CN109386738A - A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device - Google Patents

A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device Download PDF

Info

Publication number
CN109386738A
CN109386738A CN201811551126.2A CN201811551126A CN109386738A CN 109386738 A CN109386738 A CN 109386738A CN 201811551126 A CN201811551126 A CN 201811551126A CN 109386738 A CN109386738 A CN 109386738A
Authority
CN
China
Prior art keywords
pipeline
valve
connect
impulse
protection device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811551126.2A
Other languages
Chinese (zh)
Other versions
CN109386738B (en
Inventor
黄晶
聂中文
于永志
高建章
徐德腾
西敬军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
Original Assignee
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
China Petroleum Pipeline Engineering Corp Design Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Petroleum Corp, China Petroleum Pipeline Engineering Corp, China Petroleum Pipeline Engineering Corp Design Branch filed Critical China National Petroleum Corp
Priority to CN201811551126.2A priority Critical patent/CN109386738B/en
Publication of CN109386738A publication Critical patent/CN109386738A/en
Application granted granted Critical
Publication of CN109386738B publication Critical patent/CN109386738B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D5/00Protection or supervision of installations
    • F17D5/005Protection or supervision of installations of gas pipelines, e.g. alarm

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Measuring Fluid Pressure (AREA)
  • Pipeline Systems (AREA)

Abstract

The invention discloses a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device, which includes: the main pipeline for being provided with threeway A, block valve for pipeline and threeway B;Impulse pipeline A and impulse pipeline B is arranged on by-pass line for the by-pass line that both ends are connect with threeway A and threeway B respectively;One end of impulse pipeline A is connect with by-pass line upstream, and the other end is connect with block valve for pipeline;One end of impulse pipeline B and by-pass line downstream connection, the other end are connect with block valve for pipeline;Several pressure-detecting devices are respectively set on impulse pipeline A and impulse pipeline B, several pressure-detecting devices and block valve for pipeline are connect via junction box with controller, and controller calculates on-site test value and judges whether to take safeguard measure.The invention has the benefit that generation and the alarm of main pipeline booster in time, can be monitored accurately, and safeguard measure isolation emergency pipe line and yard are taken, improves gas pipeline and periphery personnel and property safety.

Description

A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device
Technical field
The present invention relates to pipe-line system technical fields, in particular to a kind of gas pipeline valve chamber main pipeline booster Monitoring, alarming and interlock protection device.
Background technique
During conduit running, due to corrosive pipeline, damage from third-party, construction quality etc., cause natural gas tube Road rupture is broken and causes natural gas leakage, finally ferments olefiant gas pipe safety accident, causes very to society and enterprise Big adverse effect, more the security of the lives and property to the pipeline people, which is brought, seriously threatens.If grasped not in time Whether pipeline the relevant informations such as cracks or fractures, and is handled in time, will lead to damage sequence and constantly aggravate, causes serious ring Border pollution and the great person and property loss.
The gas pipeline as caused by corrosive pipeline, damage from third-party, construction quality etc. is revealed, since natural gas is Compressible fluid, previous engineering can not carry out leakage monitoring with the method for oil pipeline, and it is different in appearance to cannot achieve transportation system Emergency cut-off and station in normal situation emergency shutdown function out of the station cause human eye ought only occur observable natural When the major accidents such as gas leakage, fire or explosion, relevant issues could be found.
Summary of the invention
To solve the above problems, the purpose of the present invention is to provide a kind of main pipeline booster prisons for making gas pipeline valve chamber Survey more timely alarm velocity, the higher device of accuracy rate, raising gas pipeline and periphery personnel and property safety.
The present invention provides a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device, the devices Include: main pipeline, set gradually threeway A, block valve for pipeline and threeway B thereon, and the block valve for pipeline by cable with Junction box's connection;
By-pass line, both ends are connect with the threeway A and the threeway B respectively, and valve is arranged on the bypass duct, And it is connect with high pressure blow-down pipe;
Impulse pipeline A, one end are connect with the by-pass line upstream, and the other end is connect with the block valve for pipeline, institute It states and several pressure-detecting devices is set on impulse pipeline A, several pressure-detecting devices pass through gauge valve and the pressure guiding pipe respectively Line A connection, and several pressure-detecting devices pass through cable respectively and connect with the junction box;
Impulse pipeline B, one end are connect with the block valve for pipeline, the other end and the by-pass line downstream connection;Institute It states and several pressure-detecting devices is set on impulse pipeline B, several pressure-detecting devices pass through gauge valve and the pressure guiding pipe respectively Line B connection, and several pressure-detecting devices pass through cable respectively and connect with the junction box;
Controller, input terminal are electrically connected with the junction box, the controller output end and the block valve for pipeline Executing agency's connection.
Improved as of the invention further, several gauge valves pass through respectively instrument root valve and the impulse pipeline A and The impulse pipeline B connection.
As further improvement of the invention, the high pressure blow-down pipe passes through flanged (FLGD) valve and the by-pass line Connection.
As further improvement of the invention, the block valve for pipeline is gas-oil valve.
As further improvement of the invention, several pressure-detecting devices are high accuracy pressure transmitter.
As further improvement of the invention, valve B and valve C is respectively set in the upstream and downstream of the by-pass line.
As further improvement of the invention, the impulse pipeline A is connect by valve E with the by-pass line, described Impulse pipeline A is connect by valve F with the block valve for pipeline;The impulse pipeline B is connected by valve G and the by-pass line It connects, the impulse pipeline B is connect by valve H with the block valve for pipeline.
As further improvement of the invention, blow-down pipe is set on the by-pass line between the valve B and valve A, institute Blow-down pipe is stated to connect by valve J with the by-pass line.
As further improvement of the invention, it is respectively set described in two on the impulse pipeline A and the impulse pipeline B Pressure-detecting device.
As further improvement of the invention, the valve B and the valve C are ball valve.
The invention has the benefit that by the way that by-pass line is arranged on gas pipeline valve chamber main pipeline, and bypassing Pressure-detecting device is installed on pipeline and monitors piping loss rate value, after pressure drop rate continuously super setting value certain number, is controlled Device control warning device processed issues the block valve for pipeline of upstream and downstream at alarm and interlocking close booster, isolation emergency pipe line and station , achieve the purpose that the generation of the main pipeline booster of monitoring gas pipeline valve chamber promptly and accurately and alarm, and takes protection Emergency pipe line and yard is isolated in measure, improves gas pipeline and periphery personnel and property safety.
Detailed description of the invention
Fig. 1 is a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection described in the embodiment of the present invention The structural schematic diagram of device;
In figure,
1, main pipeline;2, threeway A;3, block valve for pipeline;4, threeway B;5, by-pass line;6, impulse pipeline A;7, impulse Pipeline B;8, several pressure-detecting devices;9, gauge valve;10, instrument root valve;11, junction box;12, valve A;13, band flange Valve;14, valve B;15, valve C;16, valve E;17, valve G;18, valve F;19, valve H;20, valve J.
Specific embodiment
The present invention is described in further detail below by specific embodiment and in conjunction with attached drawing.
As shown in Figure 1, a kind of gas pipeline valve chamber main pipeline booster monitoring alarm described in the embodiment of the present invention, The device includes: main pipeline 1, sets gradually threeway A 2, block valve for pipeline 3 and threeway B 4 thereon, and block valve for pipeline 3 is logical Cable is crossed to connect with junction box 11;
By-pass line 5, both ends are connect with threeway A 2 and threeway B 4 respectively, are arranged valve on bypass duct 5, and with height Press blow-down pipe connection;
Impulse pipeline A 6, one end is connect with the upstream of by-pass line 5, and the other end is connect with block valve for pipeline 3, impulse Several pressure-detecting devices 8 are set on pipeline A 6, and several pressure-detecting devices 8 pass through gauge valve 9 and impulse pipeline A 6 respectively Connection, and several pressure-detecting devices 8 are connect by cable with junction box 11 respectively;
Impulse pipeline B 7, one end is connect with block valve for pipeline 3, the downstream connection of the other end and by-pass line 5;Impulse Several pressure-detecting devices 8 are set on pipeline B 7, and several pressure-detecting devices 8 pass through gauge valve 9 and impulse pipeline B 7 respectively Connection, and several pressure-detecting devices 8 are connect by cable with junction box 11 respectively;
Controller, input terminal are connect with junction box's electricity 11, and the controller output end is held with the block valve for pipeline The connection of row mechanism.
Further, several gauge valves 9 are connected by instrument root valve 10 and impulse pipeline A 6 and impulse pipeline B 7 respectively It connects.
Further, high pressure blow-down pipe is connect by flanged (FLGD) valve 13 with by-pass line 5.
Further, block valve for pipeline 3 is gas-oil valve.
Further, several pressure-detecting devices 8 are high accuracy pressure transmitter.
Further, valve B 14 and valve C 15 is respectively set in the upstream and downstream of by-pass line 5, and the setting of valve B 14 is being drawn Between pressure pipeline A 6 and the junction and valve A 12 of by-pass line 5, valve C 15 is arranged in impulse pipeline B 7 and shunt valve Between the junction and valve A 12 of line 5.
Further, impulse pipeline A 6 is connect by valve E 16 with by-pass line 5, and impulse pipeline A 6 passes through valve F 18 connect with block valve for pipeline 3;Impulse pipeline B 7 is connect by valve G17 with by-pass line 5, and impulse pipeline B 7 passes through valve H 19 is connect with block valve for pipeline 3.
Further, blow-down pipe is set on the by-pass line 5 between valve B 14 and valve A 12, blow-down pipe passes through valve J 20 is connect with by-pass line 5.
Further, two pressure-detecting devices 8 are respectively set on impulse pipeline A 6 and impulse pipeline B 7.
Further, valve B 14 and valve C 15 is ball valve.
When specific works:
When being full of high-pressure natural gas in gas pipeline, if some place cracks or fractures, gas pipeline valve chamber Main pipeline booster monitoring, alarming and interlock protection device can be reduced rapidly according to the pressure of upstream and downstream pipeline judges that pipeline is It is no to crack or fracture, while the Position Approximate of leakage point can be positioned using the time difference of upstream and downstream.In use, starting a kind of gas transmission The pressure drop rate critical value of device, the critical value is arranged in pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device Judge reference value as judging one that whether pipeline rupture, when at one continuously using the pressure in the period, on impulse pipeline The pressure value of detection arrangement monitors is simultaneously fed back to controller, and controller carries out calculating analysis to pressure signal, if pressure value continues Decline, and fall off rate be greater than preset pressure drop rate critical value and keep continuous downward trend for a period of time after, control Device processed controls alarm equipment alarm and starts insulation blocking measure, closes the route truncation of gas pipeline valve chamber main pipeline upstream and downstream Emergency pipe line is isolated in valve.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device, which is characterized in that the device packet It includes:
Main pipeline (1) sets gradually threeway A (2), block valve for pipeline (3) and threeway B (4), and the block valve for pipeline thereon (3) it is connect by cable with junction box (11);
By-pass line (5), both ends are connect with the threeway A (2) and the threeway B (4) respectively, on the bypass duct (5) It is arranged valve A (12), and is connect with high pressure blow-down pipe;
Impulse pipeline A (6), one end are connect with the by-pass line (5) upstream, and the other end and the block valve for pipeline (3) are even It connects, is arranged several pressure-detecting devices (8) on the impulse pipeline A (6), several pressure-detecting devices (8) pass through instrument respectively Valve (9) is connect with the impulse pipeline A (6), and several pressure-detecting devices (8) pass through cable and the junction box (11) respectively Connection;
Impulse pipeline B (7), one end are connect with the block valve for pipeline (3), and the other end and the by-pass line (5) downstream connect It connects;It is arranged several pressure-detecting devices (8) on the impulse pipeline B (7), several pressure-detecting devices (8) pass through instrument respectively Valve (9) is connect with the impulse pipeline B (7), and several pressure-detecting devices (8) pass through cable and the junction box (11) respectively Connection;
Controller, input terminal are electrically connected with the junction box (11), the controller output end and the block valve for pipeline (3) Executing agency connection.
2. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, several gauge valves (9) pass through instrument root valve (10) and the impulse pipeline A (6) and the pressure guiding pipe respectively Line B (7) connection.
3. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, the high pressure blow-down pipe is connect by flanged (FLGD) valve (13) with the by-pass line (5).
4. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, the block valve for pipeline (3) is gas-oil valve.
5. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, several pressure-detecting devices (8) are high accuracy pressure transmitter.
6. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, valve B (14) and valve C (15) is respectively set in the upstream and downstream of the by-pass line (5).
7. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, the impulse pipeline A (6) is connect by valve E (16) with the by-pass line (5), the impulse pipeline A (6) it is connect by valve F (18) with the block valve for pipeline (3);The impulse pipeline B (7) passes through valve G (17) and the side Road pipeline (5) connection, the impulse pipeline B (7) are connect by valve H (19) with the block valve for pipeline (3).
8. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 6 and interlock protection device, It is characterized in that, blow-down pipe is arranged on by-pass line (5) between the valve B (14) and valve A (12), the blow-down pipe is logical Valve J (20) is crossed to connect with the by-pass line (5).
9. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 1 and interlock protection device, It is characterized in that, two pressure-detecting devices are respectively set on the impulse pipeline A (6) and the impulse pipeline B (7) (8)。
10. a kind of gas pipeline valve chamber main pipeline booster monitoring, alarming according to claim 6 and interlock protection device, It is characterized in that, the valve B (14) and the valve C (15) are ball valve.
CN201811551126.2A 2018-12-18 2018-12-18 Pipe explosion monitoring alarm and interlocking protection device for valve chamber main pipeline of gas pipeline Active CN109386738B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811551126.2A CN109386738B (en) 2018-12-18 2018-12-18 Pipe explosion monitoring alarm and interlocking protection device for valve chamber main pipeline of gas pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811551126.2A CN109386738B (en) 2018-12-18 2018-12-18 Pipe explosion monitoring alarm and interlocking protection device for valve chamber main pipeline of gas pipeline

Publications (2)

Publication Number Publication Date
CN109386738A true CN109386738A (en) 2019-02-26
CN109386738B CN109386738B (en) 2023-11-14

Family

ID=65430424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811551126.2A Active CN109386738B (en) 2018-12-18 2018-12-18 Pipe explosion monitoring alarm and interlocking protection device for valve chamber main pipeline of gas pipeline

Country Status (1)

Country Link
CN (1) CN109386738B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110285326A (en) * 2019-05-27 2019-09-27 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure relief device and method
CN110307474A (en) * 2019-05-27 2019-10-08 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure relief device
CN110307370A (en) * 2019-05-27 2019-10-08 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure releasing method
CN111720745A (en) * 2019-03-19 2020-09-29 中国石油天然气股份有限公司 Cutoff valve chamber risk prevention and control device

Family Cites Families (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2422561C2 (en) * 1974-05-09 1983-11-03 Hoechst Ag, 6230 Frankfurt Device for monitoring leaks in a pipeline
US3952759A (en) * 1974-08-14 1976-04-27 M & J Valve Company Liquid line break control system and method
DE2609717A1 (en) * 1976-03-09 1977-09-15 Siemens Ag DEVICE FOR MEASURING LEAK LEAKAGE IN A LIQUID PIPING SYSTEM
JP3050745B2 (en) * 1994-03-04 2000-06-12 矢崎総業株式会社 Gas leak detection device
JPH0886713A (en) * 1994-09-19 1996-04-02 Ito Koki Kk Piping leakage detecting device
JP3668344B2 (en) * 1996-11-22 2005-07-06 オリンパス株式会社 Air supply device
JP2002168400A (en) * 2000-12-01 2002-06-14 Yazaki Corp Self-diagnostic method of regulated pressure and gas leakage detecting apparatus
CN101354110A (en) * 2007-07-23 2009-01-28 上海市莘格高级中学 Intelligent coal gas leakage alarming and cutting system
JP5243917B2 (en) * 2008-10-15 2013-07-24 愛知時計電機株式会社 Gas pressure monitoring device and gas piping network construction method
RU2396483C1 (en) * 2009-05-07 2010-08-10 Общество С Ограниченной Ответственностью "Газпромэнергодиагностика" Bench for fluid and gas leaks control in ball cocks of mains
CN102313138B (en) * 2010-07-06 2013-05-01 中国石油天然气集团公司 Online density measurement method of petroleum transmission pipeline
CN202228922U (en) * 2011-03-18 2012-05-23 北京爱社时代科技发展有限公司 Energy saving management unit for pipeline gas supply
CN102588744B (en) * 2012-03-12 2013-06-19 中冶南方工程技术有限公司 On-line leakage detecting method of gas cutting-off system
CN202756726U (en) * 2012-07-26 2013-02-27 中国石油天然气股份有限公司 Gas-liquid linkage block valve control system on oil-gas transmission pipeline
CN204477703U (en) * 2015-02-09 2015-07-15 中煤科工集团武汉设计研究院有限公司 A kind of pipeline valve bidirection press protective gear
KR20180057391A (en) * 2016-11-22 2018-05-30 박재호 Continuous pressure leak test device module
CN106439495B (en) * 2016-12-14 2018-03-20 中国石油天然气集团公司 Gas pipeline pressure flow hybrid control system integration skid-mounted unit
CN106382466B (en) * 2016-12-14 2018-02-23 中国石油天然气集团公司 A kind of gas pipeline metering regulator and method
CN206398370U (en) * 2016-12-29 2017-08-11 重庆长风生物科技有限公司 A kind of anti-backflow feeding system
CN206582536U (en) * 2016-12-30 2017-10-24 四川川能恒远工程技术有限公司 A kind of natural gas line makes somebody a mere figurehead security system
CN107355679B (en) * 2017-07-31 2018-12-14 特瑞斯能源装备股份有限公司 A kind of integrated natural gas line pressure testing feeder and its temprature control method
CN207935760U (en) * 2018-02-07 2018-10-02 广州莱仑特种装备有限公司 A kind of self feed back denoising device for pipe network natural gas pressure regulating
CN209445069U (en) * 2018-12-18 2019-09-27 中国石油天然气集团有限公司 A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111720745A (en) * 2019-03-19 2020-09-29 中国石油天然气股份有限公司 Cutoff valve chamber risk prevention and control device
CN111720745B (en) * 2019-03-19 2022-06-03 中国石油天然气股份有限公司 Cutoff valve chamber risk prevention and control device
CN110285326A (en) * 2019-05-27 2019-09-27 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure relief device and method
CN110307474A (en) * 2019-05-27 2019-10-08 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure relief device
CN110307370A (en) * 2019-05-27 2019-10-08 中国石油天然气集团有限公司 A kind of fluid pipeline dead oil section pressure releasing method

Also Published As

Publication number Publication date
CN109386738B (en) 2023-11-14

Similar Documents

Publication Publication Date Title
CN109386738A (en) A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device
CN109578818B (en) Gas pipeline valve chamber trunk pipeline pipe burst monitoring alarm and interlocking protection method
CN109578817A (en) A kind of gas pipeline terminal main line pressure drop rate monitoring, alarming interlocking method
RU2484361C1 (en) Safety control in repair at main pipelines and system to this end
CN109555975A (en) A kind of gas pipeline point defeated station main pipeline booster monitoring, alarming and interlocking method
CN109404742A (en) Gas pipeline valve chamber main pipeline booster monitoring, alarming and protective device, method
CN109555976B (en) Monitoring and alarming interlocking device and method for pressure drop rate of trunk line of gas transmission pipeline end station
CN209445069U (en) A kind of gas pipeline valve chamber main pipeline booster monitoring, alarming and interlock protection device
CN109357165A (en) A kind of gas pipeline Trunk Line pressure drop rate monitoring alarm and method
CN107883056B (en) Real-time online safety valve monitoring system and safety valve leakage monitoring method
CN209386021U (en) A kind of gas pipeline terminal main line pressure drop rate monitoring, alarming interlock
CN103867775A (en) Large tank farm pipeline emergency cut-off system
CN105387558A (en) Chilled water tail end system and fault detection method thereof
CN104373819B (en) Monitoring device and monitoring method for prefabricated directly-buried thermal insulation pipe alarm line
CN105755202A (en) Oxygen pipeline system and anti-blasting device of extra-large converter oxygen lance valve station
CN109373202B (en) Monitoring and alarming interlocking device for pressure drop rate of trunk line of gas transmission pipeline end station
CN207569316U (en) Safety valve real time on-line monitoring system
CN209309684U (en) A kind of gas pipeline point defeated station main pipeline booster monitoring, alarming and interlock
CN109406046A (en) Trunk Line pressure drop rate alarming method by monitoring in a kind of station of gas pipeline initial station
CN201034794Y (en) Test calibration device used for acoustic wave leak detection system
CN204364748U (en) Fusible plug control panel
CN210739978U (en) Inlet fire alarm valve bypass pipeline of natural gas pressure regulating station
CN209196558U (en) A kind of automatic pressure relief device
CN109357164B (en) Main pipeline pipe burst monitoring alarm and interlocking device for gas pipeline branch transmission station
EP2142840A1 (en) Pipeline for transport of gas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 100120 Xicheng District six paw Kang in Beijing City

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Applicant after: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant after: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

Address before: 100120 Xicheng District six paw Kang in Beijing City

Applicant before: China National Petroleum Corp.

Applicant before: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant before: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20231019

Address after: 100007 No. 9 North Main Street, Dongcheng District, Beijing, Dongzhimen

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Applicant after: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant after: CHINA PETROLEUM PIPELINE ENGINEERING Corp.

Address before: 100120 Xicheng District six paw Kang in Beijing City

Applicant before: CHINA NATIONAL PETROLEUM Corp.

Applicant before: China Petroleum Pipeline Engineering Co.,Ltd.

Applicant before: DESIGN BRANCH OF CHINA PETROLEUM PIPELINE ENGINEERING Corp.

GR01 Patent grant
GR01 Patent grant