CN109457870A - A kind of concrete-filled double skin steel tube colossal column and its construction method - Google Patents

A kind of concrete-filled double skin steel tube colossal column and its construction method Download PDF

Info

Publication number
CN109457870A
CN109457870A CN201811611358.2A CN201811611358A CN109457870A CN 109457870 A CN109457870 A CN 109457870A CN 201811611358 A CN201811611358 A CN 201811611358A CN 109457870 A CN109457870 A CN 109457870A
Authority
CN
China
Prior art keywords
double
crotch
steel
steel plate
way opposed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811611358.2A
Other languages
Chinese (zh)
Other versions
CN109457870B (en
Inventor
丁发兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201811611358.2A priority Critical patent/CN109457870B/en
Publication of CN109457870A publication Critical patent/CN109457870A/en
Application granted granted Critical
Publication of CN109457870B publication Critical patent/CN109457870B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/36Columns; Pillars; Struts of materials not covered by groups E04C3/32 or E04C3/34; of a combination of two or more materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

A kind of concrete-filled double skin steel tube colossal column and its construction method, concrete-filled double skin steel tube colossal column include to drawing stirrup, rectangular steel pipe, concrete, elevator & stairs and door opening.Both ends part bending to stirrup is drawn, and with rectangular steel pipe inner wall is tangent is arranged, be fixed by welding on steel pipe inner wall, pour high-strength concrete between the rectangular steel pipe then placed with one heart at two.Bearing capacity of the present invention is high, Hysteresis Behavior is good, anti-side rigidity is big, ductility is good, reasonable stress, concrete-filled double skin steel tube colossal column easy for construction, from heavy and light, both the not sufficiently effective defect of steel tube confinement had been compensated for, difficulty when can greatly reduce thickness of steel pipe again, thick steel plate being avoided to weld, the problem of mammoth structure vertical transportation is also solved simultaneously, is suitable for high building structure.

Description

A kind of concrete-filled double skin steel tube colossal column and its construction method
Technical field
The present invention relates to technical field of buildings, specially a kind of concrete-filled double skin steel tube colossal column and its construction party Method.
Background technique
As building function is intended to diversification and synthesization development, the trend of world's Development of High-rise Buildings is competitively to release Height is more than the huge structure of the super high-rise building and the skyscraper for meeting some specific functions of 500m.Giant frame structure is As a kind of new and effective Lateral Resistant System for adapting to super high-rise building development.It by as main structure giant frame structure and Floor frame as secondary structure forms.Mega-frame is main Lateral Resistant System, and floor frame only plays booster action and big Energy consumption effect under shake, and be responsible for flooring vertical load passing to main frame.Since the column of secondary structure is away from small, load is small, because And its beam, column section can be made very small, and be conducive to the reasonable employment of flooring.It can be seen that mammoth structure is a kind of with huge The large scale structure system of big lateral rigidity and integral working.
It is lateral to subject huge vertical load and earthquake, wind etc. as giant frame structure vertical member for colossal column Load action, colossal column have that good tension is bent and ability is turned round in shearing resistance, and colossal column is due to the advantages of its own and feature, It is increasingly taken seriously, and is increasingly being applied to engineering reality.The steel reinforced concrete generallyd use in engineering at present is huge Type column and concrete filled steel tube colossal column have in place of following technical deficiency: 1. huge column cross-section sizes are big, according to steel reinforced concrete Structure must take the strong ties mode of overall height, avoid the occurrence of similar according to correlation test conclusion between each isolated reinforcing bar in column The arrangement of the separate type of lattice column, it is ensured that the thus whole ductility of column will generate a large amount of stirrup bindings, template support work, no Just it constructs;2. the characteristics of concrete filled steel tube colossal column is due to section form, concrete of the section close to centroid position can not be mentioned For how many bending stiffness, bending stiffness and anti-bending bearing capacity are lower, while concrete filled steel tube colossal column node construction is complicated, limit Its application is made.
Therefore, research and develop a kind of economical and practical, concrete-filled double skin steel tube colossal column structure type easy for construction has Highly important practice significance and social economic value.
Summary of the invention
The present invention solves the deficiencies in the prior art and provides that a kind of bearing capacity is high, anti-seismic performance is good, anti-side rigidity is big Concrete-filled double skin steel tube colossal column and its construction method, the present invention accept rationally, from heavy and light, easy for construction, both solved The not sufficiently effective problem of steel tube confinement, and difficulty when can greatly reduce thickness of steel pipe, thick steel plate being avoided to weld, while also solving The problem of mammoth structure of having determined vertical transportation is suitable for high building structure.
To achieve the goals above, the present invention adopts the following technical scheme:
A kind of concrete-filled double skin steel tube colossal column, including interior rectangle steel pipe column, it is coaxially mounted to interior rectangle steel pipe column The outer rectangle steel tubing string in outside and it is cast in high-strength concrete between inside and outside rectangle steel tubing string in interlayer, the inside and outside square Steel reinforcement cage is installed in the interlayer between shape steel pipe column, inside and outside the steel reinforcement cage respectively with interior rectangle steel pipe column and outer rectangle Steel pipe column is fixed, by the steel reinforcement cage that the opposite face of both inside and outside rectangle steel tubing strings and outer rectangle steel tubing string is opposite Face is fixedly connected, and pipeline, hollow portion in the interior rectangle steel pipe column are embedded in the interlayer between the inside and outside rectangle steel tubing string Position is provided with elevator and/or stair, and the steel reinforcement cage is double-way opposed-pulling stirrup cage, and the double-way opposed-pulling stirrup cage includes more edges Short transverse laying, the positioning to play the role of positioning, which are indulged muscle and be fixed on the vertical muscle of positioning, laterally lays double-way opposed-pulling stirrup, described Double-way opposed-pulling stirrup is indulged muscle extending direction along positioning on positioning vertical muscle, is laid with multilayer, the double-way opposed-pulling with a fixed spacing The both ends of stirrup are separately fixed inside and outside rectangle steel tubing string opposite face and outer rectangle steel tubing string opposite face, the double-way opposed-pulling It is fixed in the middle part of stirrup on the vertical muscle of positioning.
Further, the diameter of the double-way opposed-pulling stirrup is greater than the diameter for positioning vertical muscle.
Further, the two-way right of spacing and adjacent layer is arranged in the horizontal direction in double-way opposed-pulling stirrup described in same layer Stirrup is drawn to be longitudinally arranged spacing identical.
Further, the strength of high strength concrete is not less than C60.
Further, the outer rectangle steel tubing string is assembled by general steel plate component and crotch steel plate member, described curved Hook plate component includes steel plate member and the crotch that is fixed on the inside of steel plate member, and the general steel plate Member Welding is described double To drawing in stirrup cage, the double-way opposed-pulling stirrup cage is equipped with the corresponding transverse direction cloth with crotch position with crotch steel plate member junction If transverse steel, the transverse steel is welded on the end of double-way opposed-pulling stirrup, and the same direction in same layer is laid Double-way opposed-pulling stirrup connection it is integral, the crotch steel plate member preset installation site in double-way opposed-pulling stirrup cage is Welding procedure zone of action, the welding procedure zone of action facilitate worker to general steel plate component and double-way opposed-pulling stirrup cage into Row welding activity, after the completion of general steel plate Member Welding, the crotch steel plate member is mounted by crotch is fixed on described pair To draw stirrup cage on, and the crotch steel plate member with it is tangent on the outside of double-way opposed-pulling stirrup cage.
Further, crotch steel plate member position corresponding with transverse steel at crotch is equipped with plug welding slot, described After crotch steel plate member is mounted on the horizontal line reinforcing bar of double-way opposed-pulling stirrup cage, then plug welding is in double-way opposed-pulling stirrup cage.
Further, double-way opposed-pulling stirrup both ends bend, and the bending part of the double-way opposed-pulling stirrup and it is interior, The tangent connection of inner wall of outer rectangle steel tubing string, junction and inside and outside rectangle steel tubing string weld.
Further, be equipped with multiple groups crotch on the inside of the crotch steel plate member, the position of crotch described in each group with it is two-way To drawing each layer of double-way opposed-pulling stirrup in stirrup cage corresponding, every group of crotch includes multiple crotches that transversely reinforcing bar is laid.
A kind of concrete-filled double skin steel tube colossal column applied on skyscraper, including above-mentioned hollow sandwich steel pipe are mixed Soil colossal column is coagulated, is embedded with pipeline, hollow portion in the interior rectangle steel pipe column in the interlayer between the inside and outside rectangle steel tubing string Position is provided with elevator and/or stair.
Further, the stair are prefabricated assembled stair or integral cast-in-situ formula reinforced concrete stairs.
A kind of construction method of concrete-filled double skin steel tube colossal column, includes the following steps:
A, according to practice of construction situation determine in rectangle steel pipe column, outer rectangle steel tubing string, double-way opposed-pulling stirrup cage size, Rectangle steel pipe column and double-way opposed-pulling stirrup cage, prepare the general steel plate component and crotch for assembling outer rectangle steel tubing string in assembling Steel plate member, the crotch steel plate member include steel plate member and the multiple groups crotch that is fixed on the inside of steel plate member, each group of institute The position for stating crotch is corresponding with each layer of double-way opposed-pulling stirrup in double-way opposed-pulling stirrup cage, the double-way opposed-pulling stirrup cage with it is curved Hook plate element joints are equipped with the transverse steel laterally laid corresponding with crotch position, and the transverse steel is welded on two-way right The end for drawing stirrup, the double-way opposed-pulling stirrup connection that the same direction in same layer is laid are integral;
B, after interior rectangle steel pipe column being fixed on bottom plate or basis, double-way opposed-pulling stirrup cage is covered from top to bottom in interior rectangle Then outside of steel pipe column the outer wall on the inside of steel reinforcement cage with interior rectangle steel pipe column is welded and fixed;
C, outer rectangle steel tubing string is installed: determining that the general steel plate component of outer rectangle steel tubing string and crotch steel plate member exist first Pre-installed position on the outside of double-way opposed-pulling stirrup cage, the pre-installed position of the crotch steel plate member is for convenience of worker to ordinary steel Board member and double-way opposed-pulling stirrup cage carry out welding activity, and general steel plate component is connected with bottom plate or basis then, passes through The pre-installed position of crotch steel plate member by general steel plate Member Welding on the outside of double-way opposed-pulling stirrup cage, then by crotch steel plate Component is mounted by multiple groups crotch to be fixed on the transverse steel of the double-way opposed-pulling stirrup cage, and by crotch steel plate member Bottom and bottom plate or basis are fixed, finally by between adjacent general steel plate component, general steel plate component and crotch steel plate member it Between welding assembly so that being formed with the hollow folder of built-in double-way opposed-pulling stirrup cage between interior rectangle steel pipe column and outer rectangle steel tubing string Layer;
D, it after the completion of every layer of inside and outside rectangle steel tubing string and double-way opposed-pulling stirrup cage are laid, is poured in hollow sandwich High-strength concrete and vibration compacting.
By using above scheme, after interior rectangle steel pipe column is connect with double-way opposed-pulling stirrup cage, then fixed outer square When shape steel pipe column, crotch steel plate member is hung in double-way opposed-pulling stirrup cage by crotch, thus prevent by general steel plate component with After the welding of double-way opposed-pulling stirrup cage, space is too small between inside and outside rectangle steel tubing string can not be by remaining steel plate member and double-way opposed-pulling The case where stirrup cage is welded, to facilitate the installation of external rectangle steel tubing string, and the steel tube concrete made in this way Native colossal column, compensates for that rectangular steel pipe inside and outside Concrete-filled Double Skin Steel Tube Columns is insufficient to the constraint of concrete, internal layer rectangle steel Defect of the pipe to concrete without effect of contraction improves the bearing capacity of the huge steel core concrete column of hollow sandwich, makes its structural behaviour It is advanced optimized.
Further, after having poured high-strength concrete, Lift & Stairs, the stair are installed in colossal column inner space For prefabricated assembled stair or integral cast-in-situ formula reinforced concrete stairs.
Further, the double-way opposed-pulling stirrup cage includes more vertical along short transverse laying, the positioning to play the role of positioning It muscle and is fixed on the vertical muscle of positioning and laterally lays double-way opposed-pulling stirrup, the double-way opposed-pulling stirrup is vertical along positioning on positioning vertical muscle Muscle extending direction is laid with multilayer with a fixed spacing, and the both ends of the double-way opposed-pulling stirrup are separately fixed inside and outside rectangular steel pipe Column opposite face and outer rectangle steel tubing string opposite face are fixed in the middle part of the double-way opposed-pulling stirrup on the vertical muscle of positioning.
Further, in production, double-way opposed-pulling stirrup cage is connected the double-way opposed-pulling stirrup cage with crotch steel plate member The transverse steel connect is inwardly indented a distance to match with crotch size, for accommodating crotch.
Further, crotch steel plate member position corresponding with transverse steel at crotch is equipped with plug welding slot, described After crotch steel plate member is mounted on the horizontal line reinforcing bar of double-way opposed-pulling stirrup cage, then plug welding is in double-way opposed-pulling stirrup cage.
After adopting the above technical scheme, the invention has the following advantages that
1. section is carried out, structure overall stiffness is big.
By the section rigidity EI=Ebh of rectangular cross section beam3In/12 it is found that the cube of section rigidity and depth of section at Direct ratio.Concrete-filled double skin steel tube colossal column is due to hollow development, in the case where same self weight, the section ruler of huge component It is very little more much bigger than ordinary elements, therefore its rigidity is necessarily more much larger than the rigidity of ordinary construction.
2. lateral rigidity is big, and along being highly evenly distributed, force path is clear, is a kind of ideal lateral resisting structure body System.
3. system is versatile and flexible, be conducive to antidetonation.
Mammoth structure is a kind of big system, and colossal column can form in irregular building from different structural units The mammoth structure of rule, each component of mega-structure system have different Seismic Fortifications, multiple defence line are formed, to antidetonation Favorably.In the conceived case, other active energy-consuming devices can also be installed in structure to guarantee the safety of structure.
4. can make full use of the vertical transportation that the space inside colossal column solves mammoth structure, installed inside colossal column Elevator or stair effectively improve the usable floor area of building, large space or aerial tableland or gate can be arranged in building Hole, the flexibility arranged to room create advantage.
5. construction speed is fast.
Mega-structure system can first construct its main structure, after the completion of colossal column, separate each working face and construct simultaneously time Structure substantially reduces construction period.
6. having bigger stability and higher efficiency.
The present invention is compared with steel core concrete column, and concrete-filled double skin steel tube colossal column is since section is carried out, same In the case of self weight, bending stiffness is bigger.Under reasonable design conditions, using the outer rectangle steel tubing string of identical size, in The bearing capacity of empty interlayer steel tube concrete colossal column is not less than corresponding solid steel tube concrete, and has and solid steel tube coagulation Mechanical property as great soil group.The steel pipe of solid steel tube concrete is located at cross-sectional circumference, its stabilization is easily lost under fire effect and is held Power is carried, and concrete-filled double skin steel tube colossal column is since concrete is to the package action of inner tube, inner tube is protected well Effect, can not lose its stable bearing capacity in a long time.
The present invention is compared with shear wall Core Walls Structure, and concrete-filled double skin steel tube colossal column is due to steel pipe and two-way right Draw stirrup to the effect of contraction of concrete, core concrete made be in three dimension stress state, can increase the rigidity of colossal column with Lateral resisting;Inner-concrete with high intensity and double-way opposed-pulling stirrup can prevent local buckling, so that deformation reduces, to enhance steel The stability and ductility of pipe.Therefore compared with shear wall Core Walls Structure, the lateral resistant ability of colossal column, plastic deformation ability, ductility and Anti-seismic performance is all more superior.The superiority of colossal column, which also resides in, can strive for practical space spacious as far as possible, make various auxiliary The servant space reaches Administrative Area and flexibly divides into the centralized of plane, the convenient and fast effect of internal transportation.
In conclusion bearing capacity of the present invention is high, Hysteresis Behavior is good, anti-side rigidity is big, ductility is good, reasonable stress, construction party Just, from the concrete-filled double skin steel tube colossal column of heavy and light, the not sufficiently effective defect of steel tube confinement had not only been compensated for, but also can have been subtracted significantly Difficulty when lacking thickness of steel pipe, thick steel plate being avoided to weld, while the problem of mammoth structure vertical transportation is also solved, it is suitable for height Layer building structure.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of colossal column and Huge Beam of the present invention.
Fig. 2 is that colossal column of the present invention applies the structural schematic diagram on skyscraper.
Fig. 3 is that colossal column of the present invention applies the external structure schematic diagram on skyscraper.
Fig. 4 is the schematic diagram of the section structure of colossal column of the present invention.
Fig. 5 is the perspective view of rectangle steel pipe column in the present invention.
Fig. 6 is the structural schematic diagram of crotch steel plate member of the present invention.
Fig. 7 is the structural schematic diagram of steel reinforcement cage of the present invention.
In figure: rectangle steel pipe column in 1., 2. outer rectangle steel tubing strings, 3. double-way opposed-pulling stirrups, 4. high-strength concretes, 5. common Steel plate member, 6. crotch steel plate members, 7. crotches, 8. position vertical muscle, 9. colossal columns, 10. Huge Beams, 11. elevators, 12. stair, 13. door opening.
Specific embodiment
For a better understanding of the present invention, with reference to the accompanying drawing and embodiment, invention is described in further detail, but The implementation of the present invention is not limited to this.
It include colossal column 9 and Huge Beam 10 in skyscraper, colossal column 9 uses hollow folder in this example such as attached drawing 1 to Fig. 7 Layer concrete filled steel tube colossal column, including interior rectangle steel pipe column 1 and outer rectangle steel tubing string 2 as made of straight steel plate assembly welding, electricity Ladder 11, stair 12 and door opening 13, the hollow sandwich between interior rectangle steel pipe column 1 and outer rectangle steel tubing string 2 are built-in with double-way opposed-pulling Stirrup 3, and poured high-strength concrete 4.
The interior rectangle steel pipe column 1 and outer rectangle steel tubing string 2 use Q345 grades of steel plates, then by two squares of different sizes Shape steel pipe is placed with one heart, pours high-strength concrete between inside and outside rectangle steel tubing string.
For the double-way opposed-pulling stirrup that production double-way opposed-pulling stirrup 3 uses for HPB235, the double-way opposed-pulling stirrup cage includes more Root is indulged muscle 8 and be fixed on the vertical muscle of positioning along short transverse laying, the positioning to play the role of positioning laterally lays double-way opposed-pulling stirrup 3, the double-way opposed-pulling stirrup 3 is laid with multilayer along vertical 8 extending direction of muscle of positioning, with a fixed spacing on positioning vertical muscle 8, described The both ends of double-way opposed-pulling stirrup 3 are separately fixed on inside and outside steel pipe column opposite face and outer steel pipe column opposite face, described two-way right Draw the middle part of stirrup 3 to be fixed on the vertical muscle 8 of positioning, the double-way opposed-pulling stirrup cage and 6 junction of crotch steel plate member be equipped with The corresponding transverse steel 9 laterally laid in crotch position, the transverse steel 9 are welded on the end of double-way opposed-pulling stirrup, will be in The double-way opposed-pulling stirrup connection that the same direction of same layer is laid is integral,
In order to improve weld strength, the bending of double-way opposed-pulling stirrup both ends, and with rectangular steel pipe inner wall is tangent is arranged, then lead to It crosses and is weldingly fixed on interior rectangle steel pipe column 1 and outer 2 inner wall of rectangle steel tubing string, bending place can increase bonding area and improve welding Intensity, the double-way opposed-pulling stirrup place of intersecting vertically are connected using spot welding, and double-way opposed-pulling stirrup is along rectangular steel pipe length and short transverse Equidistant arrangement, double-way opposed-pulling stirrup can be improved rectangular steel pipe to the effective lateral restraint of core concrete and improve steel pipe Stability.
The intensity of the high-strength concrete is not less than C60.
The construction method of concrete-filled double skin steel tube colossal column, comprising the following steps:
1) according to practice of construction situation determine in rectangle steel pipe column, outer rectangle steel tubing string, double-way opposed-pulling stirrup cage size, Rectangle steel pipe column and double-way opposed-pulling stirrup cage, prepare the general steel plate component and crotch for assembling outer rectangle steel tubing string in assembling Steel plate member, the crotch steel plate member include steel plate member and the multiple groups crotch that is fixed on the inside of steel plate member, every group of crotch Spacing match with double-way opposed-pulling stirrup axial spacing two-way in double-way opposed-pulling stirrup cage, the crotch steel plate member is in crotch Locate position corresponding with transverse steel and is also provided with multiple plug welding slots;
2) it by double-way opposed-pulling stirrup cage, interior rectangle steel pipe column, general steel plate component and crotch steel plate member, is transported to existing ?;Position baseline is marked in construction ground;
3) after interior rectangle steel pipe column being fixed on bottom plate or basis, double-way opposed-pulling stirrup cage is covered from top to bottom in interior rectangle Then outside of steel pipe column the outer wall on the inside of double-way opposed-pulling stirrup cage with interior rectangle steel pipe column is welded and fixed;
4) after general steel plate component being connected with bottom plate or basis, using crotch steel plate member in double-way opposed-pulling stirrup cage The welding procedure zone of action that upper corresponding installation site is formed, by general steel plate Member Welding on the outside of double-way opposed-pulling stirrup cage, Then after crotch steel plate member being mounted on the double-way opposed-pulling stirrup cage by multiple groups crotch, then by plug welding slot weld double It is to drawing in stirrup cage, the bottom of crotch steel plate member and bottom plate or basis is fixed, finally by adjacent general steel plate component, will Crotch steel plate member welding assembly, so that being formed with built-in double-way opposed-pulling stirrup between interior rectangle steel pipe column and outer rectangle steel tubing string The concrete-filled double skin steel tube colossal column colossal column of cage;
5) high-strength concrete 4 then is being poured between interior rectangle steel tubing string 1 and outer rectangle steel tubing string 2;
6) after having poured high-strength concrete, elevator 11 is installed in colossal column inner space and stair 12, the stair are Prefabricated assembled stair or integral cast-in-situ formula reinforced concrete stairs.
In addition, it should be noted that, this patent is not limited to above embodiment, as long as its part does not specify specific size Or shape, then the part can be any size or shape adaptable with its structure, no matter and making in its material composition Any variation, it is all to be designed using structure provided by the present invention, all it is a kind of deformation of the invention, is considered as in the present invention Within protection scope.

Claims (16)

1. a kind of concrete-filled double skin steel tube colossal column, it is characterised in that: including interior rectangle steel pipe column (1), be coaxially mounted to It outer rectangle steel tubing string (2) on the outside of interior rectangle steel pipe column (1) and is cast between inside and outside rectangle steel tubing string (2) in interlayer High-strength concrete is equipped with double-way opposed-pulling stirrup cage in the interlayer between the inside and outside rectangle steel tubing string (2), described two-way right It draws and is fixed respectively with interior rectangle steel pipe column (1) and outer rectangle steel tubing string (2) inside and outside stirrup cage, pass through the double-way opposed-pulling hoop The opposite face in both inside and outside rectangle steel tubing strings (2) opposite face and outer rectangle steel tubing string (2) is fixedly connected by muscle cage, described Pipeline is embedded in interlayer between inside and outside rectangle steel tubing string (2), the interior hollow part of the interior rectangle steel pipe column (1) is provided with Elevator and/or stair.
2. concrete-filled double skin steel tube colossal column according to claim 1, it is characterised in that: the double-way opposed-pulling stirrup Cage include more laid along short transverse, muscle (8) are indulged in the positioning that plays the role of positioning and are fixed on positioning indulges and laterally lay on muscle (8) Double-way opposed-pulling stirrup (3), the double-way opposed-pulling stirrup (3) is on positioning vertical muscle (8) along vertical muscle (8) extending direction of positioning, with one Fixed spacing is laid with multilayer, and the both ends of the double-way opposed-pulling stirrup (3) are separately fixed inside and outside rectangle steel tubing string (2) opposite face And outer rectangle steel tubing string (2) opposite face, it is fixed in the middle part of the double-way opposed-pulling stirrup (3) on positioning vertical muscle (8).
3. concrete-filled double skin steel tube colossal column according to claim 2, it is characterised in that: the double-way opposed-pulling stirrup (3) diameter is greater than the diameter for positioning vertical muscle (8).
4. concrete-filled double skin steel tube colossal column according to claim 2, it is characterised in that: in double described in same layer To identical to drawing stirrup (3) to arrange that spacing with the double-way opposed-pulling stirrup (3) of adjacent layer is longitudinally arranged spacing in the horizontal direction.
5. concrete-filled double skin steel tube colossal column according to claim 1, it is characterised in that: the high-strength concrete is strong Degree is not less than C60.
6. concrete-filled double skin steel tube colossal column according to claim 1, it is characterised in that: the stair are prefabricated dress With formula stair or integral cast-in-situ formula reinforced concrete stairs.
7. concrete-filled double skin steel tube colossal column according to one of claims 1 to 6, it is characterised in that: the outer square Shape steel pipe column (2) is assembled by general steel plate component (5) and crotch steel plate member (6), and the crotch steel plate member (6) includes Steel plate member and the crotch being fixed on the inside of steel plate member, the general steel plate component (5) are welded on the double-way opposed-pulling stirrup On cage, the double-way opposed-pulling stirrup cage is equipped with crotch position the corresponding cross laterally laid with crotch steel plate member (6) junction To reinforcing bar, the transverse steel is welded on the end of the double-way opposed-pulling stirrup (3) of composition double-way opposed-pulling stirrup cage, will be in same Double-way opposed-pulling stirrup (3) connection that the same direction of layer is laid is integral, and the crotch steel plate member (6) is mounted by crotch It is fixed on the transverse steel of the double-way opposed-pulling stirrup cage, adjacent general steel plate component (5), adjacent crotch steel plate member (6) And it is welded between adjacent general steel plate component (5) and crotch steel plate member (6).
8. band lacing wire concrete-filled double skin steel tube according to claim 7 pours building body, it is characterised in that: the crotch steel Board member (6) preset installation site in double-way opposed-pulling stirrup cage is welding procedure zone of action, the welding procedure activity Region is convenient to carry out welding activity to general steel plate component (5) and double-way opposed-pulling stirrup cage, has welded in general steel plate component (5) Cheng Hou, the crotch steel plate member (6) is mounted by crotch to be fixed in the double-way opposed-pulling stirrup cage, and the crotch steel Board member (6) with it is tangent on the outside of double-way opposed-pulling stirrup cage.
9. concrete-filled double skin steel tube colossal column according to claim 7, it is characterised in that: the crotch steel plate member (6) position corresponding with transverse steel is equipped with plug welding slot at crotch, and the crotch steel plate member (6) is mounted on double-way opposed-pulling hoop After on the horizontal line reinforcing bar of muscle cage, then plug welding is in double-way opposed-pulling stirrup cage.
10. concrete-filled double skin steel tube colossal column according to claim 7, it is characterised in that: the double-way opposed-pulling hoop The bending of muscle (3) both ends, and the bending part of the double-way opposed-pulling stirrup (3) and the inner wall of inside and outside rectangle steel tubing string (2) are tangent Connection, junction and inside and outside rectangle steel tubing string (2) are welded.
11. concrete-filled double skin steel tube colossal column according to claim 7, it is characterised in that: the crotch steel plate structure Multiple groups crotch, each layer of double-way opposed-pulling hoop on the position of crotch described in each group and double-way opposed-pulling stirrup cage are equipped on the inside of part (6) Muscle (3) is corresponding, and every group of crotch includes multiple crotches that transversely reinforcing bar is laid.
12. a kind of construction method of concrete-filled double skin steel tube colossal column, characterized by the following steps:
A, according to practice of construction situation determine in rectangle steel pipe column (1), outer rectangle steel tubing string (2), double-way opposed-pulling stirrup cage ruler It is very little, interior rectangle steel pipe column (1) and double-way opposed-pulling stirrup cage are assembled, the general steel plate for assembling outer rectangle steel tubing string (2) is prepared Component (5) and crotch steel plate member (6), the crotch steel plate member (6) include steel plate member and are fixed on the inside of steel plate member Multiple groups crotch, the position of crotch described in each group is corresponding with each layer double-way opposed-pulling stirrup (3) in double-way opposed-pulling stirrup cage, The double-way opposed-pulling stirrup cage is equipped with crotch position the corresponding lateral steel laterally laid with crotch steel plate member (6) junction Muscle, the transverse steel are welded on the end of double-way opposed-pulling stirrup (3), and it is two-way right that the same direction in same layer is laid Draw stirrup (3) connection integral;
B, after interior rectangle steel pipe column (1) being fixed on bottom plate or basis, double-way opposed-pulling stirrup cage is covered from top to bottom in interior rectangle On the outside of steel pipe column (1), then the outer wall on the inside of steel reinforcement cage with interior rectangle steel pipe column (1) is welded and fixed;
C, outer rectangle steel tubing string (2) is installed: determining the general steel plate component (5) and crotch steel plate of outer rectangle steel tubing string (2) first Pre-installed position of the component (6) on the outside of double-way opposed-pulling stirrup cage, the pre-installed position of the crotch steel plate member (6) is for convenience Welding activity is carried out to general steel plate component (5) and double-way opposed-pulling stirrup cage, then by general steel plate component (5) with bottom plate or base Plinth is connected, and general steel plate component (5) is welded on double-way opposed-pulling stirrup cage by the pre-installed position of crotch steel plate member (6) Crotch steel plate member (6) is then mounted the transverse steel for being fixed on the double-way opposed-pulling stirrup cage by outside by multiple groups crotch On, and it is the bottom of crotch steel plate member (6) and bottom plate or basis is fixed, finally by between adjacent general steel plate component (5), Welding assembly between general steel plate component (5) and crotch steel plate member (6), so that interior rectangle steel pipe column (1) and outer rectangular steel pipe The hollow sandwich of built-in double-way opposed-pulling stirrup cage is formed between column (2);
D, after the completion of every layer of inside and outside rectangle steel tubing string (2) and double-way opposed-pulling stirrup cage are laid, height is poured in hollow sandwich Reinforced concrete and vibration compacting.
13. the construction method of concrete-filled double skin steel tube colossal column according to claim 12, it is characterised in that: when pouring After having built high-strength concrete, Lift & Stairs are installed in colossal column inner space, the stair are prefabricated assembled stair or whole Body cast-type reinforced concrete stairs.
14. the construction method of concrete-filled double skin steel tube colossal column according to claim 12, it is characterised in that: described Double-way opposed-pulling stirrup cage includes more and indulges muscle (8) along short transverse laying, the positioning to play the role of positioning and be fixed on the vertical muscle of positioning (8) it is laterally laid on double-way opposed-pulling stirrup (3), the double-way opposed-pulling stirrup (3) is vertical muscle (8) along positioning on positioning vertical muscle (8) Extending direction is laid with multilayer with a fixed spacing, and the both ends of the double-way opposed-pulling stirrup (3) are separately fixed inside and outside rectangle steel It is vertical to be fixed on positioning in the middle part of the double-way opposed-pulling stirrup (3) for tubing string (2) opposite face and outer rectangle steel tubing string (2) opposite face On muscle (8).
15. the construction method of concrete-filled double skin steel tube colossal column according to claim 12, it is characterised in that: described For double-way opposed-pulling stirrup cage in production, transverse steel that double-way opposed-pulling stirrup cage is connected with crotch steel plate member (6) is to inside contracting Into a distance to match with crotch size, for accommodating crotch.
16. the construction method of concrete-filled double skin steel tube colossal column according to claim 12, it is characterised in that: described Crotch steel plate member (6) position corresponding with transverse steel at crotch is equipped with plug welding slot, and the crotch steel plate member (6) mounts After on the horizontal line reinforcing bar of double-way opposed-pulling stirrup cage, then plug welding is in double-way opposed-pulling stirrup cage.
CN201811611358.2A 2018-12-27 2018-12-27 Hollow sandwich steel tube concrete giant column and construction method thereof Active CN109457870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811611358.2A CN109457870B (en) 2018-12-27 2018-12-27 Hollow sandwich steel tube concrete giant column and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811611358.2A CN109457870B (en) 2018-12-27 2018-12-27 Hollow sandwich steel tube concrete giant column and construction method thereof

Publications (2)

Publication Number Publication Date
CN109457870A true CN109457870A (en) 2019-03-12
CN109457870B CN109457870B (en) 2023-10-27

Family

ID=65615009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811611358.2A Active CN109457870B (en) 2018-12-27 2018-12-27 Hollow sandwich steel tube concrete giant column and construction method thereof

Country Status (1)

Country Link
CN (1) CN109457870B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201103167Y (en) * 2007-08-30 2008-08-20 江苏科技大学 Giant steel frame support structure
CN103061449A (en) * 2012-12-27 2013-04-24 长安大学 A double stiffened SCS square steel tube concrete structure based on stirrups and stiffening ribs
CN203583779U (en) * 2013-10-31 2014-05-07 中国航空规划建设发展有限公司 Assembly type long column with frame with steel corbel
CN104372873A (en) * 2014-12-01 2015-02-25 王立久 Manufacturing method for formwork shear wall assembled in modularized mode
CN105133793A (en) * 2015-09-07 2015-12-09 姚攀峰 Space constraint multi-cavity pipe-in-pipe steel bar concrete huge column and construction method
CN207525999U (en) * 2017-12-04 2018-06-22 东华理工大学 A kind of rubber concrete coupled column
KR20180135736A (en) * 2017-06-13 2018-12-21 주식회사 액트파트너 Mega multi-tube column with a dual structural concept
CN209637111U (en) * 2018-12-27 2019-11-15 中南大学 A kind of concrete-filled double skin steel tube colossal column

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201103167Y (en) * 2007-08-30 2008-08-20 江苏科技大学 Giant steel frame support structure
CN103061449A (en) * 2012-12-27 2013-04-24 长安大学 A double stiffened SCS square steel tube concrete structure based on stirrups and stiffening ribs
CN203583779U (en) * 2013-10-31 2014-05-07 中国航空规划建设发展有限公司 Assembly type long column with frame with steel corbel
CN104372873A (en) * 2014-12-01 2015-02-25 王立久 Manufacturing method for formwork shear wall assembled in modularized mode
CN105133793A (en) * 2015-09-07 2015-12-09 姚攀峰 Space constraint multi-cavity pipe-in-pipe steel bar concrete huge column and construction method
KR20180135736A (en) * 2017-06-13 2018-12-21 주식회사 액트파트너 Mega multi-tube column with a dual structural concept
CN207525999U (en) * 2017-12-04 2018-06-22 东华理工大学 A kind of rubber concrete coupled column
CN209637111U (en) * 2018-12-27 2019-11-15 中南大学 A kind of concrete-filled double skin steel tube colossal column

Also Published As

Publication number Publication date
CN109457870B (en) 2023-10-27

Similar Documents

Publication Publication Date Title
CN101581115B (en) Mixed steel-concrete composite frame structure
CN106703197B (en) A kind of large span multilayer anti-seismic frame structure system and its construction method
CN102418387B (en) Post-tensioning external prestressed steel beam and pre-tensioning prestressed superposed beam combined building structure system and construction technology thereof
CN102979179A (en) Steel pipe-reinforced concrete laminated framework structural system
CN104963415A (en) Circular steel tube constraint type steel concrete column and steel beam node structure
CN203569795U (en) Long span prestress cube type steel rib concrete superposed beam
CN103397695A (en) Concrete filled steel tube combination column high position connected structure provided with bidirectional steel trusses
CN105369892B (en) A kind of steel tube concrete superposed frame structure system
CN209637113U (en) A kind of band lacing wire concrete-filled double skin steel tube pours building body
CN209637111U (en) A kind of concrete-filled double skin steel tube colossal column
CN106088328A (en) A kind of group frame
CN210597882U (en) Lattice type steel reinforced concrete combined column beam column node
CN204715539U (en) A kind of round steel pipe binding type steel concrete column and reinforced concrete beam node structure
CN109457870A (en) A kind of concrete-filled double skin steel tube colossal column and its construction method
CN202248960U (en) Ultra-high-performance concrete prefabricated assembly balcony bottom plate
CN103498530A (en) Prestressed tooth hole-shaped web T-shaped steel reinforced concrete composite beam
CN209637072U (en) A kind of connecting node of prefabricated superstructure and out-hung panel, vertical supporting member
CN105040828B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
CN209779872U (en) High-rise and super high-rise building structure system
CN209082702U (en) Octagon steel core concrete column and concealed beam integrated structure
CN203603370U (en) Prestress perforation-shaped web box type steel reinforced concrete composite beam
CN203462575U (en) Concrete-filled steel tube combination column high-conjoined structure provided with two-way steel trusses
CN110469054A (en) A kind of lattice steel reinforced concrete coupled column bean column node
CN109653423A (en) A kind of connecting node of prefabricated superstructure and out-hung panel, vertical supporting member
CN203640157U (en) Prestressed H-shaped steel concrete composite beam with inverted T-shaped section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant