CN109441491A - A kind of railway tunnel self-adhesive waterproof material and its construction method - Google Patents

A kind of railway tunnel self-adhesive waterproof material and its construction method Download PDF

Info

Publication number
CN109441491A
CN109441491A CN201811269871.8A CN201811269871A CN109441491A CN 109441491 A CN109441491 A CN 109441491A CN 201811269871 A CN201811269871 A CN 201811269871A CN 109441491 A CN109441491 A CN 109441491A
Authority
CN
China
Prior art keywords
self
adhering type
waterproofing plate
drainable waterproofing
geotextiles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811269871.8A
Other languages
Chinese (zh)
Inventor
谢方成
杨寰
易峰
耿开亮
左小勇
周顺畅
甄小辉
罗军
李蕾
刘衍君
罗彪
杨戈
钟万波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju 1st Engineering Co Ltd filed Critical China Railway Erju 1st Engineering Co Ltd
Priority to CN201811269871.8A priority Critical patent/CN109441491A/en
Publication of CN109441491A publication Critical patent/CN109441491A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of railway tunnel self-adhesive waterproof material and its construction method, which is self-adhering type drainable waterproofing plate, and the surface distribution of self-adhering type drainable waterproofing plate is provided with lug boss, and the surface mount of self-adhering type drainable waterproofing plate is fixed with self-adhesive tape.To substitute existing splash guard and laying method, solve splash guard and easily punctured or penetrated by holdfast, cause splash guard damaged, construction quality not can guarantee, and splash guard be not easy with gunite concrete surface it is closely connected, the problems such as increasing difficulty of construction, reduce waterproof effect.Belong to constructing tunnel field of engineering technology.

Description

A kind of railway tunnel self-adhesive waterproof material and its construction method
Technical field
The present invention relates to a kind of railway tunnel self-adhesive waterproof material and its construction methods, belong to constructing tunnel engineering technology Field.
Background technique
Currently, the tunnel of China's construction largely uses splash guard as waterproof layer, laying method mainly has " suspension method " " hot melt gasket melts patch method "." suspension method " is to beat in the electricity consumption of Tunnel surface into holdfast, then passes through splash guard The suspender belt of behind is fixed with holdfast." hot melt gasket melts patch method " is then first to fix geotextiles using gasket, then waterproof Plate is welded with hot melt gasket.
Squeezing action of the splash guard by concrete outside " suspension method " fixed point, it is easy to be punctured by holdfast, cause to prevent Water plate pulls breakage, and the splash guard in " suspension method " is not easy closely connected with gunite concrete surface simultaneously, increases difficulty of construction, drop Low waterproof effect seldom uses in construction at present." hot melt gasket melts patch method " constructing operation is simple, gasket installation spirit It is living, but the welding of gasket and splash guard is difficult to grasp, and the case where splash guard through welding often occurs, construction quality not can guarantee.
Summary of the invention
It is an object of the invention to: a kind of railway tunnel self-adhesive waterproof material and its construction method are provided, it is existing to substitute Some splash guards and laying method solve splash guard and are easily punctured or penetrated by holdfast, cause splash guard damaged, construction quality can not Guarantee, and splash guard be not easy with gunite concrete surface it is closely connected, the problems such as increasing difficulty of construction, reduce waterproof effect.
To solve the above problems, such a railway tunnel self-adhesive waterproof material of proposed adoption, the self-adhesive waterproof material Surface distribution for self-adhering type drainable waterproofing plate, self-adhering type drainable waterproofing plate is provided with lug boss, and the surface of self-adhering type drainable waterproofing plate Stickup is fixed with self-adhesive tape.
The lug boss is circular protrusions structure, and it is highly 5-15mm, between lug boss etc. that the diameter of lug boss, which is 5-15mm, It is arranged away from distribution, and the distance between adjacent projections are 5-15mm.
The construction method of above-mentioned railway tunnel self-adhesive waterproof material is as follows:
1. preparation of construction;
2. tunnel Special geotextile is laid with;
3. self-adhering type drainable waterproofing plate is laid with;
4. draining blind pipe installation;
5. self-adhering type rubber fastening band is installed.
Above-mentioned steps 1. in specific preparation it is as follows:
1) prepare outside hole: examining self-adhering type drainable waterproofing plate quality, divide middle line with the welding of mark stroke and vault, by every circulation Design length interception, symmetrical rolled for future use;
2) section measures: Measure section carries out measurement inspection to tunnel clearance, handles individual digging positions of owing, with Meet Clearance requirement;Measuring vault divides middle line simultaneously;
3) basal plane is handled:
3.1) local leak is directly drained using grouting for water blocking or embedded drainpipe to side, and steel mesh etc. protrudes part, first With hammer riveting flat wiping mortar element ash after cutting, when having the pipeline of protrusion, smoothed out with mortar;
3.2) it when anchor pole has protruding parts, after 5mm cutting is reserved on the screw crown, is handled with plastic cap;
3.3) preliminary bracing should be without hollowing, crack, crisp pastry, and surface is smooth, and concavo-convex amount must not exceed ± 5cm.
The concrete operations of above-mentioned steps 2. are as follows:
1) geotextile laying is laid with using splash guard Mobile workbench, is first marked at tunnel vault position when being laid with geotextiles vertical To the midline, and according to basal plane bumps situation surplus capacity is stopped, is preferably laid with from arch to two sides abutment wall;
2) thermoplastic gasket and geotextiles are smoothly fixed on basal plane with nailing, fixed point spacing arch be 0.5m, Abutment wall 0.8m, is in quincunx arrangement, and basal plane bumps larger part should increase fixed point, keep geotextiles closely connected with basal plane;
3) geotextiles seam lap width is more than or equal to 5cm, circumferential seam is only set, when length is inadequate, if longitudinal seam And ensure that top (by one of arch) compresses using lower part (by one of bottom) geotextiles, and keep geotextiles close with basal plane Patch, the geotextiles of laying are smooth, no protuberance, corrugationless.
The concrete operations of above-mentioned steps 3. are as follows:
By self-adhering type drainable waterproofing plate along tunnel circumferential direction spread, top length in reserve 8m~10m;In paving hanging platform roof quadrangle Self-adhering type drainable waterproofing plate is held up, notices that joint sealing area reserves overlap edge with a upper width and is aligned;By self-adhering type drainable waterproofing plate with Geotextiles are compressed by the self-adhesive tape on surface pastes, and bonding while is fastened using rubber hammer.
Concrete operations are as follows:
1) setting-out is carried out before being laid with, pop-up normal line carries out the size of determining one ring of drainable waterproofing plate after examination paving, reduces to the greatest extent Connector;
2) self-adhering type drainable waterproofing plate is laid with using sequence from below to up, it is elastic should appropriateness and there are surplus, when inspection wants Guarantee that drainable waterproofing plate entire area can arrive to just branch;
3) lap width of two width self-adhering type drainable waterproofing plates is no less than 150mm;
4) when circumferential laying, lower part drainable waterproofing plate should push down top drainable waterproofing plate;
5) overlapping the slot of self-adhering type drainable waterproofing plate circumferential direction should be climbed using double weld seams, temperature adjustment, the automatic of speed regulation thermal wedge minor function Line heat-sealing machine sweat soldering, detailed treatment or repairing use hand torch, and effective weld width of single weld seam is no less than 15mm, welding is tight, must not weld burnt burn-through;
6) longitudinal lap joint of self-adhering type drainable waterproofing plate is cleared up viscous using the method for " adhesive sealing+convex hull buckle+welding gun edge sealing " Paste area;The non-bituminous adhesive polymer tape-stripping that width is 18cm is reserved into drainable waterproofing plate convex hull body concave surface in lining cutting longitudinal lap joint Side simultaneously ensures the position of single-coated foam lower than overlap joint area edge 1cm;Reserved drainable waterproofing plate buckle will be overlapped to compress, lap width 25cm should be not less than;It is handled using plastic welding gun edge sealing.Welding gun drop temperature should be advisable at 300~330 DEG C, and hot blast temperature is adjusted to Minimum, according to joint gap size appropriate adjustment speed of welding.
7) overlapping the slot of self-adhering type drainable waterproofing plate is staggered lining construction seam not less than 100cm.
8) self-adhering type drainable waterproofing plate is repaired
The repairing block that width is not less than damaged 2 times of long edge size is cut, non-2cm shorter than repairing block width of width is cut Pitch adhesive polymer adhesive tape is simultaneously pasted on repairing block convex hull body convex surface side, after being cleaned out region to be repaired with geotextiles Block buckle will be repaired in breakage, handled using plastic welding gun edge sealing, finally stickup single-coated foam region is blown with air-heater and be used in combination Rubber hammer fastening.
The concrete operations of above-mentioned steps 4. are as follows:
1) longitudinal drainage blind pipe applies
Longitudinal drainage blind pipe is laid in along longitudinal direction in the short abutment wall of left and right side inverted arch, is two diameters under internal rail top at 30cm For 100 double-walled of φ punch bellows, be mounted on the reinforced frame welded, and connecting bend andLateral aqueduct, when installation Ensure water-permeable pipe punching up, finally uses geotextiles and self-adhering type drainable waterproofing plate anti-package longitudinal drainage blind pipe.
2) inverted arch short abutment wall position transverse direction aqueduct applies
Short abutment wall position transverse direction aqueduct extends laterally through short abutment wall, and spacing 3m, delivery line is away from lateral sulcus bottom about 20- 30cm is drawn delivery line using two 90 ° of elbows, and centre adds threeway and connect longitudinal drainage blind pipe with lateral aqueduct.
Using hole making drill aperture on self-adhering type drainable waterproofing plate, elbow and lateral aqueduct are pierced by self-adhering type guarded drainage Plate, seam crossing are handled using saddle connector, and in seam crossing smearing structure glue encapsulation process.
The concrete operations of above-mentioned steps 5. are as follows:
1) self-adhering type waterstop mounting process
Waterstop → fixation waterstop (waterstop is centrally arranged) → is laid to take off isolation film and (remove waterstop and wait for pouring concrete Side isolation film, other side isolation film retain them temporarily, and avoid self-adhesive contaminated and fail) → connector connection (vertical equity construction Buried self-adhering rubber sealing belt lacing uses heat cure joint process in seam) → Feng Mo → casting concrete, demoulding.
2) self-adhering type sealing belt lacing is constructed
Self-adhering rubber waterstop uses RLH-I type portable field heat cure junction device, and equipment volume is small, temperature and pressure The adjustable control of power.
Self-adhering type waterstop heat cure joint process are as follows:
2.1) it preheats.Portable thermal vulcanized joint device temperature is adjusted to 130 DEG C~150 DEG C, preheats 15min.
2.2) connector is handled.Waterstop joint cutting is neat, it clears up joint surface dust and removes connector 5cm range Interior self-adhesive.
2.3) connector heat cure connects.3cm wide raw rubber connection strap is put among seam, sealing belt lacing fin is complete Portion is embedded in joint mold, and closed joint equipment is forced into 10MPa, power supply is closed after 20min, and welding terminates.
2.4) glue is covered.Self-adhesion adhesive tape is covered in self-adhesion water stop band joint.
Compared with prior art, splash guard is made into convex hull shape by the present invention, and in factory is fixed on self-adhesive tape with glue anti- On water plate, scene directly pastes fixed splash guard using self-adhesive tape and geotextiles and achievees the effect that self-adhesion;Using on splash guard Convex hull gap achievees the effect that circumferential face draining, punches bellows using 100 double-walled of φ, inner wall smooth can effectively prevent ripple Water crystallization is leaked in pipe;Using self-adhering type waterproof material construction safety, convenient, reliable in quality, shorten the construction period, saves Construction cost, economic benefit and social benefit are good, and chael-de-fer mountain Tunnel Project achieves preferable effect after constructing using this method Fruit, and two lining no one percolating water of paragraph constructed, the height by relevant units such as management, owners are praised.
Self-adhering type waterproof material is as a kind of new material, new technology, by its material composition and construction technology Total innovation and improvement, all kinds of construction environments can be adapted to, from now in the guarded drainages building field such as underground engineering, It will further optimize the design of material, guarantee construction quality, shorten the construction period, promote construction speed, it is seen that it will be in the present Put it in guarded drainage field application afterwards, potential technology wide market.
Detailed description of the invention
Fig. 1 is construction flow chart of the invention;
Fig. 2 is that self-adhering type method paving hangs process flow chart;
Fig. 3 is that longitudinal drainage blind pipe in tunnel bottom applies structural schematic diagram;
Fig. 4 is guarded drainage material construction cross-section diagram;
Fig. 5 is the positive structure schematic of self-adhering type drainable waterproofing plate;
Wherein, appended drawing reference: 1 indicates self-adhering type drainable waterproofing plate, and 2 indicate lug boss, and 4 indicate longitudinal drainage blind pipe, and 5 indicate Geotextiles, the lateral aqueduct of 6 expressions, 7 expression tunnel middle lines, the 8 left line line midlines of expression, the 9 right line line midlines of expression, 10 Indicate design rail level, 11 indicate preliminary bracing, and 12 indicate back sticking type self-adhering rubber waterstop, and buried self-adhering rubber stops in 13 expressions Water band, 14, which indicate secondary, pours lining-up, and 15 indicate longitudinal construction joint, and 16 indicate water expandable waterstop, and 17 indicate the anti-row of 2m wide Water plate+non-woven fabrics, 18 indicate mortar levelling layer (5cm), and 19 indicate draining blind pipe, and 20 indicate non-fine concrete filling, and 21 indicate Single slope drainage pipe.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention is made into one below in conjunction with attached drawing The detailed description of step, it should be understood that described herein specific examples are only used to explain the present invention, is not used to limit this hair It is bright.
Embodiment:
Referring to attached drawing 1 to Fig. 5, the present embodiment provides a kind of railway tunnel self-adhesive waterproof material and its construction method, institutes Stating railway tunnel self-adhesive waterproof material is self-adhering type drainable waterproofing plate 1, and the inside EDS maps of self-adhering type drainable waterproofing plate 1 are provided with convex Portion 2 is played, lug boss 2 is circular protrusions structure, and it is highly 10mm that the diameter of lug boss 2, which is 10mm, 2 equidistantly distributed of lug boss Setting, and the distance between adjacent projections 2 are 10mm, the surface mount of self-adhering type drainable waterproofing plate 1 is fixed with self-adhesive tape.
The problem of for existing construction technology, applicant material property testing, preparation test, type approval test and On the basis of model investigation, it is combined into the test section construction of honored guest special chael-de-fer mountain tunnel 300m, forms railway tunnel with newly Novel guarded drainage material installation procedure and the processes such as type self-adhering type drainable waterproofing plate, self-adhering type waterstop, draining blind pipe, form suitable For the construction technology of the novel guarded drainage material of railway tunnel self-adhering type, on this basis, summary forms this method, Specific construction Method is as follows:
1. preparation of construction:
1) prepare outside hole: examining self-adhering type drainable waterproofing plate quality, divide middle line with the welding of mark stroke and vault, by every circulation Design length interception, symmetrical rolled for future use;
2) section measures: Measure section carries out measurement inspection to tunnel clearance, handles individual digging positions of owing, with Meet Clearance requirement;Measuring vault divides middle line simultaneously;
3) basal plane is handled:
3.1) local leak is directly drained using grouting for water blocking or embedded drainpipe to side, and steel mesh etc. protrudes part, first With hammer riveting flat wiping mortar element ash after cutting, when having the pipeline of protrusion, smoothed out with mortar;
3.2) it when anchor pole has protruding parts, after 5mm cutting is reserved on the screw crown, is handled with plastic cap;
3.3) preliminary bracing should be without hollowing, crack, crisp pastry, and surface is smooth, and concavo-convex amount must not exceed ± 5cm.
2. tunnel Special geotextile is laid with:
1) geotextile laying is laid with using splash guard Mobile workbench, is first marked at tunnel vault position when being laid with geotextiles vertical To the midline, and according to basal plane bumps situation surplus capacity is stopped, is preferably laid with from arch to two sides abutment wall;
2) thermoplastic gasket and geotextiles are smoothly fixed on basal plane with nailing, fixed point spacing arch be 0.5m, Abutment wall 0.8m, is in quincunx arrangement, and basal plane bumps larger part should increase fixed point, keep geotextiles closely connected with basal plane;
3) geotextiles seam lap width is more than or equal to 5cm, circumferential seam is only set, when length is inadequate, if longitudinal seam And ensure that top (by one of arch) compresses using lower part (by one of bottom) geotextiles, and keep geotextiles close with basal plane Patch, the geotextiles of laying are smooth, no protuberance, corrugationless.
3. self-adhering type drainable waterproofing plate is laid with:
By self-adhering type drainable waterproofing plate along tunnel circumferential direction spread, two side lengths are about the same, top length in reserve 8m~10m; Self-adhering type drainable waterproofing plate is held up in paving hanging platform roof quadrangle, notices that joint sealing area reserves overlap edge with a upper width and is aligned; Self-adhering type drainable waterproofing plate and geotextiles are compressed by the self-adhesive tape on surface and are pasted, bonding while is carried out tight using rubber hammer Gu.
Concrete operations are as follows:
1) setting-out is carried out before being laid with, pop-up normal line carries out the size of determining one ring of drainable waterproofing plate after examination paving, reduces to the greatest extent Connector;
2) self-adhering type drainable waterproofing plate is laid with using sequence from below to up, it is elastic should appropriateness and there are surplus, when inspection wants Guarantee that drainable waterproofing plate entire area can arrive to just branch;
3) lap width of two width self-adhering type drainable waterproofing plates is no less than 150mm;
4) when circumferential laying, lower part drainable waterproofing plate should push down top drainable waterproofing plate;
5) overlapping the slot of self-adhering type drainable waterproofing plate circumferential direction should be climbed using double weld seams, temperature adjustment, the automatic of speed regulation thermal wedge minor function Line heat-sealing machine sweat soldering, detailed treatment or repairing use hand torch, and effective weld width of single weld seam is no less than 15mm, welding is tight, must not weld burnt burn-through;
6) longitudinal lap joint of self-adhering type drainable waterproofing plate is cleared up viscous using the method for " adhesive sealing+convex hull buckle+welding gun edge sealing " Paste area;The non-bituminous adhesive polymer tape-stripping that width is 18cm is reserved into drainable waterproofing plate convex hull body concave surface in lining cutting longitudinal lap joint Side simultaneously ensures the position of single-coated foam lower than overlap joint area edge 1cm;Reserved drainable waterproofing plate buckle will be overlapped to compress, lap width 25cm should be not less than;It is handled using plastic welding gun edge sealing.Welding gun drop temperature should be advisable at 300~330 DEG C, and hot blast temperature is adjusted to Minimum, according to joint gap size appropriate adjustment speed of welding.
7) overlapping the slot of self-adhering type drainable waterproofing plate is staggered lining construction seam not less than 100cm.
8) self-adhering type drainable waterproofing plate is repaired
The repairing block that width is not less than damaged 2 times of long edge size is cut, non-2cm shorter than repairing block width of width is cut Pitch adhesive polymer adhesive tape is simultaneously pasted on repairing block convex hull body convex surface side, after being cleaned out region to be repaired with geotextiles Block buckle will be repaired in breakage, handled using plastic welding gun edge sealing, finally stickup single-coated foam region is blown with air-heater and be used in combination Rubber hammer fastening.
4. draining blind pipe installation:
1) longitudinal drainage blind pipe applies
Longitudinal drainage blind pipe 4 is laid in along longitudinal direction in the short abutment wall of left and right side inverted arch, is two straight under internal rail top at 30cm Diameter be 100 double-walled of φ punch bellows, be mounted on the reinforced frame welded, and connecting bend andLateral aqueduct, installation When ensure water-permeable pipe punching up, finally use 1 anti-package longitudinal drainage blind pipe 4 of geotextiles 5 and self-adhering type drainable waterproofing plate, such as Fig. 3 It is shown.
2) inverted arch short abutment wall position transverse direction aqueduct applies
Short abutment wall position transverse direction aqueduct 6 extends laterally through short abutment wall, and spacing 3m, delivery line is away from lateral sulcus bottom about 20- 30cm is drawn delivery line using two 90 ° of elbows, and centre adds threeway and connects longitudinal drainage blind pipe 4 and lateral aqueduct 6 It connects.
Using hole making drill aperture on self-adhering type drainable waterproofing plate 1, elbow and lateral aqueduct 6 are pierced by self-adhering type guarded drainage Plate 1, seam crossing is handled using saddle connector, and in seam crossing smearing structure glue encapsulation process.
5. self-adhering type rubber fastening band is installed:
1) self-adhering type waterstop mounting process
Waterstop → fixation waterstop (waterstop is centrally arranged) → is laid to take off isolation film and (remove waterstop and wait for pouring concrete Side isolation film, other side isolation film retain them temporarily, and avoid self-adhesive contaminated and fail) → connector connection (vertical equity construction Buried self-adhering rubber sealing belt lacing uses heat cure joint process in seam) → Feng Mo → casting concrete, demoulding.
2) self-adhering type sealing belt lacing is constructed
Self-adhering rubber waterstop uses RLH-I type portable field heat cure junction device, and equipment volume is small, temperature and pressure The adjustable control of power.
Self-adhering type waterstop heat cure joint process are as follows:
(cleaning end, width be not small for the preheating of heat cure junction device (130~150 DEG C, preheat 15min) → connector processing In 15cm) → connector heat cure connection (1, connection strap, bind item it is in place;2, junction device is closed;3, it is forced into 10MPa and protects Press 20min.) → cover glue (covers self-adhesive adhesive tape).Specific steps are as follows:
2.1) it preheats.Portable thermal vulcanized joint device temperature is adjusted to 130 DEG C~150 DEG C, preheats 15min.
2.2) connector is handled.Waterstop joint cutting is neat, it clears up joint surface dust and removes connector 15cm range Interior self-adhesive.
2.3) connector heat cure connects.3cm wide raw rubber connection strap is put among seam, sealing belt lacing fin is complete Portion is embedded in joint mold, and closed joint equipment is forced into 10MPa, power supply is closed after 20min, and welding terminates.
2.4) glue is covered.Self-adhesion adhesive tape is covered in self-adhesion water stop band joint.
Technological principle are as follows: splash guard is made into convex hull shape, and is fixed on self-adhesive tape on splash guard with glue in factory, scene Fixed splash guard directly, which is pasted, using self-adhesive tape and geotextiles achievees the effect that self-adhesion;Reached using the convex hull gap on splash guard The effect of circumferential face draining.Bellows is punched using 100 novel double-wall of φ, inner wall smooth can effectively prevent leakage in bellows Water crystallization.
The technology is in April, 2017~2018 year June in line Leshan, newly built railway Chengdu to Kweiyang to Kweiyang iron leg helmet mountain In constructing tunnel, the guarded drainage construction in DK469+200~DK469+500 sections of the tunnel, newly built railway Chengdu to Kweiyang are completed Line Leshan to Kweiyang iron leg helmet mountain tunnel is located at Guizhou Province, iron-stone township, Qianxi County, rises up to mileage D4K466+785~DK472+ 012, overall length 5227m, this tunnel are pressed passenger train designed driving speed 250km/ hours, the design of Line for Passenger Transportation double track tunnel.This tunnel Road DK469+200~DK469+500 sections is constructed using self-adhering type waterproof material, ends 2018 6 in April, 2017 Month, two serve as a contrast the 300m that constructed, and the two lining paragraph guarded drainages constructed meet design and code requirement, achieve preferable effect Fruit, and two lining no one percolating water of paragraph constructed.Construction period has obtained the consistent favorable comment of owner and supervisor.
Economic benefit:
Analyze from the construction time: every circulation (12m) two lining splash guard construction is using " hot melt gasket melts patch method " 6 people of installation It needs 8 hours or so, 4 people of this engineering method only needs 6 hours or so can be completed, and saves working hour 1 half.
Analyze from materials'use: one of circumferential direction φ 50mm wave need to be arranged in tradition " hot melt gasket melts patch method " every 9m of method construction Line pipe.This method does not need circumferential blind pipe.Cost concrete analysis is as shown in table 1.
1 prime cost expense comparison sheet of table
Note: table data are calculated by taking the construction of chael-de-fer mountain tunnel exit as an example on 1..
2. or more expense calculate according to this engineering location material price calculate.
Social benefit: novel self formula guarded drainage material construction convenient and quick construction, it is quality controllable reliable, it can be effective It shortening the construction period, this engineering method is greatly improved to waterproof and Drainage Construction of Tunnel quality, it ensure that waterproof and Drainage Construction of Tunnel quality, The high evaluation and praise extensively of the units such as owner, management are received in process of construction.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (8)

1. a kind of railway tunnel self-adhesive waterproof material, it is characterised in that: the self-adhesive waterproof material is self-adhering type drainable waterproofing plate (1), the surface distribution of self-adhering type drainable waterproofing plate (1) is provided with lug boss (2), and the surface mount of self-adhering type drainable waterproofing plate (1) It is fixed with self-adhesive tape.
2. a kind of railway tunnel self-adhesive waterproof material according to claim 1, it is characterised in that: the lug boss (2) is The diameter of circular protrusions structure, lug boss (2) is 5-15mm, is highly 5-15mm, the setting of lug boss (2) equidistantly distributed, and The distance between adjacent projections (2) are 5-15mm.
3. the construction method of railway tunnel self-adhesive waterproof material as claimed in claim 1 or 2, which is characterized in that construction procedure is such as Under:
1. preparation of construction;
2. tunnel Special geotextile is laid with;
3. self-adhering type drainable waterproofing plate is laid with;
4. draining blind pipe installation;
5. self-adhering type rubber fastening band is installed.
4. construction method according to claim 3, which is characterized in that above-mentioned steps 1. in specific preparation it is as follows:
1) prepare outside hole: examining self-adhering type drainable waterproofing plate quality, divide middle line with the welding of mark stroke and vault, by every cyclic design Length interception, symmetrical rolled for future use;
2) section measures: Measure section carries out measurement inspection to tunnel clearance, handles individual digging positions of owing, to meet Clearance requirement;Measuring vault divides middle line simultaneously;
3) basal plane is handled:
3.1) local leak is directly drained using grouting for water blocking or embedded drainpipe to side, and the protrusion such as steel mesh part is initially switched off Afterwards with hammer riveting flat wiping mortar element ash, when having the pipeline of protrusion, smoothed out with mortar;
3.2) it when anchor pole has protruding parts, after 5mm cutting is reserved on the screw crown, is handled with plastic cap;
3.3) preliminary bracing should be without hollowing, crack, crisp pastry, and surface is smooth, and concavo-convex amount must not exceed ± 5cm.
5. construction method according to claim 3, which is characterized in that the concrete operations of above-mentioned steps 2. are as follows:
1) geotextile laying is laid with using splash guard Mobile workbench, is first marked in longitudinal direction at tunnel vault position when being laid with geotextiles Line, and surplus capacity is stopped according to basal plane bumps situation, it is laid with from arch to two sides abutment wall;
2) thermoplastic gasket and geotextiles are smoothly fixed on basal plane with nailing, fixed point spacing arch is 0.5m, abutment wall 0.8m, is in quincunx arrangement, and basal plane bumps larger part should increase fixed point, keep geotextiles closely connected with basal plane;
3) geotextiles seam lap width is more than or equal to 5cm, only sets circumferential seam, when length is inadequate, if longitudinal seam and true It protects top to compress using lower part geotextiles, and keeps geotextiles closely connected with basal plane, the geotextiles of laying are smooth, no protuberance, corrugationless.
6. construction method according to claim 3, which is characterized in that the concrete operations of above-mentioned steps 3. are as follows:
By self-adhering type drainable waterproofing plate along tunnel circumferential direction spread, top length in reserve 8m~10m;It will be certainly in paving hanging platform roof quadrangle Viscous formula drainable waterproofing plate is held up, and notices that joint sealing area reserves overlap edge with a upper width and is aligned;By self-adhering type drainable waterproofing plate and geotechnique Cloth is compressed by the self-adhesive tape on surface to be pasted, and bonding while is fastened using rubber hammer.
7. construction method according to claim 3, which is characterized in that the concrete operations of above-mentioned steps 4. are as follows:
1) longitudinal drainage blind pipe applies
Longitudinal drainage blind pipe (4) is laid in along longitudinal direction in the short abutment wall of left and right side inverted arch, is two diameters under internal rail top at 30cm For 100 double-walled of φ punch bellows, be mounted on the reinforced frame welded, and connecting bend andLateral aqueduct, when installation Ensure water-permeable pipe punching up, finally uses geotextiles (5) and self-adhering type drainable waterproofing plate (1) anti-package longitudinal drainage blind pipe (4);
2) inverted arch short abutment wall position transverse direction aqueduct applies
Short abutment wall position transverse direction aqueduct (6) extends laterally through short abutment wall, and spacing 3m, delivery line is away from lateral sulcus bottom about 20- 30cm is drawn delivery line using two 90 ° of elbows, and centre adds threeway for longitudinal drainage blind pipe (4) and lateral aqueduct (6) Connection;
Using hole making drill aperture on self-adhering type drainable waterproofing plate (1), elbow and lateral aqueduct (6) are pierced by self-adhering type guarded drainage Plate (1), seam crossing is handled using saddle connector, and in seam crossing smearing structure glue encapsulation process.
8. construction method according to claim 3, which is characterized in that the concrete operations of above-mentioned steps 5. are as follows:
1) self-adhering type waterstop mounting process
It lays waterstop → fixation waterstop → and takes off isolation film → connector connection → Feng Mo → casting concrete, demoulding;
2) self-adhering type sealing belt lacing is constructed
Self-adhering rubber waterstop uses RLH-I type portable field heat cure junction device;
Self-adhering type waterstop heat cure joint process are as follows:
2.1) it preheats, adjusts Portable thermal vulcanized joint device temperature to 130 DEG C~150 DEG C, preheat 15min;
2.2) connector handle, waterstop joint cutting is neat, clear up joint surface dust and remove within the scope of connector 5cm from Viscose glue;
2.3) connector heat cure connects, and 3cm wide raw rubber connection strap is put among seam, and sealing belt lacing fin is all embedding Enter in joint mold, closed joint equipment, is forced into 10MPa, power supply is closed after 20min, welding terminates;
2.4) glue is covered, self-adhesion adhesive tape is covered in self-adhesion water stop band joint.
CN201811269871.8A 2018-10-29 2018-10-29 A kind of railway tunnel self-adhesive waterproof material and its construction method Pending CN109441491A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811269871.8A CN109441491A (en) 2018-10-29 2018-10-29 A kind of railway tunnel self-adhesive waterproof material and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811269871.8A CN109441491A (en) 2018-10-29 2018-10-29 A kind of railway tunnel self-adhesive waterproof material and its construction method

Publications (1)

Publication Number Publication Date
CN109441491A true CN109441491A (en) 2019-03-08

Family

ID=65550158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811269871.8A Pending CN109441491A (en) 2018-10-29 2018-10-29 A kind of railway tunnel self-adhesive waterproof material and its construction method

Country Status (1)

Country Link
CN (1) CN109441491A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056376A (en) * 2019-03-12 2019-07-26 中交一公局桥隧工程有限公司 Tunnel waterproof plate lapping process
CN110486037A (en) * 2019-08-26 2019-11-22 中铁二局第一工程有限公司 A kind of constructing structure that railway tunnel vault prevents two lining vaults from coming to nothing and method
CN110617083A (en) * 2019-10-12 2019-12-27 重庆建工建筑产业技术研究院有限公司 Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN112096426A (en) * 2020-09-04 2020-12-18 江苏凯伦建材股份有限公司 Self-adhesive waterproof and drainage integrated plate for tunnel and application thereof
CN112228122A (en) * 2020-12-02 2021-01-15 苏州凯伦高分子新材料科技有限公司 Drainage-prevention combined self-adhesive waterproof board for mine-method underground excavation tunnel and construction method thereof
CN112360519A (en) * 2020-10-28 2021-02-12 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200949469Y (en) * 2006-06-02 2007-09-19 郑远黎 Self-adhering partition water-proof plates
CN101260809A (en) * 2008-04-18 2008-09-10 中铁一局集团有限公司 Back surface stuck AB fastener self-adhering -type water-proof board construction process
CN104018857A (en) * 2014-03-26 2014-09-03 福州市规划设计研究院 Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel
JP2014163090A (en) * 2013-02-25 2014-09-08 Kfc Ltd Tunnel structure and construction method thereof
CN105840215A (en) * 2016-04-12 2016-08-10 四川皓德斯新材料科技有限公司 Tunnel waterproof board bonding and laying process
CN205578014U (en) * 2016-04-16 2016-09-14 衡水中铁建工程橡胶有限责任公司 Plastics waterproof board with prevent scurrying water function
CN106168136A (en) * 2016-08-15 2016-11-30 中国铁道科学研究院铁道建筑研究所 Self-adhesive waterproof plate, draining board, drainable waterproofing plate
CN107060879A (en) * 2017-04-18 2017-08-18 衡水旗舰桥隧橡塑有限公司 A kind of easily paving hung type drain bar and its installation method
CN107327308A (en) * 2017-07-13 2017-11-07 高军 A kind of Railway Tunnel waterproof method
CN107476352A (en) * 2017-09-07 2017-12-15 中建五局第三建设有限公司 Connecting method of steel-edged rubber water stop
CN107498877A (en) * 2017-08-14 2017-12-22 合肥卓立雅工程材料科技有限公司 A kind of rubber water-proof belt lacing sweat soldering method
CN207161122U (en) * 2017-09-08 2018-03-30 中国铁道科学研究院铁道建筑研究所 Tunnel waterproof and water drainage system
CN108286447A (en) * 2018-01-19 2018-07-17 中国铁道科学研究院铁道建筑研究所 A kind of self-adhesive pad formula waterproof roll paving hanging method

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200949469Y (en) * 2006-06-02 2007-09-19 郑远黎 Self-adhering partition water-proof plates
CN101260809A (en) * 2008-04-18 2008-09-10 中铁一局集团有限公司 Back surface stuck AB fastener self-adhering -type water-proof board construction process
JP2014163090A (en) * 2013-02-25 2014-09-08 Kfc Ltd Tunnel structure and construction method thereof
CN104018857A (en) * 2014-03-26 2014-09-03 福州市规划设计研究院 Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel
CN105840215A (en) * 2016-04-12 2016-08-10 四川皓德斯新材料科技有限公司 Tunnel waterproof board bonding and laying process
CN205578014U (en) * 2016-04-16 2016-09-14 衡水中铁建工程橡胶有限责任公司 Plastics waterproof board with prevent scurrying water function
CN106168136A (en) * 2016-08-15 2016-11-30 中国铁道科学研究院铁道建筑研究所 Self-adhesive waterproof plate, draining board, drainable waterproofing plate
CN107060879A (en) * 2017-04-18 2017-08-18 衡水旗舰桥隧橡塑有限公司 A kind of easily paving hung type drain bar and its installation method
CN107327308A (en) * 2017-07-13 2017-11-07 高军 A kind of Railway Tunnel waterproof method
CN107498877A (en) * 2017-08-14 2017-12-22 合肥卓立雅工程材料科技有限公司 A kind of rubber water-proof belt lacing sweat soldering method
CN107476352A (en) * 2017-09-07 2017-12-15 中建五局第三建设有限公司 Connecting method of steel-edged rubber water stop
CN207161122U (en) * 2017-09-08 2018-03-30 中国铁道科学研究院铁道建筑研究所 Tunnel waterproof and water drainage system
CN108286447A (en) * 2018-01-19 2018-07-17 中国铁道科学研究院铁道建筑研究所 A kind of self-adhesive pad formula waterproof roll paving hanging method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑西铁路客运专线有限责任公司: "《郑西高速铁路工程总结》", 31 December 2011 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056376A (en) * 2019-03-12 2019-07-26 中交一公局桥隧工程有限公司 Tunnel waterproof plate lapping process
CN110486037A (en) * 2019-08-26 2019-11-22 中铁二局第一工程有限公司 A kind of constructing structure that railway tunnel vault prevents two lining vaults from coming to nothing and method
CN110486037B (en) * 2019-08-26 2024-04-05 中铁二局第一工程有限公司 Construction structure and method for preventing double-lining vault from being hollow for railway tunnel vault
CN110617083A (en) * 2019-10-12 2019-12-27 重庆建工建筑产业技术研究院有限公司 Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN112096426A (en) * 2020-09-04 2020-12-18 江苏凯伦建材股份有限公司 Self-adhesive waterproof and drainage integrated plate for tunnel and application thereof
CN112096426B (en) * 2020-09-04 2024-05-17 江苏凯伦建材股份有限公司 Self-adhesive drainage-preventing integrated plate for tunnel and application thereof
CN112360519A (en) * 2020-10-28 2021-02-12 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality
CN112360519B (en) * 2020-10-28 2023-02-17 中铁隧道局集团有限公司 Geotextile positioning method for positioning geotextile and improving tunnel waterproof plate laying quality
CN112228122A (en) * 2020-12-02 2021-01-15 苏州凯伦高分子新材料科技有限公司 Drainage-prevention combined self-adhesive waterproof board for mine-method underground excavation tunnel and construction method thereof

Similar Documents

Publication Publication Date Title
CN109441491A (en) A kind of railway tunnel self-adhesive waterproof material and its construction method
CN108194136B (en) Lining construction method
CN106088364B (en) A kind of basement antiseep connection structure and its construction method
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN104632277A (en) Bonded flexible water proof and drainage coiled material for road and railway tunnel and laying method thereof
CN110344879A (en) A kind of tunnel water proofing drainage system
CN210263442U (en) Deformation joint leakage repair structure
CN102817382A (en) Repair constructing method of basement deformation joint leakage
CN101748757B (en) Construction method of bentonite waterproof blankets
CN107327308A (en) A kind of Railway Tunnel waterproof method
CN102041800A (en) Method for constructing PVC (polyvinyl chloride) composite geomembrane watertight core of earth-rockfill dam
CN204646270U (en) Shield method waterproof construction system
CN205502264U (en) Waterproof structure of movement joint
CN109208651A (en) Underground engineering super-long structural body deformation joint waterproof/drainage structure construction method and structure
CN110145364A (en) A kind of construction method of tunnel water handling structure
CN106988440A (en) A kind of waterproof construction and its construction method at subway station main body and accessory interface
CN108150202A (en) Using the lining cutting waterproof/drainage structure of anti-viscous formula splash guard
CN207598266U (en) A kind of portable adjustable tunnel longitudinal direction steel side sealing carrying jig
CN212336350U (en) Deformation joint waterproof structure
CN205936663U (en) Undercut tunnel waterproof construction
CN209669813U (en) A kind of water delivery analysis on aqueduct structure seam leakage reparation structure
CN208685664U (en) A kind of city branch line underground pipe gallery construction system
CN204476468U (en) A kind of highway, the bonded flexible guarded drainage coiled material of railway tunnel
CN110847246A (en) Manufacturing method of rigid landfill seepage prevention system and rigid landfill seepage prevention system
CN115898469A (en) Tunnel secondary lining construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190308

RJ01 Rejection of invention patent application after publication