CN109403321A - Construction method of filling slope prestressed anchor cable - Google Patents

Construction method of filling slope prestressed anchor cable Download PDF

Info

Publication number
CN109403321A
CN109403321A CN201811074088.6A CN201811074088A CN109403321A CN 109403321 A CN109403321 A CN 109403321A CN 201811074088 A CN201811074088 A CN 201811074088A CN 109403321 A CN109403321 A CN 109403321A
Authority
CN
China
Prior art keywords
steel bushing
prestress anchorage
anchorage cable
anchor cable
support column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811074088.6A
Other languages
Chinese (zh)
Inventor
周海清
李�灿
宋强辉
李晓雷
汪儒鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Institute of Geology and Mineral Resources
Army Service Academy of PLA
Original Assignee
Chongqing Institute of Geology and Mineral Resources
Army Service Academy of PLA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Institute of Geology and Mineral Resources, Army Service Academy of PLA filed Critical Chongqing Institute of Geology and Mineral Resources
Priority to CN201811074088.6A priority Critical patent/CN109403321A/en
Publication of CN109403321A publication Critical patent/CN109403321A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a construction method of a pre-stressed anchor cable for a filling side slope. The method comprises the installation method and the process of the anchor cable, the steel pipe and the steel column component. The multi-strand steel strand is arranged in the steel sleeve along the axis direction and is attached to the inner surface of the lower part of the steel sleeve; the steel column is fixed on the bedrock and supports the steel sleeve to prevent the steel sleeve from generating excessive deformation. The process of using the steel pipe and the steel column in a combined mode can enable the free section of the anchor cable to be prevented from being subjected to transverse shearing force, the prestressed anchor cable can work normally under the filling condition, and the safety and stability of engineering are guaranteed. The construction process has the advantages of simple steps, low production cost, small engineering quantity, improvement of the installation efficiency of the anchor cable under the condition of filling soil, shortening of the construction period, good isolation between the anchor cable and the filling soil, strong corrosion resistance and improvement of the service life. The problems of large construction work amount, long construction period and high construction cost of the protection anchor cable under the existing filling condition are solved.

Description

A kind of construction method of embankment side slope prestress anchorage cable
Technical field
The present invention relates to construction field, in particular to the construction of free section of anchor cable stress under the conditions of a kind of protection is banketed Technique.
Background technique
Prestress anchorage cable is the firm Rock And Soil that takes a proactive approach in engineering, by drilling through soft stratum or sliding Face, is anchored at one end in hard rock stratum and (claims Inner bolt head), then carries out tensioning in another free end (claiming outer anchor head), from And pressure is applied to rock stratum, unstable rock mass is anchored.
Currently, prestress anchorage cable usually applies to finally carry out tensioning in excavation and cart-away, directly drilling installation anchor cable.But It is that design of its support is usually carried out in such a way that pile plate wall is combined with prestress anchorage cable in some environmental slopes, in order to meet Ground elevation is designed, usually exists and needs the case where backfilling, prestress anchorage cable free segment a part is exposed to embankment region at this time In, if untreated, compacting and natural subsidence after banketing can generate cross shear to anchor cable, influence the stress shape of anchor cable State, makes its cisco unity malfunction, and prestressed failure cannot reach firm soil body effect, be easy to cause engineering harm.
The stressing influence to be banketed in order to prevent to anchor cable, existing traditional construction technique are banketed region in free section of anchor cable Concrete protective pier is set, by anchor cable and completely isolated, the guarantee normal stress of anchor cable of banketing.But the construction technology cost compared with Height, especially encounter basement rock position (i.e. protection pier pier bottom) apart from anchor cable farther out when, the concrete protective pier scale of construction is very big, increases Unnecessary project amount and cost.
Summary of the invention
The object of the present invention is to provide a kind of construction methods of embankment side slope prestress anchorage cable, to solve to deposit in the prior art The problem of.
To realize the present invention purpose and the technical solution adopted is that a kind of such, construction of embankment side slope prestress anchorage cable Method, comprising the following steps:
1) according to design drawing, side slope to be onstructed is handled, and by the measuring of anchor hole position in slope surface.Wherein, the side slope It from top to bottom successively include surface overburden layer, strongly weathered sand-rock, middle weathered rock formation and stable basement rock.
2) breast boards is installed.Wherein, the breast boards is fixedly connected with friction pile, forms pile plate wall.
3) diagonal brace prestress anchorage cable, sealing off and covering anchorage after prestressed stretch-draw are installed.It will be in the tensioning section of prestress anchorage cable and breast boards Side anchor is solid.It drills in slope surface, the anchoring section of prestress anchorage cable is introduced in the hole being drilled, cement injection mortar carries out anchor into hole Gu.Wherein, the prestress anchorage cable is in tilted layout.The free segment outer sheath of the prestress anchorage cable is equipped with steel bushing.
4) support column is installed.Wherein, the support column is arranged in below steel bushing.Length of the support column along steel bushing It uniformly lays in direction.The lower end of the support column is mounted in stable basement rock, and upper end connects by the way that connecting elements and steel bushing are fixed It connects.
5) wall back backfill is carried out, placement in layers compacted fill forms fill stratum to design standard height.Wherein, the freedom Section is embedded in fill stratum.The steel bushing completely cuts off free segment and fill stratum.
Further, the diameter of the free segment is d.The internal diameter of the steel bushing is D.Wherein, d=2/3D.The freedom Section is located at the lower part of steel bushing tube inner chamber.
Further, the section of the support column is circle.The support column diameter is l.Between adjacent two support columns Spacing is 12~15l.
Further, the connecting elements generally blocks.The upper surface of the connecting elements is fixedly connected with steel bushing, Lower surface is fixedly connected with the upper surface of support column.
Further, depth is not less than 500mm in the stable basement rock of steel bushing insertion.
Further, in step 5), the basis of banketing of close steel bushing part is rammed after influencing line design tamping point, using artificial Compacting mode rams steel bushing two sides and bankets.
The solution have the advantages that unquestionable:
1. guaranteeing that prestress anchorage cable free segment not by cross shear, can be played normally under embankment engineering specifications Prestressing force effect generates fastening effect to the soil body;
2. easy for construction simple, the duration is shortened, and project cost reduces.
Detailed description of the invention
Fig. 1 is operation schematic diagram;
Fig. 2 is steel bushing structural schematic diagram;
Fig. 3 is support column arrangement schematic diagram;
Fig. 4 is connecting elements schematic diagram.
In figure: prestress anchorage cable 1, free segment 102, tensioning section 103, stablizes basement rock 2, breast boards 3, bankets anchoring section 101 Layer 4, steel bushing 5, support column 6, connecting elements 7.
Specific embodiment
Below with reference to embodiment, the invention will be further described, but should not be construed the above-mentioned subject area of the present invention only It is limited to following embodiments.Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and used With means, various replacements and change are made, should all include within the scope of the present invention.
Embodiment 1:
Referring to Fig. 1, the present embodiment discloses a kind of construction method of embankment side slope prestress anchorage cable, comprising the following steps:
1) according to design drawing, side slope to be onstructed is handled, and by the measuring of anchor hole position in slope surface.Wherein, the side slope It from top to bottom successively include surface overburden layer, strongly weathered sand-rock, middle weathered rock formation and stable basement rock 2.
2) breast boards 3 is installed.Wherein, the breast boards 3 is fixedly connected with friction pile, forms pile plate wall.
3) diagonal brace prestress anchorage cable 1, sealing off and covering anchorage after prestressed stretch-draw are installed.Referring to Fig. 1, the prestress anchorage cable 1 includes anchor Gu section 101, free segment 102 and tensioning section 103.It will be anchored on the inside of the tensioning section 103 of prestress anchorage cable 1 and breast boards 3.In slope surface Drilling introduces the anchoring section 101 of prestress anchorage cable 1 in the hole being drilled, and into hole, cement injection mortar is anchored.Wherein, The prestress anchorage cable 1 is in tilted layout.102 outer sheath of free segment of the prestress anchorage cable 1 is equipped with steel bushing 5.Referring to fig. 2, The diameter of the free segment 102 is d.The internal diameter of the steel bushing 5 is D.Wherein, d=2/3D.The free segment 102 is located at steel The lower part of 5 inner cavity of sleeve.5 inner cavity top of steel bushing reserves settlement space.
4) support column 6 is installed.Wherein, referring to Fig. 3, the support column 6 is arranged in 5 lower section of steel bushing.6 edge of support column The length direction of steel bushing 5 is uniformly laid.The lower end of the support column 6 is mounted in stable basement rock 2, and upper end passes through connecting elements 7 are fixedly connected with steel bushing 5.Support column 6 prevents steel bushing 5 from generating large deformation in earth filling tamping and natural subsidence, subtracts simultaneously The settling amount of small steel bushing 5 avoids tube wall contact prestress anchorage cable and generates cross force to it, influences its stress performance.It is described The section of support column 6 is circle.6 diameter of support column is l.Spacing between adjacent two support columns 6 is 12~15l.
Referring to fig. 4, the connecting elements 7 generally blocks.The upper surface of the connecting elements 7 and steel bushing 5 are fixed Connection, lower surface is fixedly connected with the upper surface of support column 6.
The support column 6 is used to support steel bushing 5, prevents 5 interlude of steel bushing from generating excessive deformation, while preventing steel bushing Cylinder 5 follows to banket to be settled together.The present embodiment being capable of reasonable effective protection free segment 102.Steel bushing settlement space is reserved, is made Free segment 102 by cross shear, can not allow prestress anchorage cable 1 to work normally under the conditions of embankment, guarantee that engineering safety is steady It is fixed, have the characteristics that the simple and economical effect of structure is good.
5) wall back backfill is carried out, placement in layers compacted fill forms fill stratum 4 to design standard height.Wherein, the freedom Section 102 is embedded in fill stratum 4.The steel bushing 5 completely cuts off free segment 102 and fill stratum 4, guarantee prestress anchorage cable 1 not by To cross force, the vertical stretch capability of prestress anchorage cable 1 is made full use of, applies prestressing force and consolidates the soil body.Close to 5 part of steel bushing After banketing according to influence line design tamping point is rammed, 5 two sides of steel bushing are rammed using hand compaction mode and are banketed.
The present embodiment step is simple, and production cost is low, and project amount is small, improves the installation effectiveness of anchor cable under the conditions of banketing, contracting Casual labourer's phase, anchor cable and insulating of banketing are good, and corrosion resistance is strong, improves service life.It solves and protects anchor under the conditions of existing embankment Rope construction work amount is big, long in time limit, the high problem of cost.

Claims (6)

1. a kind of construction method of embankment side slope prestress anchorage cable, which comprises the following steps:
1) according to design drawing, side slope to be onstructed is handled, and by the measuring of anchor hole position in slope surface;Wherein, the side slope is from upper It successively include surface overburden layer, strongly weathered sand-rock, middle weathered rock formation and stabilization basement rock (2) under;
2) breast boards (3) is installed;Wherein, the breast boards (3) is fixedly connected with friction pile, forms pile plate wall;
3) diagonal brace prestress anchorage cable (1) is installed, sealing off and covering anchorage after prestressed stretch-draw;By the tensioning section (103) of prestress anchorage cable (1) and gear Anchoring on the inside of native plate (3);It drills, the anchoring section (101) of prestress anchorage cable (1) is introduced in the hole being drilled, into hole in slope surface Cement injection mortar is anchored.Wherein, the prestress anchorage cable (1) is in tilted layout;The free segment of the prestress anchorage cable (1) (102) outer sheath is equipped with steel bushing (5);
4) support column (6) are installed;Wherein, the support column (6) is arranged in below steel bushing (5);The support column (6) is along steel bushing The length direction of cylinder (5) is uniformly laid;The lower end of the support column (6) is mounted in stable basement rock (2), and upper end passes through connection structure Part (7) is fixedly connected with steel bushing (5);
5) wall back backfill is carried out, placement in layers compacted fill is formed fill stratum (4) to design standard height;Wherein, the free segment (102) it is embedded in fill stratum (4);The steel bushing (5) completely cuts off free segment (102) and fill stratum (4).
2. a kind of construction method of embankment side slope prestress anchorage cable according to claim 1, it is characterised in that: the freedom The diameter of section (102) is d;The internal diameter of the steel bushing (5) is D;Wherein, d=2/3D;The free segment (102) is located at steel bushing The lower part of cylinder (5) inner cavity.
3. a kind of construction method of embankment side slope prestress anchorage cable according to claim 1 or 2, it is characterised in that: described The section of support column (6) is circle;Support column (6) diameter is l;Spacing between adjacent two support columns (6) is 12~ 15l。
4. a kind of construction method of embankment side slope prestress anchorage cable according to claim 1,2 or 3, it is characterised in that: institute State connecting elements (7) generally blocks;The upper surface of the connecting elements (7) is fixedly connected with steel bushing (5), lower surface with The upper surface of support column (6) is fixedly connected.
5. a kind of construction method of embankment side slope prestress anchorage cable according to claim 1, it is characterised in that: the steel bushing Cylinder (5) is embedded in depth in stable basement rock (2) and is not less than 500mm.
6. a kind of construction method of embankment side slope prestress anchorage cable according to claim 1, it is characterised in that: step 5) In, the basis of banketing of close steel bushing (5) part is rammed after influencing line design tamping point, rams steel bushing using hand compaction mode (5) two sides are banketed.
CN201811074088.6A 2018-09-14 2018-09-14 Construction method of filling slope prestressed anchor cable Pending CN109403321A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811074088.6A CN109403321A (en) 2018-09-14 2018-09-14 Construction method of filling slope prestressed anchor cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811074088.6A CN109403321A (en) 2018-09-14 2018-09-14 Construction method of filling slope prestressed anchor cable

Publications (1)

Publication Number Publication Date
CN109403321A true CN109403321A (en) 2019-03-01

Family

ID=65464911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811074088.6A Pending CN109403321A (en) 2018-09-14 2018-09-14 Construction method of filling slope prestressed anchor cable

Country Status (1)

Country Link
CN (1) CN109403321A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111058475A (en) * 2019-12-29 2020-04-24 中铁二院工程集团有限责任公司 High-intensity seismic area pile foundation joist constant-weight retaining wall structure and construction method
CN111485493A (en) * 2020-03-25 2020-08-04 中国电建集团中南勘测设计研究院有限公司 Suspension bridge anchorage structure and implementation method thereof
CN115198775A (en) * 2022-08-13 2022-10-18 广东博意建筑设计院有限公司 Filling area prestress anchor-pull type pile-plate wall and construction method thereof

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1666614A1 (en) * 1989-05-15 1991-07-30 Ярославский политехнический институт Supporting structure
US5551810A (en) * 1994-06-08 1996-09-03 Schnabel Foundation Company Retaining wall with an outer face and method of forming the same
KR100728266B1 (en) * 2007-03-28 2007-06-13 주식회사 행림종합 건축사사무소 A matrix and structure of wire connection
CN102296571A (en) * 2011-06-08 2011-12-28 西安理工大学 Rock-fill dam of anchoring panel and construction method thereof
CN104790394A (en) * 2015-04-23 2015-07-22 万军利 Pressure anchor cable structure with prefabricated anchor head and construction method of pressure anchor cable structure
CN105525627A (en) * 2016-01-29 2016-04-27 中冶集团武汉勘察研究院有限公司 Two-way anchorage plate retaining wall and construction method thereof
CN205348194U (en) * 2016-01-11 2016-06-29 浙江宝业建设集团有限公司 It spouts compound supporting construction of stake with anchor rope soon to throw to one side to prop
CN205387721U (en) * 2016-03-18 2016-07-20 张乐 Highway retaining wall reinforced structure
CN206220120U (en) * 2016-11-11 2017-06-06 叶晓明 Framed bent anchor draws barricade
CN107100180A (en) * 2017-06-29 2017-08-29 湖南工业大学 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering
CN206457843U (en) * 2016-12-27 2017-09-01 中信建筑设计研究总院有限公司 A kind of band anchor retaining wall being combined with agent structure
CN206844128U (en) * 2017-05-10 2018-01-05 广东省建筑设计研究院 A kind of slopes ruggedized construction
RU2649347C1 (en) * 2017-02-28 2018-04-02 Федеральное государственное автономное образовательное учреждение высшего образования "Сибирский федеральный университет" Retaining wall anchoring system

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1666614A1 (en) * 1989-05-15 1991-07-30 Ярославский политехнический институт Supporting structure
US5551810A (en) * 1994-06-08 1996-09-03 Schnabel Foundation Company Retaining wall with an outer face and method of forming the same
KR100728266B1 (en) * 2007-03-28 2007-06-13 주식회사 행림종합 건축사사무소 A matrix and structure of wire connection
CN102296571A (en) * 2011-06-08 2011-12-28 西安理工大学 Rock-fill dam of anchoring panel and construction method thereof
CN104790394A (en) * 2015-04-23 2015-07-22 万军利 Pressure anchor cable structure with prefabricated anchor head and construction method of pressure anchor cable structure
CN205348194U (en) * 2016-01-11 2016-06-29 浙江宝业建设集团有限公司 It spouts compound supporting construction of stake with anchor rope soon to throw to one side to prop
CN105525627A (en) * 2016-01-29 2016-04-27 中冶集团武汉勘察研究院有限公司 Two-way anchorage plate retaining wall and construction method thereof
CN205387721U (en) * 2016-03-18 2016-07-20 张乐 Highway retaining wall reinforced structure
CN206220120U (en) * 2016-11-11 2017-06-06 叶晓明 Framed bent anchor draws barricade
CN206457843U (en) * 2016-12-27 2017-09-01 中信建筑设计研究总院有限公司 A kind of band anchor retaining wall being combined with agent structure
RU2649347C1 (en) * 2017-02-28 2018-04-02 Федеральное государственное автономное образовательное учреждение высшего образования "Сибирский федеральный университет" Retaining wall anchoring system
CN206844128U (en) * 2017-05-10 2018-01-05 广东省建筑设计研究院 A kind of slopes ruggedized construction
CN107100180A (en) * 2017-06-29 2017-08-29 湖南工业大学 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111058475A (en) * 2019-12-29 2020-04-24 中铁二院工程集团有限责任公司 High-intensity seismic area pile foundation joist constant-weight retaining wall structure and construction method
CN111485493A (en) * 2020-03-25 2020-08-04 中国电建集团中南勘测设计研究院有限公司 Suspension bridge anchorage structure and implementation method thereof
CN115198775A (en) * 2022-08-13 2022-10-18 广东博意建筑设计院有限公司 Filling area prestress anchor-pull type pile-plate wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN111119935B (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN102767173A (en) High polymer material slurry filled discrete material pile composite foundation and construction method thereof
CN109339029B (en) Construction method for resisting uplift deformation in excavation of foundation pit above existing tunnel
CN103603369B (en) Construction method of anchor pile counterfort retaining wall
CN108547336B (en) Sedimentation, reinforcement, jacking and leveling method suitable for independent pile foundation of industrial plant
CN108035754A (en) A kind of roadway bolt anchor cable combination supporting method
CN109403321A (en) Construction method of filling slope prestressed anchor cable
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN107503257A (en) One kind is close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN108343068A (en) Composite soil nailing wall and pile-anchor retaining composite supporting construction and construction method
CN104631438A (en) Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN102304927B (en) Prestress anchor cable buttress-type parapet suitable for rock substrate
CN205382507U (en) Two -way anchored retaining wall by tie rods
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN112081157B (en) Construction method for forming reinforced composite pile foundation by high-rise building retreating type grouting
CN109505641A (en) A kind of soft-rock tunnel bottom plate anchor pouring reinforcement method
CN206599785U (en) A kind of campshed anchor draws cement earth pile diaphragm wall supporting construction
CN113863706B (en) Construction method and application device of existing building low-clearance lower rotary-jet static pressure composite pile
CN201033872Y (en) Slip casting type anchor bar
CN101691759A (en) Construction method for digging composite environmental protection base of anchorage bar adding rock
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN206971247U (en) A kind of concrete plinth foundation ruggedized construction being placed on Unloading Rock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination