- polyurethane
- thermal
- pipe
- prefabricated direct
- outer protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009413 insulation Methods 0.000 title claims abstract description 33
- 229920003023 plastic Polymers 0.000 title claims abstract description 27
- 239000004033 plastic Substances 0.000 title claims abstract description 27
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 10
- 229920002635 polyurethane Polymers 0.000 claims abstract description 33
- 239000004814 polyurethane Substances 0.000 claims abstract description 33
- 239000010410 layer Substances 0.000 claims description 19
- 238000005187 foaming Methods 0.000 claims description 15
- 238000000034 method Methods 0.000 claims description 7
- 238000000465 moulding Methods 0.000 claims description 6
- 239000004821 Contact adhesive Substances 0.000 claims description 3
- JOYRKODLDBILNP-UHFFFAOYSA-N Ethyl urethane Chemical compound CCOC(N)=O JOYRKODLDBILNP-UHFFFAOYSA-N 0.000 claims description 3
- 238000007664 blowing Methods 0.000 claims description 3
- 238000001125 extrusion Methods 0.000 claims description 3
- 239000002245 particle Substances 0.000 claims description 3
- 239000011248 coating agent Substances 0.000 description 2
- 238000000576 coating method Methods 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 238000010276 construction Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L59/00—Thermal insulation in general
- F16L59/02—Shape or form of insulating materials, with or without coverings integral with the insulating materials
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D23/00—Producing tubular articles
- B29D23/001—Pipes; Pipe joints
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L11/00—Hoses, i.e. flexible pipes
- F16L11/04—Hoses, i.e. flexible pipes made of rubber or flexible plastics
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L11/00—Hoses, i.e. flexible pipes
- F16L11/04—Hoses, i.e. flexible pipes made of rubber or flexible plastics
- F16L11/12—Hoses, i.e. flexible pipes made of rubber or flexible plastics with arrangements for particular purposes, e.g. specially profiled, with protecting layer, heated, electrically conducting
Abstract
It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe and manufacturing method of flexible coil pipe.The ununified intelligent alarm system of current prefabricated direct-buried plastic, thermal-insulation pipe, can not predict the actual operating mode of utilidor, the ability more repaired in advance without preliminary examination, can not timeliness discovery leak source, there is the risks of prefabricated direct-buried plastic, thermal-insulation pipe booster, and then the serious accident that happens suddenly.Present invention composition includes: instrumentation tubes (1), the work tube outer surface has soft bubble layer of polyurethane (2), the soft bubble layer of polyurethane is connect by glue-line with outer protection tube (3), and 2 alarming lines (4) are equipped in the soft bubble layer of polyurethane, is corrugated outside the outer protection tube.The present invention is used for prefabricated direct-buried plastic, thermal-insulation pipe.
Description
Technical field:
The present invention relates to a kind of prefabricated direct-buried plastic, thermal-insulation pipes and manufacturing method for capableing of flexible coil pipe.
Background technique:
The actual life of prefabricated direct-buried plastic, thermal-insulation pipe currently on the market is unable to satisfy the design requirement of 30-50, main
The Trinity structure for meeting pipeline can not be sent out because of plastic, thermal-insulation pipe, expanded with heat and contract with cold and easily caused the de- of outer protection tube and polyurethane
It falls, aliquation.
The ununified intelligent alarm system of current prefabricated direct-buried plastic, thermal-insulation pipe, can not predict the reality of utilidor
Operating condition, the ability more repaired in advance without preliminary examination, can not timeliness discovery leak source, there is prefabricated direct-buried plastic, thermal-insulation pipes
The risk of booster, and then the serious accident that happens suddenly.
At present insulating tube due to structure it is harder, the length for being able to carry out coil pipe is small, cause the connector in specific length more,
It is easy to appear leakage problem.
Summary of the invention:
The object of the present invention is to provide a kind of prefabricated direct-buried plastic, thermal-insulation pipes and manufacturing method for capableing of flexible coil pipe.
Above-mentioned purpose is realized by following technical scheme:
A kind of prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe, composition includes: instrumentation tubes, the work tube outer surface
With soft bubble layer of polyurethane, the soft bubble layer of polyurethane is connect by glue-line with outer protection tube, in the soft bubble layer of polyurethane
2 alarming lines are installed, are corrugated outside the outer protection tube.
The prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe, the outer protection tube is PE outer protection tube.
A kind of manufacturer using the prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe described in one of claim 1-2
Method,
Uncoiler by instrumentation tubes uncoiling, unreel;
Instrumentation tubes are corrected instrumentation tubes, traction device provides pulling force for instrumentation tubes, and temperature control equipment is to work by means for correcting
Make pipe and carry out temperature control, guarantees 35-40 degrees Celsius of optimum temperature when foaming;
Adhering device provides a contact adhesive layer before foaming for foaming mould, can improve polyurethane and the bonding force of PE, moreover it is possible to rise
To the purpose of mold releasability;
Intelligent alarm line is installed;
Mold foaming, high-presure polyurethane foaming machine will be injected into polyurethane blowing mold after urethane raw high pressure mixing, real
Existing polyurethane mould is continuous foamed;
The plasticizing of PE particle is extruded into PE outer protection tube, is existed using the method for vacuum suction by the molding of PE outer protection tube, single screw extrusion machine
Polyurethane surface forms PE outer protection tube;
Dragger provides pulling force for molding insulating tube;
Cutting machine cuts pipeline according to the length of design;
The insulating tube that manufacture is completed is coiled radius according to design and coiled by winder, then bundlees, completes the system of insulating tube
It makes.
The utility model has the advantages that
The present invention is corrugated by the polyurethane insulation coating of prefabricated direct-buried plastic, thermal-insulation pipe and the design of PE outer protection tube, greatly reduces
The coiling radius of insulating tube can also produce random length so that the joint length of insulating tube greatly prolongs according to the demand of user
The customization pipeline of size.
The present invention reduces the usage quantity of repaired mouth since the length of single pipe is extended, and reduces pipeline laying
Meteorological, reduces the risk of leakage, and substantially increases the security performance of pipe network.
The present invention is since intelligent prefabricated direct buried plastic, thermal-insulation pipe is in PE outer protection tube layer and protective polyurethane layer medium design
One layer of glue-line, substantially increases the overall performance of insulating tube, has been truly realized the Trinity structure of insulating tube, and guarantor improves pre-
The service life of direct-buried thermal insulation pipe processed.
The present invention devises intelligent alarm line in the polyurethane insulation coating of prefabricated direct-buried thermal insulation pipe, and pipe network may be implemented
Intelligent monitoring, realize foresight maintenance, greatly reduce the risk of pipe burst, avoid the generation of great burst accident.
Flexible coil pipe may be implemented in the prefabricated direct-buried plastic, thermal-insulation pipe of the present invention, and single pipe length is up to hundred meters of even public affairs
In, it greatly reduced repaired mouth, reduce the construction cost of pipeline.Due to the reduction of repaired mouth quantity, prefabricated direct-buried thermal insulation pipe
Risk of leakage also decreases.
Detailed description of the invention:
Attached drawing 1 is structural schematic diagram of the invention.
Attached drawing 2 is sectional view of the invention.
Specific embodiment:
Embodiment 1:
A kind of prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe, composition includes: instrumentation tubes 1, the instrumentation tubes appearance
Face has soft bubble layer of polyurethane 2, and the soft bubble layer of polyurethane is connect by glue-line with outer protection tube 3, the soft bubble polyurethane
2 alarming lines 4 are installed in layer, are corrugated outside the outer protection tube.
The thermal coefficient of prefabricated direct-buried plastic, thermal-insulation pipe can be stable control at 0.027W/ (mK), and polyurethane density
Uniformly.
Embodiment 2:
According to the prefabricated direct-buried plastic, thermal-insulation pipe described in embodiment 1 for capableing of flexible coil pipe, the outer protection tube is PE outer protection tube.
The prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe can greatly prolong the joint length of pipeline, reduce repaired mouth
Quantity reduces the input cost that pipeline is laid with.
It can accomplish few connector even zero connector for special user, greatly improve the leakage of prefabricated direct-buried thermal insulation pipe
Risk improves the total quality of pipe network.
Since intelligent prefabricated direct buried plastic, thermal-insulation pipe is in PE outer protection tube layer and one layer of glue of protective polyurethane layer medium design
Layer, substantially increases the overall performance of insulating tube, has been truly realized the Trinity structure of insulating tube, and guarantor improves prefabricated direct-buried
The service life of insulating tube.
Embodiment 3:
It is a kind of using it is claimed in claims 1-2 being capable of the flexible prefabricated direct-buried plastic, thermal-insulation pipe of coil pipe and the manufacture of manufacturing method
Method,
Uncoiler by instrumentation tubes uncoiling, unreel;
Instrumentation tubes are corrected instrumentation tubes, traction device provides pulling force for instrumentation tubes, and temperature control equipment is to work by means for correcting
Make pipe and carry out temperature control, guarantees 35-40 degrees Celsius of optimum temperature when foaming;
Adhering device provides a contact adhesive layer before foaming for foaming mould, can improve polyurethane and the bonding force of PE, moreover it is possible to rise
To the purpose of mold releasability;
Intelligent alarm line is installed;
Mold foaming, high-presure polyurethane foaming machine will be injected into polyurethane blowing mold after urethane raw high pressure mixing, real
Existing polyurethane mould is continuous foamed;
The plasticizing of PE particle is extruded into PE outer protection tube, is existed using the method for vacuum suction by the molding of PE outer protection tube, single screw extrusion machine
Polyurethane surface forms PE outer protection tube;
Dragger provides pulling force for molding insulating tube;
Cutting machine cuts pipeline according to the length of design;
The insulating tube that manufacture is completed is coiled radius according to design and coiled by winder, then bundlees, completes the system of insulating tube
It makes.
Claims (3)
1. one kind is capable of the prefabricated direct-buried plastic, thermal-insulation pipe of flexible coil pipe, composition includes: instrumentation tubes, it is characterized in that: described
The tube outer surface that works has soft bubble layer of polyurethane, and the soft bubble layer of polyurethane is connect by glue-line with outer protection tube, and described is soft
2 alarming lines are installed in bubble layer of polyurethane, are corrugated outside the outer protection tube.
2. the prefabricated direct-buried plastic, thermal-insulation pipe according to claim 1 for capableing of flexible coil pipe, it is characterized in that: the outer shield
Pipe is PE outer protection tube.
3. a kind of manufacturer using the prefabricated direct-buried plastic, thermal-insulation pipe for capableing of flexible coil pipe described in one of claim 1-2
Method, it is characterized in that:
Uncoiler by instrumentation tubes uncoiling, unreel;
Instrumentation tubes are corrected instrumentation tubes, traction device provides pulling force for instrumentation tubes, and temperature control equipment is to work by means for correcting
Make pipe and carry out temperature control, guarantees 35-40 degrees Celsius of optimum temperature when foaming;
Adhering device provides a contact adhesive layer before foaming for foaming mould, can improve polyurethane and the bonding force of PE, moreover it is possible to rise
To the purpose of mold releasability;
Intelligent alarm line is installed;
Mold foaming, high-presure polyurethane foaming machine will be injected into polyurethane blowing mold after urethane raw high pressure mixing, real
Existing polyurethane mould is continuous foamed;
The plasticizing of PE particle is extruded into PE outer protection tube, is existed using the method for vacuum suction by the molding of PE outer protection tube, single screw extrusion machine
Polyurethane surface forms PE outer protection tube;
Dragger provides pulling force for molding insulating tube;
Cutting machine cuts pipeline according to the length of design;
The insulating tube that manufacture is completed is coiled radius according to design and coiled by winder, then bundlees, completes the system of insulating tube
It makes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811583703.6A CN109404629A (en) | 2018-12-24 | 2018-12-24 | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe and manufacturing method of flexible coil pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811583703.6A CN109404629A (en) | 2018-12-24 | 2018-12-24 | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe and manufacturing method of flexible coil pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109404629A true CN109404629A (en) | 2019-03-01 |
Family
ID=65460776
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811583703.6A Pending CN109404629A (en) | 2018-12-24 | 2018-12-24 | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe and manufacturing method of flexible coil pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109404629A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1363076A (en) * | 1970-10-12 | 1974-08-14 | British Oxygen Co Ltd | Pipeline insulation |
US6576312B1 (en) * | 1998-11-18 | 2003-06-10 | Tokai Rubber Industries, Ltd. | Fuel transporting tube |
CN104373699A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated directly-buried thermal insulation pipe crosslinked polyethylene working pipe and manufacturing method |
CN105299389A (en) * | 2015-12-08 | 2016-02-03 | 朗格斯特哈尔滨环保节能产品制造有限公司 | Thermal insulation pipe with corrugated outer protective pipe and manufacturing method for thermal insulation pipe |
CN106523809A (en) * | 2016-12-27 | 2017-03-22 | 哈尔滨朗格思特供热装备科技有限公司 | Coiled flexible polyurethane insulation pipe and production and application method |
CN106764118A (en) * | 2015-11-23 | 2017-05-31 | 青岛大仓防腐有限公司 | A kind of intelligent heat preserving pipe |
CN209245499U (en) * | 2018-12-24 | 2019-08-13 | 哈尔滨朗格斯特节能科技有限公司 | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe of flexible coil pipe |
-
2018
- 2018-12-24 CN CN201811583703.6A patent/CN109404629A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1363076A (en) * | 1970-10-12 | 1974-08-14 | British Oxygen Co Ltd | Pipeline insulation |
US6576312B1 (en) * | 1998-11-18 | 2003-06-10 | Tokai Rubber Industries, Ltd. | Fuel transporting tube |
CN104373699A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated directly-buried thermal insulation pipe crosslinked polyethylene working pipe and manufacturing method |
CN106764118A (en) * | 2015-11-23 | 2017-05-31 | 青岛大仓防腐有限公司 | A kind of intelligent heat preserving pipe |
CN105299389A (en) * | 2015-12-08 | 2016-02-03 | 朗格斯特哈尔滨环保节能产品制造有限公司 | Thermal insulation pipe with corrugated outer protective pipe and manufacturing method for thermal insulation pipe |
CN106523809A (en) * | 2016-12-27 | 2017-03-22 | 哈尔滨朗格思特供热装备科技有限公司 | Coiled flexible polyurethane insulation pipe and production and application method |
CN209245499U (en) * | 2018-12-24 | 2019-08-13 | 哈尔滨朗格斯特节能科技有限公司 | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe of flexible coil pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209245499U (en) | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe of flexible coil pipe | |
CN106641585A (en) | PPR insulating composite tube for home decoration and preparation method of composite tube | |
CN202327529U (en) | Heat-insulation water supply pipeline and heat-insulation water supply pipeline system | |
CN109404629A (en) | It is capable of the prefabricated direct-buried plastic, thermal-insulation pipe and manufacturing method of flexible coil pipe | |
CN205207953U (en) | Outer pillar insulating tube of flexible software polyethylene | |
CN202852335U (en) | Glass fiber reinforced plastic polyurethane thermal insulation pipe | |
CN201096235Y (en) | Plastic pipe material with surface foaming layer | |
KR101823512B1 (en) | Multi-tube | |
CN103971795B (en) | A kind of middle pressure crosslinked cable using method with header structure | |
CN217301937U (en) | Multilayer winding PE pipe | |
CN105351638A (en) | Bendable thermal insulation pipe with soft polyethylene outer protecting pipe and bending method | |
CN104819350A (en) | High pressure conveying pipe made from novel wax-prevention and wax-removing flexible composite plastic and production process | |
CN101749508A (en) | Integrated electric thermal insulation plastic water pipe and manufacturing process thereof | |
CN104806846B (en) | Oil transportation insulation flexible compound plastic high voltage conveying pipe production process | |
CN202510886U (en) | Lightning-protective insulation pipe fitting for gas pipeline | |
CN208107447U (en) | A kind of three-layer structure is broken hot single layer tubing | |
CN105799111A (en) | Production process and device of solar foaming insulation pipe | |
CN210034671U (en) | PP-R pipeline system for full decoration | |
CN104930272A (en) | High density polyethylene pipe and manufacturing method thereof | |
CN219530219U (en) | Heat preservation composite construction suitable for pipe clamp staple bolt is outer | |
CN214368339U (en) | Flexible interface heat supply pipeline | |
CN219221674U (en) | Joint coating device applied to prefabricated directly-buried heat-insulation pipeline | |
CN218032024U (en) | Anticorrosive heat preservation elbow | |
CN215928667U (en) | Liquid fluid transport pipe and liquid fluid transport system | |
CN212273296U (en) | Water pipe connecting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190301 |
|
WD01 | Invention patent application deemed withdrawn after publication |