CN109457979A - Prefabricated board lifts rock-steady structure and method - Google Patents

Prefabricated board lifts rock-steady structure and method Download PDF

Info

Publication number
CN109457979A
CN109457979A CN201811586594.3A CN201811586594A CN109457979A CN 109457979 A CN109457979 A CN 109457979A CN 201811586594 A CN201811586594 A CN 201811586594A CN 109457979 A CN109457979 A CN 109457979A
Authority
CN
China
Prior art keywords
prefabricated board
jacking
lifts
rock
framed bent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811586594.3A
Other languages
Chinese (zh)
Inventor
吴赟栋
毛子成
熊玎玮
施智亮
张丽骏
马文浩
唐健
唐天宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201811586594.3A priority Critical patent/CN109457979A/en
Publication of CN109457979A publication Critical patent/CN109457979A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention provides a kind of prefabricated board lifting rock-steady structure and methods, the present invention is available when prefabricated board independently supports and is not able to satisfy its requirement for height, framed bent steel pipe on the outside of precast beam prepares jacking, crossbeam is configured on jacking, it is made to link into an integrated entity, jacking extends at the absolute altitude of prefabricated board bottom height, the full hall scaffold set up needed for saving in traditional handicraft and take tear framed bent open needed for the time, saved cost and shortened the duration.The present invention can shorten the construction period under the premise of guaranteeing safety and quality, reduce cost.

Description

Prefabricated board lifts rock-steady structure and method
Technical field
The present invention relates to a kind of prefabricated board lifting rock-steady structure and methods.
Background technique
Existing prefabricated board lifts rock-steady structure, is all using the support construction for being independently used for prefabricated board, this support knot The setting of structure will lead to construction period length, problem at high cost.
Summary of the invention
The purpose of the present invention is to provide a kind of prefabricated board lifting rock-steady structure and methods, are able to solve existing prefabricated board Support construction existing for the construction period is long, problem at high cost.
To solve the above problems, the present invention provides a kind of prefabricated board lifting rock-steady structure, comprising:
It is set to the framed bent steel pipe of the support precast beam in the outside of precast beam;
It is connected to the jacking of the framed bent steel pipe top;
The crossbeam being connected on the jacking, the cross beam support is in the lower part of prefabricated board.
Further, in said structure, it between the gap of the lower part of the crossbeam and the prefabricated board, is additionally provided with and carves Shape wood particle.
Further, in said structure, the adjusting bolt of jacking length is provided on the jacking.
Further, in said structure, the prefabricated board SP is prestressed cored slab.
Further, in said structure, the horizontal spacing between adjacent crossbeam is no more than 0.8 meter.
Another side according to the present invention provides a kind of prefabricated board lifting antihunt means, comprising:
In the framed bent steel pipe of the outside of precast beam setting support precast beam;
Jacking is connected in the framed bent steel pipe top;
The connecting cross beam on the jacking, the cross beam support is in the lower part of prefabricated board.
Further, in the above-mentioned methods, the connecting cross beam on the jacking, the cross beam support is in the lower part of prefabricated board Later, further includes:
Wedge wood particle is set between the gap of the lower part of the crossbeam and the prefabricated board.
Further, in the above-mentioned methods, after the framed bent steel pipe top connects jacking, further includes:
The adjusting bolt of jacking length is provided on the jacking.
Further, in the above-mentioned methods, the prefabricated board SP is prestressed cored slab.
Further, in the above-mentioned methods, on the jacking in connecting cross beam,
The horizontal spacing between adjacent crossbeam is set to be no more than 0.8 meter.
Compared with prior art, the present invention is available when prefabricated board independently supports and is not able to satisfy its requirement for height, prefabricated Framed bent steel pipe on the outside of beam prepares jacking, configures crossbeam on jacking, so that it is linked into an integrated entity, jacking extends to prefabricated board bottom height Absolute altitude at, the full hall scaffold set up needed for saving in traditional handicraft and take tear framed bent open needed for the time, saved cost And shorten the duration.The present invention can shorten the construction period under the premise of guaranteeing safety and quality, reduce cost.
Detailed description of the invention
Fig. 1 is the schematic diagram of the prefabricated board lifting rock-steady structure of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
As shown in Figure 1, the present invention provides a kind of prefabricated board lifting rock-steady structure, comprising:
It is set to the framed bent steel pipe 2 of the support precast beam in the outside of precast beam 1;
It is connected to the jacking 3 at 2 top of framed bent steel pipe;
The crossbeam 4 being connected on the jacking 3, the crossbeam 4 are supported in the lower part of prefabricated board 5.
Here, the precast beam can be PC beam.
The present invention is available when prefabricated board independently supports and is not able to satisfy its requirement for height, the framed bent steel pipe on the outside of precast beam Jacking is prepared, crossbeam is configured on jacking, so that it is linked into an integrated entity, jacking extends at the absolute altitude of prefabricated board bottom height, saves The full hall scaffold set up needed in traditional handicraft and take tear framed bent open needed for the time, saved cost and shortened the duration.This Invention can shorten the construction period under the premise of guaranteeing safety and quality, reduce cost.
In prefabricated board lifting one embodiment of rock-steady structure of the invention, the gap of the lower part of the crossbeam and the prefabricated board Between, it is additionally provided with wedge wood particle.
Here, being embedded in adjustment plate horizontal position using wedge wood particle, do not adjusted using crowbar directly, in order to avoid there are edges of boards Damage.
In prefabricated board lifting one embodiment of rock-steady structure of the invention, the adjusting spiral shell of jacking length is provided on the jacking Bolt.
Here, framed bent steel pipe precast beam on the outside of available when prefabricated board independently supports and is not able to satisfy its requirement for height Jacking is prepared, crossbeam is configured on jacking, so that it is linked into an integrated entity, be adjusted to using bolt at the absolute altitude of prefabricated board bottom height.
In prefabricated board lifting one embodiment of rock-steady structure of the invention, the prefabricated board SP is prestressed cored slab.
Here, flexibility is bigger using SP prestressed cored slab, be able to satisfy to the punching of plate, be open, plate end cantilever or There are a variety of situations such as larger concentrated stress load requirement.
In prefabricated board lifting one embodiment of rock-steady structure of the invention, the horizontal spacing between adjacent crossbeam is no more than 0.8 meter, to guarantee the stability to the lower support of prefabricated board.
Another side according to the present invention provides a kind of prefabricated board lifting antihunt means, comprising:
In the framed bent steel pipe of the outside of precast beam setting support precast beam;
Jacking is connected in the framed bent steel pipe top;
The connecting cross beam on the jacking, the cross beam support is in the lower part of prefabricated board.
Here, the precast beam can be PC beam.
The present invention is available when prefabricated board independently supports and is not able to satisfy its requirement for height, the framed bent steel pipe on the outside of precast beam Jacking is prepared, crossbeam is configured on jacking, so that it is linked into an integrated entity, jacking extends at the absolute altitude of prefabricated board bottom height, saves The full hall scaffold set up needed in traditional handicraft and take tear framed bent open needed for the time, saved cost and shortened the duration.This Invention can shorten the construction period under the premise of guaranteeing safety and quality, reduce cost.
Further, in the above-mentioned methods, the connecting cross beam on the jacking, the cross beam support is in the lower part of prefabricated board Later, further includes:
Wedge wood particle is set between the gap of the lower part of the crossbeam and the prefabricated board.
Here, being embedded in adjustment plate horizontal position using wedge wood particle, do not adjusted using crowbar directly, in order to avoid there are edges of boards Damage.
Further, in the above-mentioned methods, after the framed bent steel pipe top connects jacking, further includes:
The adjusting bolt of jacking length is provided on the jacking.
Here, framed bent steel pipe precast beam on the outside of available when prefabricated board independently supports and is not able to satisfy its requirement for height Jacking is prepared, crossbeam is configured on jacking, so that it is linked into an integrated entity, be adjusted to using bolt at the absolute altitude of prefabricated board bottom height.
Further, in the above-mentioned methods, the prefabricated board SP is prestressed cored slab.
Here, flexibility is bigger using SP prestressed cored slab, be able to satisfy to the punching of plate, be open, plate end cantilever or There are a variety of situations such as larger concentrated stress load requirement.
Further, in the above-mentioned methods, on the jacking in connecting cross beam,
It sets the horizontal spacing between adjacent crossbeam to be no more than 0.8 meter, to guarantee the lower support to prefabricated board Stability.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the invention is also intended to include including these modification and variations.

Claims (10)

1. a kind of prefabricated board lifts rock-steady structure characterized by comprising
It is set to the framed bent steel pipe of the support precast beam in the outside of precast beam;
It is connected to the jacking of the framed bent steel pipe top;
The crossbeam being connected on the jacking, the cross beam support is in the lower part of prefabricated board.
2. prefabricated board as described in claim 1 lifts rock-steady structure, which is characterized in that under the crossbeam and the prefabricated board Between the gap in portion, it is additionally provided with wedge wood particle.
3. prefabricated board as described in claim 1 lifts rock-steady structure, which is characterized in that be provided with jacking length on the jacking Adjusting bolt.
4. prefabricated board as described in claim 1 lifts rock-steady structure, which is characterized in that the prefabricated board SP is pre-stress hollow Plate.
5. prefabricated board as described in claim 1 lifts rock-steady structure, which is characterized in that the horizontal spacing between adjacent crossbeam No more than 0.8 meter.
6. a kind of prefabricated board lifts antihunt means characterized by comprising
In the framed bent steel pipe of the outside of precast beam setting support precast beam;
Jacking is connected in the framed bent steel pipe top;
The connecting cross beam on the jacking, the cross beam support is in the lower part of prefabricated board.
7. prefabricated board as claimed in claim 6 lifts antihunt means, which is characterized in that the connecting cross beam on the jacking, institute Cross beam support is stated after the lower part of prefabricated board, further includes:
Wedge wood particle is set between the gap of the lower part of the crossbeam and the prefabricated board.
8. prefabricated board as claimed in claim 6 lifts antihunt means, which is characterized in that connect and push up in the framed bent steel pipe top After support, further includes:
The adjusting bolt of jacking length is provided on the jacking.
9. prefabricated board as claimed in claim 6 lifts antihunt means, which is characterized in that the prefabricated board SP is pre-stress hollow Plate.
10. prefabricated board as claimed in claim 6 lifts antihunt means, which is characterized in that on the jacking in connecting cross beam,
The horizontal spacing between adjacent crossbeam is set to be no more than 0.8 meter.
CN201811586594.3A 2018-12-25 2018-12-25 Prefabricated board lifts rock-steady structure and method Pending CN109457979A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811586594.3A CN109457979A (en) 2018-12-25 2018-12-25 Prefabricated board lifts rock-steady structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811586594.3A CN109457979A (en) 2018-12-25 2018-12-25 Prefabricated board lifts rock-steady structure and method

Publications (1)

Publication Number Publication Date
CN109457979A true CN109457979A (en) 2019-03-12

Family

ID=65615049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811586594.3A Pending CN109457979A (en) 2018-12-25 2018-12-25 Prefabricated board lifts rock-steady structure and method

Country Status (1)

Country Link
CN (1) CN109457979A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3048043A1 (en) * 1980-12-19 1982-07-15 Österreichische Doka Schalungs- und Gerüstungstechnik GmbH, 3300 Amstetten Ceiling formwork support structure - has folding legs swinging and set at angle round telescopic upright
CN202380722U (en) * 2011-12-31 2012-08-15 青建集团股份公司 Steel tube formwork supporting system
CN204663030U (en) * 2015-04-17 2015-09-23 中国十七冶集团有限公司 Assembled-type house precast floor slab installation sectional shelf-unit
CN105442833A (en) * 2015-12-30 2016-03-30 大连三川建筑科技有限公司 Cast-in-situ template reinforcing device of T-shaped connection position between external assembly walls and internal cast-in-situ wall
CN106284985A (en) * 2016-09-09 2017-01-04 五冶集团上海有限公司 A kind of Formwork Installation Method of reserved post-cast strip
CN206385802U (en) * 2016-12-30 2017-08-08 陕西华邦建设工程有限公司 A kind of steel construction high residential building cast-in-place concrete floor steel wood mixing supporting construction
CN207277541U (en) * 2017-10-23 2018-04-27 浙江展诚建设集团股份有限公司 Prefabricated component and cast-in-place column assembled integral concrete frame structure
CN209538709U (en) * 2018-12-25 2019-10-25 上海建工五建集团有限公司 Prefabricated board lifts rock-steady structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3048043A1 (en) * 1980-12-19 1982-07-15 Österreichische Doka Schalungs- und Gerüstungstechnik GmbH, 3300 Amstetten Ceiling formwork support structure - has folding legs swinging and set at angle round telescopic upright
CN202380722U (en) * 2011-12-31 2012-08-15 青建集团股份公司 Steel tube formwork supporting system
CN204663030U (en) * 2015-04-17 2015-09-23 中国十七冶集团有限公司 Assembled-type house precast floor slab installation sectional shelf-unit
CN105442833A (en) * 2015-12-30 2016-03-30 大连三川建筑科技有限公司 Cast-in-situ template reinforcing device of T-shaped connection position between external assembly walls and internal cast-in-situ wall
CN106284985A (en) * 2016-09-09 2017-01-04 五冶集团上海有限公司 A kind of Formwork Installation Method of reserved post-cast strip
CN206385802U (en) * 2016-12-30 2017-08-08 陕西华邦建设工程有限公司 A kind of steel construction high residential building cast-in-place concrete floor steel wood mixing supporting construction
CN207277541U (en) * 2017-10-23 2018-04-27 浙江展诚建设集团股份有限公司 Prefabricated component and cast-in-place column assembled integral concrete frame structure
CN209538709U (en) * 2018-12-25 2019-10-25 上海建工五建集团有限公司 Prefabricated board lifts rock-steady structure

Similar Documents

Publication Publication Date Title
CN107313589A (en) Outer wall of basement one side steel form support system and its construction method
CN106192758A (en) A kind of construction method utilizing the cantilever form large-scale high pier stud of construction
JP5045214B2 (en) Column head construction method
CN106884541B (en) Positioning assembly, positioning device and positioning method for reserved dowel bars in shear wall
CN203594213U (en) Flexible assembling and disassembling bearing truss
CN105714683A (en) Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames
CN110093977A (en) Prefabricated component mounting structure and its installation method
CN108517961A (en) A kind of direct insertion installation node of quick assembling beam column of steel structure and its installation method
CN107687254A (en) A kind of concrete disjunctor group storehouse slip form construction device and construction method
CN110820565A (en) Suspended casting method for corrugated steel web hanging basket
CN209538709U (en) Prefabricated board lifts rock-steady structure
CN110820566A (en) Corrugated steel web part bearing type hanging basket suspension casting construction method
CN111851317B (en) Method for installing arch ring of arch bridge
CN109457814A (en) Towering and major diameter building top cover construction method based on Bailey bracket structure
CN109457979A (en) Prefabricated board lifts rock-steady structure and method
CN105442453A (en) Construction method for suspension bridge tower crossbeam combination support
CN110043035B (en) Post-cast strip construction supporting method
JP6905556B2 (en) Truss bridge member replacement method and replacement method
CN107152112A (en) A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region
JP2924626B2 (en) Bridge pier construction method by self-elevating formwork method
JP2010255204A (en) Method for erecting precast member
JP6632157B2 (en) Replacement method of truss structure members
CN110820567A (en) Bearing type hanging basket for PC box girder part with corrugated steel web plate
CN105715046A (en) Steel and wood template component and construction method thereof
CN102926537A (en) Method and device for fixing root of external wall formwork

Legal Events