CN109440770A - It is a kind of reduce piling construction noise draw a device - Google Patents

It is a kind of reduce piling construction noise draw a device Download PDF

Info

Publication number
CN109440770A
CN109440770A CN201811567120.4A CN201811567120A CN109440770A CN 109440770 A CN109440770 A CN 109440770A CN 201811567120 A CN201811567120 A CN 201811567120A CN 109440770 A CN109440770 A CN 109440770A
Authority
CN
China
Prior art keywords
stake
hammer
pile crown
cavity
piling construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811567120.4A
Other languages
Chinese (zh)
Other versions
CN109440770B (en
Inventor
钱崑
殷晓旺
陈雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Joint Insurance Engineering Consulting Co Ltd
Original Assignee
Jiangxi Joint Insurance Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Joint Insurance Engineering Consulting Co Ltd filed Critical Jiangxi Joint Insurance Engineering Consulting Co Ltd
Priority to CN201811567120.4A priority Critical patent/CN109440770B/en
Publication of CN109440770A publication Critical patent/CN109440770A/en
Application granted granted Critical
Publication of CN109440770B publication Critical patent/CN109440770B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/005Sound absorbing accessories in piling

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The present invention relates to a kind of Pile Sinking by Guide stake device, it is especially a kind of can reduce noise during piling construction draw a device.A kind of device that draws reducing piling construction noise, including hammer and pile crown, hammer is lifted in a cavity, and can be moved up and down in stake cavity;The bottom of stake is stretched out at the tip of pile crown, and top is connected in a cavity, and lifting piece is fixedly connected at the top of pile crown, and the axial direction that the other end of lifting piece passes through hammer is connect with exterior part;Driven Piles head drives stake to move down to hammer under the effect of external force.Compared with the prior art, the invention has the following advantages: 1, reduce soil layer upper side and hinder effect to pile body, improve pile sinking efficiency;2, hammer works in stake cavity, greatly reduces the noise in pile driving process.

Description

It is a kind of reduce piling construction noise draw a device
Technical field
It is especially a kind of that drawing for noise can be reduced during piling construction the present invention relates to a kind of Pile Sinking by Guide stake device Stake device.
Background technique
When traditional hammer piling is constructed, by hammering pile body wall, whole stake is squeezed into soil layer.Since hammer force is Driven Piles It is transmitted to pile crown again after body wall, certain active force loss can be generated and influence construction efficiency, while will also result in very big make an uproar Sound impacts construction area and surrounding enviroment.
Summary of the invention
Present invention aim to address problems of the prior art, provide a kind of low noise, pile sinking efficiency it is high can Reduce piling construction noise draws a device.
To achieve the goals above, the present invention adopts the following technical scheme: it is a kind of can reduce piling construction noise draw stake Device, including hammer and pile crown, hammer is lifted in a cavity, and can be moved up and down in stake cavity;Stake is stretched out at the tip of pile crown Bottom, top are connected in a cavity, and lifting piece is fixedly connected at the top of pile crown, and the other end of lifting piece passes through the axial direction of hammer It is connect with exterior part;Driven Piles head drives stake to move down to hammer under the effect of external force.
Preferably, the bottom surface setting of hammer is fluted, and groove has been embedded in cushion, the bottom surface of cushion and hammer bottom face profile one It causes, for reducing noise and protection pile crown of the hammer when hitting.
Preferably, it is provided with gasket at the top of pile crown, is provided on gasket and holds the through-hole that lifting piece passes through, shim size is big In pile crown top dimension, for being clamped with stake cavity.
Preferably, the lifting piece is sunpender.
Preferably, removable cover is provided at the top of stake, removable cover size is consistent with stake top dimension, lifting piece End is connected and fixed with removable cover.
Preferably, pass through flanged joint between stake and stake.
Preferably, the hollow loaded cylinder of interior empty outer wall closure, hollow loaded cylinder are provided between gasket at the top of pile crown Axial direction be provided with and hold the through-hole that passes through of lifting piece, hollow loaded cylinder shape is matched with stake cavity.
Preferably, the section of the stake is quadrangle, circle or other abnormity.
Preferably, the tip of the pile crown is taper.
Principle: pile crown upper gasket is to expand position, for being bonded with pile crown;There is lifting piece in centre, for pile sinking extremely Pile crown is extracted out after specified absolute altitude.By hammering direct Driven Piles bottom position, i.e. gasket and pile crown into shape, it is possible to reduce the resistance of soil layer upper side Effect to pile body improves pile sinking efficiency;Moreover, because hammer is worked in hollow cavity, applied compared to conventional piles hammering stake top Work, the noise that can be significantly reduced in pile driving process.
Compared with the prior art, the invention has the following advantages:
1, reduce effect of the soil layer upper side resistance to pile body, improve pile sinking efficiency;
2, hammer works in stake cavity, greatly reduces the noise in pile driving process.
Detailed description of the invention
Fig. 1 is 1 structural schematic diagram of the embodiment of the present invention;
Fig. 2 is the structural schematic diagram hammered into shape in Fig. 1;
Fig. 3 is gasket construction schematic diagram in Fig. 1;
Fig. 4 is pile crown structural schematic diagram in Fig. 1;
Fig. 5 is 2 structural schematic diagram of the embodiment of the present invention;
Fig. 6 is 3 structural schematic diagram of the embodiment of the present invention;
In figure, 1, hammer;2, lifting rope;3, cushion;4, gasket;5, pile crown;6, sunpender;7, cover board;8, stake;9, hollow loaded cylinder.
Specific embodiment
It should be noted that in an embodiment of the present invention, the noun of locality: upper and lower, top, bottom etc. are according to attached It is described, is not construed as limiting the invention shown in figure.Identical structure is using unified number mark in embodiment 1-3.
1-6 is further described the present invention with reference to the accompanying drawing:
Embodiment 1
As shown in Figs 1-4, a kind of device that draws reducing piling construction noise, including hammer 1 and pile crown 5, hammer 1 pass through lifting rope 2 It is lifted in 8 cavity of stake, external force pulls lifting rope 2 to move up and down hammer 1 in 8 cavity of stake;It is provided in the bottom cavity of stake 8 Protrusion, protrusion are arranged around stake cavity inside diameter;The tip of pile crown 5 is taper, stretches out the bottom of stake 8, and gasket 4, pad is arranged in top The outer dimension of piece 4 is slightly larger than 5 top dimension of pile crown, and matches with protrusion, and pile crown 5 is connected in a cavity by gasket 4 In protrusion;Sunpender 6 is connected and fixed at the top of pile crown 5, the axial direction that the other end of sunpender 6 passes through hammer 1 is connect with exterior part, for working as Pile crown is extracted out from stake 8 after pile sinking to specified absolute altitude;Hammering pile crown 5 drives stake to move down to hammer under the effect of external force.
In order to which the noise for hammering pile crown 5 during the pile driving process is smaller, groove is opened up hammering 1 bottom into shape, groove embeds cushion 3, The shape of cushion 3 is matched with hammer bottom face profile, can be moved with moving up and down for hammer, for reducing noise of the hammer when hitting With protection pile crown.
When pile sinking, it will first be arrived in stake cavity under pile crown, gasket 4, hammer 1 then sequentially passed through into the sunpender 6 on pile crown, external force Lifting rope is pulled to make hammer hammering gasket 4, pile crown drives stake not have underground layer gradually downwards, and when reaching elevation location, external force is pulled Lifting rope lifts hammer, and sunpender is then pulled to pull out gasket, pile crown;Then a certain amount of concrete is poured into stake, then is placed in Pile crown is squeezed by secondary hammering, and stake bottom holding force rock-soil layer is downwardly and outwardly squeezed to diffusion and eventually forms closely knit concrete enlarged footing. Then hammering device will be hung out later again, and will continue that concrete will be perfused into stake, until completion.
Embodiment 2
As shown in figure 5, a kind of device that draws that can reduce piling construction noise, including hammer 1 and pile crown 5, hammer 1 are hung by lifting rope 2 Loaded in 8 cavity of stake, external force pulls lifting rope 2 to move up and down hammer 1 in 8 cavity of stake;It is provided in the bottom cavity of stake 8 convex It rises, protrusion is arranged around stake cavity inside diameter;The tip of pile crown 5 is taper, stretches out the bottom of stake 8, and gasket 4, gasket 4 is arranged in top Outer dimension be slightly larger than 5 top dimension of pile crown, and with protrusion match, pile crown 5 pass through gasket 4 be connected in the protrusion in a cavity On;Sunpender 6 is connected and fixed at the top of pile crown 5, the axial direction that the other end of sunpender 6 passes through hammer 1 is connect with exterior part, for working as pile sinking Pile crown is extracted out from stake 8 after to specified absolute altitude;Hammering pile crown 5 drives stake to move down to hammer under the effect of external force.
In order to improve construction efficiency, cover board 7 is set at the top of stake, the size of the cover plate is consistent with stake top dimension, i.e. cover board Hammer is limited in 8 cavity of stake;The end of sunpender 6 is pierced by cover board 7 and is attached thereto fixation.Since the end of cover board 7 is just covered It covers in the top circumference of stake 8, when hammer hammers pile crown 5, cover board 7 can be driven by sunpender 6, application acts on pile lining Power drives stake to move down;Pile crown drives stake to move down simultaneously, improves construction efficiency.
When pile sinking, it will first be arrived in stake cavity under pile crown, gasket 4, hammer 1 then sequentially passed through into the sunpender 6 on pile crown, external force Lifting rope is pulled to make hammer hammering gasket 4, pile crown 5 and cover board 7 drive stake not have underground layer gradually downwards, when reaching elevation location, External force pulls lifting rope to lift hammer together with cover board, gasket and pile crown;Then a certain amount of concrete is poured into stake, then is set Enter pile crown, squeezed by secondary hammering, stake bottom holding force rock-soil layer is downwardly and outwardly squeezed to diffusion and eventually forms closely knit concrete expansion Head.Then hammering device will be hung out later again, and will continue that concrete will be perfused into stake, until completion.
Embodiment 3
As shown in fig. 6, it is a kind of can reduce piling construction noise draw a device, it is similar with the structure in embodiment 1, it is secondary no longer It repeats.
, can be in the junction connecting flange of stake 8 and stake 8 when carrying out pile sinking after needing more pile connections, while padding The hollow loaded cylinder 9 of empty outer wall closure in arranging between piece 4 and pile crown 5, the hollow needs of loaded cylinder 9 are matched with stake cavity inside diameter, And its height need to arrive the junction of flange just, gasket 4 is just placed on the upper surface of a flange, and sunpender is disposed through sky Through-hole on 9 axis of heart loaded cylinder, by hammering the gasket on hollow loaded cylinder 9, gasket and pile crown drive stake to move down reality Existing pile sinking.
Two section stakes by flanged joint together, when pile sinking, hammer 1, gasket 4, hollow loaded cylinder 9 axially extending bore successively wear The sunpender 6 on pile crown, the gasket 4 that external force pulls lifting rope that hammer is made to hammer hollow 9 top of loaded cylinder are crossed, pile crown 5 drives stake downward Do not have underground layer gradually, when reaching elevation location, external force pulls lifting rope to lift hammer, then pulls sunpender 6 by pile crown 5, gasket 4 And hollow loaded cylinder 9 pulls out;Then a certain amount of concrete is poured into stake, then is placed in pile crown, is squeezed by secondary hammering, it will Stake bottom holding force rock-soil layer downwardly and outwardly squeezes diffusion and eventually forms closely knit concrete enlarged footing.Then hammering device will be hung later again Out, continue that concrete is perfused into stake, until completion.
Above-described embodiment is only not to be construed as limiting the invention to further explanation of the invention.In embodiment 2 Cover board can also be simultaneously in embodiment 3;In addition, the cross sectional shape of stake can for quadrangle, circle or other abnormity, when So, hammer, gasket, the hollow loaded cylinder of interior empty outer wall closure, pile crown shape also must the shape of foundation stake make corresponding change. The tip of pile crown is not limited to the taper in embodiment, can also be other shapes.Those of ordinary skill in the art are in the present invention On the basis of done any amplification, deformation be within the scope of the invention.

Claims (9)

1. one kind can reduce the device that draws of piling construction noise, including hammer and pile crown, it is characterised in that: hammer is lifted on a cavity It is interior, and can be moved up and down in stake cavity;The bottom of stake is stretched out at the tip of pile crown, and top is connected in a cavity, on pile crown top Portion is fixedly connected with lifting piece, and the axial direction that the other end of lifting piece passes through hammer is connect with exterior part;Hammer is hammered into shape under the effect of external force Hitting pile crown drives stake to move down.
2. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: the bottom surface of hammer is arranged Fluted, groove has been embedded in cushion, and the bottom surface of cushion is consistent with hammer bottom face profile.
3. it is according to claim 1 or 2 reduce piling construction noise draw a device, it is characterised in that: on pile crown top Portion is provided with gasket, is provided on gasket and holds the through-hole that lifting piece passes through, and shim size is greater than pile crown top dimension, is used for and stake Cavity clamping.
4. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: the lifting piece is Sunpender.
5. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: set at the top of stake It is equipped with removable cover, removable cover size is consistent with stake top dimension, and end and the removable cover of lifting piece are connected and fixed.
6. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: lead between stake and stake Cross flanged joint.
7. it is according to claim 3 reduce piling construction noise draw a device, it is characterised in that: at the top of pile crown with Be provided with the hollow loaded cylinder of interior empty outer wall closure between gasket, the axial direction of hollow loaded cylinder be provided with hold lifting piece pass through it is logical Hole, hollow loaded cylinder shape are matched with stake cavity.
8. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: the section of the stake For quadrangle, circle or other abnormity.
9. it is according to claim 1 reduce piling construction noise draw a device, it is characterised in that: the point of the pile crown End is taper.
CN201811567120.4A 2018-12-21 2018-12-21 Pile guiding device capable of reducing pile sinking construction noise Active CN109440770B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811567120.4A CN109440770B (en) 2018-12-21 2018-12-21 Pile guiding device capable of reducing pile sinking construction noise

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811567120.4A CN109440770B (en) 2018-12-21 2018-12-21 Pile guiding device capable of reducing pile sinking construction noise

Publications (2)

Publication Number Publication Date
CN109440770A true CN109440770A (en) 2019-03-08
CN109440770B CN109440770B (en) 2024-03-29

Family

ID=65560162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811567120.4A Active CN109440770B (en) 2018-12-21 2018-12-21 Pile guiding device capable of reducing pile sinking construction noise

Country Status (1)

Country Link
CN (1) CN109440770B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115031058A (en) * 2022-06-08 2022-09-09 中国建筑土木建设有限公司 Short-distance excavation-free sleeve pre-embedding device and method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB576236A (en) * 1944-07-17 1946-03-25 West S Piling & Construction C Improvements relating to the driving of piles
US5449253A (en) * 1992-07-31 1995-09-12 Bouygues Offshore Method and apparatus for driving a tube into the ground by hammering, in particular for making a foundation pile
JP2002227196A (en) * 2001-02-06 2002-08-14 Shoowa Kensho:Kk Nose impact type pile and its installation method
CN100999900A (en) * 2006-01-09 2007-07-18 立基工程有限公司 Bottom impacting type steel pipe concrete pole and construction method thereof
CN101191330A (en) * 2006-12-02 2008-06-04 吕怀民 Construction method for large bearing capacity pile and pile foundation and inner hole deposition device
CN202247878U (en) * 2011-09-09 2012-05-30 苏州力高建筑工程技术有限公司 Novel piling equipment for foundation construction
CN104099925A (en) * 2014-07-25 2014-10-15 王继忠 Construction device for concrete pile and construction method thereof
CN207739253U (en) * 2017-12-26 2018-08-17 浙江大学 Slip casting structure is surveyed at hammer piling and synchronous end in band shoe pipe pile end
CN209508971U (en) * 2018-12-21 2019-10-18 江西联保工程咨询有限公司 It is a kind of reduce piling construction noise draw a device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB576236A (en) * 1944-07-17 1946-03-25 West S Piling & Construction C Improvements relating to the driving of piles
US5449253A (en) * 1992-07-31 1995-09-12 Bouygues Offshore Method and apparatus for driving a tube into the ground by hammering, in particular for making a foundation pile
JP2002227196A (en) * 2001-02-06 2002-08-14 Shoowa Kensho:Kk Nose impact type pile and its installation method
CN100999900A (en) * 2006-01-09 2007-07-18 立基工程有限公司 Bottom impacting type steel pipe concrete pole and construction method thereof
CN101191330A (en) * 2006-12-02 2008-06-04 吕怀民 Construction method for large bearing capacity pile and pile foundation and inner hole deposition device
CN202247878U (en) * 2011-09-09 2012-05-30 苏州力高建筑工程技术有限公司 Novel piling equipment for foundation construction
CN104099925A (en) * 2014-07-25 2014-10-15 王继忠 Construction device for concrete pile and construction method thereof
CN207739253U (en) * 2017-12-26 2018-08-17 浙江大学 Slip casting structure is surveyed at hammer piling and synchronous end in band shoe pipe pile end
CN209508971U (en) * 2018-12-21 2019-10-18 江西联保工程咨询有限公司 It is a kind of reduce piling construction noise draw a device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115031058A (en) * 2022-06-08 2022-09-09 中国建筑土木建设有限公司 Short-distance excavation-free sleeve pre-embedding device and method
CN115031058B (en) * 2022-06-08 2023-06-09 中国建筑土木建设有限公司 Short-distance excavation-free sleeve embedding device and method

Also Published As

Publication number Publication date
CN109440770B (en) 2024-03-29

Similar Documents

Publication Publication Date Title
US8496072B2 (en) Preloaded drop hammer for driving piles
CN207974103U (en) The isolating device of cast-in-situ bored pile pile crown
CN101672034A (en) Vibratory pile hammer for cast-in-situ bellout wedge-shaped reinforced concrete pile and construction method
CN202000352U (en) Concrete filling pile head crusher
CN209508971U (en) It is a kind of reduce piling construction noise draw a device
CN108797575B (en) Extending arm type steel pipe pile and construction method thereof
CN110725305B (en) Construction method for improving bearing capacity of oblique steel pipe pile
CN109440770A (en) It is a kind of reduce piling construction noise draw a device
CN207739253U (en) Slip casting structure is surveyed at hammer piling and synchronous end in band shoe pipe pile end
CN105926618A (en) Construction method for prefabricated piles
CN105926594A (en) Double-pipe construction method for static pressure pipe-sinking carrier cast-in-place pile
CA2641408A1 (en) Method and apparatus for building support piers from one or more successive lifts formed in a soil matrix
CN206987814U (en) A kind of plate-hammer crusher of improved structure
CN104110034B (en) The construction of Static Pressure Pile method of casting and penetrating resistance can be reduced
CN207047834U (en) A kind of construction system of hollow preformed pile
CN215441884U (en) Drilling and hammering integrated machine
CN116005667A (en) Self-force-measuring ground anchor pile and working method thereof
CN106087958B (en) The method of basement process device and basement process
CN2262568Y (en) Detachable multi-section combined pile head
CN213358613U (en) Pulling device for steel pipe slope protection pile
CN213684873U (en) Adjustable horsehead pin of oil pumping unit
CN105544507B (en) A kind of steel pipe pile device with overhanging arm
CN113863274A (en) Construction method of stable foundation
CN107060764A (en) The plate-hammer crusher and breaking method of a kind of improved structure
CN208347270U (en) A kind of construction assistance platform of rivers pile foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant