CN109301752A - A kind of hot line robot metal oxide arrester replacing options - Google Patents

A kind of hot line robot metal oxide arrester replacing options Download PDF

Info

Publication number
CN109301752A
CN109301752A CN201811280070.1A CN201811280070A CN109301752A CN 109301752 A CN109301752 A CN 109301752A CN 201811280070 A CN201811280070 A CN 201811280070A CN 109301752 A CN109301752 A CN 109301752A
Authority
CN
China
Prior art keywords
mechanical arm
arm
metal oxide
oxide arrester
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811280070.1A
Other languages
Chinese (zh)
Inventor
黄清
秦勇明
纪良
郭建
郭毓
黄颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811280070.1A priority Critical patent/CN109301752A/en
Publication of CN109301752A publication Critical patent/CN109301752A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Manipulator (AREA)
  • Forklifts And Lifting Vehicles (AREA)

Abstract

The present invention proposes a kind of metal oxide arrester replacing options, hot line robot has the mechanical arm being arranged on robot platform, including first mechanical arm, second mechanical arm and auxiliary mechanical arm, first mechanical arm, second mechanical arm and auxiliary mechanical arm complete the replacement of metal oxide arrester in response to control data;The control data are the angle desired value of each joint of mechanical arm movement, and when shaking operation, which is resolved according to each joint angles delta data of main manipulator by data processing and control system and obtained;When AUTONOMOUS TASK, data processing and control system cook up the space path of each mechanical arm using cartesian space paths planning method, then calculate the angle desired value of each joint of mechanical arm movement.The present invention can not power off, not on-load in the case where by the mechanical arm of hot line robot metal oxide arrester is replaced.

Description

A kind of hot line robot metal oxide arrester replacing options
The application be application No. is: 201611155219.4, invention and created name is a kind of " hot line robot gold Belong to Oxide Arrester replacing options ", the applying date are as follows: the divisional application of the application for a patent for invention on December 14th, 2016.
Technical field
The invention belongs to technical field of electric power, and in particular to a kind of hot line robot metal oxide arrester replacement Method.
Background technique
Metal oxide arrester is widely used in current electric system electric line, becomes excessively electric in electric system Press the capital equipment of protection.
With the longtime running of power distribution network, metal oxide arrester is likely to occur nut loosening, insulator rupture, rubber ring Aging variety of problems, needs replacing.Usual way is the replacement that has a power failure, if power failure area is larger, will cause the loss that can not be estimated, Seriously affect the economic benefit and social benefit of power supply enterprise.Present numerous researchers are also in actively research live-line replacing The method of metal oxide arrester.But artificial replacement and maintenance, operating personnel will the operation near electrification in high voltage route, With some potential safety problems.
Live-line replacing metal oxide arrester mainly uses insulating glove working system, insulating glove in distribution line Operating personnel dresses a full set of insulating protection apparatus in working system, carries out livewire work by insulating glove.Also needing can to human body The electrical body and grounding body that can be touched carry out insulation masking.Electric arc is often generated in replacement process, and easily operating personnel is made At burning;It needs to disconnect upper and lower lead in replacement process, also has the danger of electric shock;Operating personnel is in insulation bucket arm Operation on insulation bucket on vehicle, there is the risk of high falling;, may be due to the fault of manual operation in operation process, visitor Alternate lead spacing is small in sight, may cause phase fault event, gives people's property, and personal safety threatens.
Summary of the invention
Present invention solves the technical problem that be to propose a kind of metal oxide arrester replacing options, this method can be It does not power off, the mechanical arm in the case where on-load by hot line robot is not to the metal oxide in 10kv distribution line Arrester is replaced automatically, while reducing the danger that small operating personnel is faced, is simplified job step, is improved work Industry efficiency.
In order to solve the above technical problem, the present invention provides a kind of metal oxide arrester replacing options, livewire work Robot has the mechanical arm being arranged on robot platform, including first mechanical arm, second mechanical arm and auxiliary machinery Arm, first mechanical arm, second mechanical arm and auxiliary mechanical arm complete following work in response to control data:
Clamping device is installed in first mechanical arm, second mechanical arm and auxiliary mechanical arm end, clamps insulation with clamping device and hides It covers material and insulation masking is carried out to the electrical body of label;Then first mechanical arm and second mechanical arm end change the outfit bolt disassembly work Tool;
The fixed device of auxiliary mechanical arm clamping lead is moved to cross-arm nearby and will be on the fixation hole and cross-arm of wire fixture Intrinsic fixation hole alignment;First mechanical arm and second mechanical arm, which are fixed using the installation of bolt disassembly tool for anchor leg, to be filled The fixed device of anchor leg is fixed on cross-arm by the bolt set;
Auxiliary mechanical arm clamps upper lead, first mechanical arm and second mechanical arm and uses bolt disassembly tool dismounting metal oxide The bolt of fixed upper lead on arrester, then the upper lead disassembled is moved on wire fixture by auxiliary mechanical arm Near the fixation hole at end;The spiral shell of first mechanical arm and second mechanical arm using the installation of bolt disassembly tool for fixed upper lead Upper lead is fixed on the upper end of wire fixture by bolt;
Auxiliary mechanical arm stops clamping upper lead, and is moved to lower lead and nearby clamps to lower lead;First mechanical arm and Second mechanical arm removes the bolt of fixed lower lead on metal oxide arrester using bolt disassembly tool, and then auxiliary is mechanical The lower lead disassembled is moved near the fixation hole of wire fixture lower end by arm;First mechanical arm and second mechanical arm Lower lead, is fixed on the lower end of wire fixture by the bolt using the installation of bolt disassembly tool for fixed lower lead;
Auxiliary mechanical arm stops clamping lower lead, and be moved to metal oxide arrester nearby to metal oxide arrester into Row clamping;First mechanical arm and second mechanical arm are removed using bolt disassembly tool is used for fixing metal oxide arrester and cross The bolt of load;After disassembling bolts, metal oxide arrester is moved on robot platform and places by auxiliary mechanical arm;
Auxiliary mechanical arm clamps new metal oxide arrester, and new metal oxide arrester is moved near cross-arm; First mechanical arm and second mechanical arm install the bolt for fixing fuse switch and cross-arm using bolt disassembly tool, will Fuse switch is fixed with cross-arm;
Auxiliary mechanical arm stops clamping metal oxide arrester, then is clamped to the lower lead on wire fixture; First mechanical arm and second mechanical arm remove the bolt for fixed upper lead using bolt disassembly tool, by lower lead from lead It is removed on fixed device;Lower lead is moved near the mounting hole of metal oxide arrester lower end by auxiliary mechanical arm, the The bolt of one mechanical arm and second mechanical arm using the installation of bolt disassembly tool for fixed lower lead, is fixed on gold for lower lead Belong to Oxide Arrester lower end;
Auxiliary mechanical arm stops clamping lower lead, then is clamped to the upper lead on wire fixture;First mechanical arm The bolt for fixed upper lead is removed using bolt disassembly tool with second mechanical arm, by upper lead from wire fixture It removes;Upper lead is moved to the mounting hole near metal oxide arrester upper end by auxiliary mechanical arm, first mechanical arm with Bolt of the second mechanical arm using the installation of bolt disassembly tool for fixed upper lead, is fixed on metal oxide for upper lead and keeps away Thunder device upper end;
Auxiliary mechanical arm stops clamping upper lead, then clamping lead fixes device;First mechanical arm and second mechanical arm use Bolt disassembly tool removes the bolt for anchor leg fixed device and cross-arm, and wire fixture is removed from cross-arm Come;Wire fixture is put back to tool box special on robot platform by auxiliary mechanical arm;
First mechanical arm and second mechanical arm change the outfit clamping device, are hidden using the insulation that clamping device clamping is covered on electrical body Material is covered, insulation masking material is removed;
Perhaps second mechanical arm or auxiliary mechanical arm push the active module of fuse switch to first mechanical arm, to close Upper fuse switch.
Further, the control data are the angle desired value of each joint of mechanical arm movement, and the angle desired value is by charging Work robot data processing and control system are according to each joint angles variation number of the main manipulator for being set to insulation bucket arm car It is obtained according to resolving;Main manipulator includes the first main manipulator, the second main manipulator and auxiliary main manipulator;First main manipulator, Second main manipulator and auxiliary main manipulator are corresponding with first mechanical arm, second mechanical arm and auxiliary mechanical arm respectively, constitute master From operative relationship.
Further, the control data are the angle desired value of each joint of mechanical arm movement;Hot line robot data Processing and control systems use Descartes according to the relative position and job task action sequence of each mechanical arm and manipulating object Space path planing method cooks up the space path of each mechanical arm, then calculates each joint of mechanical arm according to space path and transports Dynamic angle desired value.
Further, the insulation masking material is insulating sheath or epoxy glass fabric.
Further, the wire fixture includes ontology, and position is used for and cross-arm fixation between setting in the body The fixation hole for fixed upper lead and lower lead at both ends is descended in fixation hole, and setting on the body.
Further, the metal oxide arrester, which is placed on, is moved in the tool box special on robot platform.
Compared with prior art, the present invention its remarkable advantage is, due to replacing gold automatically using hot line robot Belong to Oxide Arrester, improves operating efficiency and accuracy, avoid the possibility of human error, can reduce to a certain extent A possibility that accident occurs;The negative effect of line outage bring is largely avoided, power off time is greatly reduced, mentions High power supply reliability;Simultaneously reduce the danger that small operating personnel is faced, without consider electric arc generate when to human body burn with And the problems such as Danger Electric shock risk, falling from high altitude, substantially increase the safety in operation process.
Detailed description of the invention
Fig. 1 is hot line robot overall structure diagram of the present invention;
Fig. 2 is the structural schematic diagram of robot platform in the present invention;
Fig. 3 is the method for the invention flow chart;
Fig. 4 is wire fixture structural schematic diagram used in the present invention;
Fig. 5 is hot line robot charged for replacement metal oxide arrester operating environment schematic diagram of the present invention.
Specific embodiment
It is readily appreciated that, technical solution according to the present invention, in the case where not changing connotation of the invention, this field Those skilled in the art can imagine a variety of realities of hot line robot metal oxide arrester replacing options of the present invention Apply mode.Therefore, following specific embodiments and attached drawing are only the exemplary illustrations to technical solution of the present invention, without should It is considered as whole of the invention or is considered as the limitation or restriction to technical solution of the present invention.
In conjunction with attached drawing, hot line robot includes aerial lift device with insulated arm 1, control room 2, telescopic arm 3, robot platform 4.Its In, set up control room 2 and telescopic arm 3 on aerial lift device with insulated arm 1,3 end of telescopic arm connects robot platform 4, robot platform 4 with Using fiber optic Ethernet communication or wireless communication between control room 2.
Aerial lift device with insulated arm 1 is for operator's driving, so that robot platform 4 is transported operation field.Insulation bucket arm Supporting leg is housed, supporting leg can be unfolded, thus by the firm support of aerial lift device with insulated arm 1 and ground on vehicle 1.On aerial lift device with insulated arm 1 Equipped with generator, to power to control room 2 and telescopic arm 3.
Telescopic arm 3 is equipped with the driving device along telescopic direction, and operator can be by controlling driving device, thus by machine Device people platform 4 is elevated to operation height.The telescopic arm 3 is made of insulating material, for realizing robot platform 4 and control room 2 Insulation.In the present invention, telescopic arm 3 can have by scissor-type lifting mechanism or the replacement of other mechanisms.
Data processing and control system and display screen, the first main manipulator, the second main operation are provided in control room 2 Hand, auxiliary main manipulator and communication module etc..
Robot platform 4 includes insulator 46, first mechanical arm 43, second mechanical arm 44, auxiliary mechanical arm 42, the first work Control machine 48, binocular camera 45, full-view camera 41, depth camera 410, battery 49, tool box special 47, communication mould Block.
The insulator 46 of robot platform 4 is used to support first mechanical arm 43, second mechanical arm 44, auxiliary mechanical arm 42, The shell of these three mechanical arms and robot platform 4 are insulated.
Battery 49 is the first industrial personal computer 48, first mechanical arm 43, second mechanical arm 44, auxiliary mechanical arm 42, panorama are taken the photograph As head 41, binocular camera 45, depth camera 410, communication module power supply.
Tool box special 47 is the place for placing the power tools such as gripping apparatus, spanner.Mechanical arm tail end is equipped with tool quick change Device.Mechanical arm obtains power tool using tool fast replacing device into tool box special 47 according to the type of job task.
First main manipulator, the second main manipulator and auxiliary main manipulator are a kind of for artificial long-range in control room 2 The operating device of operating robotic arm, they and first mechanical arm 43, second mechanical arm 44 and auxiliary mechanical arm 42 constitute principal and subordinate behaviour Make relationship.Mechanical arm and main manipulator structure having the same, only main manipulator dimensions is smaller than mechanical arm, in order to grasp Make personnel's operation.Mechanical arm and main manipulator are gathered around there are six joint, and there are photoelectric encoder acquisition angles data in each joint, respectively The angle-data in six joints is sent to the second industrial personal computer by serial ports by the microcontroller of main manipulator.
Data between robot platform 4 and control room 2 are transmitted through optical fiber wire transmission, or use wireless network transmissions. Communication module on robot platform 4 is fiber optical transceiver, and fiber optical transceiver is for realizing the optical signal and twisted pair in optical fiber In electric signal mutual conversion, thus in communication realize robot platform 4 and control room 2 electrical isolation.In control room 2 Communication module be fiber optical transceiver, fiber optical transceiver for realizing optical signal and the electric signal in twisted pair in optical fiber phase Mutually conversion, to realize the electrical isolation of robot platform 4 and control room 2 in communication.
Hot line robot of the present invention not only can be carried out remotely shaking operation by operating personnel to complete livewire work, but also can To carry out autonomous livewire work.
The process that hot line robot replaces fuse switch is as follows:
Before replacing metal oxide arrester 120, the operation that operating personnel first carries out hot line robot prepares, and checks Meteorological condition, verification shaft tower number, arrangement are live, safety barrier, working signal and related warning mark is arranged in working site, Surface insulation resistance detection is carried out to the insulating tool used using Insulation Resistance Tester, resistance value is not less than 700 megaohms.By Aerial lift device with insulated arm 1 is driven into 100 neighbouring position of shaft tower and arranges scene by aerial lift device with insulated arm driver.Job position is specially wait make Position and nearby power line and barrier are avoided near industry shaft tower 100, avoids being parked on channel cover board, aerial lift device with insulated arm 1 Supporting leg sequence is first to stretch out horizontal support legs, then stretch out vertical leg, and it is in horizontal for supporting to place rear vehicle all around.
After aerial lift device with insulated arm arrangement is appropriate, hot line robot, capturing panoramic view image are opened.Operator is according to aobvious Show the real scene image that device is shown, controls telescopic arm 3 for robot platform 4 and be moved to fuse switch job position.Operator The real scene image that member returns according to binocular camera 45 on mechanical arm is to the electrical body in job area in insulating safety distances It is marked.
First mechanical arm 43, second mechanical arm 44 and auxiliary mechanical arm 42 complete following work in response to control data:
Clamping device is installed in first mechanical arm 43, second mechanical arm 44 and 42 end of auxiliary mechanical arm, is clamped with clamping device Insulation masking material carries out insulation masking to the electrical body of label.Insulate masking material such as insulating sheath, epoxy glass fabric etc..It is auxiliary The fixed device 190 of 42 clamping lead of mechanical arm is helped to be moved to cross-arm 103 nearby and by the fixation hole of wire fixture 190 and horizontal Intrinsic fixation hole alignment in load 103;It changes the outfit bolt disassembly tool in first mechanical arm 43 and 44 end of second mechanical arm, first The bolt of mechanical arm 43 and second mechanical arm 44 using the installation of bolt disassembly tool for the fixed device 190 of anchor leg, will consolidate Determine wire fixture 190 to be fixed on cross-arm 103;The wire fixture includes ontology, position between setting in the body Descend the fixation for fixed above lead and lower lead at both ends on the body for the fixation hole fixed with cross-arm, and setting Hole.Aperture on wire fixture meets the standard of minimum safe distance.
Auxiliary mechanical arm 42 clamps upper lead 101, while first mechanical arm 43 and second mechanical arm 44 use bolt disassembly Tool removes the bolt of fixed upper lead 101 on metal oxide arrester 120, and then auxiliary mechanical arm 42 will disassemble Upper lead 101 is moved near the fixation hole of 190 upper end of wire fixture;First mechanical arm 43 and second mechanical arm 44 use Bolt of the bolt disassembly tool installation for fixed upper lead 101, is fixed on the upper of wire fixture 190 for upper lead 101 End.
Auxiliary mechanical arm 42 stops clamping upper lead 101, and is moved to lower lead 102 and nearby presss from both sides to lower lead 102 It holds.Meanwhile first mechanical arm 43 and second mechanical arm 44 are removed on metal oxide arrester 120 admittedly using bolt disassembly tool The bolt of lead 102 is fixed, then the lower lead 102 disassembled is moved to wire fixture 190 by auxiliary mechanical arm 42 Near the fixation hole of lower end;Lead under first mechanical arm 43 and second mechanical arm 44 are used to fix using the installation of bolt disassembly tool Lower lead 102 is fixed on the lower end of wire fixture 190 by 102 bolt.
42 end of auxiliary mechanical arm stops clamping lower lead 102, and is moved to metal oxide arrester 120 nearby to gold Belong to Oxide Arrester 120 to be clamped.At this point, first mechanical arm 43 and second mechanical arm 44 are removed using bolt disassembly tool Bolt for fixing metal oxide arrester 120 and cross-arm 103;After disassembling bolts, auxiliary mechanical arm 42 aoxidizes metal Object arrester 120 is moved to tool box special 47 on robot platform 4.
After replaced metal oxide arrester 120 is put into tool box special 47 by auxiliary mechanical arm 42, then press from both sides Metal oxide arrester 120 new in tool box special 47 is held, new metal oxide arrester 120 is then moved to cross Near load 103.First mechanical arm 43 and second mechanical arm 44 are installed using bolt disassembly tool for fixing fuse switch It is with the bolt of cross-arm 103, fuse switch and cross-arm 103 is fixed.
Auxiliary mechanical arm 42 stops clamping metal oxide arrester 120, then is clamped to wire fixture 190 On lower lead 102.First mechanical arm 43 and second mechanical arm 44 are removed using bolt disassembly tool for fixed upper lead 101 Bolt, lower lead 102 is removed from wire fixture 190.Lower lead 102 is moved to metal by auxiliary mechanical arm 42 Near the mounting hole of 120 lower end of Oxide Arrester, first mechanical arm 43 and second mechanical arm 44 are pacified using bolt disassembly tool Bolt of the dress for fixed lower lead 102, is fixed on 120 lower end of metal oxide arrester for lower lead 102.
Auxiliary mechanical arm 42 stops clamping lower lead 102, then is clamped to the upper lead on wire fixture 190 101.First mechanical arm 43 and second mechanical arm 44 remove the bolt for fixed upper lead 101 using bolt disassembly tool, will Upper lead 101 is removed from wire fixture 190.Upper lead 101 is moved to metal oxide and kept away by auxiliary mechanical arm 42 Mounting hole near 120 upper end of thunder device, first mechanical arm 43 and second mechanical arm 44 are using the installation of bolt disassembly tool for solid Surely the bolt of upper lead 101, is fixed on 120 upper end of metal oxide arrester for upper lead 101.
Auxiliary mechanical arm 42 stops clamping upper lead 101, then clamping lead fixes device 190.43 He of first mechanical arm Second mechanical arm 44 removes the bolt for anchor leg fixed device 190 and cross-arm 103 using bolt disassembly tool, by lead Fixed device 190 is removed from cross-arm 103.Auxiliary mechanical arm 42 puts back to wire fixture 190 on robot platform 4 specially With tool box 47.
First mechanical arm 43 and second mechanical arm 44 change the outfit clamping device, are covered on electrical body using clamping device clamping Insulation masking material, remove insulation masking material.
First mechanical arm 43 pushes the active module of fuse switch, to close fuse switch.
When completing the above process by manually shaking operation, the control data are the angle expectation of each joint of mechanical arm movement Value, the angle desired value is by hot line robot data processing and control system according to the main behaviour for being set to insulation bucket arm car Make each joint angles delta data of hand and resolves acquisition;Main manipulator includes the first main manipulator, the second main manipulator and auxiliary master Manipulator;First main manipulator, the second main manipulator and auxiliary main manipulator respectively with first mechanical arm 43, second mechanical arm 44 It is corresponding with auxiliary mechanical arm 42, constitute master-slave operation relationship.
When hot line robot independently completes the above process, the control data are the angle of each joint of mechanical arm movement Desired value;Hot line robot data processing and control system are according to the relative position and work of each mechanical arm and manipulating object Industry task action sequence, the space path of each mechanical arm is cooked up using cartesian space paths planning method, then according to sky Between path calculate the angle desired value of each joint of mechanical arm movement.
The method of the present invention can pass through the mechanical arm of hot line robot to gold in the case where not powering off without load Belong to Oxide Arrester and carry out charged for replacement, avoids the negative effect of power failure bring, power off time is greatly reduced, improve and supply Electric reliability alleviates electricity consumption and complains contradiction.The present invention replaces people to carry out livewire work using hot line robot, compared to exhausted Edge bar working system has function more abundant.The present invention can be exempted from using hot line robot compared to insulating glove working system In consider electric arc lead to the problem of when to human body burn and Danger Electric shock risk, falling from high altitude.The present invention uses hot line robot It is controlled by operator's rocking bar, operating personnel labor intensity is required small, reduce that operation intensity is big human error occurs Situation substantially increases the safety in operation process, can reduce the generation of accident to a certain extent.

Claims (3)

1. a kind of metal oxide arrester replacing options, which is characterized in that hot line robot, which has, to be arranged in robot Mechanical arm on platform (4), including first mechanical arm (43), second mechanical arm (44) and auxiliary mechanical arm (42), the first machine Tool arm (43), second mechanical arm (44) and auxiliary mechanical arm (42) complete following work in response to control data:
Clamping device is installed in first mechanical arm (43), second mechanical arm (44) and auxiliary mechanical arm (42) end, with clamping work Tool clamping insulation masking material carries out insulation masking to the electrical body of label;Then first mechanical arm (43) and second mechanical arm (44) end changes the outfit bolt disassembly tool;
Auxiliary mechanical arm (42) clamping lead fixed device (190) is moved to cross-arm (103) nearby and by wire fixture (190) fixation hole is aligned with fixation hole intrinsic on cross-arm (103);First mechanical arm (43) and second mechanical arm (44) use Bolt of the bolt disassembly tool installation for anchor leg fixed device (190), anchor leg fixed device (190) is fixed on On cross-arm (103);
Lead (101) in auxiliary mechanical arm (42) clamping, first mechanical arm (43) and second mechanical arm (44) use bolt disassembly Tool removes the bolt of fixed upper lead (101) on metal oxide arrester (120), and then auxiliary mechanical arm (42) will be dismantled The upper lead (101) to get off is moved near the fixation hole of wire fixture (190) upper end;First mechanical arm (43) and second Bolt of the mechanical arm (44) using the installation of bolt disassembly tool for fixed upper lead (101), upper lead (101) is fixed on and is drawn The upper end of line fixed device (190);
Auxiliary mechanical arm (42) stops clamping upper lead (101), and be moved to lower lead (102) nearby to lower lead (102) into Row clamping;First mechanical arm (43) and second mechanical arm (44) use bolt disassembly tool dismounting metal oxide arrester (120) bolt of fixed lower lead (102) on, then the lower lead (102) disassembled is moved to by auxiliary mechanical arm (42) Near the fixation hole of wire fixture (190) lower end;First mechanical arm (43) and second mechanical arm (44) use bolt disassembly Lower lead (102), is fixed on the lower end of wire fixture (190) by bolt of the tool installation for fixed lower lead (102);
Auxiliary mechanical arm (42) stops clamping lower lead (102), and is moved to metal oxide arrester (120) nearby to metal Oxide Arrester (120) is clamped;First mechanical arm (43) and second mechanical arm (44) are removed using bolt disassembly tool Bolt for fixing metal oxide arrester (120) and cross-arm (103);After disassembling bolts, auxiliary mechanical arm (42) will be golden Category Oxide Arrester (120), which is moved on robot platform 4, to be placed;
Auxiliary mechanical arm (42) clamps new metal oxide arrester (120), and new metal oxide arrester (120) is moved It moves near cross-arm (103);First mechanical arm (43) and second mechanical arm (44) are installed using bolt disassembly tool for fixing The bolt of metal oxide arrester and cross-arm (103), metal oxide arrester and cross-arm (103) is fixed;
Auxiliary mechanical arm (42) stops clamping metal oxide arrester (120), then is clamped to wire fixture (190) the lower lead (102) on;First mechanical arm (43) and second mechanical arm (44) are removed using bolt disassembly tool for solid The bolt of surely upper lead (101), lower lead (102) is removed from wire fixture (190);Auxiliary mechanical arm (42) will Lower lead (102) is moved near the mounting hole of metal oxide arrester (120) lower end, first mechanical arm (43) and the second machine Bolt of the tool arm (44) using the installation of bolt disassembly tool for fixed lower lead (102), is fixed on metal for lower lead (102) Oxide Arrester (120) lower end;
Auxiliary mechanical arm (42) stops clamping lower lead (102), then be clamped on wire fixture (190) on draw Line (101);First mechanical arm (43) and second mechanical arm (44) are removed using bolt disassembly tool for fixed upper lead (101) Bolt, upper lead (101) is removed from wire fixture (190);Auxiliary mechanical arm (42) moves upper lead (101) It moves to the mounting hole near metal oxide arrester (120) upper end, first mechanical arm (43) and second mechanical arm (44) use Bolt of the bolt disassembly tool installation for fixed upper lead (101), is fixed on metal oxide arrester for upper lead (101) (120) upper end;
Auxiliary mechanical arm (42) stops clamping upper lead (101), then clamping lead is fixed device (190);First mechanical arm (43) it is removed using bolt disassembly tool for anchor leg fixed device (190) and cross-arm (103) with second mechanical arm (44) Bolt, wire fixture (190) is removed from cross-arm (103);Auxiliary mechanical arm (42) is by wire fixture (190) tool box special (47) on robot platform (4) is put back to;
First mechanical arm (43) and second mechanical arm (44) change the outfit clamping device, are covered on electrical body using clamping device clamping Insulation masking material, remove insulation masking material;The control data are the angle desired value of each joint of mechanical arm movement, should Angle desired value is by hot line robot data processing and control system according to the main manipulator for being set to insulation bucket arm car Each joint angles delta data, which resolves, to be obtained;Main manipulator includes the first main manipulator, the second main manipulator and auxiliary main operation Hand;First main manipulator, the second main manipulator and auxiliary main manipulator respectively with first mechanical arm (43), second mechanical arm (44) It is corresponding with auxiliary mechanical arm (42), constitute master-slave operation relationship.
2. metal oxide arrester replacing options as described in claim 1, which is characterized in that the insulation masking material is exhausted Edge sheath or epoxy glass fabric.
3. metal oxide arrester replacing options as described in claim 1, which is characterized in that the metal oxide arrester (120) it is placed in the tool box special (47) being moved on robot platform (4).
CN201811280070.1A 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options Pending CN109301752A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811280070.1A CN109301752A (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201611155219.4A CN106451224B (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options
CN201811280070.1A CN109301752A (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201611155219.4A Division CN106451224B (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options

Publications (1)

Publication Number Publication Date
CN109301752A true CN109301752A (en) 2019-02-01

Family

ID=58217567

Family Applications (4)

Application Number Title Priority Date Filing Date
CN201811280070.1A Pending CN109301752A (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options
CN201811281091.5A Pending CN109473903A (en) 2016-12-14 2016-12-14 One kind being used for metal oxide arrester replacing options
CN201811280068.4A Pending CN109309358A (en) 2016-12-14 2016-12-14 A kind of replacing options for hot line robot metal oxide arrester
CN201611155219.4A Active CN106451224B (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options

Family Applications After (3)

Application Number Title Priority Date Filing Date
CN201811281091.5A Pending CN109473903A (en) 2016-12-14 2016-12-14 One kind being used for metal oxide arrester replacing options
CN201811280068.4A Pending CN109309358A (en) 2016-12-14 2016-12-14 A kind of replacing options for hot line robot metal oxide arrester
CN201611155219.4A Active CN106451224B (en) 2016-12-14 2016-12-14 A kind of hot line robot metal oxide arrester replacing options

Country Status (1)

Country Link
CN (4) CN109301752A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109950830A (en) * 2019-04-08 2019-06-28 南京理工大学 The provision for disengagement of hot line robot arrester and method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108616076B (en) * 2018-03-20 2020-04-17 南京理工大学 Method for disassembling and assembling lightning arrester by live working robot
CN108544215A (en) * 2018-04-11 2018-09-18 南京理工大学 A kind of hot line robot arrester replacing method based on force feedback master & slave control
CN111293626B (en) * 2018-12-07 2021-09-28 国网内蒙古东部电力有限公司经济技术研究院 Live replacement method based on lightning protection device
CN114603562B (en) * 2022-04-19 2024-04-30 南方电网电力科技股份有限公司 Distribution network electrified lead connecting device and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1385283A (en) * 2002-06-24 2002-12-18 山东鲁能智能技术有限公司 Robot for high-voltage hot-line work
CN203398619U (en) * 2013-05-28 2014-01-15 国家电网公司 Line arrester replacing device
CN104638564A (en) * 2015-01-23 2015-05-20 国网山西省电力公司晋城供电公司 Insulated fixing device for use in live replacement of drop-out fuse

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2593610B2 (en) * 1992-03-27 1997-03-26 古河電気工業株式会社 Operation method of power distribution work robot
CN102601782B (en) * 2012-04-01 2014-08-27 山东电力研究院 High-voltage live working robot device
CN204546543U (en) * 2015-04-28 2015-08-12 国家电网公司 High-tension line drop switch changes control system automatically

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1385283A (en) * 2002-06-24 2002-12-18 山东鲁能智能技术有限公司 Robot for high-voltage hot-line work
CN203398619U (en) * 2013-05-28 2014-01-15 国家电网公司 Line arrester replacing device
CN104638564A (en) * 2015-01-23 2015-05-20 国网山西省电力公司晋城供电公司 Insulated fixing device for use in live replacement of drop-out fuse

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
赵峻峰 等: ""金属氧化物避雷器状态诊断新方法与应用"", 《河北电力技术》 *
陈昶: ""10KV跌落式熔断器带电更换作业"", 《大众用电》 *
陈泽: ""基于虚拟现实的危险作业机器人遥操作控制***研究"", 《中国优秀硕士学位论文全文数据库 信息科技辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109950830A (en) * 2019-04-08 2019-06-28 南京理工大学 The provision for disengagement of hot line robot arrester and method

Also Published As

Publication number Publication date
CN109473903A (en) 2019-03-15
CN109309358A (en) 2019-02-05
CN106451224B (en) 2018-11-02
CN106451224A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106451224B (en) A kind of hot line robot metal oxide arrester replacing options
CN106786140B (en) A kind of hot line robot strain insulator replacing options
CN110421546A (en) A kind of distribution network live line work robot with automatic quick change engaging tool system
CN102601782B (en) High-voltage live working robot device
CN107650124A (en) A kind of robot for high-voltage hot-line work aerial work platform and its method for unloading gold utensil screw
CN103111996B (en) Converting station hot-line work robot insulation protection system
CN108616076B (en) Method for disassembling and assembling lightning arrester by live working robot
CN1385283A (en) Robot for high-voltage hot-line work
CN106826756A (en) A kind of conducting wire mending method based on robot for high-voltage hot-line work
CN106595762A (en) Hot-line work robot tension insulator detection method
CN106532565B (en) A kind of hot line robot fuse switch replacing options
CN104020400A (en) Subsection alternating current voltage withstanding test method for 750kV insulation tool and instrument
CN104538889A (en) Live-line replacing method of straight pole insulator of distribution network line
CN2597163Y (en) High-voltage live-wire working device for manipulator
WO2017144208A1 (en) High-voltage circuit breaker having an arrangement and method for supplying energy to the circuit breaker
CN203031600U (en) Converting station hot-line work robot insulation protection system
CN203607749U (en) Shielding cover for distribution-line disconnecting switch
CN104577831A (en) Diverting tool and electrical equipment hotline maintenance method
CN109950830A (en) The provision for disengagement of hot line robot arrester and method
CN106695785A (en) Hot-line work robot fall fuse detecting method
CN104538888B (en) A kind of distribution line straight line pole cross-arm charged for replacement method
CN114421192B (en) Distribution network three-phase line grounding operation mechanical arm assembly
CN108598989A (en) A kind of hot line robot fuse switch replacing options based on force feedback master & slave control
CN205863847U (en) The orientable bus duct of safety that a kind of power equipment is special
CN107069531B (en) A kind of isolation switch replacing options of hot line robot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No. 27, Tianning District Bureau, front street, Changzhou, Jiangsu Province

Applicant after: STATE GRID JIANGSU ELECTRIC POWER Co.,Ltd. CHANGZHOU POWER SUPPLY BRANCH

Applicant after: STATE GRID JIANGSU ELECTRIC POWER Co.,Ltd.

Applicant after: STATE GRID CORPORATION OF CHINA

Address before: No. 27, Tianning District Bureau, front street, Changzhou, Jiangsu Province

Applicant before: STATE GRID CHANG ZHOU CURRENT SUPPLY COMPANY OF JIANGSU ELECTRIC POWER Co.

Applicant before: STATE GRID JIANGSU ELECTRIC POWER Co.

Applicant before: State Grid Corporation of China

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190201