CN109281422A - Prefabricated concrete structure wall-column all steel key connection structure and assembling method - Google Patents
Prefabricated concrete structure wall-column all steel key connection structure and assembling method Download PDFInfo
- Publication number
- CN109281422A CN109281422A CN201811329141.2A CN201811329141A CN109281422A CN 109281422 A CN109281422 A CN 109281422A CN 201811329141 A CN201811329141 A CN 201811329141A CN 109281422 A CN109281422 A CN 109281422A
- Authority
- CN
- China
- Prior art keywords
- wall
- prefabricated
- prefabricated post
- shear wall
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 83
- 239000010959 steel Substances 0.000 title claims abstract description 83
- 239000004567 concrete Substances 0.000 title claims abstract description 57
- 238000000034 method Methods 0.000 title claims abstract description 26
- 238000010008 shearing Methods 0.000 claims abstract description 15
- 238000009434 installation Methods 0.000 claims abstract description 6
- 210000003205 muscle Anatomy 0.000 claims description 70
- UHOVQNZJYSORNB-UHFFFAOYSA-N Benzene Chemical compound C1=CC=CC=C1 UHOVQNZJYSORNB-UHFFFAOYSA-N 0.000 claims description 54
- 230000002787 reinforcement Effects 0.000 claims description 36
- 230000003014 reinforcing effect Effects 0.000 claims description 24
- 238000004519 manufacturing process Methods 0.000 claims description 21
- 238000005266 casting Methods 0.000 claims description 10
- 238000004458 analytical method Methods 0.000 claims description 8
- 239000002184 metal Substances 0.000 claims description 6
- 238000009415 formwork Methods 0.000 claims description 4
- 239000000203 mixture Substances 0.000 claims description 3
- 238000003780 insertion Methods 0.000 claims description 2
- 230000037431 insertion Effects 0.000 claims description 2
- 239000006071 cream Substances 0.000 claims 1
- 239000004575 stone Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 15
- 230000008878 coupling Effects 0.000 abstract description 5
- 238000010168 coupling process Methods 0.000 abstract description 5
- 238000005859 coupling reaction Methods 0.000 abstract description 5
- 238000004134 energy conservation Methods 0.000 description 3
- 230000007613 environmental effect Effects 0.000 description 3
- 229910052602 gypsum Inorganic materials 0.000 description 3
- 239000010440 gypsum Substances 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 238000007596 consolidation process Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 208000002193 Pain Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/64—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B1/4107—Longitudinal elements having an open profile, with the opening parallel to the concrete or masonry surface, i.e. anchoring rails
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/64—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
- E04B2/66—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete characterised by special cross-section of the elongated members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B2001/4192—Connecting devices specially adapted for embedding in concrete or masonry attached to concrete reinforcing elements, e.g. rods or wires
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
The present invention relates to prefabricated assembled concrete structural construction field, specially a kind of prefabricated concrete structure wall-column all steel key connection structure and assembling method.The structure includes prefabricated post-wall built-in fitting, prefabricated post, precast shear wall, precast shear wall is located between two prefabricated posts, prefabricated post-wall built-in fitting between prefabricated post and precast shear wall is corresponding, passes through I-shaped column-wall connection key connection between the prefabricated post being oppositely arranged-wall built-in fitting.Prefabricated post of the present invention and precast shear wall complete the transmitting of wall-intercolumniation coupling part shearing, further enhance the globality of structure, anti-seismic performance is more preferable by the way that built-in fitting and I-steel shear key is arranged in precast shear wall and prefabricated post coupling part.The present invention does not include the processes such as scene grouting or concreting, and whole processes are all the in-site installation connections of prefabricated components, does not need wet construction, greatly shortens the time required for building-site is constructed, can greatly improve speed of application.
Description
[technical field]
The present invention relates to prefabricated assembled concrete structural construction field, specially a kind of prefabricated concrete structure wall-
Column all steel is keyed structure and assembling method.
[background technique]
Prefabricated concrete structure has many advantages, such as that fast speed of application, energy conservation and environmental protection, on-site wet operation amount are small, exists in recent years
The country is grown rapidly.Concrete frame-shear wall structure (abbreviation frame-shear structure) is the primary structure that China applies at present
One of form.Therefore, connection frame-shear structure how is split, forming assembled system becomes important the asking of civil engineer's concern
Topic.Previous related wall-column connection, it is main that the then method in junction casting concrete or grouting material is connected using reinforcing bar, it applies
Work needs wet construction, and construction technology is cumbersome, and speed of application is slow, and the quality of connecting portion is not easy to guarantee.For this purpose, before inventor
Invention " a kind of assembled frame-shear structure curved scissors type combination keyway connection structure " and a kind of " assembly concrete frame-shear wall key
Slot connection structure ", and authorized.Above-mentioned two patent is connected using grouting, is needed in piece between handling component
Wet construction, and wall-column junction, the ability that both limitations disengage are weaker.For this purpose, proposing prefabricated concrete structure wall-column
All steel is keyed structure and assembling method.
[summary of the invention]
The purpose of the present invention is to provide a kind of prefabricated concrete structure wall-column all steel key connection structure and assembly sides
Method, under the premise of being connected between guaranteeing various precast concretes, completely without wet construction, greatly improve speed of application and
Construction quality.
Technical solution of the present invention:
A kind of prefabricated concrete structure wall-column all steel is keyed structure, including prefabricated post-wall built-in fitting, prefabricated post, pre-
Shear wall processed, precast shear wall are located between two prefabricated posts, prefabricated post-wall built-in fitting between prefabricated post and precast shear wall
It is corresponding, pass through I-shaped column-wall connection key connection between the prefabricated post being oppositely arranged-wall built-in fitting, in which:
(1) prefabricated post-wall built-in fitting is made of ribbed steel and circular hole, and the side of ribbed steel is arranged in parallel transversal up and down
Face is the floor of L-type, and circular hole, circular hole parallel arrangement are arranged on monolith ribbed steel, and the lateral stressed muscle of shear wall passes through circular hole, rib
Plate forms groove with the side of ribbed steel respectively, and upper and lower two grooves are opposite;
(2) prefabricated post is poured mixed by longitudinal stress muscle, prefabricated column tie-bar, vertical reinforcement sleeve and ribbed steel in prefabricated post
Local soil type is coagulated at longitudinal stress muscle connects to form frame structure by prefabricated column tie-bar in four prefabricated posts of the arrangement that is square, often
The bottom of longitudinal stress muscle is set with vertical reinforcement sleeve in a prefabricated post, and the one side of the frame structure is uniformly set from top to bottom
Prefabricated post-wall built-in fitting is set, concreting is in frame structure inner side and outer side;
(3) precast shear wall includes framework of steel reinforcement, prefabricated post-wall built-in fitting and concrete, the two sides difference of framework of steel reinforcement
Prefabricated post-wall built-in fitting is set, and concreting is in framework of steel reinforcement inner side and outer side;Framework of steel reinforcement is shear wall longitudinal stress
The lateral stressed muscle of muscle, shear wall, shear wall confined boundary member stirrup and shearing wall lacing wire composition, two rows of shear wall longitudinal stresses
Muscle is oppositely arranged in parallel, and by the lateral stressed muscle connection of shear wall between every row's shear wall longitudinal stress muscle, what is be oppositely arranged is cut
It is connected between power wall longitudinal stress muscle by shearing wall lacing wire, outside is flat up and down between the edge of two rows of shear wall longitudinal stress muscle
Row setting shear wall confined boundary member stirrup.
The prefabricated concrete structure wall-column all steel is keyed structure, I-shaped column-wall connecting key 4 by vertical plate,
Level board, convex ribs composition, the level board setting up and down of vertical plate are in I-shaped structure, both ends one at the top of superposed level board
Parallel convex ribs are arranged in body, are wholely set parallel convex ribs, I-shaped column-wall connecting key positioned at the level board bottom both ends of lower part
4 two sides are connect with prefabricated post-wall built-in fitting respectively, I-shaped column-wall connecting key by upper and lower two convex ribs respectively with it is prefabricated
The two groove inserting cooperations up and down of column-wall built-in fitting.
The prefabricated concrete structure wall-column all steel is keyed structure, interconnecting piece between prefabricated post and precast shear wall
Cover board is arranged in position outside, and cover board includes cover board cross direction profiles muscle, cover board genesis analysis muscle and billet, the parallel opposite lid of a row
Plate cross direction profiles muscle and the parallel opposite cover board genesis analysis muscle of a row form steel reinforcement net.
The prefabricated concrete structure wall-column all steel is keyed structure, and billet is welded on certain in steel reinforcement net
Between two adjacent cover board cross direction profiles muscle, specific link position corresponds to fill benzene plate center between prefabricated post and precast shear wall.
The prefabricated concrete structure wall-column all steel key connection structure assembling method, includes the following steps:
(1) lifting of prefabricated post and precast shear wall first lifts two prefabricated posts and a precast shear wall in place, in advance
Shear wall processed is located between two prefabricated posts;
(2) the corresponding insertion work between prefabricated post-wall built-in fitting and prefabricated post in precast shear wall-wall built-in fitting in prefabricated post
Font column-wall connecting key makes prefabricated post-wall built-in fitting and I-shaped in prefabricated post in prefabricated post-wall built-in fitting and precast shear wall
Type column-wall connecting key is in close contact, and is then welded, and the connection of connecting key between prefabricated post and precast shear wall is completed;
(3) between prefabricated post-is inserted into prefabricated post-wall in gap between wall built-in fitting and prefabricated post and precast shear wall with the shape
Filling benzene plate, then correspondence installs the I-shaped column in I-shaped column-wall connecting key side-wall connecting key filling benzene with the shape
Plate completes the connection of vacant position benzene plate in prefabricated post and precast shear wall connecting portion;
(4) connecting portion between prefabricated post and shear wall is installed outside prefabricated post and precast shear wall connecting portion corresponding position
Connecting portion balustrade deching between prefabricated post and precast shear wall is first placed on connecting portion and corresponds to vacant locations by balustrade deching,
Then sequentially passed through between former and later two corresponding prefabricated posts and precast shear wall on connecting portion balustrade deching with interspersed reinforcing bar
Billet, then the both ends of interspersed reinforcing bar are secured with nuts, complete the fixed installation of connecting portion balustrade deching between column and shear wall;
(5) the billet recess between the column and shear wall after all completions are fixedly mounted on connecting portion balustrade deching
Gypsum is smeared, keeps recess smooth, completes the connection between prefabricated post and precast shear wall.
The assembling method of the prefabricated concrete structure wall-column all steel key connection structure in step (4), interts steel
Distance adds two sides between the length of muscle should be the billet outer surface between the shear wall of correspondence on connecting portion balustrade deching
The thickness of corresponding fixture nut.
The prefabricated concrete structure wall-column all steel key connection structure assembling method, the manufacturing process of prefabricated post
Are as follows:
(1) vertical reinforcement sleeve is inserted into the lower end of longitudinal stress muscle in prefabricated post, then binds prefabricated column tie-bar, complete
Steel bar arrangement in prefabricated post;
(2) upper end of longitudinal stress muscle should reserve a part in prefabricated post, and it is perpendicular that the length of reserved part should be prefabricated post
To the half of reinforced bar sleeve height;
(3) prefabricated post-wall built-in fitting is passed through into hole fixation with steel wire on prefabricated column tie-bar, prefabricated post-wall built-in fitting
It is uniformly distributed along prefabricated post short transverse;
(4) the reinforcing bar outer support template in prefabricated post, casting concrete, concrete should pour in template to prefabricated
Column-wall built-in fitting outer surface, form removal after concrete setting complete the production of prefabricated post.
The prefabricated concrete structure wall-column all steel key connection structure assembling method, the production of precast shear wall
Process are as follows:
(1) shear wall longitudinal stress muscle and shear wall confined boundary member stirrup are bound, confined boundary member reinforcing bar is formed,
Then remaining shear wall longitudinal stress muscle and the lateral stressed muscle 9 of shear wall are bound, finally binding shearing wall lacing wire, forms prefabricated cut
The reinforcing bar of power within the walls;
(2) prefabricated post-wall built-in fitting is that shear wall side is fixed on by metal binding wire, and metal binding wire passes through prefabricated
Reserved circular hole above column-wall built-in fitting is bound in precast shear wall on confined boundary member stirrup, and wall is laterally homogeneous
It is distributed in two side areas;
(3) formwork supporting plate on the outside of framework of steel reinforcement, casting concrete, concrete should be poured in template to column wall built-in fitting
Outer surface;Form removal after concrete setting completes the production of precast shear wall.
The invention has the advantages and beneficial effects that:
1. master operation of the invention does not include that processes, whole processes such as scene grouting or concreting are all prefabricated structures
The in-site installation of part connects, and does not need wet construction, greatly shortens the time required for building-site is constructed, can greatly improve
Speed of application, save the cost.
2. prefabricated post of the present invention and precast shear wall, by the way that built-in fitting is arranged in precast shear wall and prefabricated post coupling part
With I-steel shear key, the transmitting of wall-intercolumniation coupling part shearing is completed, the globality of structure, anti-seismic performance are further enhanced
More preferably.
3. the high part of present invention production required precision, including prefabricated post, precast shear wall and prefabricated post-wall are pre-buried
The production of part, I-steel shear key, is completed in factory.The difficulty of on-site consolidation is of less demanding, can save construction personnel
Learning cost, increase substantially construction efficiency.
4. the power transmission between component of the present invention relies on weld seam force transferring structure more than single by the occlusion and welding of built-in fitting
Add reliable.
5. the present invention uses a large amount of assembling work, greatly reduces than original cast-in-place operation, meet energy conservation and environmental protection and economy
The advantages of prefabricated concrete structures such as the Green Architectural Development requirement of safety.
Detailed description of the invention
Fig. 1 is the three-dimensional figure of vertical reinforcement sleeve.
Fig. 2 is prefabricated post-wall built-in fitting three-dimensional figure.
Fig. 3 is I-shaped column-wall connecting key three-dimensional figure.
Fig. 4 is the steel bar arrangement three-dimensional figure in prefabricated post.
Fig. 5 is that the three-dimensional figure finished is welded in reinforcing bar binding in prefabricated post-wall built-in fitting and prefabricated post.
Fig. 6 is the three-dimensional figure with prefabricated post-wall built-in fitting prefabricated post.
Fig. 7 is the steel bar arrangement three-dimensional figure in precast shear wall.
Fig. 8 is that the three-dimensional figure finished is welded in reinforcing bar binding in prefabricated post-wall built-in fitting and precast shear wall.
Fig. 9 is the three-dimensional figure with prefabricated post-wall built-in fitting precast shear wall.
Figure 10 is cutting with prefabricated post-wall built-in fitting prefabricated post with prefabricated post-the prefabricated of wall built-in fitting after rigging out
Power wall constitutional diagram.
Figure 11 is that prefabricated post-wall for being installed on I-shaped column-wall connecting key between prefabricated post and precast shear wall is pre-buried
Installation process three-dimensional figure between part.
Figure 12 is three-dimensional figure when I-shaped column-wall connecting key is completed between prefabricated post and precast shear wall.
Figure 13 is filling benzene plate in gap between prefabricated post and precast shear wall.
Figure 14 is I-steel side-facing depressions gap filling benzene plate.
Figure 15 is the process three-dimensional figure that Figure 13 is installed on Figure 12.
Figure 16 is the process three-dimensional figure that Figure 14 is installed on Figure 12.
Figure 17 is the three-dimensional figure filling benzene plate between prefabricated post and precast shear wall and installing.
Figure 18 is the steel bar arrangement three-dimensional figure of cover board.
Figure 19 is the three-dimensional figure that cover board completes.
Figure 20 is the three-dimensional figure of cover board installation process.
Figure 21 is the three-dimensional figure that cover board is installed.
Figure 22 is that the three-dimensional figure after gypsum completes is smeared at cover plate bolt hole.
In figure, 1 vertical reinforcement sleeve;2 ribbed steels;3 circular holes;4 I-shaped columns-wall connecting key;5 reinforcing bar future insufficiencies;6
Longitudinal stress muscle in prefabricated post;7 prefabricated column tie-bars;8 shear wall longitudinal stress muscle;The lateral stressed muscle of 9 shear walls;10 shear walls are about
Beam edge member stirrup;11 shearing wall lacing wires;Benzene plate is used in filling between 12 prefabricated posts-wall;13 I-shaped columns-wall connecting key filling is used
Benzene plate;14 billets;15 cover board genesis analysis muscle;16 cover board cross direction profiles muscle;17 cover boards;18 prefabricated posts;19 precast shear walls;
20 floors;21 vertical plates;22 level boards;23 convex ribs.
Specific embodiment
As shown in Fig. 1-Figure 22, prefabricated concrete structure wall of the present invention-column all steel is keyed structure, mainly includes prefabricated
Column-wall built-in fitting, prefabricated post, precast shear wall, prefabricated connecting portion cover board, and for being connected between above-mentioned component and filling
I-shaped column-wall connecting key and benzene plate etc., prefabricated post-wall built-in fitting between prefabricated post and precast shear wall is corresponding, relatively
Pass through I-shaped column-wall connection key connection between the prefabricated post of setting-wall built-in fitting.
(1) as shown in Fig. 2, prefabricated post-wall built-in fitting specific structure and manufacturing process are as follows:
(1) prefabricated post-wall built-in fitting is made of ribbed steel 2 and circular hole 3, and the side of ribbed steel 2 is arranged in parallel up and down
Cross section is the floor 20 of L-type, circular hole 3 is arranged on monolith ribbed steel, floor 20 forms with the side of ribbed steel 2 recessed respectively
Slot, upper and lower two grooves are opposite.
As shown in Fig. 3, Figure 11 and Figure 12, I-shaped column-wall connecting key 4 is by vertical plate 21, level board 22,23 groups of convex ribs
At the level board setting up and down 22 of vertical plate 21 is in I-shaped structure, and superposed 22 top both ends of level board are wholely set
Parallel convex ribs 23 are wholely set parallel convex ribs, I-shaped column-wall connecting key 4 positioned at the level board bottom both ends of lower part
Two sides are connect with prefabricated post-wall built-in fitting respectively, I-shaped column-wall connecting key 4 by upper and lower two convex ribs respectively with prefabricated post-
Two groove inserting cooperations up and down of wall built-in fitting.In addition, the two sides upper and lower side of vertical plate 21 opens up reinforcing bar future insufficiency respectively
5, after I-shaped column-wall connecting key 4 assembles, reinforcing bar can be worn into reinforcing bar future insufficiency 5.
(2) number of circular hole 3 is 4 groups 8, parallel arrangement.The diameter of circular hole 3 be 20mm, with guarantee shear wall laterally by
Power muscle 9 can pass through circular hole 3.
(3) width of ribbed steel 2 needs the width than prefabricated post 18 (Fig. 6) and precast shear wall 19 (Fig. 9) 20mm small,
The requirement for preventing junction steel plate from corroding.
(4) shearing that the shear wall and intercolumniation that I-shaped column-wall connecting key 4 (Fig. 3) quantity is connected according to it transmit
Calculate determination.
(2) as shown in Fig. 1, fig. 4 to fig. 6, specific structure and the manufacturing process difference of prefabricated post are as follows:
(1) prefabricated post 18 is by longitudinal stress muscle 6, prefabricated column tie-bar 7, vertical reinforcement sleeve 1 and ribbed steel 2 in prefabricated post
Casting concrete forms, and longitudinal stress muscle 6 forms frame by the connection of prefabricated column tie-bar 7 in four prefabricated posts of the arrangement that is square
Structure, the bottom of longitudinal stress muscle 6 is set with vertical reinforcement sleeve 1 in each prefabricated post, and the one side of the frame structure is from upper
Prefabricated post-wall built-in fitting is uniformly arranged under and, concreting is in frame structure inner side and outer side.
(2) manufacturing process of prefabricated post 18 are as follows: firstly, vertical reinforcement is inserted into the lower end of longitudinal stress muscle 6 in prefabricated post
Then sleeve 1 binds prefabricated column tie-bar 7, complete the steel bar arrangement in prefabricated post.
The upper end of longitudinal stress muscle 6 should reserve a part in prefabricated post, and it is vertical that the length of reserved part should be prefabricated post
The half of 1 height of reinforced bar sleeve.
By prefabricated post-wall built-in fitting through hole fixation with steel wire on prefabricated column tie-bar 7, prefabricated post-wall built-in fitting
Number is determining according to the shear force calculation for needing to transmit between precast shear wall 19 and prefabricated post 18, and along 18 short transverse of prefabricated post
It is uniformly distributed.
Reinforcing bar outer support template in prefabricated post 18, casting concrete, concrete should pour in template to prefabricated post-
The outer surface of wall built-in fitting, form removal after concrete setting complete the production of prefabricated post.
(3) as shown in Figure 7 to 9, the specific structure of precast shear wall 19 and manufacturing process difference are as follows:
(1) precast shear wall 19 mainly include framework of steel reinforcement, prefabricated post-wall built-in fitting and concrete, the two of framework of steel reinforcement
Prefabricated post-wall built-in fitting is respectively set in side, and concreting is in framework of steel reinforcement inner side and outer side;Framework of steel reinforcement is that shear wall is longitudinal
The lateral stressed muscle 9 of principal rod 8, shear wall, shear wall confined boundary member stirrup 10 and shearing wall lacing wire 11 form, two rows shearing
Wall longitudinal stress muscle 8 is oppositely arranged in parallel, and is connected between every row's shear wall longitudinal stress muscle 8 by the lateral stressed muscle 9 of shear wall,
It is connected between the shear wall longitudinal stress muscle 8 being oppositely arranged by shearing wall lacing wire 11, the side of two rows of shear wall longitudinal stress muscle 8
Shear wall confined boundary member stirrup 10 is arranged in parallel in outside up and down between edge.
(2) manufacturing process of precast shear wall are as follows: binding shear wall longitudinal stress muscle 8 and shear wall constrained edge structure first
Part stirrup 10 forms confined boundary member reinforcing bar, then binds remaining shear wall longitudinal stress muscle and the lateral stressed muscle of shear wall
9, finally binding shearing wall lacing wire 11, forms the reinforcing bar in precast shear wall.
Prefabricated post-wall built-in fitting is that shear wall side is fixed on by metal binding wire, and metal binding wire passes through prefabricated post-wall
Reserved circular hole above built-in fitting is bound in precast shear wall on confined boundary member stirrup, wall it is laterally uniform
Two side areas.
The formwork supporting plate on the outside of framework of steel reinforcement, casting concrete, concrete should be poured in template to outside column wall built-in fitting
Side surface.Form removal after concrete setting completes the production of precast shear wall.
(4) as shown in Figure 18 to Figure 19, the specific structure of connecting portion balustrade deching and production between prefabricated post and shear wall
Process is as follows:
(1) cover board 17 is set on the outside of connecting portion between prefabricated post 18 and precast shear wall 19, and cover board 17 includes that cover board is lateral
Distributing reinforcement 16, cover board genesis analysis muscle 15 and billet 14, the parallel opposite cover board cross direction profiles muscle 16 of a row are parallel with a row
Opposite cover board genesis analysis muscle 15 forms steel reinforcement net.And billet 14 is then welded to certain two phase in steel reinforcement net
Between adjacent cover board cross direction profiles muscle 16, specific link position corresponds to fill benzene plate center between prefabricated post 18 and precast shear wall 19.
(2) between prefabricated post 18 and precast shear wall 19 connecting portion balustrade deching manufacturing process are as follows: first binding cover board
Cross direction profiles muscle 16, cover board genesis analysis muscle 15 form steel reinforcement net, billet 14 are then welded, on the outside of steel reinforcement net
Formwork supporting plate, casting concrete, concrete should be poured in template to steel reinforcement net outer surface.Mould is removed after concrete setting
Plate completes the production of connecting portion balustrade deching between prefabricated post and shear wall.
The prefabricated completion in factory of above-mentioned prefabricated components, then transports to construction site and assembles, and specific hoisting process is as follows:
(1) as shown in Figure 10, the lifting of prefabricated post and precast shear wall first prefabricated cuts two prefabricated posts 18 with one
Power wall 19 lifts in place, and precast shear wall 19 is located between two prefabricated posts 18.
(2) as shown in Figure 11 to Figure 12, prefabricated post-wall built-in fitting and prefabricated post-in precast shear wall in prefabricated post 18
It is corresponding between wall built-in fitting to be inserted into I-shaped column-wall connecting key 4, make in prefabricated post in prefabricated post-wall built-in fitting and precast shear wall
Prefabricated post-wall built-in fitting and I-shaped column-wall connecting key 4 are in close contact, and are then welded, and are completed prefabricated post 18 and are cut with prefabricated
The connection of connecting key between power wall 19.
(3) empty between wall built-in fitting and prefabricated post 18 and precast shear wall 19 in prefabricated post-as shown in Figure 13 to Figure 17
Filling benzene plate 12 between prefabricated post-wall is inserted into gap with the shape, then correspondence installs I-shaped column -4 side of wall connecting key with the shape
I-shaped column-wall connecting key filling benzene plate 13, completes vacant position benzene in prefabricated post 18 and 19 connecting portion of precast shear wall
The connection of plate.
(4) it installs outside 19 connecting portion corresponding position of prefabricated post 18 and precast shear wall and connects between prefabricated post and shear wall
Connecting portion balustrade deching between prefabricated post 18 and precast shear wall 19 is first placed on connecting portion pair by socket part position balustrade deching 17
Vacant locations are answered, then sequentially pass through interconnecting piece between former and later two corresponding prefabricated posts 18 and precast shear wall 19 with interspersed reinforcing bar
Billet 14 on the balustrade deching of position, then the both ends of interspersed reinforcing bar are secured with nuts, it completes between column and shear wall outside connecting portion
The fixed installation of side cover plate 17.Wherein, the length for interting reinforcing bar should be connecting portion balustrade deching between the shear wall of correspondence
On 14 outer surface of billet between distance add two sides to correspond to the thickness of fixture nut.
(5) as shown in Figure 18 to Figure 22, the connecting portion outboard cover between the column and shear wall after all completions are fixedly mounted
14 recess of billet on plate 17 smears gypsum, keeps recess smooth, completes the connection between prefabricated post and precast shear wall.
It includes the processes such as scene grouting or concreting, whole works that result of implementation, which shows master operation of the invention not,
Sequence is all the in-site installation connection of prefabricated components, does not need wet construction, greatly shortens time required for building-site is constructed, energy
It is enough greatly to improve speed of application, save the cost.Prefabricated post and precast shear wall, by being connected in precast shear wall with prefabricated post
Part setting prefabricated post-wall built-in fitting and I-shaped column-wall connecting key complete the transmitting of wall-intercolumniation coupling part shearing, into one
The globality of enhancing structure is walked, anti-seismic performance is more preferable.Make the high part of required precision, including prefabricated post, precast shear wall with
And the production of prefabricated post-wall built-in fitting, I-steel shear key, completed in factory.The difficulty of on-site consolidation is of less demanding, energy
The learning cost for enough saving construction personnel, increases substantially construction efficiency.Power transmission between component of the present invention, by stinging for built-in fitting
It closes and welds, it is more relatively reliable by weld seam force transferring structure than single.Using a large amount of assembling work, significantly than original cast-in-place operation
Reduce, the advantages of meeting the prefabricated concrete structures such as the Green Architectural Development requirement of energy conservation and environmental protection and economic security, have compared with
Good future in engineering applications.
Claims (8)
1. a kind of prefabricated concrete structure wall-column all steel is keyed structure, which is characterized in that including prefabricated post-wall built-in fitting,
Prefabricated post, precast shear wall, precast shear wall is located between two prefabricated posts, prefabricated between prefabricated post and precast shear wall
Column-wall built-in fitting is corresponding, is keyed between the prefabricated post being oppositely arranged-wall built-in fitting by I-shaped column-wall connection,
In:
(1) prefabricated post-wall built-in fitting is made of ribbed steel and circular hole, and the side of ribbed steel is arranged in parallel cross section up and down and is
The floor of L-type, circular hole, circular hole parallel arrangement are arranged on monolith ribbed steel, and the lateral stressed muscle of shear wall passes through circular hole, floor point
Groove is not formed with the side of ribbed steel, upper and lower two grooves are opposite;
(2) prefabricated post is by longitudinal stress muscle, prefabricated column tie-bar, vertical reinforcement sleeve and ribbed steel casting concrete in prefabricated post
It forms, longitudinal stress muscle connects to form frame structure by prefabricated column tie-bar in four prefabricated posts of the arrangement that is square, each pre-
The bottom of longitudinal stress muscle is set with vertical reinforcement sleeve in column processed, and the one side of the frame structure is uniformly arranged pre- from top to bottom
Column processed-wall built-in fitting, concreting is in frame structure inner side and outer side;
(3) precast shear wall includes that framework of steel reinforcement, prefabricated post-wall built-in fitting and concrete, the two sides of framework of steel reinforcement are respectively set
Prefabricated post-wall built-in fitting, concreting is in framework of steel reinforcement inner side and outer side;Framework of steel reinforcement is shear wall longitudinal stress muscle, cuts
The lateral stressed muscle of power wall, shear wall confined boundary member stirrup and shearing wall lacing wire composition, two rows of shear wall longitudinal stress muscle are flat
Row is oppositely arranged, by the lateral stressed muscle connection of shear wall between every row's shear wall longitudinal stress muscle, the shear wall being oppositely arranged
It is connected between longitudinal stress muscle by shearing wall lacing wire, outside is set in parallel up and down between the edge of two rows of shear wall longitudinal stress muscle
Set shear wall confined boundary member stirrup.
2. prefabricated concrete structure wall described in accordance with the claim 1-column all steel is keyed structure, which is characterized in that I-shaped
Type column-wall connecting key 4 is made of vertical plate, level board, convex ribs, and the level board setting up and down of vertical plate is in I-shaped structure, position
Both ends are wholely set parallel convex ribs at the top of the level board on top, and the level board bottom both ends positioned at lower part are wholely set in parallel
Convex ribs, I-shaped column-wall connecting key 4 two sides connect with prefabricated post-wall built-in fitting respectively, and I-shaped column-wall connecting key is logical
Crossing two convex ribs up and down, two groove insertings cooperate up and down with prefabricated post-wall built-in fitting respectively.
3. prefabricated concrete structure wall described in accordance with the claim 1-column all steel is keyed structure, which is characterized in that prefabricated
Cover board is set on the outside of connecting portion between column and precast shear wall, cover board include cover board cross direction profiles muscle, cover board genesis analysis muscle and
Billet, the parallel opposite cover board genesis analysis muscle of a row parallel opposite cover board cross direction profiles muscle and a row form framework of steel reinforcement
Net.
4. prefabricated concrete structure wall described in accordance with the claim 3-column all steel is keyed structure, which is characterized in that steel pad
Plate is welded in steel reinforcement net between certain two adjacent cover board cross direction profiles muscle, specific link position correspond to prefabricated post with it is prefabricated
Benzene plate center is filled between shear wall.
5. prefabricated concrete structure wall described in a kind of one of Claims 1-4-column all steel key connection structure assembly side
Method, which comprises the steps of:
(1) lifting of prefabricated post and precast shear wall first lifts two prefabricated posts and a precast shear wall in place, prefabricated to cut
Power wall is located between two prefabricated posts;
(2) corresponding insertion is I-shaped between prefabricated post-wall built-in fitting and prefabricated post in precast shear wall-wall built-in fitting in prefabricated post
Column-wall connecting key makes prefabricated post-wall built-in fitting and I-shaped column-in prefabricated post in prefabricated post-wall built-in fitting and precast shear wall
Wall connecting key is in close contact, and is then welded, and the connection of connecting key between prefabricated post and precast shear wall is completed;
(3) it is filled between prefabricated post-is inserted into prefabricated post-wall in gap between wall built-in fitting and prefabricated post and precast shear wall with the shape
With benzene plate, then correspondence installs the I-shaped column in I-shaped column-wall connecting key side-wall connecting key filling benzene plate with the shape, complete
At the connection of vacant position benzene plate in prefabricated post and precast shear wall connecting portion;
(4) it is installed outside prefabricated post and precast shear wall connecting portion corresponding position between prefabricated post and shear wall on the outside of connecting portion
Connecting portion balustrade deching between prefabricated post and precast shear wall is first placed on connecting portion and corresponds to vacant locations, then by cover board
The steel pad between former and later two corresponding prefabricated posts and precast shear wall on connecting portion balustrade deching is sequentially passed through with interspersed reinforcing bar
Plate, then the both ends of interspersed reinforcing bar are secured with nuts, complete the fixed installation of connecting portion balustrade deching between column and shear wall;
(5) the billet recess between the column and shear wall after all completions are fixedly mounted on connecting portion balustrade deching smears stone
Cream keeps recess smooth, completes the connection between prefabricated post and precast shear wall.
6. prefabricated concrete structure wall-column all steel key connection structure assembling method according to claim 5, feature
It is, in step (4), the length of interspersed reinforcing bar should be the billet between the shear wall of correspondence on connecting portion balustrade deching
Distance adds two sides to correspond to the thickness of fixture nut between outer surface.
7. prefabricated concrete structure wall-column all steel key connection structure assembling method according to claim 5, feature
It is, the manufacturing process of prefabricated post are as follows:
(1) vertical reinforcement sleeve is inserted into the lower end of longitudinal stress muscle in prefabricated post, then binds prefabricated column tie-bar, complete prefabricated
Steel bar arrangement in column;
(2) upper end of longitudinal stress muscle should reserve a part in prefabricated post, and the length of reserved part should be prefabricated post vertical steel
The half of muscle sleeve height;
(3) prefabricated post-wall built-in fitting is passed through into hole fixation with steel wire on prefabricated column tie-bar, prefabricated post-wall built-in fitting is along pre-
Column short transverse processed is uniformly distributed;
(4) the reinforcing bar outer support template in prefabricated post, casting concrete, concrete should be poured in template to prefabricated post-wall
The outer surface of built-in fitting, form removal after concrete setting complete the production of prefabricated post.
8. prefabricated concrete structure wall-column all steel key connection structure assembling method according to claim 5, feature
It is, the manufacturing process of precast shear wall are as follows:
(1) shear wall longitudinal stress muscle and shear wall confined boundary member stirrup are bound, forms confined boundary member reinforcing bar, then
Remaining shear wall longitudinal stress muscle and the lateral stressed muscle 9 of shear wall are bound, finally binding shearing wall lacing wire, forms precast shear wall
Interior reinforcing bar;
(2) prefabricated post-wall built-in fitting is that shear wall side is fixed on by metal binding wire, and metal binding wire passes through prefabricated post-wall
Reserved circular hole above built-in fitting is bound in precast shear wall on confined boundary member stirrup, wall it is laterally uniform
Two side areas;
(3) formwork supporting plate on the outside of framework of steel reinforcement, casting concrete, concrete should be poured in template to the outside of column wall built-in fitting
Surface;Form removal after concrete setting completes the production of precast shear wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811329141.2A CN109281422A (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column all steel key connection structure and assembling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811329141.2A CN109281422A (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column all steel key connection structure and assembling method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109281422A true CN109281422A (en) | 2019-01-29 |
Family
ID=65175367
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811329141.2A Pending CN109281422A (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column all steel key connection structure and assembling method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109281422A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335467A (en) * | 2020-03-20 | 2020-06-26 | 哈尔滨工业大学 | Self-resetting node connecting structure and assembling method for beam column of assembled concrete frame |
CN111335466A (en) * | 2020-03-20 | 2020-06-26 | 哈尔滨工业大学 | Fabricated concrete self-resetting beam-column joint connecting structure and assembling method |
CN112695926A (en) * | 2021-01-07 | 2021-04-23 | 中铁建设集团有限公司 | Connect precast concrete composite window wall based on PBL |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0762731A (en) * | 1993-08-27 | 1995-03-07 | Okumura Corp | Joining method of pillar and beam |
CN104727467A (en) * | 2015-03-23 | 2015-06-24 | 河北联合大学 | Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method |
CN207260378U (en) * | 2017-09-30 | 2018-04-20 | 沈阳建筑大学 | A kind of assembled frame-shear structure curved scissors type combines keyway connection structure |
CN107989231A (en) * | 2018-01-12 | 2018-05-04 | 新疆大学 | A kind of Prefabricated concrete-filled steel tube frame-shear wall and its construction method |
CN108086488A (en) * | 2017-12-01 | 2018-05-29 | 沈阳建筑大学 | Assembled frame-shear structure wall splitlevel connection structure and assembling method |
CN209227836U (en) * | 2018-11-09 | 2019-08-09 | 沈阳建筑大学 | Prefabricated concrete structure wall-column all steel is keyed structure |
-
2018
- 2018-11-09 CN CN201811329141.2A patent/CN109281422A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0762731A (en) * | 1993-08-27 | 1995-03-07 | Okumura Corp | Joining method of pillar and beam |
CN104727467A (en) * | 2015-03-23 | 2015-06-24 | 河北联合大学 | Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method |
CN207260378U (en) * | 2017-09-30 | 2018-04-20 | 沈阳建筑大学 | A kind of assembled frame-shear structure curved scissors type combines keyway connection structure |
CN108086488A (en) * | 2017-12-01 | 2018-05-29 | 沈阳建筑大学 | Assembled frame-shear structure wall splitlevel connection structure and assembling method |
CN107989231A (en) * | 2018-01-12 | 2018-05-04 | 新疆大学 | A kind of Prefabricated concrete-filled steel tube frame-shear wall and its construction method |
CN209227836U (en) * | 2018-11-09 | 2019-08-09 | 沈阳建筑大学 | Prefabricated concrete structure wall-column all steel is keyed structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111335467A (en) * | 2020-03-20 | 2020-06-26 | 哈尔滨工业大学 | Self-resetting node connecting structure and assembling method for beam column of assembled concrete frame |
CN111335466A (en) * | 2020-03-20 | 2020-06-26 | 哈尔滨工业大学 | Fabricated concrete self-resetting beam-column joint connecting structure and assembling method |
CN112695926A (en) * | 2021-01-07 | 2021-04-23 | 中铁建设集团有限公司 | Connect precast concrete composite window wall based on PBL |
CN112695926B (en) * | 2021-01-07 | 2024-04-30 | 中铁建设集团有限公司 | PBL-based connection precast concrete composite window wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108951870B (en) | Construction method of low-rise fully-assembled concrete shear wall structure system | |
CN107245934A (en) | A kind of assembled steel profiled sheet concrete combined board small box girder | |
CN104264786A (en) | Steel bar connection mode of precast concrete components and application thereof | |
CN105317137A (en) | Prefabricated wall, prefabricated wallboard, construction method of prefabricated wall and production method of prefabricated wallboard | |
CN106639093A (en) | Close splicing seam-type laminated slab | |
CN209227836U (en) | Prefabricated concrete structure wall-column all steel is keyed structure | |
CN206707124U (en) | Prefabricated assembling type reinforced concrete component with joint of steel structure | |
CN204059601U (en) | A kind of steel bar connecting structure of prefabricated concrete element | |
CN108086488B (en) | Assembled frame shear structure wall staggered connection structure and assembling method | |
KR100731593B1 (en) | A pre-fabricating forms for concrete-structure and the construction method thereof | |
CN207660136U (en) | A kind of assembly concrete frame-shear wall keyway connection structure | |
CN109281422A (en) | Prefabricated concrete structure wall-column all steel key connection structure and assembling method | |
CN106481023A (en) | Assembled steel reinforced concrete bondbeam structure and its implementation | |
CN108104284B (en) | Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method | |
CN108301545A (en) | A kind of big module overlapping contignation of the assembled with space truss temporary support | |
CN113653235A (en) | Laminated slab, connecting structure of laminated slab and combination beam and construction method | |
CN110748077A (en) | Prestressed truss wallboard, wall body manufactured by using wallboard and manufacturing method of wall body | |
CN110761443A (en) | Assembled concrete structure wall-column concrete filled steel tube key connection structure and assembling method thereof | |
CN107514083B (en) | Side-hung reinforced bar concrete composite floor slab structure with shear key and connecting method | |
CN114319977B (en) | Steel pipe concrete row column type connection precast shear wall structure and construction method | |
CN111502080A (en) | Steel-concrete composite structure frame-cast-in-place concrete shear wall structure system | |
CN108104310B (en) | Assembled frame shear structure column staggered connection structure and assembling method | |
CN110644662A (en) | Prefabricated flat slab composite slab based on stress and splitting method thereof | |
CN111648411B (en) | Down-turned post-pouring belt support changing structure, construction method and post-pouring belt construction method | |
CN212453065U (en) | Assembled building frame structure member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |