CN109235605A - It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel - Google Patents

It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel Download PDF

Info

Publication number
CN109235605A
CN109235605A CN201811159399.2A CN201811159399A CN109235605A CN 109235605 A CN109235605 A CN 109235605A CN 201811159399 A CN201811159399 A CN 201811159399A CN 109235605 A CN109235605 A CN 109235605A
Authority
CN
China
Prior art keywords
pipeline
forebay
deposit
control valve
pump group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811159399.2A
Other languages
Chinese (zh)
Inventor
董磊
张欣
陈昱霖
肖艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201811159399.2A priority Critical patent/CN109235605A/en
Publication of CN109235605A publication Critical patent/CN109235605A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • E03F1/001Methods, systems, or installations for draining-off sewage or storm water into a body of water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F9/00Arrangements or fixed installations methods or devices for cleaning or clearing sewer pipes, e.g. by flushing
    • E03F9/007Devices providing a flushing surge
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F2201/00Details, devices or methods not otherwise provided for
    • E03F2201/20Measuring flow in sewer systems

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)
  • Cleaning In General (AREA)

Abstract

The present invention discloses a kind of device that automatic removing pipeline deposit is responsible for suitable for multichannel, including the Forebay of Pumping Station in municipal drainage pumping plant, section dirty pump group, rainwater pump group, Forebay of Pumping Station is connected with multiple drainage system general pipeline, Forebay of Pumping Station is respectively connected to cut dirty pump group and rainwater pump group by pipeline, and withdrawal of currency from circulation water pipe is additionally provided between Forebay of Pumping Station and rainwater pump group;One access well of setting, the access well are connect by adding row pressure hydraulic piping with water pipe is steam again on each drainage system general pipeline;It is equipped with washing control valve door between described plus row pressure hydraulic piping and access well, the second control valve is equipped between the withdrawal of currency from circulation water pipe and the Forebay of Pumping Station, third control valve door is equipped between the rainwater pump group and river.The present invention reduces pumping plant by way of cutting down pipeline deposit and puts river, solves the problems, such as the drainage system that river is black smelly, applied to various systems from the root, it is with strong points, flexible operation, construction investment is few, can realize effective control that river pollution is put to pumping plant in a short time.

Description

It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
Technical field
The invention belongs to black-odor riverway Treatment process fields, are related to a kind of automatic method and device for removing pipeline deposit, The automatic device for removing pipeline deposit is responsible for suitable for multichannel more particularly to a kind of.
Background technique
As rapid urban and the density of population are continuously increased, river water environmental problems are increasingly highlighted, most cities Black-odor riverway is developed into river.Black-odor riverway problem seriously affects nearby residents quality of life, city image generation.River The black smelly origin cause of formation is other than leading to river channel ecology system destruction due to urban construction, and most importantly pollutant directly enters river and causes External source pollution.
In existing black-odor riverway Treatment process, sewage interception along river, bed mud dredging, restoration of the ecosystem, the technologies such as clean water diversion It is widely used, but since each technological means is there are respective limitation, is difficult to solve the problems, such as that river is black smelly in a short time.
Sewage interception along river, which refers to, lays wastewater interception pipe along river two sides, by it is originally in line enter river sewage access cut dirty pipe Road, and it is delivered to sewage treatment plant, mitigate the in line impact to river water quality of sewage.But interception project implement engineering cost compared with Height, implementation cycle are longer.After the completion of interception project, since the sewage of rain dirt hybrid junction accumulation is in rain in combined sewage and municipal pipeline It can put river by pumping plant driving and enter river, influence river quality of water environment again.
Bed mud dredging is to blow the mud for depositing river bed using mechanical equipment to stir into the watery of muddiness, and transport extraction.Clearly Deposit technique can reduce the endogenous pollution in river, but improper for the sludge handling of extraction be easy to cause secondary pollution.
River corridor restoration refers in river land-based area control line, is meeting the rivers basic training such as flood control, water drainage and diversion On the basis of energy, urban river water ecosystem restoration is promoted by artificial reclamation activities, constructs healthy, complete, stable urban river water The activity of the ecosystem.But the technology to black-odor riverway renovating effect there are limitation, rainfall day put river with pumping plant, pollute Object can destroy river channel ecology system back into river.
Clean water diversion is to introduce polluted river channel upstream or neighbouring cleaning by the regulation of water conservancy projects (such as gate, pumping plant) Water source enhances the diffusion, purification and output of water pollutant to improve the hydrodynamic conditions in river, being capable of rapid recovery water body It is black smelly, but can not achieve the improvement steady in a long-term of black-odor riverway water quality.
For the black-odor riverway Treatment process applied at this stage there are long construction period, investment is big, and the limitation such as can not take effect in short term Property.In addition, often river as before, it is clear long to cannot achieve Changzhi again multiple " black " after heavy rain.Tracing it to its cause is pollutant warp Over long distances, it deposits to form mud in tube bottom after low flow velocity conveying, when catchment occurs, pumping plant rainwater pump group is opened, pipeline Interior deposit is washed into water body.For combined flow system, when pipe diameter determing, considers that (pipeline is set for 2 ~ 5 times of interception ratio The flow of meter is 3 ~ 6 times of dry flow sewage amount), flow velocity is lower in pipeline when dry days sewage transport, and dirty water pollutant can be in pipe It is deposited in road.For separate flow system, the problems such as due to rain dirt hybrid junction, dry flow sewage enters storm sewer, and sewage passes through rainwater The dirty pump that cuts of pumping plant is delivered to sewerage;Many drainage systems are in high water level operational mode, and rain pipe caliber is pressed 3 ~ 5 years Return period designs (i.e. pipe design conveying capacity is tens times of dry flow sewage amount or more), and caliber is larger, and dry flow sewage is in rain Flow velocity is lower in waterpipe, and polluter is deposited in tube bottom.
Since system high water level is run, tradition connects impulsive force that interim water pipe rinses and has been consumed at the pipeline access in 1m Damage, mud is difficult to be washed, even if origin or beginning can also be deposited again by the deposit that instantaneous flow takes up in subsequent main pipe;It is external It is only 100m that high-pressure water pipeline flushing device maximum, which rinses range, and Chinese large-sized sewerage system main pipe length is generally more than 1km, as Shanghai City large size drains conveying main pipe longest up to 55km.Therefore, a kind of automatic side for removing pipeline deposit is developed Method and device, which put river pollution to reduction pumping plant, positive meaning, is to realize that black-odor riverway improvement Changzhi is necessary hand clearly long Section.
Summary of the invention
It is responsible for the automatic device for removing pipeline deposit suitable for multichannel it is an object of the invention to provide a kind of, by cutting Subtract the deposit in municipal pipeline, the reduction rainy day puts the total amount of pollutant that river enters river by pumping plant, river is solved from source The black smelly problem in road, the effect for maintaining black-odor riverway to administer realize that Changzhi is clear long.
In order to achieve the above object, technical scheme is as follows: one kind being suitable for the automatic removing pipeline of multichannel supervisor The device of deposit, including the Forebay of Pumping Station in municipal drainage pumping plant, section dirty pump group, rainwater pump group, Forebay of Pumping Station and multiple rows Water system general pipeline is connected, and Forebay of Pumping Station is respectively connected to cut dirty pump group and rainwater pump group, Forebay of Pumping Station and rainwater pump by pipeline Withdrawal of currency from circulation water pipe is additionally provided between group;It is characterized in that at least one access well is set on each drainage system general pipeline, it is described to connect Enter well to connect by adding row pressure hydraulic piping with water pipe is steam again;Washing control valve is equipped between described plus row pressure hydraulic piping and access well Door is equipped with the second control valve between the withdrawal of currency from circulation water pipe and the Forebay of Pumping Station, third is equipped between the rainwater pump group and river Control valve.
Further, described plus row pressure hydraulic piping is pumped using closed steel pipe, ductile iron pipe, plastic tube etc. according to rainwater Length, caliber and the buried depth of the parameter adjustment pipeline of group water pump.Pumping plant high for configuration pump head, flow is big, adds row pressure Hydraulic piping length is long, caliber is relatively large;For configuring pump head is small, flow is small pumping plant, add row pressure hydraulic piping length it is shorter, Caliber is relatively small;Buried depth of pipeline can be according to adding discharge pipe performance to be adjusted.
Further, it accesses toxic and harmful gas when setting deodorization device prevents the circulatory system from running in well and dissipates and overflow.
For according to drainage system actual conditions, multiple access wells are set in the different location of drainage system general pipeline, and set Setting multichannel adds row pressure hydraulic piping to realize to drainage system multichannel supervisor simultaneously to the multiple access well by the control of valve Or the flushing of timesharing, cut down deposit in pipeline.
Further, installation deposit monitors system in access well, to monitor thickness of deposits in drainage system general pipeline.
Further, it accesses in well and the refluence that anti-water recovery apparatus avoids circulating flushing wash water is set, guarantee flushing water for silt Mud deposit is washed away.
Further, water quality monitoring system is installed in Forebay of Pumping Station, to monitor the water quality of Forebay of Pumping Station.
Further, when drainage system general pipeline caliber is larger, submersible agitator is installed in the inspection shaft of drainage system general pipeline, Promote deposit to wash away, accelerates circulation flushing process.Various ways, including vertical installation, opposite peace can be used in blender installation Be filled with and misorientation installation etc..
Further, described device further includes control system, and the control system monitors system, water quality with deposit respectively Monitoring system, washing control valve door, the second control valve are connected with third control valve door.
The control system is divided into rainfall pumping station test run mode, pumping plant puts river mode and pipe flushing mode Three models, When deposit then starts pipe flushing mode, work as water more than setting value in deposit monitoring system detection to drainage system general pipeline When quality supervision examining system detects Forebay of Pumping Station water stabilization, then stop pipe flushing mode.Rainfall pumping station test run mode, pumping plant are put River mode is the prior art, and Starting mode is not introduced herein.
When pipe flushing mode, washing control valve door is opened, and the second control valve and third control valve door are closed, before pumping plant Pond, rainwater pump group steam again water pipe plus row pressure hydraulic piping, access well, drainage system general pipeline composition circle irrigation system, rainwater pump Group extracts the water in Forebay of Pumping Station, by steaming again water pipe and adding row pressure hydraulic piping, the access well being delivered on drainage system general pipeline, To promote access well to flow velocity in the pipeline of drainage system general pipeline between Forebay of Pumping Station, tube bottom deposit is washed away;Cut dirt High-concentration sewage in circle irrigation system is delivered to urban sewage system by pump group;Access the sewage of low concentration supplement of well upstream Continue to wash away into circle irrigation system.
When rainfall pumping station test run mode, washing control valve door is closed, and the second control valve is opened and third control valve door closes When closing, rainwater pump group extracts the water in Forebay of Pumping Station, sends Forebay of Pumping Station back to further through water pipe is steam again.
When pumping plant puts river mode, washing control valve door is closed, and second controls valve closing, and third control valve door is opened, rain Water pump group extracts the water in Forebay of Pumping Station, and is vented to river.
The present invention arranges (or multichannel) circulating flushing all the way by adding using the draining pump and withdrawal of currency from circulation drainage facility of built Municipal pumping stations Pipeline is washed, pipeline hydraulic rinse-system is formed, increases the flow velocity in pipeline, is realized to the pipeline for possessing multichannel supervisor's drainage system Deposit washes away, so that the river of putting for reducing rainy day pumping plant is polluted.Automatic removing pipeline deposit device of the invention, in dry days Simulating the rainy day drives when putting river that high flow rate scour process, tube bottom deposit are washed reduction in dry days in drainage system general pipeline, The driving of rainy day pumping plant is greatly reduced to put river and cause to pollute the risk into river.Described plus discharge pipe length, caliber can be according to drainings System manifold caliber and rainwater pump group device parameter are designed.The circle irrigation system can be according to deposition spirit in pipeline Operation living, saves operating cost.
The method that reduction pipeline deposit provided by the invention realizes that pumping plant puts pollution river reduction has the advantage that
(1) efficiently using existing facility, engineering measure is few, and investment for trnasforming urban land is small.
(2) operating method is simple, convenient for management.
(3) removal of pipeline deposit is obvious, and it is good to put river contamination control effect to pumping plant, quick.
(4) different system drainage systems, method wide application be can adapt to.
Detailed description of the invention
Fig. 1 is the process flow chart of the method and device of automatic removing pipeline deposit of the invention.
Fig. 2 circulation flushing operational mode schematic diagram.
The anti-water recovery apparatus schematic diagram of Fig. 3 Large Diameter Pipeline system superintendent.
The anti-water recovery apparatus schematic diagram of Fig. 4 small diameter tube system superintendent.
Specific embodiment
A specific embodiment of the invention is further described below in conjunction with attached drawing.
Of the invention realizes that pumping plant puts the pipe flushing formed in the method for polluting river reduction by cutting down pipeline deposit System, as shown in Figure 1, the system includes:
Forebay of Pumping Station 11, section dirty pump group 12 in municipal drainage pumping plant 1, rainwater pump group 13, the withdrawal of currency from circulation water pipe 14, intelligence control system With the access well 61(62 ... 6n of the additional row pressure hydraulic piping 51(52 ... 5n of pumping plant), reconstruction) and drainage system general pipeline 21(22 ... 2n);Increase control valve 15 and control valve 16 after the withdrawal of currency from circulation water pipe 14 is engineered;Described plus row pressure hydraulic piping 51 (52 ... 5n) be connected to steam again water pipe 14, and access drainage system general pipeline 21(22 ... 2n) on access well 6(62 ... 6n);The city 1 control room of political affairs drainage pumping plant increases intelligence control system, accesses well 6(62 ... 6n) in installation deposit monitor system, before pumping plant Water quality monitoring system is installed in pond 11.
Washing control valve door 15 and the second control valve 16 for switching rainfall pumping station test run mode, pumping plant puts river mode and Pipe flushing mode.The washing control valve door 15 is closed, when the second control valve 16 is opened and third control valve door 17 is closed, Enter the test run mode of pumping plant daily maintenance when rainwater 13 turn on pump of pump group;Washing control valve door 15 is closed, the second control valve 16 It closes, third control valve door 17 enters rainy day pumping plant when opening and puts river mode;Washing control valve door 15 is opened, the second control valve 16 close, and third control valve door 17 enters pipe flushing mode when closing.
Add row pressure hydraulic piping 51,52,5n quoted from steaming again water pipe 14 in municipal drainage pumping plant 1, and adds row pressure hydraulic piping 51, switch valve 52, is installed respectively on 5n;Described plus row pressure hydraulic piping 51(52 ... 5n) it connects and steams again water pipe 14 and drainage system General pipeline 21(22 ... 2n) on access well 61(62 ... 6n);The access well 61(62 ... 6n) it is drainage system general pipeline 21(22 ... Inspection shaft on 2n) accesses after engineered and adds row pressure hydraulic piping 51(52 ... 5n), access well 61(62 ... 6n) according to deodorizing facility Prevent foul smell during circulation flushing scattered excessive.
Rainwater, combined sewage, hybrid junction sewage in plot and branch pipe import drainage system general pipeline 21(22 ... 2n), and convey To the Forebay of Pumping Station 11 of municipal drainage pumping plant 1.The siltation in pipeline forms pipeline deposition to pollutant in water during transportation Object, the wastewater pollutants concentration for reaching Forebay of Pumping Station 11 is lower, cuts dirty pump group 12 and sewage of low concentration is only delivered to sewerage. When municipal drainage pumping plant 1, which opens rainy day pumping plant, puts river mode, deposit can enter river with current scour in pipeline;
After pipe flushing mode starts, rainwater pump group 13 extracts the water in Forebay of Pumping Station 11, by steaming again water pipe 14 and adding row pressure Hydraulic piping 51(52 ... 5n), be delivered to drainage system general pipeline 21(22 ... 2n) on access well 61(62 ... 6n), connect to be promoted Enter well 61(62 ... 6n) flow velocity into the pipeline of 11 drainage system general pipeline 21(22 ... 2n of Forebay of Pumping Station), to tube bottom deposit into Row washes away, and pollutant concentration quickly increases in pipeline, and pollutant flows through Forebay of Pumping Station → withdrawal of currency from circulation water pipe → plus row pressure power with water flow Pipeline → drainage system general pipeline circulation;It cuts dirty pump group 12 and keeps continuous service, high-concentration sewage is delivered to municipal sewage system System;Access well 61(62 ... 6n) sewage of low concentration of upstream is supplemented into circle irrigation system and continues to wash away.
It can realize and drainage system general pipeline 21,22 ... 2n are rinsed simultaneously by the switching of control valve, it can also be with Drainage system general pipeline 21,22 ... 2n are rinsed in realization stage by stage.
It is comprised the following steps using the method that reduction pipeline deposit of the invention realizes that pumping plant puts pollution river reduction:
Step 1, when thickness of deposits reaches the 20% of duct height in pipeline (ratio can be adjusted according to system actual conditions), Intelligence control system starts flushing process, opening controlling valve door 15, closing control valve 16, closing control valve 17, unlatching rain 1 ~ 2,13 moderate rain water pump of water pump group.
Step 2, it cuts dirty pump group 12 and opens normal operation, continue Forebay of Pumping Station middle and high concentration sewage transport to municipal sewage System.
Step 3, it after 11 water quality of Forebay of Pumping Station is gradually decreased and tended towards stability, can be selected according to deposit situation in pipeline The rainwater pump for closing rainwater pump group 13, terminates to rinse;Cutting dirty pump group can choose whether to continue to run according to water level in system.
Drainage system general pipeline 21,22 ... 2n can be rinsed simultaneously by the switching of control valve, it can also be to row Water system general pipeline 21,22 ... 2n are rinsed stage by stage, are realized the synchronous developing be responsible for drainage system multichannel and are alternately rinsed.
In the present invention, the Municipal pumping stations rainwater pump group, section dirty pump group, Forebay of Pumping Station are that general Municipal pumping stations are set substantially It applies, can be applied to pipeline hydraulic rinse-system without transformation.The Municipal pumping stations rainwater pump group cuts dirty pump group, Forebay of Pumping Station Matched equipment can be used directly, without transformation.
It is described to steam again the basic facilities that water pipe is general pumping plant, it is applied to pipeline hydraulic rinse-system after engineered.It is described It steams again water pipe and adds the second control valve at access Forebay of Pumping Station, and increase bypass for connection plus row pressure hydraulic piping.It is described Multichannel add row pressure hydraulic piping to lay from pumping plant to the access well on each road general pipeline of drainage system;Buried depth of pipeline, Guan Weike according to Actual conditions freely adjust.The access well is the inspection shaft on drainage system general pipeline, and selection is closed with pumping plant distance, transformation difficulty Suitable inspection shaft is transformed, access plus row pressure hydraulic piping, and in well indoor location deodorizing facility, when preventing rinse-system from running Foul smell, which dissipates, to overflow.
Each road supervisor caliber of the drainage system of the multichannel supervisor is generally different, and the Municipal pumping stations of the end are generally arranged Rainwater pump of different sizes, small pump lift is big, flow is small, opens small pump impulse and washes the lesser system superintendent of caliber, rinse distance compared with It is long;Big pump lift is small, flow is big, to rinse the biggish system manifold of caliber, rinses apart from relatively short.
In the access well, back-flow preventer 7 can be installed in access plus row pressure hydraulic piping end.The back-flow preventer 7 Applied in the access well of Large Diameter Pipeline system manifold, the back-flow preventer arranges different pore size apopore (71 hole of large aperture hole Diameter > in 72 apertures of pore > small size pores, 73 aperture), upper layer be arranged large aperture hole 71, guarantee conveyance capacity, middle layer sets mesoporous Small size pores 73 are arranged in diameter hole 72, lower layer, increase lower layer's water discharge speed, play souring to tube bottom deposit, raising is washed away Efficiency;The back-flow preventer 8 is applied to small diameter tube system manifold (general caliber≤DN1000), is not influencing area of passage Under the premise of prevent circulating flushing wash water flow back.Row pressure hydraulic piping end is being added to form oblique angle, the nozzle height of the nearly borehole wall is lower than remote Nozzle height from the borehole wall.
The intelligence control system includes deposit monitoring, Forebay of Pumping Station water quality monitoring system etc. in pipeline.The intelligence The system of can control can automatically turn on according to pipeline deposition, terminate flushing process.
Deposit monitoring system is mostly installed in system superintendent in the pipeline, for monitoring thickness of deposits, to pipe Deposit reaches certain proportion in road, opens circle irrigation system.
Carrying out pipe flushing in dry days is to carry out pipe flushing using idle rainwater pump group in non-rainfall day;The rainwater Pump group configuration rainwater pump can be steam again on water pipe and newly-built pressure pipeline access general pipeline from drawing water and passing through in Forebay of Pumping Station Inspection shaft realizes the flushing to deposit in access well to Forebay of Pumping Station segment pipe;The rainwater pump conveying energy of the rainwater pump group Power is strong, can increase pipe flow speed in drainage system general pipeline, is conducive to washing away for deposit in pipeline.
Circulation flushing refers to that deposit can uniformly mix after washing away in pipeline in pipeline, and defeated via drainage system general pipeline It send to Forebay of Pumping Station;Water in the Forebay of Pumping Station is taken by rainwater pump group rainwater pumping, defeated via withdrawal of currency from circulation water pipe and pressure pipeline It send to access well.It moves in circles through this, Forebay of Pumping Station water pollutant concentration increases;Described section of dirty pump group continuous service, will be high Concentration sewage transport is to urban sewage system, and low concentration of water enters back into the circulatory system before accessing well;By long-play, follow Concentration of wastewater gradually reduces in ring rinse-system;Pipeline deposit is washed completely substantially in system manifold after access well.
After Forebay of Pumping Station water quality tends towards stability, i.e., deposit can stop recycling after washing away completely in pipeline after access well System operation, energy saving;If long-time Municipal pumping stations rainwater pump group does not drive to put river, intelligent control after circulation flushing System will restart flushing process.
Pipeline deposition fraction is lower when opening rinse-system, and the open frequency of automated development is higher, and deposit cuts down effect Fruit is more preferable, but energy consumption is higher;Pipeline deposition fraction is higher when opening rinse-system, and the open frequency of automated development is lower, energy Consumption is lower, but deposit reduction effect is weaker.
Described plus row pressure hydraulic piping is laid to the access well on each road general pipeline of drainage system, can be with by valve transfer It realizes that multiloop loop system general pipeline is rinsed simultaneously, each road supervisor also may be implemented and alternately rinse.
The pipe flushing system is adapted to separate sewage system and combined drainage system.For separate system system System, can be by the conveying capacity of shut off in amplification pumping plant facility scale and facility back end line (including sewage treatment facility Processing capacity etc.), accelerate the speed that forebay water quality tends towards stability, reduce the time of flushing process, reduces energy consumption.Combined flow system The facility scale that shuts off is larger, and this problem is not present.
The present invention by cut down pipeline deposit realize pumping plant put river pollute reduced method maximum possible be utilized it is built Urban operating mechanism, avoid tearing open greatly build in large scale under the premise of, strive with smaller project inputs, realize in a short time and river dirt is put to pumping plant Dye control effectively.For caliber DN3600, the system manifold that about 1.6 kilometers of length was rushed by 10 hours or so pipelines Wash, can cut down wash away in range 80% or more pipeline deposit.
It is discussed in detail although the contents of the present invention have passed through above preferred embodiment, but it should be appreciated that above-mentioned Description is not considered as limitation of the present invention.After those skilled in the art have read above content, for of the invention A variety of modifications and substitutions all will be apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (10)

1. a kind of be responsible for the automatic device for removing pipeline deposit suitable for multichannel, before the pumping plant in municipal drainage pumping plant Dirty pump group, rainwater pump group are cut in pond, and Forebay of Pumping Station is connected with multiple drainage system general pipeline, and Forebay of Pumping Station is separately connected by pipeline To dirty pump group and rainwater pump group is cut, withdrawal of currency from circulation water pipe is additionally provided between Forebay of Pumping Station and rainwater pump group;It is characterized in that in each row One access well of setting, the access well are connect by adding row pressure hydraulic piping with water pipe is steam again on water system general pipeline;Described plus row pressure It is equipped with washing control valve door between hydraulic piping and access well, the second control valve is equipped between the withdrawal of currency from circulation water pipe and the Forebay of Pumping Station Door is equipped with third control valve door between the rainwater pump group and river.
2. as described in claim 1 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that described Add row pressure hydraulic piping using steel pipe, ductile iron pipe, plastic tube etc..
3. as described in claim 1 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that access Deodorization device is set in well, and toxic and harmful gas, which dissipates, when preventing the circulatory system from running overflows.
4. as described in claim 1 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that arranging Multiple access wells are arranged in the different location of water system general pipeline, and multichannel is arranged and adds row pressure hydraulic piping to the multiple access well, lead to It crosses the control of valve, realizes to drainage system multichannel supervisor simultaneously or the flushing of timesharing, cut down deposit in pipeline.
5. as described in claim 1 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that draining Submersible agitator is installed in the inspection shaft of system manifold.
6. as described in claim 1 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that access Installation deposit monitors system in well, to monitor thickness of deposits in drainage system general pipeline.
7. as claimed in claim 6 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that pumping plant Water quality monitoring system is installed, to monitor the water quality of Forebay of Pumping Station in forebay.
8. as claimed in claim 7 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that described Device further includes control system, and the control system monitors system, water quality monitoring system, washing control valve with deposit respectively Door, the second control valve are connected with third control valve door.
9. as claimed in claim 8 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that described Control system is divided into rainfall pumping station test run mode, pumping plant puts river mode and pipe flushing mode Three models, when deposit monitors Deposit is more than setting value in system detection to drainage system general pipeline, then starts pipe flushing mode, when water quality monitoring system is examined When measuring Forebay of Pumping Station water stabilization, then stop pipe flushing mode.
10. as claimed in claim 9 suitable for the automatic device for removing pipeline deposit of multichannel supervisor, which is characterized in that pipe When road rinse mode, washing control valve door is opened, and the second control valve and third control valve door are closed, Forebay of Pumping Station, rainwater pump Group steams again water pipe plus row pressure hydraulic piping, access well, drainage system general pipeline composition circle irrigation system, rainwater pump group extraction pumping plant Water in forebay, by steaming again water pipe and adding row pressure hydraulic piping, the access well being delivered on drainage system general pipeline connects to be promoted Enter well to flow velocity in the pipeline of drainage system general pipeline between Forebay of Pumping Station, tube bottom deposit is washed away;Cutting dirty pump group will recycle High-concentration sewage in rinse-system is delivered to urban sewage system;The sewage of low concentration of access well upstream is supplemented into circulating flushing The system of washing continues to wash away;
When rainfall pumping station test run mode, washing control valve door is closed, when the second control valve is opened and third control valve door is closed, Rainwater pump group extracts the water in Forebay of Pumping Station, sends Forebay of Pumping Station back to further through water pipe is steam again;
When pumping plant puts river mode, washing control valve door is closed, and second controls valve closing, and third control valve door is opened, rainwater pump Group extracts the water in Forebay of Pumping Station, and is vented to river.
CN201811159399.2A 2018-09-30 2018-09-30 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel Pending CN109235605A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811159399.2A CN109235605A (en) 2018-09-30 2018-09-30 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811159399.2A CN109235605A (en) 2018-09-30 2018-09-30 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel

Publications (1)

Publication Number Publication Date
CN109235605A true CN109235605A (en) 2019-01-18

Family

ID=65054272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811159399.2A Pending CN109235605A (en) 2018-09-30 2018-09-30 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel

Country Status (1)

Country Link
CN (1) CN109235605A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115853093A (en) * 2022-11-21 2023-03-28 合肥中科国禹智能工程有限公司 Drainage pipe network dynamic detection method and system capable of identifying rain and sewage mixed connection

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002309660A (en) * 2001-04-17 2002-10-23 Ngk Insulators Ltd System for supplying treated sewage
CN101905907A (en) * 2010-08-03 2010-12-08 上海市环境科学研究院 Method for reducing pollutants discharged to river from rain and sewage hybrid junction drainage system
CN102080647A (en) * 2011-01-06 2011-06-01 上海市城市建设设计研究院 Rain pump station monitoring system
CN209523268U (en) * 2018-09-30 2019-10-22 上海市政工程设计研究总院(集团)有限公司 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002309660A (en) * 2001-04-17 2002-10-23 Ngk Insulators Ltd System for supplying treated sewage
CN101905907A (en) * 2010-08-03 2010-12-08 上海市环境科学研究院 Method for reducing pollutants discharged to river from rain and sewage hybrid junction drainage system
CN102080647A (en) * 2011-01-06 2011-06-01 上海市城市建设设计研究院 Rain pump station monitoring system
CN209523268U (en) * 2018-09-30 2019-10-22 上海市政工程设计研究总院(集团)有限公司 It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115853093A (en) * 2022-11-21 2023-03-28 合肥中科国禹智能工程有限公司 Drainage pipe network dynamic detection method and system capable of identifying rain and sewage mixed connection
CN115853093B (en) * 2022-11-21 2024-02-27 合肥中科国禹智能工程有限公司 Drainage pipe network dynamic detection method and system capable of identifying rain and sewage hybrid connection

Similar Documents

Publication Publication Date Title
CN109235602A (en) A kind of pipeline deposit automatic clearing apparatus steaming again water pipe by pumping plant
CN206859397U (en) The flushing desilting system of gravity stream sewage pipe in pipe gallery
CN104196118B (en) A kind of pond automatic vacuum rinses Accrete clearing device and method
CN111932403A (en) Urban sewage pipe network and water environment quality-improving and efficiency-increasing technology integration method
CN107761900A (en) It is a kind of to carry the double shunting wells of flap gate including the drainage system of the shunting well and water discharge control method
CN109629657A (en) A kind of multiple-effect multiplication storage pond
CN104975648A (en) Combined system underground initial rainwater storage tank
CN105178425B (en) Cities and towns water drainage, moisturizing, water-change pump station hinge
CN106545069A (en) Method for treating urban black and odorous water by serially connecting sewage interception and collection pipes
CN114045915B (en) System that dams that has function of washing to rain sewage deposit in pipe network
CN109235604A (en) A method of automatic removing pipeline deposit is responsible for suitable for multichannel
CN103669547A (en) Method and equipment for raising urban water-logging prevention standard and controlling water pollution
CN210086451U (en) Multiple-effect multiplication regulation and storage tank
CN209523268U (en) It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
CN109235605A (en) It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
CN109235603A (en) A method of water pipe is steam again by pumping plant and realizes automatic removing pipeline deposit
CN112554274A (en) Integrated double-cylinder water taking intelligent pump station
CN211172272U (en) System for flushing and shunting municipal sewage pipe
CN204753798U (en) Confluence system underground initial stage rainwater regulation pond
CN209523269U (en) A kind of pipeline deposit automatic clearing apparatus steaming again water pipe by pumping plant
CN109629656A (en) A method of realizing that municipal drainage pumping plant puts river contamination control using storage pond
CN207436244U (en) A kind of pipe flushing system
CN106592748A (en) Storage and utilization system for underwater initial rainwater
CN210857472U (en) Bury formula dispersion regulation storage battery system
CN104563277B (en) A kind of folding door type flushing device for Drain pipe network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination