CN109235470B - Anti-slip structure for electrified management of power transmission line tower landslide - Google Patents

Anti-slip structure for electrified management of power transmission line tower landslide Download PDF

Info

Publication number
CN109235470B
CN109235470B CN201811256969.XA CN201811256969A CN109235470B CN 109235470 B CN109235470 B CN 109235470B CN 201811256969 A CN201811256969 A CN 201811256969A CN 109235470 B CN109235470 B CN 109235470B
Authority
CN
China
Prior art keywords
landslide
foundation
tower
connecting beam
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811256969.XA
Other languages
Chinese (zh)
Other versions
CN109235470A (en
Inventor
姜燕波
金涛
丁黎
赖文华
杨晓龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Construction Group Yunnan Electric Power Design Institute Co ltd
Original Assignee
China Energy Construction Group Yunnan Electric Power Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Construction Group Yunnan Electric Power Design Institute Co ltd filed Critical China Energy Construction Group Yunnan Electric Power Design Institute Co ltd
Priority to CN201811256969.XA priority Critical patent/CN109235470B/en
Publication of CN109235470A publication Critical patent/CN109235470A/en
Application granted granted Critical
Publication of CN109235470B publication Critical patent/CN109235470B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Abstract

The invention discloses an anti-slip structure for electrified treatment of a power transmission line tower landslide, which comprises an anti-slip pile, a connecting beam for connecting the anti-slip pile with a power tower foundation and a foundation upright post well type reinforcing ring. The anti-slide pile is firmly anchored into the stable rock soil layer, and the connecting beam connects the anti-slide pile and the original tower foundation into a whole, so that stable support is provided for the tower foundation, and the effects of resisting landslide and stabilizing the tower are achieved. The landslide control scheme provided by the invention can be used for reinforcing the tower landslide without power failure, and has incomparable superiority to other landslide control schemes.

Description

Anti-slip structure for electrified management of power transmission line tower landslide
Technical Field
The invention relates to a reinforced pile structure technology for anti-skid of a power transmission line tower, in particular to an anti-skid pile structure system for electrified treatment of power transmission line tower landslide.
Background
The tower of the power transmission line in areas with easily slippery rock and soil such as strong weathered granite is easy to slide in rainy seasons, and the safe operation of the power transmission line is seriously threatened. For a power transmission line tower landslide, the most commonly used treatment scheme is as follows: lane change, slope treatment and the like; although the line change is safe and reliable, besides a stable tower site, power is required to be cut off during construction, and the slope surface treatment can only treat shallow landslide, so that the landslide slope surface treatment effect is not ideal once the depth of a sliding surface is large. The current anti-slide pile is mainly used for reservoir dam landslide control, highway landslide control and the like, and generally plays a role in stabilizing a part (or a whole) of a sliding soil body.
Disclosure of Invention
The invention aims to provide an anti-slide pile system for electrified treatment of a power transmission line tower landslide, which is mainly used for stabilizing a tower foundation by carrying out anti-slide treatment without power failure and can solve the problem of reinforcement of the power failure and displacement condition of the electric tower. When a particularly important power transmission line cannot cut power and needs to treat a tower landslide, the invention adopts an electrified construction mode, namely, the tower is electrified and reinforced by driving an anti-slide pile nearby the tower. The anti-slide pile utilizes the self bending resistance and the lateral resistance of the underground stable rock and soil layer, and the anti-slide pile and the original tower foundation are connected into a whole through the connecting beam, so that stable support is provided for the tower foundation, and the effects of resisting landslide and stabilizing the tower are achieved. The design and the pile arrangement of the anti-slide piles are flexible, and the principle is clear; by excavating the pile hole, the geological condition can be directly observed, the rechecking and verification of the design are facilitated, and the construction process is simple.
To achieve the object, the invention provides:
the invention discloses an anti-slip structure for electrified management of a power transmission line tower landslide, which is characterized in that: comprises eight anti-slide piles (1), a connecting beam (2) for connecting the anti-slide piles with a tower foundation (4), and a foundation upright post well type reinforcing ring (3). Four anti-slide piles (1) are respectively arranged on two sides of an electric tower foundation (4) side by side along a horizontal landslide direction, the four anti-slide piles (1A) on the outer side are respectively connected through vertical connecting beams (2A), and the four anti-slide piles (1B) on the inner side are mutually connected after the foundation is anchored through the vertical connecting beams (2B); each row of anti-skid piles are connected in series by a transverse connecting beam (2C), and four foundations are connected by a transverse connecting beam (2D) and then are lapped on a vertical connecting beam (2A), so that the four foundations are connected and combined into a nine-format integral structure system; a well type reinforcing ring (3) is arranged on the upright post of the electric tower foundation (4) to perform sleeve joint reinforcement on the upright post of the electric tower foundation (4); the electric tower foundation (4) is connected with the connecting beam (2), and the bottom plate of the electric tower foundation (4) is connected with the well type reinforcing ring (3) in a reinforcing manner by adopting a bar planting technology.
Compared with the prior art, the invention has the beneficial effects that:
(1) While conventional slide pile systems are typically used to stabilize a mass of landslide soil (or soil block) so that a built-up (constructed) building on the landslide mass is endangered by the landslide, the present invention aims to directly fix a landslide-endangered electric tower foundation onto the slide pile system, and the engineering objective is directly effective and in one step.
(2) The eight anti-slide piles are connected with the foundation through the connecting beams to form a nine-format integral structure system, and compared with the original anti-slide structure system, the anti-slide pile structure system is more reasonable in arrangement, the effect of resisting landslide hazard is enhanced, and the reliability of the power transmission tower in a special environment is more powerfully ensured.
(3) The invention adopts the well type reinforcing ring to reinforce the foundation at the joint of the original electric tower foundation and the anti-slide pile connecting beam, adopts the reinforcement planting technology to reinforce the connection, and is verified by engineering examples, the method is simple and effective and is convenient to implement.
(4) The invention can carry out landslide treatment on the electric tower under the condition of no power failure and has good economic and social benefits.
Drawings
FIG. 1 is a schematic view of a pile-beam planar arrangement of the present invention;
fig. 2 is a schematic construction diagram of the present invention.
Detailed description of the preferred embodiments
The invention will now be described in further detail with reference to the drawings and examples of embodiments.
As shown in fig. 1, the invention is a slip-resistant structure for electrified management of a power transmission line tower landslide, which is characterized in that: comprises eight anti-slide piles (1), a connecting beam (2) for connecting the anti-slide piles with a tower foundation (4), and a foundation upright post well type reinforcing ring (3). Four anti-slide piles (1) are respectively arranged on two sides of an electric tower foundation (4) side by side along a horizontal landslide direction, the four anti-slide piles (1A) on the outer side are respectively connected through vertical connecting beams (2A), and the four anti-slide piles (1B) on the inner side are mutually connected after the foundation is anchored through the vertical connecting beams (2B); each row of anti-skid piles are connected in series by a transverse connecting beam (2C), and four foundations are connected by a transverse connecting beam (2D) and then are lapped on a vertical connecting beam (2A), so that the four foundations are connected and combined into a nine-format integral structure system; a well type reinforcing ring (3) is arranged on the upright post of the electric tower foundation (4) to perform sleeve joint reinforcement on the upright post of the electric tower foundation (4); the electric tower foundation (4) is connected with the connecting beam (2), and the bottom plate of the electric tower foundation (4) is connected with the well type reinforcing ring (3) in a reinforcing manner by adopting a bar planting technology.
The construction method of the invention is that before the construction is started, the temporary stay wire is led out from the special positions (sixteen nodes are black points) of the tower body and is connected with the lower stay wire disc, thereby fixing the electric tower.
As shown in fig. 1, which is a schematic view of the pile-beam planar arrangement of the present invention. After the power transmission tower is effectively fixed, pile foundation construction is started. When pile holes are excavated, feasible drainage measures and illumination measures are needed. If construction is performed in rainy season, measures are added to prevent rainwater from entering pile holes. In the process of excavation, irregular air supply to the holes is preferably adopted for the pile holes which are possibly lack of oxygen. And the protection wall is cast while digging the hole. When the pile bottom needs to be drilled, the rock surface is blasted and cleaned by rock drilling, shallow hole small-dosage blasting and wet operation are adopted for drilling. The earth dug by the digging hole needs to be transported away in time, and the earth cannot be piled up in one meter of the four weeks of the hole. When the steel bar is dug to the designed elevation, the depth of the sliding surface needs to be checked again, so that the position of the steel bar is determined again. When the pile hole reaches the designed depth, the bottom of the hole is cleaned, the bearing layer at the pile end is strictly forbidden to be immersed by underground water, and after the pile hole is checked and accepted by geology personnel, the pile body is finished by adopting one-time continuous pouring of concrete.
In order to ensure safety, the construction of the slide-resistant piles is firstly completed and the connection of the slide-resistant piles and the tower foundation is carried out after the completion of the connection, and the construction is carried out according to a certain sequence, as shown in figure 2, the construction sequence of the connecting beam can be S-1- & gt S-2- & gt S-3- & gt S-4, and the construction of the next stage is allowed after the backfill is constructed in each stage. The reinforcing steel bars of the well type connecting reinforcing ring are reserved in the S-1 stage construction. Meanwhile, vertical construction joints are reserved strictly according to the requirements of construction joint reserved drawings. When the construction joint is constructed next time, after necessary cleaning roughening measures are carried out on the construction joint, cement mortar with the same components as concrete is paved at the construction joint, and then pouring and tamping are carried out.
As shown in fig. 1, the tie beam is connected to the slide piles and the foundation columns. The beam and the foundation upright post are connected by a bar planting method, and the concrete scheme is as follows: firstly, all concrete protective layers at the joints of the beams and the foundation upright posts are removed, and the longitudinal reinforcing steel bars of the foundation upright posts are exposed by roughening. And then the foundation protective cap is opened, the positions of the footing bolts are confirmed, the original positions of the steel bars are properly adjusted, holes are drilled on the foundation upright posts, the steel bars of the original upright posts and the foundation bolts are staggered for connection (construction is carried out according to the related requirements of a steel bar planting method), and the protective cap is supplemented.
As a further scheme of the invention: the included angle between the temporary stay wire and the ground is 30-45 degrees. The single GJ-100 is adopted for wire drawing, LP1.2 is adopted for wire drawing disc, and the burial depth is 2.5m. Since for live operation care is taken to ensure that the distance between the pull wire and the nearest wire is not less than 1.5m and other necessary safety measures are taken.
The foregoing description is only of the preferred embodiments of the present invention, and is not intended to limit the invention, but any minor modifications, equivalents, and improvements made to the above embodiments according to the technical principles of the present invention should be included in the scope of the technical solutions of the present invention.

Claims (1)

1. A anti-skidding structure for administering transmission line tower position landslide with electricity, its characterized in that: comprises eight anti-slide piles (1), a connecting beam (2) for connecting the anti-slide piles with a tower foundation (4), and a foundation upright post well type reinforcing ring (3); four anti-slide piles (1) are respectively arranged on two sides of an electric tower foundation (4) side by side along a horizontal landslide direction, the four anti-slide piles (1A) on the outer side are respectively connected through vertical connecting beams (2A), and the four anti-slide piles (1B) on the inner side are mutually connected after the foundation is anchored through the vertical connecting beams (2B); each row of anti-skid piles are connected in series by a transverse connecting beam (2C), and four foundations are connected by a transverse connecting beam (2D) and then are lapped on a vertical connecting beam (2A), so that the four foundations are connected and combined into a nine-format integral structure system; a well type reinforcing ring (3) is arranged on the upright post of the electric tower foundation (4) to perform sleeve joint reinforcement on the upright post of the electric tower foundation (4); the electric tower foundation (4) is connected with the connecting beam (2), and the bottom plate of the electric tower foundation (4) is connected with the well type reinforcing ring (3) in a reinforcing manner by adopting a bar planting technology.
CN201811256969.XA 2018-10-26 2018-10-26 Anti-slip structure for electrified management of power transmission line tower landslide Active CN109235470B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811256969.XA CN109235470B (en) 2018-10-26 2018-10-26 Anti-slip structure for electrified management of power transmission line tower landslide

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811256969.XA CN109235470B (en) 2018-10-26 2018-10-26 Anti-slip structure for electrified management of power transmission line tower landslide

Publications (2)

Publication Number Publication Date
CN109235470A CN109235470A (en) 2019-01-18
CN109235470B true CN109235470B (en) 2024-02-06

Family

ID=65082337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811256969.XA Active CN109235470B (en) 2018-10-26 2018-10-26 Anti-slip structure for electrified management of power transmission line tower landslide

Country Status (1)

Country Link
CN (1) CN109235470B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012012815A (en) * 2010-06-30 2012-01-19 Chugoku Electric Power Co Inc:The Foundation construction method of tower-like structure and foundation structure thereof
JP2012172295A (en) * 2011-02-17 2012-09-10 Tokyo Electric Power Co Inc:The Reinforcement method of steel tower for power transmission
CN207405635U (en) * 2017-06-05 2018-05-25 吴震 Friction pile adds the antiskid structure that row's antiskid anchor pole administers bedding plane landslide
CN209162856U (en) * 2018-10-26 2019-07-26 中国能源建设集团云南省电力设计院有限公司 A kind of antiskid structure to come down for charging improvement power transmission line column position

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012012815A (en) * 2010-06-30 2012-01-19 Chugoku Electric Power Co Inc:The Foundation construction method of tower-like structure and foundation structure thereof
JP2012172295A (en) * 2011-02-17 2012-09-10 Tokyo Electric Power Co Inc:The Reinforcement method of steel tower for power transmission
CN207405635U (en) * 2017-06-05 2018-05-25 吴震 Friction pile adds the antiskid structure that row's antiskid anchor pole administers bedding plane landslide
CN209162856U (en) * 2018-10-26 2019-07-26 中国能源建设集团云南省电力设计院有限公司 A kind of antiskid structure to come down for charging improvement power transmission line column position

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
抗滑桩在送电线路塔位滑坡治理中的应用;姜燕波;;云南电力技术(第02期);全文 *

Also Published As

Publication number Publication date
CN109235470A (en) 2019-01-18

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN106498953A (en) Cut slope composite supporting construction and its construction method
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN104676110A (en) On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN103726495B (en) Coastal waters deep foundation pit supporting structure and construction method thereof
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
CN109339079A (en) A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN108149692B (en) Supporting construction suitable for non-closed foundation ditch
CN101768960B (en) Bored concrete pile construction method of permafrost layer
CN105040707B (en) Combine the construction method of close pile deep foundation pit support building enclosure
CN108755719A (en) Seabed municipal tunnel over strait cofferdam open cutting construction method
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
CN107165641A (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
RU2587673C1 (en) Transport junction and method for construction thereof
CN107178088A (en) A kind of basement waterproofing foundation pit structure and its construction method
CN109235470B (en) Anti-slip structure for electrified management of power transmission line tower landslide
CN105926660A (en) Construction method of wind power low pile bearing platform foundation in intertidal zone
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
CN205605215U (en) Big section loess tunnel is grooving method construction structures in advance
CN209162856U (en) A kind of antiskid structure to come down for charging improvement power transmission line column position
CN209687506U (en) Wear river shallow buried covered excavation electric power tunnel constructing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant