CN109267488B - Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load - Google Patents

Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load Download PDF

Info

Publication number
CN109267488B
CN109267488B CN201811201483.6A CN201811201483A CN109267488B CN 109267488 B CN109267488 B CN 109267488B CN 201811201483 A CN201811201483 A CN 201811201483A CN 109267488 B CN109267488 B CN 109267488B
Authority
CN
China
Prior art keywords
fabrication machine
bridge fabrication
section
sections
measuring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811201483.6A
Other languages
Chinese (zh)
Other versions
CN109267488A (en
Inventor
杨川
赵兵
石华锋
黄传圣
张树发
黄飞
占文进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201811201483.6A priority Critical patent/CN109267488B/en
Publication of CN109267488A publication Critical patent/CN109267488A/en
Application granted granted Critical
Publication of CN109267488B publication Critical patent/CN109267488B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M5/00Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings
    • G01M5/0008Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings of bridges
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/06Power analysis or power optimisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Bridges Or Land Bridges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a method for preloading a segment girder bridge fabrication machine by utilizing dynamic concentrated loads, which comprises the steps of firstly calculating the weight of the dynamic concentrated loads, and selecting a preloaded girder segment for providing the concentrated loads; assembling the movable support bridge fabrication machine, and moving the movable support bridge fabrication machine forwards to a first hole to-be-erected hole position; then, sequentially suspending all sections of the first-hole box girder on a bridge fabrication machine; hoisting the pre-pressed beam section to a bridge fabrication machine, dividing the beam length into n sections, monitoring and measuring the deflection and the stress measuring point of the key section after the pre-pressed beam section moves for one section and the deformation is stable, and analyzing the rigidity and the strength of the structure at the moment; and finally, all sections of the pre-pressed beam section and the first hole box beam are unloaded, after the deformation is stable, the deflection of each control section and the stress measuring point of the key section are measured, and the data are analyzed. The invention not only can greatly improve the construction efficiency of loading and unloading in the pre-pressing process of the bridge fabrication machine, but also greatly reduces the construction investment, and can also reduce various construction risks in the prior pre-pressing process.

Description

Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load
Technical Field
The invention relates to the technical field of railway modification, in particular to a method for prepressing a segment girder bridge fabrication machine by utilizing dynamic concentrated load.
Background
With the requirements of the national security supervision department and the railway industry on the bearing capacity, the design rigidity and the stability of large equipment and the higher and higher safe operation conditions, more and more mobile support bridge fabrication machines appear on the current construction site, but the mobile support bridge fabrication machines cannot be divided into special equipment, and no national function is available for detection. A convenient, quick and low-cost detection method must be found to detect the existing bridge fabrication machine to ensure the safety and reliability of construction.
The accurate measurement of the elastic deformation and the inelastic deformation of the movable support directly controls the assembly precision of the beam body, and the assembly precision must be determined through precompression measurement calculation.
Disclosure of Invention
In view of the above problems, the present invention provides a method for preloading a segmental girder bridge fabrication machine by using dynamic concentrated load, which can realize rapid, precise and synchronous load application and unloading, equivalently eliminate the inelastic deformation of a bracket, and obtain the elastic deformation of the bracket. The technical scheme is as follows:
a method for preloading a segment girder bridge fabrication machine by utilizing dynamic concentrated load comprises the following steps:
step 1: calculating the weight of the dynamic concentrated load, and selecting a pre-pressed beam section for providing the concentrated load;
step 2: assembling the movable support bridge fabrication machine, and moving the movable support bridge fabrication machine forwards to a first hole to-be-erected hole position;
and step 3: sequentially suspending each section of the first-hole box girder on a bridge fabrication machine until all sections are suspended;
and 4, step 4: evenly dividing n measuring sections on the section beam bridge fabrication machine;
and 5: hoisting the pre-pressed beam section to a bridge fabrication machine, moving to the position with the length of 1/n beam, monitoring and measuring the span-middle deflection value, the section stress measuring point at the joint of the beam end and the n-1 measuring sections after the deformation is stable, and analyzing the rigidity and the strength of the structure at the moment;
step 6: sequentially moving the pre-pressed beam section to the length of 2/n, … … (n-1)/n beams, monitoring and measuring the span center deflection value, the beam end and the section stress measuring point at the joint of n-1 measuring sections after each row reaches one position to be deformed stably, and analyzing the rigidity and the strength of the structure at the moment;
and 7: and (3) completely unloading all sections of the pre-pressed beam section and the first-hole box beam, monitoring and measuring a cross-center deflection value, a beam end and a section stress measuring point at the joint of the n-1 measuring sections after the pre-pressed beam section and the first-hole box beam are deformed stably, and analyzing the rigidity and the strength of the structure at the moment.
Further, the mobile stent bridging machine adopts a TPZ80/2500 model.
Furthermore, the first-hole box girder is 13 sections.
Further, the measuring section is 4 sections.
The invention has the beneficial effects that: the invention adopts the bridge fabrication machine to hoist a beam section to move on the bridge fabrication machine to provide concentrated load instead of uniformly distributed load, can eliminate the inelastic deformation of the bracket and achieve the purpose of elastic deformation of the bracket, not only can greatly improve the construction efficiency of loading and unloading in the pre-pressing process of the bridge fabrication machine, but also greatly reduces the construction investment and can also reduce various construction risks in the pre-pressing process in the past.
Drawings
Fig. 1 is a schematic diagram of a bridge fabrication machine.
Fig. 2 is a schematic view of a beam section completely suspended on a bridge fabrication machine.
Fig. 3 is a schematic view of the pre-stressed beam section moving to 1/4 beam lengths.
Fig. 4 is a schematic view of the pre-stressed beam section moving to 1/2 beam lengths.
Detailed Description
The invention is described in further detail below with reference to the figures and specific embodiments. The invention is suitable for the prepressing operation of the bridge fabrication machine, wherein the movable support bridge fabrication machine is positioned above the concrete main beam, and the beam conveying trolley can carry the beam section to freely walk on the movable support. The construction steps are as follows:
the first step is as follows: calculating the weight of the dynamic concentrated load, and selecting a beam section (hereinafter referred to as a pre-pressed beam section) providing the concentrated load.
The second step is that: as shown in figure 1, the TPZ80/2500 type mobile stent bridging machine is assembled and moved forward to the position of the first hole to be erected.
The third step: and successively suspending the 13 sections of the first box girder on the bridge fabrication machine until all the sections are suspended. As shown in fig. 2.
The fourth step: and hoisting the pre-pressed beam section to the bridge fabrication machine and moving to the L/4 position, as shown in figure 3. After the deformation is stable, the deflection and stress measuring points of key sections (such as beam ends and sections at 1/4, 1/2 and 3/4) are monitored and measured, and the rigidity and the strength of the structure at the moment are analyzed.
The fifth step: the pre-pressed beam section moves to the L/2 position, as shown in figure 4. And after the deformation is stable, monitoring and measuring the deflection and the stress measuring point of the key section and analyzing the rigidity and the strength of the structure at the moment.
And a sixth step: and (3) moving the pre-pressed beam section to a 3L/4 position, monitoring and measuring deflection and a key section stress measuring point after the deformation is stable, and analyzing the rigidity and the strength of the structure at the moment.
The seventh step: and (3) completely unloading the 13 sections of the pre-pressed beam section and the first hole beam, measuring the deflection of each control section and the stress measuring point of the key section after the deformation is stable, and analyzing the data. The control cross-sections selected in this example are 1/4, 1/2, 3/4 beam lengths.
Finally, the measured values of the obtained measurement data, the analysis results and the like are compared with the theoretical values of modeling calculation, and the safety of each stress rod piece of the bridge fabrication machine is analyzed.
Analyzing the working principle: and pre-pressing the movable support by not less than 1.1 times of the maximum construction load before assembling and erecting the beam body for the first time according to the standard. The load of the bridge crane is determined to be G and the pre-pressing load is determined to be G through accurate calculation when the bridge crane is fully loaded (after the whole hole beam section is completely suspended)0Assuming that 1.1 × G, then theoretically a uniform load of 0.1 × G would need to be applied, then the uniform load q is:
Figure BDA0001830112110000031
span bending moment M with uniformly distributed load acting on bridge fabrication machine1Comprises the following steps:
Figure BDA0001830112110000032
when a bridge fabrication machine overhead crane is used for hoisting a beam section (the weight N is more than or equal to 0.1 × G) to a midspan position, a midspan bending moment M is generated2Comprises the following steps:
Figure BDA0001830112110000033
obviously, M2>M1And the shearing force of the beam section and the midspan shearing force are the same in the two pre-pressing modes. That is to say, it is completely feasible that the bridge fabrication machine hoists a beam section to move on the bridge fabrication machine to provide concentrated load instead of uniformly distributed load prepressing.
In the construction, the uniform load is generally applied by adopting a prepressing block weight pressing mode, the work efficiency is very low, if a bridge fabrication machine is adopted to hoist a beam section to move on the bridge fabrication machine to provide concentrated load to replace the uniform load, the aim of eliminating the inelastic deformation of the support and obtaining the elastic deformation of the support can be achieved, and the prepressing is very efficient.

Claims (4)

1. A method for preloading a segment girder bridge fabrication machine by utilizing dynamic concentrated load is characterized by comprising the following steps:
step 1: calculating the weight of the dynamic concentrated load, and selecting a pre-pressed beam section for providing the concentrated load;
step 2: assembling the movable support bridge fabrication machine, and moving the movable support bridge fabrication machine forwards to a first hole to-be-erected hole position;
and step 3: sequentially suspending each section of the first-hole box girder on a bridge fabrication machine until all sections are suspended;
and 4, step 4: evenly dividing n measuring sections on the section beam bridge fabrication machine;
and 5: hoisting the pre-pressed beam section to a bridge fabrication machine, moving to the position with the length of 1/n beam, monitoring and measuring the span-middle deflection value, the section stress measuring point at the joint of the beam end and the n-1 measuring sections after the deformation is stable, and analyzing the rigidity and the strength of the structure at the moment;
step 6: sequentially moving the pre-pressed beam section to the length of 2/n, … … (n-1)/n beams, monitoring and measuring the span center deflection value, the beam end and the section stress measuring point at the joint of n-1 measuring sections after each row reaches one position to be deformed stably, and analyzing the rigidity and the strength of the structure at the moment;
and 7: and (3) completely unloading all sections of the pre-pressed beam section and the first-hole box beam, monitoring and measuring a cross-center deflection value, a beam end and a section stress measuring point at the joint of the n-1 measuring sections after the pre-pressed beam section and the first-hole box beam are deformed stably, and analyzing the rigidity and the strength of the structure at the moment.
2. The method for pre-pressing a segmental beam bridge fabrication machine with dynamic concentrated loads according to claim 1, wherein the mobile scaffold bridge fabrication machine is of the TPZ80/2500 type.
3. The method for utilizing a dynamic concentrated load preloading segment girder bridge fabrication machine according to claim 1, wherein the first box girder is 13 segments.
4. The method for preloading a segment girder bridge fabrication machine with dynamic concentrated loads according to claim 1, wherein the measuring section is 4 sections.
CN201811201483.6A 2018-10-16 2018-10-16 Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load Active CN109267488B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811201483.6A CN109267488B (en) 2018-10-16 2018-10-16 Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811201483.6A CN109267488B (en) 2018-10-16 2018-10-16 Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load

Publications (2)

Publication Number Publication Date
CN109267488A CN109267488A (en) 2019-01-25
CN109267488B true CN109267488B (en) 2020-09-29

Family

ID=65196975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811201483.6A Active CN109267488B (en) 2018-10-16 2018-10-16 Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load

Country Status (1)

Country Link
CN (1) CN109267488B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080083374A (en) * 2007-03-12 2008-09-18 (주)삼현피에프 Prestressed temporary bridge preloaded by cable-tie and method thereof
CN102704401A (en) * 2012-05-28 2012-10-03 宁波二十冶建设有限公司 Multizone pre-pressing technology for full framing
CN102912738A (en) * 2012-11-07 2013-02-06 北京市公路桥梁建设集团有限公司 Overall prepressing device for hanging basket
CN103628422A (en) * 2013-10-30 2014-03-12 中建三局建设工程股份有限公司 Counter-force type stay rope hanging basket prepressing device and implement method thereof
CN107905109A (en) * 2017-11-21 2018-04-13 重庆建工市政交通工程有限责任公司 The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205046487U (en) * 2015-10-08 2016-02-24 武汉一冶建筑安装工程有限责任公司 Pre -compaction device of bath formula bridge rubber raft
CN205741926U (en) * 2016-05-22 2016-11-30 中交第一航务工程局有限公司 Stretch-draw prepressing device in Cast-in-situ Beam steel pipe beret truss platform
CN207273465U (en) * 2017-10-19 2018-04-27 阚方义 A kind of 500t bilayer preformers for Wood-based Panel Production industry
CN108344546B (en) * 2018-04-19 2024-02-27 杭州中能透平机械装备股份有限公司 Deflection test device and method for steam turbine partition plate

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080083374A (en) * 2007-03-12 2008-09-18 (주)삼현피에프 Prestressed temporary bridge preloaded by cable-tie and method thereof
CN102704401A (en) * 2012-05-28 2012-10-03 宁波二十冶建设有限公司 Multizone pre-pressing technology for full framing
CN102912738A (en) * 2012-11-07 2013-02-06 北京市公路桥梁建设集团有限公司 Overall prepressing device for hanging basket
CN103628422A (en) * 2013-10-30 2014-03-12 中建三局建设工程股份有限公司 Counter-force type stay rope hanging basket prepressing device and implement method thereof
CN107905109A (en) * 2017-11-21 2018-04-13 重庆建工市政交通工程有限责任公司 The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
48m节段预制拼装箱梁架桥机弹性恢复的病害防治;余金江;《铁道建筑技术》;20170520;第49页-第52页、第56页 *

Also Published As

Publication number Publication date
CN109267488A (en) 2019-01-25

Similar Documents

Publication Publication Date Title
CN102530732B (en) Hydraulic hoisting, slipping and emplacing method and equipment for large scale press components
CN104989114A (en) Sliding construction device and method for large-span arc-shaped roof
CN107476581B (en) Hoisting and mounting method for steel structure double-layer overhanging structure
CN114856209B (en) Construction method of high-precision tensioning system for prestressed steel structure
CN108824210B (en) Prepressing method of bridge support
CN110374200A (en) Large span rigidity unevenly mixes rack high altitude bulk method
CN105971292B (en) A kind of twin spans rack band center pillar synchronization-sliding construction technology
CN103266570A (en) Method for accurately installing and positioning suspension bridge main cable anchor system
CN110593076B (en) Steel pipe concrete tied arch bridge hunch seat horizontal displacement monitoring and control system
CN114892873B (en) Inclined roof fish-bellied truss hoisting construction method
CN109267488B (en) Method for preloading segment girder bridge fabrication machine by utilizing dynamic concentrated load
CN111980418A (en) Construction method for hoisting steel structure roof of beam string dome in large-scale public building engineering
CN100417586C (en) Integral lifting method of large bridge crane and its appts
CN103184721B (en) Method for performing block-by-block suspension, glue splicing and linear control on precast segments to assemble polycarbonate (PC) continuous box girder
CN111275939A (en) Bridge construction equipment safety monitoring and early warning method and system
KR20120118723A (en) Simulation method of climbing hydraulic robot and construction factory
CN106768960B (en) Load loading device and load loading method
CN203270465U (en) Hydraulic pre-compression construction device for cantilever suspension basket
CN203519064U (en) A precise weighing and gravity center determination system for heavy objects
Zhou et al. Lift monitoring and analysis of multi-storey corridors in buildings
CN112499482A (en) Intelligent monitoring high-precision positioning steam drum hoisting device and hoisting method applied by same
CN219511580U (en) Rhombic hanging basket safety risk monitoring system
CN204831779U (en) Electric block proof test platform
CN217711812U (en) Steel truss sliding device
Yu Calculation method and control value of static stiffness of tower crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant