CN109462278A - A kind of electric system grid switching operation method based on PDA - Google Patents

A kind of electric system grid switching operation method based on PDA Download PDF

Info

Publication number
CN109462278A
CN109462278A CN201810097156.4A CN201810097156A CN109462278A CN 109462278 A CN109462278 A CN 109462278A CN 201810097156 A CN201810097156 A CN 201810097156A CN 109462278 A CN109462278 A CN 109462278A
Authority
CN
China
Prior art keywords
pda
ticket
grid switching
host
switching operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810097156.4A
Other languages
Chinese (zh)
Other versions
CN109462278B (en
Inventor
席俞佳
吴健
高奥
卜鹏
闵倩倩
归宇
陈昱
王涤
章铭
凌秋阳
杨海威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUZHOU ELECTRIC POWER DESIGN INSTITUTE Co Ltd
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
HUZHOU ELECTRIC POWER DESIGN INSTITUTE Co Ltd
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUZHOU ELECTRIC POWER DESIGN INSTITUTE Co Ltd, State Grid Corp of China SGCC, Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical HUZHOU ELECTRIC POWER DESIGN INSTITUTE Co Ltd
Priority to CN201810097156.4A priority Critical patent/CN109462278B/en
Publication of CN109462278A publication Critical patent/CN109462278A/en
Application granted granted Critical
Publication of CN109462278B publication Critical patent/CN109462278B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0075
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of electric system grid switching operation method based on PDA, comprising the following steps: 1, reception scheduling preliminary command, quasi- ticket people fill in scheduling operation task in production management area operation ticket system;2, grid switching operation bill is write, and review operations content is correct;3, operation task and operation order content are sent PDA by operation ticket system;4, positive order is received, control zone monitors five anti-verifications and local operation in real time;5, after operating, the complete operation data that anti-error host system, operation ticket system host can be generated by PDA can read the data in PDA or system at any time;6, return data is filed, Xie Jiami and compression, destruction digital one time intend ticket, terminate process;Papery operation order is replaced using PDA, when avoiding operating under the weather such as sleet, papery operation order is easy moist, damaged;Operating efficiency is improved, maloperation is prevented, improves the safety of power transformation O&M grid switching operation, keeps grid switching operation more intelligent, efficient.

Description

A kind of electric system grid switching operation method based on PDA
Technical field
The present invention relates to power system operation methods, and in particular to a kind of electric system grid switching operation method based on PDA.
Background technique
Electric switching operation is the important link that electric system mode switches, and traditional operation process uses papery job sheet, Process is cumbersome, and control measure are not perfect, and intelligence degree is low, depends on the behavioural norm of operator, Wu Fashi safely Existing whole process is intelligently managed.Main flow is as follows: step 1: receiving scheduling preliminary command, filling in operation order;Step 2: review operations Ticket is correct;Step 3: clearly operating purpose, Analysis about Dangerous Point and pre-control are carried out step 4: receiving scheduling positive order, simulation previews; Step 5: checking apparatus name and state;It rehearses operation step 6: calling out the names of those voted for while counting ballot-slips item by item and hooks ticket;Step 7: to scheduling reporting operations End and time;Step 8: correction chart board, label pin operation order, check evaluation.
Chinese publication CN 105511409A, publication date 2014-09-23 days, a kind of entitled substation from The method that controls and operates of dynamicization discloses a kind of electric substation automation system and controls and operates method, by the artificial behaviour of operation order Work changes to be realized by Computerized intelligent, is controlled by intelligence, is operated equipment.Generic operation each in Substation Operating is compiled in advance It collects into intelligent operation ticket, downloads in execute server: operation in pure interval is downloaded in wall smart machine;It is right In then being downloaded to across interval operation in special intelligent operation server.In substation operation, if the generic operation need to be carried out, Then through background monitoring interface or dispatching terminal in the way of remote control, order is executed to execute server transmission, by executing service Device is automatically performed a series of grid switching operation.Electric substation automation system of the invention controls and operates method, by operation order Manual operation changes to be realized by Computerized intelligent.Operating efficiency is improved, reduce or is prevented because of maloperation caused by artificial origin, Improve the safety operation level of substation.
But its shortcoming is that complete intelligence system operation can only be generated mistake and be not easy by background monitoring, monitoring process It searches.
Summary of the invention
Intelligent operation equipment background monitoring is based on the present invention be directed to existing scheme to be not easy to monitor, and devises a kind of intelligence The mode of operation that operation and artificial detection combine.
A kind of electric system grid switching operation method based on PDA, comprising the following steps:
M1, receives scheduling preliminary command, and quasi- ticket people fills in scheduling operation task in production management area operation ticket system;
M2 writes grid switching operation bill, and review operations content is correct;
Operation task and operation order content are sent PDA by M3, operation ticket system;
M4, receives positive order, and control zone monitors five anti-verifications and local operation in real time;
M5, after operation, the complete operation data that anti-error host system, operation ticket system host can be generated by PDA can To read the data in PDA or system at any time;
M6 files return data, Xie Jiami and compression, destruction digital one time intend ticket, terminate process.
Preferably, the step M2, including following sub-step:
A1 carries out first system debug, formulates Risk Pre-control rule base;
A2, operation ticket system encrypt operation task and operation order content;
Encrypted content is generated two dimensional code by A3, operation ticket system, so that PDA is obtained encrypted content by PDA scanning;
A4, PDA carry out solution encryption and obtain anti-error host service function ticket data.
Preferably, the step M3, including following sub-step:
B1, the simulation preview operation on anti-error host;
B2, anti-error host carry out latching logic judgement to each single item simulated operation, correct simulated operation content are generated practical Operation sequence;
The two dimensional code that the anti-host of B3, PDA scanning five generates, receives practical operation program;
B4, anti-error host opening operation lock.
Preferably, the step M4, including following sub-step:
C1 inputs the relevant informations such as people, time of issuing an order of issuing an order, and is handed over to operator's verification;
C2, personal information confirmation, confirms errorless carry out C3, wrong interrupt operation process;
C3, PDA are communicated to connect by bluetooth and error prevention key;
C4 opens recording system;
C5, PDA control error prevention key and operate five anti-locksets;
C6, back delivery operations information and recording after the completion of operation.
Preferably, the step B2, including following sub-step:
B21 starts simulated operation, detects to primary equipment state change;
B22 simulate and detect to secondary device state change;
B23 detects the ground line selection operation of a secondary device, not if there is the occupied or voltage class of ground line Matching then executes B24, and ground line is errorless, executes B25;
B24, label choose ground line be it is unavailable, again choose be grounded and execute B23;
B25 carries out real-time status detection to a secondary device, does not meet in PDA if state and does not pass through if setting logic state, Terminate process;
B26 carries out self-test to the anti-misoperation locking logic of anti-error host, excellent by logic when setting logic has conflict in logical AND PDA First value is distinguished, if anti-misoperation locking Logic Priority value is greater than setting logic in PDA and jumps to B27, otherwise jumps to B28, errorless Jump to B29;
B27, pausing operation, and upload anti-misoperation locking logic and audited, by then jumping to B29, not by then jumping to B28;
B28 terminates this operation;
B29 completes anti-error host simulated operation, generates data.
This programme can be while monitoring primary equipment to the real-time state monitoring of secondary device;According in operation order Hold, automatic imitation simultaneously verifies a secondary device state change, and intelligence chooses ground line, it is ensured that operation content is correct;According to risk Pre-control item rule base automatically generates the Risk Pre-control information of the operation task, and it is pre- to increase specific risk for certain particular devices Control item;Operation order automatically generates managing security tools and instruments information, extracts corresponding ground line, operational instrument as required;Tablet computer passes through Bluetooth is communicated with error prevention key, realizes a secondary device anti-misoperation, sound-recording function is automatically turned in implementation procedure, realize back brake Operate overall process recording, dangerous point voice real-time prompting;After operation, again by two dimensional code back delivery operations information, automatically Complete operation note filing;It is automatic to realize operation information statistical analysis and the analysis of operation order automatic Evaluation;
Substantial effect of the invention is to replace papery operation order, when avoiding operating under the bad weathers such as sleet, paper using PDA Matter operation order is easy moist, damaged;Effectively avoid leapfrog, leakage step, few ticking;Anti-error technology control is realized on safety benefit All standing and grid switching operation process are entirely intelligent, and grid switching operation is realized in economic benefit with no paper at all and auxiliary tool is integrated, Production cost is greatly saved, operating efficiency is improved, prevents maloperation, improve the safety of power transformation O&M grid switching operation, it is rich Rich site safety control means, keep grid switching operation safer, intelligent, efficient.
Detailed description of the invention
Fig. 1 system schematic.
Specific embodiment
Below by specific embodiment, and in conjunction with attached drawing, technical scheme of the present invention will be further explained in detail.
Embodiment 1
As shown in Figure 1, a kind of electric system grid switching operation method based on PDA, comprising the following steps:
M1, receives scheduling preliminary command, and quasi- ticket people fills in scheduling operation task in production management area operation ticket system;
M2 writes grid switching operation bill, and review operations content is correct;
Operation task and operation order content are sent PDA by M3, operation ticket system;
M4, receives positive order, and control zone monitors five anti-verifications and local operation in real time;
M5, after operation, the complete operation data that anti-error host system, operation ticket system host can be generated by PDA can To read the data in PDA or system at any time;
M6 files return data, Xie Jiami and compression, destruction digital one time intend ticket, terminate process.
According to operation order content, automatic imitation simultaneously verifies a secondary device state change, and intelligence chooses ground line, it is ensured that behaviour It is correct to make content.
The step M2, including following sub-step:
A1 carries out first system debug, formulates Risk Pre-control rule base;
A2, operation ticket system encrypt operation task and operation order content;
Encrypted content is generated two dimensional code by A3, operation ticket system, so that PDA is obtained encrypted content by PDA scanning;
A4, PDA carry out solution encryption and obtain anti-error host service function ticket data.
According to Risk Pre-control item rule base, the Risk Pre-control information of the operation task is automatically generated, is certain particular devices Increase specific Risk Pre-control item;Operation order automatically generates managing security tools and instruments information, extracts corresponding ground line, operative employee as required Tool.
The step M3, including following sub-step:
B1, the simulation preview operation on anti-error host;
B2, anti-error host carry out latching logic judgement to each single item simulated operation, correct simulated operation content are generated practical Operation sequence;
The two dimensional code that the anti-host of B3, PDA scanning five generates, receives practical operation program;
B4, anti-error host opening operation lock.
The step M4, including following sub-step:
C1 inputs the relevant informations such as people, time of issuing an order of issuing an order, and is handed over to operator's verification;
C2, personal information confirmation, confirms errorless carry out C3, wrong interrupt operation process;
C3, PDA are communicated to connect by bluetooth and error prevention key;
C4 opens recording system;
C5, PDA control error prevention key and operate five anti-locksets;
C6, back delivery operations information and recording after the completion of operation.
The step B2, including following sub-step:
B21 starts simulated operation, detects to primary equipment state change;
B22 simulate and detect to secondary device state change;
B23 detects the ground line selection operation of a secondary device, not if there is the occupied or voltage class of ground line Matching then executes B24, and ground line is errorless, executes B25;
B24, label choose ground line be it is unavailable, again choose be grounded and execute B23;
B25 carries out real-time status detection to a secondary device, does not meet in PDA if state and does not pass through if setting logic state, Terminate process;
B26 carries out self-test to the anti-misoperation locking logic of anti-error host, excellent by logic when setting logic has conflict in logical AND PDA First value is distinguished, if anti-misoperation locking Logic Priority value is greater than setting logic in PDA and jumps to B27, otherwise jumps to B28, errorless Jump to B29;
B27, pausing operation, and upload anti-misoperation locking logic and audited, by then jumping to B29, not by then jumping to B28;
B28 terminates this operation;
B29 completes anti-error host simulated operation, generates data.
Intelligence chooses ground line, avoids earthing failure.

Claims (5)

1. a kind of electric system grid switching operation method based on PDA, which comprises the following steps:
M1, receives scheduling preliminary command, and quasi- ticket people fills in scheduling operation task in production management area operation ticket system;
M2 writes grid switching operation bill, and review operations content is correct;
Operation task and operation order content are sent PDA by M3, operation ticket system;
M4, receives positive order, and control zone monitors five anti-verifications and local operation in real time;
M5, after operation, the complete operation data that anti-error host system, operation ticket system host can be generated by PDA can To read the data in PDA or system at any time;
M6 files return data, Xie Jiami and compression, destruction digital one time intend ticket, terminate process.
2. a kind of electric system grid switching operation method based on PDA according to claim 1, which is characterized in that described Step M2, including following sub-step:
A1 carries out first system debug,Formulate Risk Pre-control rule base;
A2, operation ticket system encrypt operation task and operation order content;
Encrypted content is generated two dimensional code by A3, operation ticket system, so that PDA is obtained encrypted content by PDA scanning;
A4, PDA carry out solution encryption and obtain anti-error host service function ticket data.
3. a kind of electric system grid switching operation method based on PDA according to claim 1, which is characterized in that described Step M3, including following sub-step:
B1, the simulation preview operation on anti-error host;
B2, anti-error host carry out latching logic judgement to each single item simulated operation, correct simulated operation content are generated practical Operation sequence;
The two dimensional code that the anti-host of B3, PDA scanning five generates, receives practical operation program;
B4, anti-error host opening operation lock.
4. a kind of electric system grid switching operation method based on PDA according to claim 1, which is characterized in that described Step M4, including following sub-step:
C1 inputs the relevant informations such as people, time of issuing an order of issuing an order, and is handed over to operator's verification;
C2, personal information confirmation, confirms errorless carry out C3, wrong interrupt operation process;
C3, PDA are communicated to connect by bluetooth and error prevention key;
C4 opens recording system;
C5, PDA control error prevention key and operate five anti-locksets;
C6, back delivery operations information and recording after the completion of operation.
5. a kind of electric system grid switching operation method based on PDA according to claim 3, which is characterized in that described Step B2, including following sub-step:
B21 starts simulated operation, detects to primary equipment state change;
B22 simulate and detect to secondary device state change;
B23 detects the ground line selection operation of a secondary device, not if there is the occupied or voltage class of ground line Matching then executes B24, and ground line is errorless, executes B25;
B24, label choose ground line be it is unavailable, again choose be grounded and execute B23;
B25 carries out real-time status detection to a secondary device, does not meet in PDA if state and does not pass through if setting logic state, Terminate process;
B26 carries out self-test to the anti-misoperation locking logic of anti-error host, excellent by logic when setting logic has conflict in logical AND PDA First value is distinguished, if anti-misoperation locking Logic Priority value is greater than setting logic in PDA and jumps to B27, otherwise jumps to B28, errorless Jump to B29;
B27, pausing operation, and upload anti-misoperation locking logic and audited, by then jumping to B29, not by then jumping to B28;
B28 terminates this operation;
B29 completes anti-error host simulated operation, generates data.
CN201810097156.4A 2018-01-31 2018-01-31 Power system switching operation method based on PDA Active CN109462278B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810097156.4A CN109462278B (en) 2018-01-31 2018-01-31 Power system switching operation method based on PDA

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810097156.4A CN109462278B (en) 2018-01-31 2018-01-31 Power system switching operation method based on PDA

Publications (2)

Publication Number Publication Date
CN109462278A true CN109462278A (en) 2019-03-12
CN109462278B CN109462278B (en) 2021-01-05

Family

ID=65606231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810097156.4A Active CN109462278B (en) 2018-01-31 2018-01-31 Power system switching operation method based on PDA

Country Status (1)

Country Link
CN (1) CN109462278B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110620435A (en) * 2019-10-25 2019-12-27 宁夏京能宁东发电有限责任公司 Management system of temporary grounding wire
CN112488644A (en) * 2020-11-24 2021-03-12 南方电网调峰调频发电有限公司鲁布革水力发电厂 Intelligent management system and method for valve operation of hydraulic power plant
CN113112161A (en) * 2021-04-19 2021-07-13 贵州电网有限责任公司 Operation ticket interaction method of anti-misoperation locking system and 6+1 system
CN113177404A (en) * 2021-03-30 2021-07-27 宁波万德高科智能科技有限公司 Electric power five-prevention logic verification method
CN113794754A (en) * 2021-08-25 2021-12-14 国网福建省电力有限公司 Electronic operation ticket control system and method based on mobile application
CN113822271A (en) * 2021-11-24 2021-12-21 广东电网有限责任公司惠州供电局 Ticket surface identification and sorting method, device, system and medium for power grid transformation operation ticket

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102073305A (en) * 2009-11-24 2011-05-25 广东电网公司中山供电局 Cross-platform power grid intelligent program-controlled error-preventing system and operation method and interface communication way
CN105515016A (en) * 2015-12-08 2016-04-20 中国电力科学研究院 Simulation verification method for low frequency oscillation controller
CN107276989A (en) * 2017-05-19 2017-10-20 中国神华能源股份有限公司 The method and system operated for management equipment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102073305A (en) * 2009-11-24 2011-05-25 广东电网公司中山供电局 Cross-platform power grid intelligent program-controlled error-preventing system and operation method and interface communication way
CN102073305B (en) * 2009-11-24 2012-12-05 广东电网公司中山供电局 Cross-platform power grid intelligent program-controlled error-preventing system and operation method and interface communication way
CN105515016A (en) * 2015-12-08 2016-04-20 中国电力科学研究院 Simulation verification method for low frequency oscillation controller
CN107276989A (en) * 2017-05-19 2017-10-20 中国神华能源股份有限公司 The method and system operated for management equipment

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110620435A (en) * 2019-10-25 2019-12-27 宁夏京能宁东发电有限责任公司 Management system of temporary grounding wire
CN110620435B (en) * 2019-10-25 2023-08-11 宁夏京能宁东发电有限责任公司 Management system of temporary grounding wire
CN112488644A (en) * 2020-11-24 2021-03-12 南方电网调峰调频发电有限公司鲁布革水力发电厂 Intelligent management system and method for valve operation of hydraulic power plant
CN113177404A (en) * 2021-03-30 2021-07-27 宁波万德高科智能科技有限公司 Electric power five-prevention logic verification method
CN113112161A (en) * 2021-04-19 2021-07-13 贵州电网有限责任公司 Operation ticket interaction method of anti-misoperation locking system and 6+1 system
CN113794754A (en) * 2021-08-25 2021-12-14 国网福建省电力有限公司 Electronic operation ticket control system and method based on mobile application
CN113822271A (en) * 2021-11-24 2021-12-21 广东电网有限责任公司惠州供电局 Ticket surface identification and sorting method, device, system and medium for power grid transformation operation ticket

Also Published As

Publication number Publication date
CN109462278B (en) 2021-01-05

Similar Documents

Publication Publication Date Title
CN109462278A (en) A kind of electric system grid switching operation method based on PDA
CN109617241B (en) Intelligent sequential control system and method based on panoramic data in transformer substation
CN106157167B (en) Secondary equipment remote control operation ticket system and implementation method of secondary equipment remote control operation ticket
CN100508091C (en) Intelligent remote control locking method and apparatus for preventing electric misoperation
CN110428533B (en) Intelligent lockset management system for realizing integration of misoperation-preventive lock control based on Internet of things
CN107546854B (en) Transformer substation pressure plate anti-misoperation method and device
CN103389705A (en) Operation monitoring system and method
CN103593742A (en) Secondary circuit configuration controlling method and system for intelligent substation
CN110829595B (en) Intelligent power station relay protection equipment overhaul safety isolation measure execution method and system
CN111106671B (en) Five-prevention management control method and system for substation coded lock
CN110568284B (en) Intelligent substation one-key sequential control automatic test verification method, device and system
CN101207280A (en) Method and device of intelligent calibration for power system relay protection
CN108508877A (en) A kind of T-BOX test devices and test method
CN105069587A (en) Mobile Internet-based relay protection verification device
CN113343446B (en) Data analysis and verification method and system for transformer substation monitoring system
CN105207366A (en) IEC61850-based power distribution terminal, namely plug and play model configuration tool and realization method of IEC61850-based power distribution terminal
CN109146253A (en) A kind of intelligent automatic interactive operating system for making out an invoice and protecting locking
CN114330764A (en) Operation ticket processing method and device, storage medium and electronic device
CN107977311B (en) Method and system for automatically detecting information safety of power distribution terminal
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN106227630A (en) A kind of detecting system for embedded radio module
CN111583465A (en) Intelligent key working method for electric power switching operation
CN205539239U (en) Testing device
CN105321126A (en) SCD-based method for checking intelligent substation device
CN206058696U (en) Realize the FPGA brassboards of independent debugging checking

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant