109487748A CN 109487748 A CN109487748 A CN 109487748A CN 201810559976 A CN201810559976 A CN 201810559976A CN 109487748 A CN109487748 A CN 109487748A
Authority
CN
China
Prior art keywords
campshed
quaywall
riverbed
river
supporting construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810559976.0A
Other languages
Chinese (zh)
Inventor
邓学让
罗来辉
杨立寒
罗波
彭伟斌
闻世强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Deep Water Consulting Co Ltd
Original Assignee
Shenzhen Deep Water Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Deep Water Consulting Co Ltd filed Critical Shenzhen Deep Water Consulting Co Ltd
Priority to CN201810559976.0A priority Critical patent/CN109487748A/en
Publication of CN109487748A publication Critical patent/CN109487748A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of Nearby Structure depth riverbed quaywall supporting construction and construction methods, belong to construction of hydro project technical field, solve the problems, such as that common quaywall supporting construction is difficult to construct in the case where Nearby Structure, its key points of the technical solution are that, including being poured in the soil body of river two sides vertically, and the preceding campshed and rear campshed being parallel to each other, the height of the front row stake top is lower than the height of the heel row stake top, crown beam is provided at the top of the preceding campshed and the rear campshed, formed by integrally casting is connected with the spaced coupling beam of multiple tracks between crown beam and the pile body of campshed afterwards on the preceding campshed, the two preceding campsheds are respectively and fixedly provided with the first hanging plate on the one side in river, it is further fixed between the pile body of two preceding campsheds several spaced to support beam, reach safety and stability, it is convenient to close on building The purpose constructed at the river on object side.

Description

Nearby Structure depth riverbed quaywall supporting construction and construction method
Technical field
The present invention relates to construction of hydro project technical field, in particular to Nearby Structure depth riverbed quaywall supporting construction and Construction method.
Background technique
Building is more intensive along city inland river road dyke, and when comprehensive improvement machine dyke in river is transformed, house is relocated residents from locations to be used for construction of new buildings or factories tired Difficulty, when building embankment, excavation pit needs strict control sedimentation and deformation etc., guards against to closing on house and has an adverse effect.For Groove is deeper, and the higher River Embankment deep foundation pit supporting structure of bank slope is especially needed to cause enough attention.Generally use water conservancy project gear Cob wall or campshed+anchor pole (anchor cable) supporting construction.
The shortcomings that above-mentioned quaywall supporting construction, is as follows: 1, using water conservancy project retaining wall structure, needing very big construction working face And slope space is excavated, usually in the case where Nearby Structure, it is difficult to implement;2, using campshed+anchor pole (anchor cable) supporting knot Structure exceeds land red-line range, evens penetrate into Nearby Structure ground beneath when setting there are anchor pole (anchor cable) the case where, not In the case where through ownership unit (individual) license, it is easy to produce dispute.In the recent period, regulation etc. is put into effect in many cities in succession, is being closed on When other buildings, limitation uses anchor pole (anchor cable) Scheme of Strengthening.Gu needing to design a kind of new Nearby Structure depth riverbed bank Wall supporting construction.
Summary of the invention
An object of the present invention is to provide a kind of Nearby Structure depth riverbed quaywall supporting construction, have safety and stability, The advantages of convenient river on Nearby Structure side is constructed.
Above-mentioned technical purpose of the invention has the technical scheme that Nearby Structure depth riverbed quaywall Supporting construction, including being poured in the preceding campshed and rear campshed that in the soil body of river two sides and are parallel to each other, the preceding campshed stake vertically The height on top is lower than the height of the heel row stake top, is provided with crown beam at the top of the preceding campshed and the rear campshed, institute It states formed by integrally casting between the crown beam on preceding campshed and the pile body of the rear campshed and is connected with the spaced coupling beam of multiple tracks, described in two Preceding campshed is respectively and fixedly provided with the first hanging plate on the one side in river, is further fixed between the pile body of two preceding campsheds several It is spaced to support beam.
By using above-mentioned technical proposal, the rigidly connected coupling beam of the multiple tracks added between preceding campshed and rear campshed increases The big lateral rigidity of Retaining Structure with Double-row Piles entirety, can effectively keep out the lateral pressure on river bank;On the outside of preceding campshed One hanging plate can be used as water-retaining cofferdam, reduce river water to soil erosion caused by the washing away of riverbank;Before being arranged in two between campshed Several pairs of support beams, further increase the factor of safety against overturning of Retaining Structure with Double-row Piles, without installing anchor cable, subtract significantly Retaining Structure with Double-row Piles is lacked to the occupancy of the underground space, has been carried out with safety and stability, conveniently in the river on Nearby Structure side The advantages of construction.
The further setting of the present invention, the preceding campshed and the rear campshed are combined by several bored concrete piles being arranged side by side It forms, there are gaps between adjacent two bored concrete piles.
The preceding campshed be composed of by using above-mentioned technical proposal the bored concrete pile of this size and rear piling structure jail Gu stability is high.
The hard stratum of river underground is inserted into the bottom end of the further setting of the present invention, the preceding campshed and the rear campshed In.
Structural stability by using above-mentioned technical proposal, the preceding campshed and rear campshed that are inserted into hard stratum is higher, anti-to incline It is stronger to cover ability.
The further setting of the present invention, the cross-sectional area of described pair of support beam are 80cm × 80cm, adjacent two described pair of supports The center spacing of beam is 2.5-3.0 meter Yi Gen.
By using above-mentioned technical proposal, the setting of this spacing two are horizontally supported to support beam before between campshed, into one Campshed is not susceptible to tilt before step makes.
The further setting of the present invention, described pair of support beam includes concrete river bottom protection made of being poured on steel reinforcement cage as concrete Layer, the concrete river bottom protection layer lower section are equipped with plain concrete bed course.
By using above-mentioned technical proposal, the effect that plain concrete bed course primarily serves protection foundation soil, balances integrated carrying, together When reduce corrosion function of the underground water to armored concrete.
The further setting of the present invention, element concrete bed course lower section are additionally provided with metalling and coarse sand filtering layer.
By using above-mentioned technical proposal, blotter and metalling can play the role of diffusion-induced stress with soft foundation, It can play the role of draining simultaneously, accelerate the consolidation and sedimentation of lower part soil layer.
The further setting of the present invention, the lateral surface that the rear campshed is higher than the preceding campshed are fixed with the second hanging plate.
By using above-mentioned technical proposal, the second hanging plate is higher than front-seat stake top as second level water-retaining cofferdam, in river water level When portion, river water can be reduced to soil erosion caused by the washing away of riverbank.
The further setting of the present invention is equipped with base board above several coupling beams, is provided on the base board Pavement and greenbelt, the railing being also equipped in the crown beam on the outside of pavement.
By using above-mentioned technical proposal, the setting of greenbelt and pavement makes river two sides in Retaining Structure with Double-row Piles More preferably, the setting of railing improves safety to landscape.
The second object of the present invention is to provide a kind of construction method of Nearby Structure depth riverbed quaywall supporting construction, have Safety and stability, conveniently Nearby Structure side river construct the advantages of.
Above-mentioned technical purpose of the invention has the technical scheme that Nearby Structure depth riverbed quaywall The construction method of supporting construction, comprising the following steps:
1), according to the geological conditions of river two sides, the long stake of the bored concrete pile of preceding campshed and rear campshed, stake diameter, stake spacing, preceding is determined Spacing between campshed and rear campshed is confirmed and is marked to bored concrete pile, coupling beam and to the nodal section size of support beam and stake position;
2) complete by the way of cast-in-situ bored pile according to setting height on stake position after smooth location, according to construction requirement At all bored concrete piles, the stake top of bored concrete pile is reserved with anchor bar, and the height of front-seat stake top is lower than the stake top of rear campshed Highly;
3) integrally formed crown beam and coupling beam, are poured between the stake top of preceding campshed and preceding campshed and rear campshed, at two front rows It is poured between stake several spaced apart to support beam;
4) the first hanging plate, is installed in the lateral surface of preceding campshed, the second hanging plate is installed in the lateral surface of rear campshed.
By using above-mentioned technical proposal, increase the lateral rigid of Retaining Structure with Double-row Piles entirety using coupling beam and to support beam Degree, can effectively keep out the lateral pressure on river bank, improve the factor of safety against overturning of Retaining Structure with Double-row Piles, without Anchor cable is installed, Retaining Structure with Double-row Piles is greatly reduced to the occupancy of the underground space, there is safety and stability, conveniently closing on building The advantages of river on object side is constructed.
In conclusion the invention has the following advantages:
1, the rigidly connected coupling beam of the multiple tracks added between preceding campshed and rear campshed and to support beam, increase Double-row Piles Support knot The lateral rigidity of structure entirety can effectively keep out the lateral pressure on river bank, increase the antidumping peace of Retaining Structure with Double-row Piles Overall coefficient;
2, the first hanging plate and the second hanging plate can be used as water-retaining cofferdam, it is possible to reduce river water is to water and soil stream caused by the washing away of riverbank It loses;
3, using Retaining Structure with Double-row Piles without installing anchor cable, the occupancy to the underground space is greatly reduced, it is convenient to build closing on It constructs in the river for building object side.
Detailed description of the invention
Fig. 1 is cross-section diagram of the Retaining Structure with Double-row Piles in river in the embodiment of the present invention;Structural schematic diagram;
Fig. 2 is the overall structure diagram of Retaining Structure with Double-row Piles in the embodiment of the present invention;
Fig. 3 is the enlarged drawing in Fig. 1 at A.
Appended drawing reference: 1, preceding campshed;2, rear campshed;3, crown beam;4, coupling beam;41, concrete river bottom protection layer;42, plain concrete bed course;43, Metalling;44, coarse sand filtering layer;5, the first hanging plate;6, to support beam;7, the second hanging plate;8, base board;9, pavement;10, it afforests Band;11, railing;12, miscellaneous fill layer;13, silty clay layer;14, sandy gravel stratum;15, gravelly clay layer;16, weathered granite Layer.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment
Nearby Structure depth riverbed quaywall supporting construction as depicted in figs. 1 and 2, including is poured in river two sides soil vertically In body and the preceding campshed 1 and rear campshed 2 that are parallel to each other, the height of preceding 1 stake top of campshed are lower by 5.0 than the height of rear 2 stake top of campshed Rice.The integrated pouring molding in the top of preceding campshed 1 and rear campshed 2 has crown beam 3, the crown beam 3 and rear campshed 2 at the top of preceding campshed 1 Formed by integrally casting forms coupling beam 4 between pile body, and coupling beam 4 is formed using C35 reinforcing bar concrete placings.Before two campshed 1 close to river one Face is respectively and fixedly provided with the first hanging plate 5, and the first hanging plate 5 uses the C30 reinforced concrete hanging plate of 300 mm of thickness, and campshed 1 is located at first before two There is to support beam 6 pouring molding between the pile body of 5 lower section of hanging plate.Coupling beam 4 and to support beam 6 setting increase Retaining Structure with Double-row Piles Whole lateral rigidity, can effectively keep out the lateral pressure on river bank, improve the antidumping safety of Retaining Structure with Double-row Piles Coefficient greatly reduces Retaining Structure with Double-row Piles to the occupancy of the underground space without installing anchor cable, have safety and stability, Conveniently the advantages of the river on Nearby Structure side is constructed.
The lateral surface that campshed 2 is higher than preceding campshed 1 afterwards is fixed with the second hanging plate 7, and the second hanging plate 7 is using 300 mm of thickness C30 reinforced concrete hanging plate, the second hanging plate 7 are used as second level water-retaining cofferdam, when river water level is higher than preceding 1 top of campshed, can be reduced river Water is to soil erosion caused by the washing away of riverbank.
The top of coupling beam 4 is equipped with base board 8, and pavement 9 and greenbelt 10 are provided on base board 8, is also pacified in crown beam 3 Equipped with the railing 11 for being located at 9 outside of pavement, the setting on greenbelt 10 and pavement 9 makes river two sides in Retaining Structure with Double-row Piles Landscape more preferably, the setting of railing 11 improves safety.
According to geological prospecting, the geological stratification structure of river two sides is successively miscellaneous fill layer 12, silty clay layer from top to bottom 13, sandy gravel stratum 14, gravelly clay layer 15 and weathered granite layer 16.Preceding campshed 1 and rear campshed 2 are by length 25m, diameter 1200 millimeters of bored concrete pile Side by side groupings forms, and the center spacing of adjacent two bored concrete piles is 1500 millimeters, the bottom of bored concrete pile It is inserted into the harder weathered granite layer 16 of quality, this Double-row-piles Structure stability is higher, and resistance to capsizing is stronger.
As shown in Fig. 2, being 80cm × 80cm to the cross-sectional area of support beam 6, adjacent two are to the center spacing of support beam 6 3.0 meter Yi Gen, the setting of this spacing two are horizontally supported to support beam 6 before between campshed 1, campshed 1 is not easy to send out before further making Raw inclination.
As shown in figure 3, including concrete river bottom protection layer 41, concrete river bottom protection made of being poured on steel reinforcement cage as concrete to support beam 6 The thickness of layer 41 is preferably 300 millimeters, and plain concrete bed course 42 is equipped with below concrete river bottom protection layer 41, and the thickness of plain concrete bed course 42 is preferably 150 millimeters.Plain concrete bed course 42 primarily serves protection foundation soil, balances the effect of integrated carrying, while reducing underground water to reinforcing bar The corrosion function of concrete.
Plain 42 lower section of concrete bed course is also disposed with the coarse sand filtering layer of the mm of thickness of metalling 43 and 150 of 250 millimeters thicks 44, metalling 43 is laid with using the rubble of granularity 5-20, and coarse sand filtering layer 44 is laid with using the coarse sand of granularity 0.5-5. Coarse sand filtering layer 44 and metalling 43 can be played the role of diffusion-induced stress, while can play draining, be added with soft foundation The consolidation and sedimentation of fast lower part soil layer.
The present embodiment also proposed a kind of construction method of Nearby Structure depth riverbed quaywall supporting construction, including following step It is rapid:
1), according to the geological conditions of river two sides, determine the long stake of the bored concrete pile of preceding campshed 1 and rear campshed 2, stake diameter, stake spacing, Spacing between preceding campshed 1 and rear campshed 2 confirms to bored concrete pile, coupling beam 4 and to the nodal section size of support beam 6 and stake position And label;
2) complete by the way of cast-in-situ bored pile according to setting height on stake position after smooth location, according to construction requirement At all bored concrete piles, the stake top of bored concrete pile is reserved with anchor bar, and the height of 1 stake top of preceding campshed is lower than the stake of rear campshed 2 Heights of roofs;
3) integrally formed crown beam 3 and coupling beam 4, are poured between the stake top and preceding campshed 1 and rear campshed 2 of preceding campshed 1, two It is poured between preceding campshed 1 several spaced apart to support beam 6;
4) first hanging plate 5, is installed in the lateral surface of preceding campshed 1, the second hanging plate 5 is installed in the lateral surface of rear campshed, and in coupling beam 4 Top roadbed paving plate 8, the construction on base board 8 enterprising pedestrian trade 9 and greenbelt 10, and railing 11 is installed in crown beam 3.
The course of work and principle: the rigidly connected coupling beam 4 of multiple tracks and setting are set between preceding campshed 1 and rear campshed 2 Before two between campshed 1 to support beam 6, Retaining Structure with Double-row Piles entirety factor of safety against overturning is increased, without installing Anchor cable greatly reduces Retaining Structure with Double-row Piles to the occupancy of the underground space, has safety and stability, conveniently on Nearby Structure side River the advantages of being constructed.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of invention.

Claims (9)

1. Nearby Structure depth riverbed quaywall supporting construction, which is characterized in that including being poured in the soil body of river two sides vertically and The preceding campshed (1) and rear campshed (2) being parallel to each other, the height of preceding campshed (1) stake top is lower than described rear campshed (2) stake top Highly, it is provided with crown beam (3) at the top of the preceding campshed (1) and the rear campshed (2), the crown beam on the preceding campshed (1) (3) formed by integrally casting is connected with the spaced coupling beam of multiple tracks (4), the two preceding campsheds between the pile body of the rear campshed (2) (1) it is respectively and fixedly provided with the first hanging plate (5) on the one side in river, several intervals is further fixed between the preceding campshed (1) and are set Set to support beam (6).
2. Nearby Structure depth according to claim 1 riverbed quaywall supporting construction, which is characterized in that the preceding campshed (1) with it is described after campshed (2) be composed of several bored concrete piles being arranged side by side, between adjacent two bored concrete piles there are Gap.
3. Nearby Structure depth according to claim 2 riverbed quaywall supporting construction, which is characterized in that the preceding campshed (1) it is inserted into the hard stratum of river underground with the bottom end of the rear campshed (2).
4. Nearby Structure depth according to claim 1 riverbed quaywall supporting construction, which is characterized in that described pair of support beam (6) cross-sectional area is 80cm × 80cm, and the center spacing of adjacent two described pair of supports beam (6) is 2.5-3.0 meter Yi Gen.
5. Nearby Structure depth according to claim 1 riverbed quaywall supporting construction, which is characterized in that described pair of support beam (6) include concrete river bottom protection layer (41) made of being poured on steel reinforcement cage as concrete, element is equipped with below the concrete river bottom protection layer (41) Concrete bed course (42).
6. Nearby Structure depth according to claim 5 riverbed quaywall supporting construction, which is characterized in that the element concrete bed course (42) lower section is additionally provided with metalling (43) and coarse sand filtering layer (44).
7. Nearby Structure depth according to claim 1 riverbed quaywall supporting construction, which is characterized in that campshed after described (2) the second hanging plate (7) are fixed with higher than the lateral surface of the preceding campshed (1).
8. Nearby Structure depth according to claim 1 riverbed quaywall supporting construction, which is characterized in that several coupling beams (4) it is equipped with above base board (8), is provided with pavement (9) and greenbelt (10), the crown beam on the base board (8) (3) railing (11) being also equipped on the outside of pavement (9).
9. the construction method of Nearby Structure depth riverbed quaywall supporting construction, which comprises the following steps:
1), according to the geological conditions of river two sides, determine that the stake of the bored concrete pile of preceding campshed (1) and rear campshed (2) is long, stake diameter, stake Spacing between spacing, preceding campshed (1) and rear campshed (2), to bored concrete pile, coupling beam (4) and to support beam (6) nodal section size and Stake position is confirmed and is marked;
2) complete by the way of cast-in-situ bored pile according to setting height on stake position after smooth location, according to construction requirement At all bored concrete piles, the stake top of bored concrete pile is reserved with anchor bar, and the height of preceding campshed (1) stake top is lower than rear campshed (2) Stake top height;
3) integrally formed crown beam (3), is poured between the stake top of preceding campshed (1) and preceding campshed (1) and rear campshed (2) and is connected Beam (4) pours between campshed (1) before two several spaced apart to support beam (6);
4) the first hanging plate (5), are installed in the lateral surface of preceding campshed, the second hanging plate (7) are installed in the lateral surface of rear campshed (2).
CN201810559976.0A 2018-06-02 2018-06-02 Nearby Structure depth riverbed quaywall supporting construction and construction method Pending CN109487748A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810559976.0A CN109487748A (en) 2018-06-02 2018-06-02 Nearby Structure depth riverbed quaywall supporting construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810559976.0A CN109487748A (en) 2018-06-02 2018-06-02 Nearby Structure depth riverbed quaywall supporting construction and construction method

Publications (1)

Publication Number Publication Date
CN109487748A true CN109487748A (en) 2019-03-19

Family

ID=65689233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810559976.0A Pending CN109487748A (en) 2018-06-02 2018-06-02 Nearby Structure depth riverbed quaywall supporting construction and construction method

Country Status (1)

Country Link
CN (1) CN109487748A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144784A (en) * 2019-06-13 2019-08-20 福建工程学院 The town road and its construction method constructed based on prestressed concrete plate stake
CN113026659A (en) * 2021-03-19 2021-06-25 江苏顺骁工程科技有限公司 Artificial intelligent wharf quay wall supporting structure and construction method thereof
CN114960729A (en) * 2022-05-11 2022-08-30 浙江省钱塘江管理局勘测设计院 Method for improving fortification standard of existing vertical scour prevention structure of dike foot

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535503A (en) * 2011-12-29 2012-07-04 中国一冶集团有限公司 Method utilizing slow-adhesion prestress concrete beam to prevent large-area terrace sedimentation and cracking in soft soil-layer areas
CN102561380A (en) * 2011-12-29 2012-07-11 中国一冶集团有限公司 Method for preventing settlement and cracking of large-area terrace in soft soil area by adopting unbounded prestressing concrete beams
CN102561381A (en) * 2011-12-29 2012-07-11 中国一冶集团有限公司 Method for preventing settling and cracking of large-area terrace by using bonded prestressed concrete beams in soft soil layer region
CN202936797U (en) * 2012-12-05 2013-05-15 昆明理工大学 Double-row pile supporting structure with inclined struts
CN203583495U (en) * 2013-11-25 2014-05-07 中国建筑股份有限公司 Double-row pile structure by utilization of existing adjoining building slope protection pile
CN104674754A (en) * 2015-03-18 2015-06-03 杭州金培科技有限公司 Novel city watercourse bank protection structure
CN205171532U (en) * 2015-11-25 2016-04-20 河南理工大学 Permanent side slope supporting construction
CN208501613U (en) * 2018-06-02 2019-02-15 深圳市深水水务咨询有限公司 Nearby Structure depth riverbed quaywall supporting construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535503A (en) * 2011-12-29 2012-07-04 中国一冶集团有限公司 Method utilizing slow-adhesion prestress concrete beam to prevent large-area terrace sedimentation and cracking in soft soil-layer areas
CN102561380A (en) * 2011-12-29 2012-07-11 中国一冶集团有限公司 Method for preventing settlement and cracking of large-area terrace in soft soil area by adopting unbounded prestressing concrete beams
CN102561381A (en) * 2011-12-29 2012-07-11 中国一冶集团有限公司 Method for preventing settling and cracking of large-area terrace by using bonded prestressed concrete beams in soft soil layer region
CN202936797U (en) * 2012-12-05 2013-05-15 昆明理工大学 Double-row pile supporting structure with inclined struts
CN203583495U (en) * 2013-11-25 2014-05-07 中国建筑股份有限公司 Double-row pile structure by utilization of existing adjoining building slope protection pile
CN104674754A (en) * 2015-03-18 2015-06-03 杭州金培科技有限公司 Novel city watercourse bank protection structure
CN205171532U (en) * 2015-11-25 2016-04-20 河南理工大学 Permanent side slope supporting construction
CN208501613U (en) * 2018-06-02 2019-02-15 深圳市深水水务咨询有限公司 Nearby Structure depth riverbed quaywall supporting construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144784A (en) * 2019-06-13 2019-08-20 福建工程学院 The town road and its construction method constructed based on prestressed concrete plate stake
CN113026659A (en) * 2021-03-19 2021-06-25 江苏顺骁工程科技有限公司 Artificial intelligent wharf quay wall supporting structure and construction method thereof
CN114960729A (en) * 2022-05-11 2022-08-30 浙江省钱塘江管理局勘测设计院 Method for improving fortification standard of existing vertical scour prevention structure of dike foot

Similar Documents

Publication Publication Date Title
CN105507335B (en) Steel sheet-pile cofferdam foundation pit back cover structure and construction method
CN207760804U (en) A kind of Multi-functional economy dike structure
CN109487748A (en) Nearby Structure depth riverbed quaywall supporting construction and construction method
CN104047222A (en) Bridge structure near mountain and by river and construction method of bridge
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN207211165U (en) A kind of compound antiskid piling wall retaining structure suitable for reservoir stability
CN107700514B (en) Processing method for selecting structural style of soft foundation
CN209854656U (en) Dyke
CN208501613U (en) Nearby Structure depth riverbed quaywall supporting construction
CN108570964B (en) A kind of Ecological Retaining Wall and construction method based on bank slope supporting
CN107326791A (en) The improved method and structure of a kind of overflow bridge
CN113373865B (en) Frame type embankment structure
CN212247670U (en) Structure for controlling railway deep cutting base upwarp
CN213625433U (en) A link up transition structure that is used for gravity type and sheet pile formula combination pier
CN201351279Y (en) Circular deep foundation pit support
CN103821106B (en) Small-sized fishing port and channel revetment structure
CN211872840U (en) Face combination retaining wall structure forever among urban hydraulic engineering
CN113047215A (en) Middle plate pile high pile wharf structure
CN112575777A (en) Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel
CN219908765U (en) Embankment reinforced structure
CN110185048A (en) Deep narrow river valley ultra-deep foundation pit Muddy Bottoms excavate road construction protective slope structure and method
CN215593509U (en) Cutting structure of ballastless track of strong expansion rock section
CN203755241U (en) Small fishing port and riverway revetment structure
CN217630012U (en) Multistage slope supporting construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190319