CN1093766A - Soft-clay lime deep-layer consolidation method - Google Patents

Soft-clay lime deep-layer consolidation method Download PDF

Info

Publication number
CN1093766A
CN1093766A CN 93104446 CN93104446A CN1093766A CN 1093766 A CN1093766 A CN 1093766A CN 93104446 CN93104446 CN 93104446 CN 93104446 A CN93104446 A CN 93104446A CN 1093766 A CN1093766 A CN 1093766A
Authority
CN
China
Prior art keywords
soil
soft
grey
calcium lime
lime powder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 93104446
Other languages
Chinese (zh)
Inventor
苏清洪
李梅贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU ECONOMY TECHNOLOGY DEVELOPMENT REGION ADMINISTRATION COMMITTE
Original Assignee
GUANGZHOU ECONOMY TECHNOLOGY DEVELOPMENT REGION ADMINISTRATION COMMITTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU ECONOMY TECHNOLOGY DEVELOPMENT REGION ADMINISTRATION COMMITTE filed Critical GUANGZHOU ECONOMY TECHNOLOGY DEVELOPMENT REGION ADMINISTRATION COMMITTE
Priority to CN 93104446 priority Critical patent/CN1093766A/en
Publication of CN1093766A publication Critical patent/CN1093766A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention mixes calcium lime powder, cement flour or calcium lime powder and cement flour for moulding shape bury stratum to stream, it is that curing compound carries out fixed a kind of soft-soil foundation treatment method that calcium lime powder adds flyash, it is by equipment such as the band drill bit of stirring vane and portable drilling rig, powder transmitter, air compressors powder to be sprayed into the soil body to mix and stir into grey earth pillar, grey cob wall, dirt plate or dirt entity, and the amount of dusting is 15-20%.Present technique is applicable to that the degree of depth is the remoldability soft clay foundation processing that stream is moulded state that is in 30 meters.

Description

Soft-clay lime deep-layer consolidation method
The invention belongs to and mould shape bury stratum to stream and mix curing compound and make its fixed a kind of soft-soil foundation treatment method.
The Soft Ground technology is of a great variety, as sand pile, sand drain, plastic draining board, piling prepressing or the like.(content of d≤0.002mm) is greater than 50% for fine grained, index of plasticity is greater than 25 remoldability bury, and locate the stratum that stream is moulded state, the ground stabilization difficulty is big, poor reliability, common technology is difficult to obtain good result, usually adopt vacuum method, the churning method, technology such as the deep mixing method that dusts are reinforced, be shaped as agitation pile with the bearing capacity that increases the soil body, Load Transfer is arrived bearing stratum.But when vacuum method was implemented, complex process, construction costs were higher.The churning method sprays into and contains water in the slurries, and it obviously is disadvantageous that convection current moulds that the state soil body reinforces.The deep mixing method technology of dusting is in soft soil layer, by holing in the column that destroys, use compressed air that powders such as cement or lime are evenly sprayed into, formation is the composite foundation of main supporting body with the teeter column that dusts, reach the purpose that improves bearing capacity of foundation soil, this technology is applicable to coarse granule, and (content of d≤0.002mm) is greater than 50% soil, as lam, mud matter lam or miscellaneous fill stratum, and be that curing compound is preferable with the spraying cement powder.And in the processing of remoldability soft clay foundation, adopt and do spray lime deep-layer paddling process, in engineering practice, differ greatly owing to consolidation effect, particularly lime belongs to the air-setting material, on the saturated soil stratum, particularly adopt in the following deep layer stratum of groundwater table, the report of failure is arranged when in the engineering its validity being held the suspicious attitude.(the academic proceeding of the 6th soil mechanics and Foundation Design " reason of a Base Consolidation Engineering failure ") so technology limited to aspect the construction work practicality.
The objective of the invention is to be in the ground stabilization that stream is moulded state remoldability bury for solution.It is a kind of new method for processing foundation that improves and develop on the basis of deep layer stirring technique of dusting.
The present invention is such enforcement: the calcium lime powder that adopts serial special equipment to mix 15-30% in stream is moulded state remoldability soft clay stratum according to the Technological Economy requirement of design is that curing compound evenly mixes and stirs formation lime earth pillar, lime cob wall, rendzinas plate or rendzinas entity, make mix body and the interior undisturbed soil curing of influence basin on every side thereof, reinforcement depth can be to 30 meters of below grounds, to reach bearing capacity, stability and the impervious and minimizing sedimentation sex change that improves soil effectively.Technology of the present invention is applicable to soft soil layer, and (d≤0.002mm) is main, and fine particle content is greater than 50%, and the index of plasticity of stratum soil is in the remoldability bury that stream is moulded state greater than 25 particularly to contain fine grained.
Below in conjunction with accompanying drawing in detail method of the present invention is described in detail.
Fig. 1 is the grey earth pillar of the back formation of dusting,
Fig. 2 is the grey cob wall of the back formation of dusting,
Fig. 3 is the dirt plate of the back formation of dusting,
Fig. 4 is the dirt entity of the back formation of dusting.
Require according to engineering during enforcement and the soil property determination data, design curing agent and the amount of dusting thereof, dust and layout and dust the degree of depth. Main drill bit and the portable drilling rig that utilizes with stirring vane on the technology, the powder transmitter, the serial equipments such as air compressor, in the soil body that is destroyed by blade, spray into the lime powder, repeatedly evenly mix and stir formation grey earth pillar as shown in Figure 1, namely in being reinforced the soil body, be arranged to independently pile, the pile center distance is the pile diameter greater than 2.0d(d), when the pile center distance less than 2.0d, make each pile form overlap joint in a direction, dust the grey cob wall of rear formation as shown in Figure 2, when each pile all forms overlap joint at both direction, and column length H is less than reinforcing scope length of side B, i.e. H<B, and perhaps the pile bottom surface does not reach The bottom of soft soil layer, the rear formation dirt plate that dusts, as shown in Figure 3, when each stanchion all forms overlap joint at both direction, and H 〉=B, perhaps the pile bottom surface exceeds the soft soil layer bottom surface, the rear formation dirt entity that dusts, as shown in Figure 4.
After forming the dirt pile, inter-pile soil is because of the impact of dirt physics, chemical reaction, and solidification effect is along with the distance of cylinder reduces and improves, when pile center distance≤2.0d, soil between pile and pile can be looked as a whole, have same solidification effect, be i.e. so-called post and post overlap joint.
The amount of dusting, the ratio that namely mixes curing agent quick lime weight and lime soil pile weight is 15-20%. The amount of dusting is less than 15% the time, and ash content is too small in the rendzinas, suction and caloric value deficiency in the rendzinas hydration reaction, can not give full play to humidification, and after the amount of dusting is greater than 20%, because of lime content bigger than normal, carburizing reagent is slow or incomplete, will cause the dirt pile strength to descend. Can strict selection and the control amount of dusting be to be related to the crux factor that obtain good foundation stabilization effect.
According to the technical requirements of soil structure that is reinforced the stratum and engineering, the curing compound that is mixed, can be selected for use calcium lime powder and cement flour or calcium lime powder, cement to add flyash and form combined built pile or reinforced wall with the calcium lime powder except that single.
Adopt lime deep-layer consolidation stream of the present invention to mould shape remoldability bury technology, form consolidated subsoil with grey earth pillar, grey cob wall, dirt plate or dirt entity, improve bearing capacity of foundation soil, reduce building settlement, be used to improve the mechanical property of soil, increase the angle of internal friction and the cohesion of soil, alleviate lateral pressure to building, pattern foundation pit supporting structure when making the underground structure excavation with grey cob wall, play diaphragm wall, steel sheet pile supporting and the antiseepage effect of replacing, be used for reinforcing side slope, reduce the effect of quantity of earth work.The technology of the present invention is reliable, and engineering cost can reduce significantly, can be widely used in middle and lower reaches area and lakeside areas such as the Changjiang river, the Zhujiang River, the Min River, in speedway, bridge engineering, Industrial and Civil Engineering.
Embodiment 1:
Certain canal case engineering, length overall 154m, wide 3.5m is the artificial earth fill in the high 2.5m, foundation soil top layer 1m, the thick 3-4m of following mud, the thick about 3.5m of trip shale flour sand, index of plasticity is 35, is the piebald clay down.The former reinforced concrete pipe column basis that is designed to of this engineering, after use the technology of the present invention instead and be treated to foundation soil lime earth pillar underpinning, post array pitch * row distance is 1.5 * 2.0m, column length 8.5m, column diameter is 0.5m, the lime incorporation is 16% in the rendzinas, handle the on-the-spot load test in back and determine that bearing capacity of foundation soil is 60KPa, through excavation check, intercolumniation soil is fixed good, check settling amount average 18mm after 1 year, meet engine request, adopt the more former design scheme of present technique engineering cost can save 410,000 yuan of investments.
Embodiment 2:
Certain canal case engineering, length overall 231m, basic wide 3.3m.Soil remoldability silt clay thick 17.6m in stratum more than is a barged-in fill, and this engineering adopts the lime consolidation process foundation technology gross area of the present invention to reach 762 square metres, the total linear meter(lin.m.) 3560m of the post that dusts.The employing pilespacing is 0.7 * 2.5m, stake footpath 0.5m.Column length 6.5m promptly forms the dirt plate in the foundation soil mud that is reinforced, do not reach the following bearing stratum of buried depth 17.6m at the bottom of the pile.Ground adheres to specification after handling after testing, and total settlement 1.5 years was 23mm behind the m, only was 1/3 of designed amount of precipitation.
Embodiment 3:
Certain mansion basement excavates big pattern foundation pit supporting structure.3600 square metres of foundation ditch areas, cutting depth 8m.Gu around the foundation ditch building is arranged all, construction should be guaranteed existing building safety.The top layer, stratum is the 1m miscellaneous fill, below moulds shape mud for the thick stream of 6m.This engineering adopts grey cob wall supporting of the present invention, the Shi Po excavation.Stake is 0.5m directly, pilespacing 1m, and employing is arranged the stake of dusting than big pilespacing behind the wall, and with earth lateral pressure behind the minimizing wall, more former design can be saved great amount of investment with diaphragm wall after employing the technology of the present invention, the reduction of erection time, excavate the back stability of slope, guaranteed the safety of existing building thing.
Embodiment 4:
The soft soil roadbed treatment project of certain speedway D section.The roadbed depth of fill is 6m, and foundation soil is moulded the shape silt clay for grey stream under the roadbed, natural moisture content 74.58%, and it moulds the shape light loam firmly for plastic-one down.It is 60 * 50m that the present technique ground is handled segment length * wide, and thickness is 5m, and adopting calcium lime powder to add flyash is curing compound, and replacement ratio is 0.196.Total settlement is about 30 centimetres as calculated, and the residual settlement amount is only 6 centimetres during the high class pavement construction, can satisfy requirement of engineering.Carry out now finishing after the engineering completion, carry out on-the-spot load test, foundation settlement is 2.96-4.12 centimetre when pressure is 175KPa, the bearing capacity that do not reach capacity, and modulus of deformation Ec minimum is 9.6MPa.
Embodiment 5:
Certain factory's general storage depot, insulated column basis and the supporting of founding groove excavation of foundation pit.The stratum is that 0-4.5m ploughs and to plant soil, and 4.5-8.8m is a remoldability mud, and 8.8m is following to be flour sand.Adopt Ground Treatment of the present invention, spray into quicklime or cement formation coupled column respectively by the different soil properties in stratum, and the part stake sprays into cement in supporting, and the supporting body of wall is strengthened.The construction groundwork allows bearing capacity greater than 150KPa, and the excavation of foundation pit supporting is good, and the hole wall does not have the underground water infiltration.

Claims (2)

1, a kind of method of mixing weak soil layer consolidated subsoil by the quicklime of serial special equipment as curing compound, it is characterized in that moulding the remoldability bury of state to being in stream, the degree of depth be 30 meters with interior soil layer, the curing compound that mixes 15-20% mixes and stirs and forms grey earth pillar, grey cob wall, dirt plate or dirt entity.
2, the method for soft clay stratum consolidated subsoil according to claim 1 is characterized in that the curing compound that mixes is that calcium lime powder and cement flour or calcium lime powder, cement add flyash and forms combined built pile or strengthen wall.
CN 93104446 1993-04-14 1993-04-14 Soft-clay lime deep-layer consolidation method Pending CN1093766A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 93104446 CN1093766A (en) 1993-04-14 1993-04-14 Soft-clay lime deep-layer consolidation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 93104446 CN1093766A (en) 1993-04-14 1993-04-14 Soft-clay lime deep-layer consolidation method

Publications (1)

Publication Number Publication Date
CN1093766A true CN1093766A (en) 1994-10-19

Family

ID=4985195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 93104446 Pending CN1093766A (en) 1993-04-14 1993-04-14 Soft-clay lime deep-layer consolidation method

Country Status (1)

Country Link
CN (1) CN1093766A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100410455C (en) * 2006-08-14 2008-08-13 毛心焰 Strong rammer treatment high-water content foundation soil auxiliary construction process
CN100439605C (en) * 2006-07-25 2008-12-03 南京大学 Chopped fiber reinforced rendzinas ground treatment method
CN101008178B (en) * 2007-01-12 2010-05-19 中山大学 Soft base processing construction process using excavating and stirring method
CN102212465A (en) * 2011-06-22 2011-10-12 高节义 Large-scale methane tank
CN101748910B (en) * 2009-12-23 2012-02-22 赵天祥 Construction facility
CN103912005A (en) * 2014-04-14 2014-07-09 五邑大学 Foundation structure
CN106049406A (en) * 2016-06-01 2016-10-26 上海建研地基基础工程有限公司 Method for lightly tampering lime soil foundation
CN106638575A (en) * 2017-01-10 2017-05-10 邓亚光 Reinforcing method of pile body
CN108117358A (en) * 2017-12-29 2018-06-05 福建建工建材科技开发有限公司 A kind of curing of waste soil combined processing
CN108166470A (en) * 2017-12-26 2018-06-15 武汉广益交通科技股份有限公司 A kind of method of cementitious composite waste plastics stake soft soil foundation
CN109987805A (en) * 2019-01-10 2019-07-09 浙江海洋大学 Waterway dredging slurry curing equipment
CN110258507A (en) * 2019-06-15 2019-09-20 武汉中力岩土工程有限公司 A kind of soft soil foundation reinforcing method
CN117431970A (en) * 2023-12-22 2024-01-23 四川交通职业技术学院 Intelligent supporting device and supporting method for roadbed pit

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100439605C (en) * 2006-07-25 2008-12-03 南京大学 Chopped fiber reinforced rendzinas ground treatment method
CN100410455C (en) * 2006-08-14 2008-08-13 毛心焰 Strong rammer treatment high-water content foundation soil auxiliary construction process
CN101008178B (en) * 2007-01-12 2010-05-19 中山大学 Soft base processing construction process using excavating and stirring method
CN101748910B (en) * 2009-12-23 2012-02-22 赵天祥 Construction facility
CN102212465A (en) * 2011-06-22 2011-10-12 高节义 Large-scale methane tank
CN103912005A (en) * 2014-04-14 2014-07-09 五邑大学 Foundation structure
CN106049406A (en) * 2016-06-01 2016-10-26 上海建研地基基础工程有限公司 Method for lightly tampering lime soil foundation
CN106638575A (en) * 2017-01-10 2017-05-10 邓亚光 Reinforcing method of pile body
CN108166470A (en) * 2017-12-26 2018-06-15 武汉广益交通科技股份有限公司 A kind of method of cementitious composite waste plastics stake soft soil foundation
CN108117358A (en) * 2017-12-29 2018-06-05 福建建工建材科技开发有限公司 A kind of curing of waste soil combined processing
CN109987805A (en) * 2019-01-10 2019-07-09 浙江海洋大学 Waterway dredging slurry curing equipment
CN110258507A (en) * 2019-06-15 2019-09-20 武汉中力岩土工程有限公司 A kind of soft soil foundation reinforcing method
CN110258507B (en) * 2019-06-15 2021-05-14 武汉中力岩土工程有限公司 Soft soil foundation reinforcing method
CN117431970A (en) * 2023-12-22 2024-01-23 四川交通职业技术学院 Intelligent supporting device and supporting method for roadbed pit
CN117431970B (en) * 2023-12-22 2024-04-09 四川交通职业技术学院 Intelligent supporting device and supporting method for roadbed pit

Similar Documents

Publication Publication Date Title
CN100386484C (en) New type cement soil pile and its construction method
CN1093766A (en) Soft-clay lime deep-layer consolidation method
CN102926398B (en) A kind of for Salt Lake Area iron tower of power transmission line bolts of inclined column type anti-corrosion foundation construction method
CN110512589A (en) A kind of shallow-layer ultra-soft foundation curing method of vacuum Yield rainfall relation co-oxidation magnesium carbonization
CN110067167B (en) Microbial embankment filling method
CN112323560B (en) Roadbed construction settlement control system in complex soft foundation environment
CN106245622A (en) A kind of firming agent and the hydraulic fill foundation method for rapidly reinforcing of barged-in fill line-blending
CN1718937A (en) Technology of non soil taking hole guiding prestressed pipe pile or premade square sunk pile
CN1743561A (en) Column-hammer forced tamping substitution method
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN101029486A (en) Construction for fastly fastening flexible ground
KR100451093B1 (en) Lightweight fill materials using waste styrofoam beads
CN208777297U (en) A kind of mud and the foundation structure after Soft Soil Layer in-situ solidifying in conjunction with pile foundation
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN109440756A (en) Reinforcement module pressure-bearing pile body combination curing interlayer composite foundation structure processing method is placed in backfill
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN1078282A (en) Pile shoe pouring process and special reinforcing steel cage thereof
KR100272950B1 (en) Method of forming water-resist wall of rubbish buried place
CN208183722U (en) A kind of mud and soft soil foundation in-situ solidifying foundation structure
CN112195909A (en) Method for reinforcing soft foundation of road and parking lot
CN101704649A (en) Slurry formula of pile-sinking technique of non-soil borrowing lead-hole prestress pipe pile or prefabricated square pile
CN1830850A (en) Pipeline sludge solidification treatment method
CN100460600C (en) Blowing-filling sea-mud solidification construction method
JPH06313314A (en) Foundation ground improving construction method for low storied building
CN1167854C (en) Method for building compound pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C01 Deemed withdrawal of patent application (patent law 1993)
WD01 Invention patent application deemed withdrawn after publication