CN109441489B - Tunnel deep-buried central ditch supporting structure and supporting construction method - Google Patents

Tunnel deep-buried central ditch supporting structure and supporting construction method Download PDF

Info

Publication number
CN109441489B
CN109441489B CN201811638251.7A CN201811638251A CN109441489B CN 109441489 B CN109441489 B CN 109441489B CN 201811638251 A CN201811638251 A CN 201811638251A CN 109441489 B CN109441489 B CN 109441489B
Authority
CN
China
Prior art keywords
steel frame
primary
central
supporting
central ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811638251.7A
Other languages
Chinese (zh)
Other versions
CN109441489A (en
Inventor
王旭
吴强
孟庆余
曾青
翁东郁
高树峰
陈宇
梁文雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
China Railway Tunnel Group Erchu Co Ltd
Original Assignee
China Railway Design Corp
China Railway Tunnel Group Erchu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp, China Railway Tunnel Group Erchu Co Ltd filed Critical China Railway Design Corp
Priority to CN201811638251.7A priority Critical patent/CN109441489B/en
Publication of CN109441489A publication Critical patent/CN109441489A/en
Application granted granted Critical
Publication of CN109441489B publication Critical patent/CN109441489B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel deep-buried central ditch supporting structure and a supporting construction method, wherein the supporting structure comprises primary supporting firstly-made steel frames, the primary supporting firstly-made steel frames are arranged at intervals along the tunnel direction, gaps which are formed at the lower parts of the primary supporting firstly-made steel frames and are later-installed after the primary supporting is made, the primary supporting firstly-made steel frames are connected through longitudinal reinforcing beams, and central ditch steel frames are arranged at the lower ends of the primary supporting firstly-made steel frames; the supporting construction method comprises the following steps: and (3) performing unsealed thin shell integral support, excavating soil and stones at the central ditch part, performing central ditch steel frame, placing a central drain pipe, performing steel frame after performing primary support, and completing construction. The invention has novel design concept, reasonable measures and obvious effect, solves the problems of safety and quick construction of the excavation construction of the tunnel deep-buried central ditch section under the condition that the inverted arch primary support is not closed into a ring, ensures the stability and reliability of the tunnel support structure and has wide application prospect.

Description

Tunnel deep-buried central ditch supporting structure and supporting construction method
Technical Field
The invention belongs to the field of supporting structures and supporting construction methods, and particularly relates to a supporting structure of a deep-buried central ditch of a tunnel and a supporting construction method.
Background
In recent years, a plurality of railways in severe cold or cold areas are built and planned in China, and a deep-buried central ditch drainage mode is mostly adopted in railway tunnels in cold areas so as to reduce the risk of freezing injury. However, the deep buried central ditch is arranged below the inverted arch, so that the construction process is implemented under the condition that the primary support of the tunnel is not closed into a ring, and under the condition of weak surrounding rock, if the construction method is improper, the overall stability of the tunnel support structure is reduced, deformation and damage of the support structure are possibly caused, and potential safety hazards are caused to tunnel construction.
Disclosure of Invention
The invention provides a tunnel deep-buried central ditch supporting structure and a supporting construction method, which aim to solve the problems existing in the prior art.
The technical scheme of the invention is as follows: the utility model provides a tunnel buries central ditch supporting construction deeply, includes that the preliminary bracing is first to be made the steelframe, the preliminary bracing is first to be made the steelframe and is set up along tunnel direction interval, and preliminary bracing is first to be made the steelframe lower part and is formed the breach that the steelframe was made after the preliminary bracing of later stage installation, links to each other through vertical stiffening beam between the preliminary bracing first to be made the steelframe, the preliminary bracing is first to be made the steelframe lower extreme and is provided with central ditch steelframe.
The central drain pipe base is arranged in the central drain pipe steel frame, a central drain pipe and graded broken stone are arranged at the upper end of the central drain pipe base, and heat-insulating concrete is arranged at the upper end of the graded broken stone.
And the joint of the primary support firstly applied steel frame and the longitudinal reinforcing beam is provided with a foot locking anchor rod.
The primary support is firstly applied to a steel frame and then is connected with the primary support through a No. I connecting plate.
The primary support is firstly applied to the steel frame and the outer wall of the joint of the primary support and the steel frame is respectively provided with a No. I connecting plate, and the bolt and nut assembly penetrates through the No. I connecting plates to fix the primary support.
The primary support is firstly applied to the steel frame and is connected with the central ditch steel frame through a No. II connecting plate.
The primary support is firstly applied to the outer wall of the lower side of the steel frame, the outer wall of the end part of the central ditch steel frame is provided with a No. II connecting plate, and the bolt and nut assembly penetrates through the No. II connecting plate to fix the primary support.
A supporting construction method of a tunnel deep-buried central ditch supporting structure comprises the following steps:
integral support of thin shell without closure
Under the condition that the primary support is firstly applied to a steel frame and is not closed to form a ring, the primary support which is connected along the tunnel direction by adopting a longitudinal stiffening beam is firstly applied to the steel frame, and the primary support is firstly applied to the steel frame and a Shi Zuosuo foot anchor rod at the staggered part of the longitudinal stiffening beam, so that a stable thin-shell integral support system is formed by a plurality of unsealed steel frames.
Ii, excavating soil and stones at the central ditch part and applying soil and stones to the central ditch steel frame
And excavating soil and stones at the central ditch under the protection of the thin shell supporting system, constructing a central ditch steel frame, reliably connecting the central ditch steel frame with the constructed steel frame of the primary support through a No. I connecting plate, and finally completing the sprayed concrete at the deep-buried central ditch.
Iii placing center drain pipe
Under the condition that an initial support is firstly applied to a steel frame and is connected with a central ditch steel frame to form a closed support system, a central water pipe base is paved, a central drain pipe is arranged on the central water pipe base, and graded broken stone and heat-insulating concrete are arranged on the upper part of the central drain pipe.
Iv post-construction steel frame for primary support construction
And finally, adopting a II-type connecting plate to connect the primary support corresponding to the deep-buried central ditch with the primary support firstly-applied steel frame after being applied to the primary support.
V, finishing the construction
And (5) spraying concrete to finish excavation and support of the deep-buried central ditch section.
The primary support is firstly applied to a steel frame and the longitudinal reinforcing beams are combined to form a plurality of unsealed steel frames.
The primary support is firstly applied to a steel frame, a longitudinal stiffening beam and a foot locking anchor rod to form a thin-shell integral support system.
The invention aims at the tunnel deep-buried central ditch section in the cold and severe cold region to carry out excavation supporting, has novel design concept, reasonable measures and obvious effect, well solves the problems of safety and quick construction of the excavation construction of the tunnel deep-buried central ditch section under the condition that the inverted arch primary support is not closed into a ring, ensures the stability and reliability of the tunnel supporting structure and has wide application prospect.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a cross-sectional view taken along line I-I of FIG. 1;
FIG. 3 is a cross-sectional view taken along line II-II in FIG. 1;
FIG. 4 is an enlarged schematic view of the structure of the portion A in FIG. 1;
FIG. 5 is an enlarged schematic view of the structure of the portion B in FIG. 1;
FIG. 6 is a flow chart of a support construction method of the present invention;
wherein:
1. the primary support is firstly applied to the longitudinal stiffening beam of the steel frame 2
3. Soil and stones at central ditch of foot locking anchor rod 4
5. Center drain pipe base of center ditch steel frame 6
7. 8-grade crushed stone for central drain pipe
9. Steel frame applied after initial support of heat-insulating concrete 10
11. No. I connecting plate 12 No. II connecting plate.
Detailed Description
The present invention will be described in detail below with reference to the drawings and examples:
as shown in fig. 1 to 5, a tunnel deep-buried central ditch supporting structure comprises primary supporting steel frames 1, wherein the primary supporting steel frames 1 are arranged at intervals along the tunnel direction, gaps are formed in the lower parts of the primary supporting steel frames 1 after the primary supporting steel frames are installed at the later stage, the primary supporting steel frames 1 are connected through longitudinal reinforcing beams 2, and central ditch steel frames 5 are arranged at the lower ends of the primary supporting steel frames 1.
The primary support is firstly applied to the steel frame 1, and then is applied to the steel frame 10 to be combined to form a ring shape.
The primary support is firstly applied to the steel frame 1 and uniformly distributed at equal intervals.
The central drain pipe base 6 is arranged in the central drain pipe steel frame 5, a central drain pipe 7 and graded broken stone 8 are arranged at the upper end of the central drain pipe base 6, and heat-insulating concrete 9 is arranged at the upper end of the graded broken stone 8.
The cross section of the central ditch steel frame 5 is open.
The primary support is firstly applied to the joint of the steel frame 1 and the longitudinal reinforcing beam 2, and the foot locking anchor rods 3 are arranged.
The primary support is firstly applied to the steel frame 1 and then is applied to the steel frame 10 through the I-shaped connecting plate 11.
The primary support is firstly applied to the steel frame 1 and the primary support is then applied to the outer wall of the joint of the steel frame 10, the I-shaped connecting plates 11 are arranged on the outer wall, and the bolt and nut assemblies penetrate through the I-shaped connecting plates 11 to fix the primary support.
The primary support is firstly applied to the steel frame 1 and is connected with the central ditch steel frame 5 through a II-type connecting plate 12.
The primary support is firstly applied to the outer wall of the lower side of the steel frame 1, the outer wall of the end part of the central ditch steel frame 5 is provided with a No. II connecting plate 12, and the bolt and nut assembly penetrates through the No. II connecting plate 12 to fix the primary support.
As shown in fig. 6, a supporting construction method of a supporting structure of a deep buried central ditch of a tunnel comprises the following steps:
integral support of thin shell without closure
Under the condition that the primary support is firstly applied to the steel frame 1 and is not closed to form a ring, the primary support which is connected along the tunnel direction by the longitudinal reinforcing beams 2 is firstly applied to the steel frame 1, and the primary support is firstly applied to the steel frame 1 and the Shi Zuosuo foot anchor rods 3 at the staggered parts of the longitudinal reinforcing beams 2, so that a stable thin-shell integral support system is formed by the plurality of unsealed steel frames.
Ii, excavating soil and stones at the central ditch part and applying soil and stones to the central ditch steel frame
And excavating soil and stones 4 at the central ditch under the protection of a thin shell supporting system, constructing a central ditch steel frame 5, reliably connecting the soil and stones with the initial supporting construction steel frame 1 through a No. I connecting plate 11, and finally completing the shotcrete at the deep-buried central ditch.
Iii placing center drain pipe
Under the condition that the primary support is firstly applied to a steel frame 1 and is connected with a central ditch steel frame 5 to form a closed support system, a central water pipe base 6 is paved, a central drain pipe 7 is arranged on the central water pipe base 6, and graded broken stone 8 and heat-insulating concrete 9 are arranged on the upper part of the central drain pipe 7.
Iv post-construction steel frame for primary support construction
Finally, the primary support corresponding to the deep-buried central ditch is applied to the steel frame 10 by adopting the II-type connecting plate 12, and the primary support is firstly applied to the steel frame 1 to be connected.
V, finishing the construction
And (5) spraying concrete to finish excavation and support of the deep-buried central ditch section.
The primary support is firstly applied to a steel frame 1 and a longitudinal reinforcing beam 2 to form a plurality of unsealed steel frames.
The primary support is firstly applied to a steel frame 1, a longitudinal reinforcing beam 2 and a foot locking anchor rod 3 to form a thin-shell integral support system.
The thin-shell integral supporting system provides protection for excavating soil and stones at the central ditch part and applying the soil and stones to the central ditch steel frame, and ensures the feasibility of construction of the thin-shell integral supporting system.
Furthermore, the primary support is firstly applied to the steel frame 1, the longitudinal reinforcement beam 2, the foot locking anchor rods 3 and the central ditch steel frame 5 to form a closed support system, so that the protection is provided for the laying of the central water pipe base 6 and the placement of the central water drain pipe 7, and the feasibility of the construction is ensured.
After the construction of the central drainage ditch is completed, the primary support is firstly applied to the notch of the steel frame 1, and then the steel frame 10 is applied, so that the primary support is closed into a ring.
The invention aims at the tunnel deep-buried central ditch section in the cold and severe cold region to carry out excavation supporting, has novel design concept, reasonable measures and obvious effect, well solves the problems of safety and quick construction of the excavation construction of the tunnel deep-buried central ditch section under the condition that the inverted arch primary support is not closed into a ring, ensures the stability and reliability of the tunnel supporting structure and has wide application prospect.

Claims (7)

1. A supporting construction method of a tunnel deep-buried central ditch supporting structure is characterized by comprising the following steps:
the tunnel deep-buried central ditch supporting structure comprises primary supporting construction steel frames (1), wherein the primary supporting construction steel frames (1) are arranged at intervals along the tunnel direction, gaps are formed in the lower parts of the primary supporting construction steel frames (1) after the primary supporting construction steel frames (10) are arranged at the later stage, the primary supporting construction steel frames (1) are connected through longitudinal reinforcing beams (2), central ditch steel frames (5) are arranged at the lower ends of the primary supporting construction steel frames (1), and the primary supporting construction steel frames (1) and the longitudinal reinforcing beams (2) are combined to form unsealed multiple steel frames; the primary support is firstly applied to a steel frame (1), a longitudinal stiffening beam (2) and a foot locking anchor rod (3) to form a thin-shell integral support system;
the supporting construction method of the tunnel deep-buried central ditch supporting structure comprises the following steps:
integral support of thin shell without closure
Under the condition that the primary support is firstly applied to a steel frame (1) and is not closed to form a ring, connecting the primary support along the tunnel direction by adopting a longitudinal stiffening beam (2), firstly applying the primary support to the steel frame (1), and applying Shi Zuosuo pin anchors (3) at the staggered positions of the longitudinal stiffening beam (2) to the primary support, so that a stable thin-shell integral support system is formed by a plurality of unsealed steel frames;
(ii) excavating earth and stones at the central ditch part and applying the earth and stones to the central ditch steel frame
Excavating soil and stones (4) at the central ditch under the protection of a thin shell supporting system, constructing a central ditch steel frame (5), reliably connecting the soil and stones with the initial supporting constructed steel frame (1) through a No. I connecting plate (11), and finally completing the shotcrete at the deep-buried central ditch;
(iii) placing a center drain pipe
Under the condition that an initial support is firstly applied to a steel frame (1) and is connected with a central ditch steel frame (5) to form a closed support system, a central water pipe base (6) is paved, a central drain pipe (7) is arranged on the central water pipe base (6), and graded broken stones (8) and heat-insulating concrete (9) are arranged on the upper part of the central drain pipe (7);
(iv) post-construction of the Primary support Steel frame
Finally, a II connecting plate (12) is adopted to connect the primary support post-construction steel frame (10) corresponding to the deep-buried central ditch with the primary support post-construction steel frame (1), and after the construction of the central ditch is finished, the primary support post-construction steel frame (10) is installed at the notch of the primary support post-construction steel frame (1), so that the primary support is closed into a ring;
(v) completing the construction
And (5) spraying concrete to finish excavation and support of the deep-buried central ditch section.
2. The supporting construction method of the tunnel deep-buried central ditch supporting structure according to claim 1, which is characterized by comprising the following steps: the central drain pipe base (6) is arranged in the central drain pipe steel frame (5), a central drain pipe (7) and graded broken stone (8) are arranged at the upper end of the central drain pipe base (6), and heat-insulating concrete (9) is arranged at the upper end of the graded broken stone (8).
3. The supporting construction method of the tunnel deep-buried central ditch supporting structure according to claim 1, which is characterized by comprising the following steps: the primary support is firstly applied to the joint of the steel frame (1) and the longitudinal reinforcing beam (2), and the foot locking anchor rod (3) is arranged.
4. The supporting construction method of the tunnel deep-buried central ditch supporting structure according to claim 1, which is characterized by comprising the following steps: the primary support is firstly applied to the steel frame (1) and then is applied to the steel frame (10) to be connected through the I-shaped connecting plate (11).
5. The supporting construction method of the tunnel deep-buried central ditch supporting structure, which is characterized by comprising the following steps of: the primary support is firstly applied to the steel frame (1) and then is applied to the outer wall of the joint of the steel frame (10), the I-shaped connecting plates (11) are arranged on the outer wall of the joint, and the bolt and nut assemblies penetrate through the I-shaped connecting plates (11) to fix the primary support.
6. The supporting construction method of the tunnel deep-buried central ditch supporting structure according to claim 1, which is characterized by comprising the following steps: the primary support is firstly applied to the steel frame (1) and is connected with the central ditch steel frame (5) through a II-type connecting plate (12).
7. The supporting construction method of the tunnel deep-buried central ditch supporting structure according to claim 6, which is characterized in that: the primary support is firstly applied to the outer wall of the lower side of the steel frame (1) and the outer wall of the end part of the central ditch steel frame (5), and is provided with a No. II connecting plate (12), and the bolt and nut assembly penetrates through the No. II connecting plate (12) to fix the primary support.
CN201811638251.7A 2018-12-29 2018-12-29 Tunnel deep-buried central ditch supporting structure and supporting construction method Active CN109441489B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811638251.7A CN109441489B (en) 2018-12-29 2018-12-29 Tunnel deep-buried central ditch supporting structure and supporting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811638251.7A CN109441489B (en) 2018-12-29 2018-12-29 Tunnel deep-buried central ditch supporting structure and supporting construction method

Publications (2)

Publication Number Publication Date
CN109441489A CN109441489A (en) 2019-03-08
CN109441489B true CN109441489B (en) 2024-04-05

Family

ID=65539684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811638251.7A Active CN109441489B (en) 2018-12-29 2018-12-29 Tunnel deep-buried central ditch supporting structure and supporting construction method

Country Status (1)

Country Link
CN (1) CN109441489B (en)

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
JP2013234459A (en) * 2012-05-07 2013-11-21 Sekisui Chem Co Ltd Fireproofing protection structure for steelwork
CN204457864U (en) * 2015-01-19 2015-07-08 中铁十八局集团有限公司 The narrow tunnel drainage structure of a kind of rich water
CN104989451A (en) * 2015-07-15 2015-10-21 山东大学 Method for treating operating tunnel leakage with water diversion plate
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain
CN105673074A (en) * 2016-01-19 2016-06-15 铁道第三勘察设计院集团有限公司 Tunnel base local deep-buried drainage ditch structure
CN205477742U (en) * 2016-01-19 2016-08-17 西南交通大学 Drainage structures suitable for tunnel bottom in rich water rock stratum
CN105909279A (en) * 2016-06-30 2016-08-31 中铁隧道集团有限公司 Construction method for preventing primary support of tunnel in water-rich stratum from water permeation through drilling and blasting method
CN105971667A (en) * 2016-07-20 2016-09-28 中铁二院昆明勘察设计研究院有限责任公司 Preventing and treating structure for water-rich railway tunnel ballast bed mud pumping
CN206338090U (en) * 2017-01-05 2017-07-18 中铁工程设计咨询集团有限公司 A kind of tunnel central drainage pipe
CN106988767A (en) * 2017-04-06 2017-07-28 铁道第三勘察设计院集团有限公司 The Support System in Soft Rock Tunnels supporting construction of buried Central drain
CN206468375U (en) * 2016-10-26 2017-09-05 铁道第三勘察设计院集团有限公司 Inverted arch steelframe strengthens ring structure at a kind of buried Central drain inspection shaft in tunnel
CN107201908A (en) * 2017-06-16 2017-09-26 中铁五局集团有限公司 A kind of construction method of the regional buried Central drain in tunnel of bitter cold
CN206530363U (en) * 2016-08-30 2017-09-29 中铁二院工程集团有限责任公司 One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN206636578U (en) * 2017-03-21 2017-11-14 中国铁路总公司 One kind is used for tunnel Central drain monoblock type plate device
CN108005673A (en) * 2017-12-05 2018-05-08 中国铁路设计集团有限公司 A kind of buried Central drain excavation method in tunnel of reserved foundation back-pressure soil
CN108035770A (en) * 2017-12-10 2018-05-15 成都隶盈科技有限公司 A kind of power tunnel construction method
CN108468555A (en) * 2017-12-27 2018-08-31 中铁二院工程集团有限责任公司 A kind of lining cutting of single-track railway floor type and its drainage system construction that inspection shaft is set using refuge chamber
CN208168935U (en) * 2018-05-07 2018-11-30 新疆铁道勘察设计院有限公司 The center heat preservation ditch structure of severe cold area single-track railway tunnel
CN209457947U (en) * 2018-12-29 2019-10-01 中国铁路设计集团有限公司 A kind of buried Central drain supporting construction in tunnel

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013234459A (en) * 2012-05-07 2013-11-21 Sekisui Chem Co Ltd Fireproofing protection structure for steelwork
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
CN204457864U (en) * 2015-01-19 2015-07-08 中铁十八局集团有限公司 The narrow tunnel drainage structure of a kind of rich water
CN104989451A (en) * 2015-07-15 2015-10-21 山东大学 Method for treating operating tunnel leakage with water diversion plate
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain
CN205477742U (en) * 2016-01-19 2016-08-17 西南交通大学 Drainage structures suitable for tunnel bottom in rich water rock stratum
CN105673074A (en) * 2016-01-19 2016-06-15 铁道第三勘察设计院集团有限公司 Tunnel base local deep-buried drainage ditch structure
CN105909279A (en) * 2016-06-30 2016-08-31 中铁隧道集团有限公司 Construction method for preventing primary support of tunnel in water-rich stratum from water permeation through drilling and blasting method
CN105971667A (en) * 2016-07-20 2016-09-28 中铁二院昆明勘察设计研究院有限责任公司 Preventing and treating structure for water-rich railway tunnel ballast bed mud pumping
CN206530363U (en) * 2016-08-30 2017-09-29 中铁二院工程集团有限责任公司 One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN206468375U (en) * 2016-10-26 2017-09-05 铁道第三勘察设计院集团有限公司 Inverted arch steelframe strengthens ring structure at a kind of buried Central drain inspection shaft in tunnel
CN206338090U (en) * 2017-01-05 2017-07-18 中铁工程设计咨询集团有限公司 A kind of tunnel central drainage pipe
CN206636578U (en) * 2017-03-21 2017-11-14 中国铁路总公司 One kind is used for tunnel Central drain monoblock type plate device
CN106988767A (en) * 2017-04-06 2017-07-28 铁道第三勘察设计院集团有限公司 The Support System in Soft Rock Tunnels supporting construction of buried Central drain
CN107201908A (en) * 2017-06-16 2017-09-26 中铁五局集团有限公司 A kind of construction method of the regional buried Central drain in tunnel of bitter cold
CN108005673A (en) * 2017-12-05 2018-05-08 中国铁路设计集团有限公司 A kind of buried Central drain excavation method in tunnel of reserved foundation back-pressure soil
CN108035770A (en) * 2017-12-10 2018-05-15 成都隶盈科技有限公司 A kind of power tunnel construction method
CN108468555A (en) * 2017-12-27 2018-08-31 中铁二院工程集团有限责任公司 A kind of lining cutting of single-track railway floor type and its drainage system construction that inspection shaft is set using refuge chamber
CN208168935U (en) * 2018-05-07 2018-11-30 新疆铁道勘察设计院有限公司 The center heat preservation ditch structure of severe cold area single-track railway tunnel
CN209457947U (en) * 2018-12-29 2019-10-01 中国铁路设计集团有限公司 A kind of buried Central drain supporting construction in tunnel

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
严寒地区隧道深埋中心水沟施工技术;曹建;邓世超;;建筑与预算(第04期);第60-62页 *
严寒地区高速铁路隧道深埋中心水沟施工技术;赵岩;;铁道建筑技术(第02期);全文 *
赵岩 ; .严寒地区高速铁路隧道深埋中心水沟施工技术.铁道建筑技术.2018,(第02期),全文. *

Also Published As

Publication number Publication date
CN109441489A (en) 2019-03-08

Similar Documents

Publication Publication Date Title
CN101737063B (en) Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN101769154A (en) Excavation supporting method for tunnel construction
CN104963689A (en) Three-step seven-procedure excavation method for tunnel
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN105781582A (en) Novel shallow-buried tunnel support structure applicable to urban sensitive areas and construction method of novel shallow-buried tunnel support structure applicable to urban sensitive areas
CN109372543B (en) Tunnel lining underthickness reinforcement structure and construction method
CN111520145B (en) Underground excavation tunnel primary support slope adjusting and arch changing construction method
CN106988767A (en) The Support System in Soft Rock Tunnels supporting construction of buried Central drain
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN112012762B (en) Construction method of double-layer secondary lining multi-arch tunnel structure
CN112682048A (en) Replacement and reinforcement construction method for newly-built tunnel to span existing tunnel at small clear distance
CN205475257U (en) A composite pile anchor supporting construction for deepening excavation
CN205117354U (en) Reinforcing bar grid crowd with encircle foot strengthens device temporarily
CN109441489B (en) Tunnel deep-buried central ditch supporting structure and supporting construction method
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN206503601U (en) Border on the sea high hydraulic pressure tunnel individual layer steel plate concrete composite lining structure
CN106677795B (en) Border on the sea high hydraulic pressure tunnel single layer steel plate concrete composite lining structure and mounting process
CN111411968B (en) Expanding excavation structure for shield tunnel foundation and construction method thereof
CN212003200U (en) A expand and dig structure for shield tunnel foundation is last
CN112065451B (en) Underground excavation method for underground passage
CN209457947U (en) A kind of buried Central drain supporting construction in tunnel
CN113944479A (en) Unfavorable geological tunnel three-fork construction method
CN111485560A (en) Deep foundation pit supporting structure under ultra-wide pipeline and deep foundation pit construction method under ultra-wide pipeline
CN112012761A (en) Construction method of anti-disturbance double-arch tunnel structure
CN112065479B (en) Construction method of asymmetric multi-curve double-arch tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant