CN109217185A - The method for not powering off safety transfer for ensuring sewage treatment plant's cable - Google Patents

The method for not powering off safety transfer for ensuring sewage treatment plant's cable Download PDF

Info

Publication number
CN109217185A
CN109217185A CN201811041774.3A CN201811041774A CN109217185A CN 109217185 A CN109217185 A CN 109217185A CN 201811041774 A CN201811041774 A CN 201811041774A CN 109217185 A CN109217185 A CN 109217185A
Authority
CN
China
Prior art keywords
cable
sewage treatment
treatment plant
ensuring
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811041774.3A
Other languages
Chinese (zh)
Other versions
CN109217185B (en
Inventor
林吉勇
陈永生
徐言毓
邓萱
贺沸腾
马超
沈小洁
徐海东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU INDUSTRY EQUIPMENT INSTALLATION Co Ltd
Original Assignee
CHENGDU INDUSTRY EQUIPMENT INSTALLATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU INDUSTRY EQUIPMENT INSTALLATION Co Ltd filed Critical CHENGDU INDUSTRY EQUIPMENT INSTALLATION Co Ltd
Priority to CN201811041774.3A priority Critical patent/CN109217185B/en
Publication of CN109217185A publication Critical patent/CN109217185A/en
Application granted granted Critical
Publication of CN109217185B publication Critical patent/CN109217185B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F1/00Treatment of water, waste water, or sewage
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F2201/00Apparatus for treatment of water, waste water or sewage
    • C02F2201/002Construction details of the apparatus
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F2303/00Specific treatment goals
    • C02F2303/14Maintenance of water treatment installations

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Electric Cable Installation (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The method that the invention discloses a kind of not to power off safety transfer for ensuring sewage treatment plant's cable, comprising the following steps: formulate arrangement and method for construction, prepare equipment and tool required for constructing;Original buried cable is positioned according to design drawing, and carries out unwrapping wire in position location;Former cable is dug out according to the position of unwrapping wire in abovementioned steps;The cable dug out in abovementioned steps is removed into former cable duct, and setting is fixed temporarily protective device and protects to cable;Excavate new cable ditch;It removes cable and is fixed temporarily protective device, and cable is moved into new cable ditch;Steel pipe is extracted to cable to protect, and takes fireproof blocking;Backfilling of earthwork is carried out to new cable ditch;The present invention effectively avoids the stoppage in transit of sewage treatment plant, during sewage treatment plant's reorganization and expansion, ensure that the normal operation processing of sewage.

Description

The method for not powering off safety transfer for ensuring sewage treatment plant's cable
Technical field
The present invention relates to sewage treatment plant's reorganization and expansion fields, and in particular to one kind is for ensuring that sewage treatment plant's cable is continuous The method of electric safety transfer.
Background technique
In recent years, since water resource is more paid attention in the waste of industrial wastewater discharge and water resource, let us, China is successively The execution standard for Drinking Water, sewage and industrial wastewater is promulgated.There is the restriction of these standards, allows sewage cannot be again Disorderly discharge, sewage treatment bring many benefits for our life;1) improve water quality, handled by domestic sewage treatment device Sewage, make the pollution level sharp fall of water, whether discharge or reuse, standard can be reached;2) improve ecology Environment, untreated sewage discharge not only pollute the environment into river, are also brought along to people's lives with water quality Adverse effect;3) promote water circulation system, the Natural Circulation of water is the nonequilibrium open system with institutional framework, the society of water Circulation is that have the balance system of artificial organ structure.
With the development of urbanization of population, more and more populations flock together, Drinking Water, sewage and work The discharge amount of industry waste water is increasing, certainly will may require that the processing capacity of sewage treatment plant steps up, when sewage treatment plant After processing capacity reaches capacity, in order to guarantee the normal processing of sewage, generally all can on the basis of original sewage treatment plant into Row reorganization and expansion, main electrical equipment is exactly various water pumps in sewage treatment plant, in the reorganization and expansion process for carrying out sewage treatment plant In, it needs to be laid out the distribution of water pump again or increases corresponding pump equipment, the resettlement of the electrical equipments such as existing water pump Cheng Zhong, the method taken cable are mainly two kinds: 1) replacing new cable, rewiring;2) original cable is dug out, weight New position is arrived in new resettlement;There are some problems in the two methods, such as replace new cable, rewiring, first this kind of method because To need to re-lay cable, undoubtedly increase the expense of cable replacement certainly, secondly, the cable of the electrical equipments such as some water pumps needs Professional customization is wanted, period production time is longer, influences construction speed;Second method needs prolonged power failure operation, needs A period of time is stagnated into sewage treatment, this certainly will will cause the great pressure of sewage treatment plant's treatment sewage, serious person's meeting The problem of causing sewage pollution environment.
Summary of the invention
The technical problem to be solved by the present invention is providing a kind of for ensuring that sewage treatment plant's cable does not power off safety transfer Method, during sewage treatment plant's reorganization and expansion, water pump etc. correlation electrical equipment carry out entirety in case of constant power Resettlement, guarantee safety do not stop transport in the case where, be also able to achieve the saving of cost.
To achieve the above object, The technical solution adopted by the invention is as follows:
The method for not powering off safety transfer for ensuring sewage treatment plant's cable, comprising the following steps:
S1: formulating arrangement and method for construction, prepares equipment and tool required for constructing;
S2: confirming the control switch of cable, and be identified with clear mark, is buried according to design drawing to original Ground cable is positioned, and carries out unwrapping wire in position location;
S3: former cable is dug out according to the position of unwrapping wire in S2;
S4: removing former cable duct for the cable dug out in step S3, and is arranged and is fixed temporarily protective device to cable progress Protection;
S5: new cable ditch is excavated;
S6: it removes cable and is fixed temporarily protective device, and cable is moved into new cable ditch;
S7: the cable position passed by one's way to needs is extracted steel pipe and is protected, and takes fireproof blocking;
S8: backfilling of earthwork is carried out to new cable ditch, completes construction.
Further, it is comprised the steps of: in the step S3
S31: according to the position of unwrapping wire in step S2, road surface cutting is carried out using cutting machine;
S32: mixed mud surface layer staged and layered is chiseled, and using excavator excavate soil, chisel standard according to width × Depth≤150mm × 200mm standard;
S33: construction personnel dresses good protection insulation dress ornament, first examines whether the cable dug out charges with electroscope, then adopt Manually by cable pipeline concrete pack protective layer carry out layering chisel, chisel standard according to width x depth≤150mm × The standard of 200mm;
S34: using the cable progress manually by the cable chiseled in step S33 progress by root cleaning, and to there is breakage The processing of crust package, the crust package processing method is first to wind mackintosh, then in winding exhaust gas cable skin and electricity consumption Work adhesive plaster is sealed.
Further, the method that cable removes former cable duct in the step S4 is the cable rope made of hemp that will first clean up It is tied up, then in such a way that calabash takes turns and hooks the rope made of hemp, cable is removed from former cable duct, it is described to be fixed temporarily protective device Using the wooden springboard of wide 250mm × thickness 40mm and long 2000mm × wide 1000mm bamboo slab rubber.
Further, new cable ditch is excavated in the step S5 to be excavated using excavator.
Further, to partial cables of passing by one's way in the step S7, when extracting steel pipe and being protected, including following operation step It is rapid:
S71: the steel pipe met the requirements is chosen;
S72: the steel pipe that will have been chosen, into two using cutting machine cutting;
S73: using cutting steel pipe into two, after cable is wrapped up, alignment splicing, and with electric welding machine by its splicing seams into Row welding;
S74: the steel pipe being welded is encapsulated using mixed mud C30.
In order to guarantee the safety of construction, the operation of all pairs of cables in step S1-S8 confirms cable using electroscope first Whether charge, and all constructing operation personnel wear insulating glove, insulation clothing and insulated shoes when carrying out constructing operation, avoid electricity The accident that cable electric leakage is hurted sb.'s feelings.
Compared with prior art, the invention has the following advantages:
(1) present invention realizes the safety transfer that cable does not power off, and the stoppage in transit of sewage treatment plant is effectively avoided, in dirt During water treatment plant's reorganization and expansion, the normal operation processing of sewage ensure that.
(2) present invention moves original cable to new cable duct, the only migration of cable, without being related to The replacement of cable thus greatly reduces the cost of cable resettlement, with good economic efficiency.
(3) present invention is during carrying out cable resettlement, while implementing and checking the breakage of cable, and to breakage Position has carried out winding mackintosh, then the operation for winding exhaust gas cable skin and being sealed with electrical adhesive tape, to former cable into It has gone secondary Inspection and maintenance, has effectively raised the service life of cable.
(4) present invention is carried out at cable excavation when carrying out cable excavation using mechanical and artificial mutual auxiliary Reason both ensure that the efficiency that cable excavates, and also ensure cable from mechanical injury.
(5) present invention is when removing cable, equipped with protective device is fixed temporarily, after its removal to cable, new cable ditch The injury for effectively avoiding the damage of cable when not excavating again and leaking electricity to personnel.
Detailed description of the invention
Fig. 1 is construction process block diagram of the present invention.
Specific embodiment
The invention will be further described with embodiment for explanation with reference to the accompanying drawing, and mode of the invention includes but not only limits In following embodiment.
The method for not powering off safety transfer for ensuring sewage treatment plant's cable, comprising the following steps:
S1: formulating arrangement and method for construction, prepares equipment and tool required for constructing, gives training to construction personnel, and training It is examined after having instructed, can be constructed after examination is qualified;It is on duty again after examination is qualified, ensure that the safety in work progress, have Conducive to constructing for operator's safety standard, the efficiency of construction is improved;
S2: checking the equipment in use for the cable that needs migrate, confirm whether it runs well, meanwhile, confirm it The control switch of cable, and be identified with the mark of clear and definite, it can be powered off in time after guaranteeing operator's maloperation electric shock; Original buried cable is positioned according to design drawing, and carries out unwrapping wire in position location;When unwrapping wire, with albarium or its Its eye-catching innocuous substance identifies trend and the position of cable.
S3: former cable is dug out according to the position of unwrapping wire in S2;
It digs out cable to follow the steps below, S31: road surface cutting is carried out using cutting machine;S32: using will manually mix Soil surface layer staged and layered is chiseled, and using excavator excavate soil, chisel standard according to width x depth≤150mm × The standard of 200mm;S33: being chiseled using cable pipeline concrete pack protective layer is manually carried out layering, using mechanical and artificial Mutual auxiliary carry out cable excavation processing, both ensure that the efficiency that cable excavates, also ensure cable from mechanical injury, Standard is chiseled according to width x depth≤150mm × 200mm standard;S34: using the cable that will manually be chiseled in step S33 Clear up by root, and to there is damaged cable to carry out the processing of crust package, the crust package processing method is first to wind Then mackintosh is winding exhaust gas cable skin and is being sealed with electrical adhesive tape, carrying out secondary inspection to former cable and tieed up Shield, effectively raises the service life of cable.
S4: removing former cable duct for the cable dug out in step S3, and is arranged and is fixed temporarily protective device to cable progress Protection;During cable removes, first the cable cleaned up is tied up with the rope made of hemp, then the rope made of hemp is hooked using calabash wheel Mode removes cable from former cable duct, and the protective device that is fixed temporarily is jumped using the wood of 250mm (width) × 40mm (thickness) Plate and 2000mm (length) × 1000mm (width) bamboo slab rubber.
S5: new cable ditch is excavated;To improve the efficiency excavated, excavated when excavating new cable ditch using excavator.
S6: it removes cable and is fixed temporarily protective device, and cable is moved into new cable ditch;Cable is moved into new cable again When ditch, moved into also according to the method for step S4.
S7: the cable position passed by one's way to needs is extracted steel pipe and is protected, and fireproof blocking is taken to extract steel pipe to cable It is protected;When extracting steel pipe and being protected, including following operating procedure:
S71: the steel pipe met the requirements is chosen;
S72: the steel pipe that will have been chosen, into two using cutting machine cutting;
S73: using cutting steel pipe into two, after cable is wrapped up, alignment splicing, and with electric welding machine by its splicing seams into Row welding, when welding, need for weld seam and cable to be isolated by thermal insulation board, prevent the high temperature being welded from causing to damage to cable.
S8: carrying out backfilling of earthwork to new cable ditch, and in order to guarantee the safe operation of personnel, the operation of all pairs of cables is first First using electroscope confirmation cable whether charge, and all constructing operation personnel worn when carrying out constructing operation insulating glove, Insulation clothing and insulated shoes, the accident for avoiding cable leakage from hurting sb.'s feelings.
Above-described embodiment is only one of the preferred embodiment of the present invention, should not be taken to limit protection model of the invention It encloses, as long as that in body design thought of the invention and mentally makes has no the change of essential meaning or polishing, is solved The technical issues of it is still consistent with the present invention, should all be included within protection scope of the present invention.

Claims (6)

1. for ensuring the method that sewage treatment plant's cable does not power off safety transfer, which comprises the following steps:
S1: formulating arrangement and method for construction, prepares equipment and tool required for constructing;
S2: confirm the control switch of cable, and be identified with clear mark, according to design drawing to original buried electricity Cable is positioned, and carries out unwrapping wire in position location;
S3: former cable is dug out according to the position of unwrapping wire in S2;
S4: the cable dug out in step S3 is removed into former cable duct, and setting is fixed temporarily protective device and protects to cable;
S5: new cable ditch is excavated;
S6: it removes cable and is fixed temporarily protective device, and cable is moved into new cable ditch;
S7: the cable position passed by one's way to needs is extracted steel pipe and is protected, and takes fireproof blocking;
S8: backfilling of earthwork is carried out to new cable ditch, completes construction.
2. according to claim 1 for ensuring that the method that sewage treatment plant's cable does not power off safety transfer, feature exist In being comprised the steps of: in the step S3
S31: according to the position of unwrapping wire in step S2, road surface cutting is carried out using cutting machine;
S32: mixed mud surface layer staged and layered is chiseled, and excavates soil using excavator, chisels standard according to width x depth The standard of≤150mm × 200mm;
S33: construction personnel dresses good protection insulation dress ornament, first examines whether the cable dug out charges with electroscope, then uses people Cable pipeline concrete pack protective layer is carried out layering and chiseled by work, chisels standard according to width x depth≤150mm × 200mm Standard;
S34: using and manually clear up by root by the cable chiseled in step S33, and carries out crust to the cable for having breakage Package processing, crust package processing method is first to wind mackintosh, then in winding exhaust gas cable skin and with electrician's glue Cloth is sealed.
3. according to claim 2 for ensuring that the method that sewage treatment plant's cable does not power off safety transfer, feature exist In the method that cable removes former cable duct in the step S4 is first to tie up the cable cleaned up with the rope made of hemp, then adopt With calabash take turns hook the rope made of hemp mode, cable is removed from former cable duct, it is described be fixed temporarily protective device using width 250mm × The wooden springboard of thick 40mm and long 2000mm × wide 1000mm bamboo slab rubber.
4. according to claim 3 for ensuring that the method that sewage treatment plant's cable does not power off safety transfer, feature exist In excavation new cable ditch is excavated using excavator in the step S5.
5. according to claim 4 for ensuring that the method that sewage treatment plant's cable does not power off safety transfer, feature exist In, to partial cables of passing by one's way in the step S7, when extracting steel pipe and being protected, including following operating procedure:
S71: the steel pipe met the requirements is chosen;
S72: the steel pipe that will have been chosen, into two using cutting machine cutting;
S73: using the steel pipe of cutting into two, after cable is wrapped up, alignment splicing, and welded its splicing seams with electric welding machine It connects;
S74: the steel pipe being welded is encapsulated using mixed mud C30.
6. according to claim 1 for ensuring that sewage treatment plant's cable does not power off the side of safety transfer described in -5 any one Method, which is characterized in that whether the operation of all pairs of cables in step S1-S8 is charged using electroscope confirmation cable first, and institute There are constructing operation personnel to wear insulating glove, insulation clothing and insulated shoes when carrying out constructing operation, cable leakage is avoided to hurt sb.'s feelings Accident.
CN201811041774.3A 2018-09-07 2018-09-07 Method for ensuring safe transfer of sewage treatment plant cable without power failure Active CN109217185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811041774.3A CN109217185B (en) 2018-09-07 2018-09-07 Method for ensuring safe transfer of sewage treatment plant cable without power failure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811041774.3A CN109217185B (en) 2018-09-07 2018-09-07 Method for ensuring safe transfer of sewage treatment plant cable without power failure

Publications (2)

Publication Number Publication Date
CN109217185A true CN109217185A (en) 2019-01-15
CN109217185B CN109217185B (en) 2020-11-06

Family

ID=64987093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811041774.3A Active CN109217185B (en) 2018-09-07 2018-09-07 Method for ensuring safe transfer of sewage treatment plant cable without power failure

Country Status (1)

Country Link
CN (1) CN109217185B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110783878A (en) * 2019-10-12 2020-02-11 福建省鸿官通信工程有限公司 Optical cable migration method
CN111585239A (en) * 2020-05-26 2020-08-25 中国建筑第八工程局有限公司 Construction method for airport pipeline relocation and transformation without stopping navigation
CN116742532A (en) * 2023-06-29 2023-09-12 中建八局第一建设有限公司 Temporary power cable landfill method and auxiliary device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201018221Y (en) * 2007-02-02 2008-02-06 余晓峰 Device for electric network live operation
CN103132710A (en) * 2011-12-01 2013-06-05 吉林省电力有限公司辽源供电公司 Method of electriferous integral moving of iron tower of 500-kV electric transmission line
CN104319698A (en) * 2014-11-10 2015-01-28 国网河南省电力公司济源供电公司 Method for handling breakage of insulation sleeve of cable head rapidly
CN106337688A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Sleeved inner liner reinforcing structure for electrical operation of cable tunnel and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201018221Y (en) * 2007-02-02 2008-02-06 余晓峰 Device for electric network live operation
CN103132710A (en) * 2011-12-01 2013-06-05 吉林省电力有限公司辽源供电公司 Method of electriferous integral moving of iron tower of 500-kV electric transmission line
CN104319698A (en) * 2014-11-10 2015-01-28 国网河南省电力公司济源供电公司 Method for handling breakage of insulation sleeve of cable head rapidly
CN106337688A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Sleeved inner liner reinforcing structure for electrical operation of cable tunnel and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
侯树山: "高压电缆带电移位技术保护措施探讨", 《科技信息》 *
沈黎明: "《电力电缆施工、运行与维护》", 31 January 2013, 中国电力出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110783878A (en) * 2019-10-12 2020-02-11 福建省鸿官通信工程有限公司 Optical cable migration method
CN110783878B (en) * 2019-10-12 2020-12-08 福建省鸿官通信工程有限公司 Optical cable migration method
CN111585239A (en) * 2020-05-26 2020-08-25 中国建筑第八工程局有限公司 Construction method for airport pipeline relocation and transformation without stopping navigation
CN111585239B (en) * 2020-05-26 2021-02-19 中国建筑第八工程局有限公司 Construction method for airport pipeline relocation and transformation without stopping navigation
CN116742532A (en) * 2023-06-29 2023-09-12 中建八局第一建设有限公司 Temporary power cable landfill method and auxiliary device

Also Published As

Publication number Publication date
CN109217185B (en) 2020-11-06

Similar Documents

Publication Publication Date Title
CN109217185A (en) The method for not powering off safety transfer for ensuring sewage treatment plant's cable
CN109024674A (en) Underground pipe gallery passes through protection underground utilities construction method
CN111156006A (en) Construction method for shield underpass of dangerous pipeline
CN107574834A (en) A kind of old basic transformation reinforcement means of power machine
CN105546278A (en) Method for protecting underground pipeline during pipe ditch excavation
CN104577364A (en) Small-resistance-value grounding grid of large device and design construction method
CN105862711B (en) A kind of hydraulic reclamation device and method for being used to cover mud sealing stabilization by drainage
CN111764373A (en) Construction method of underground continuous wall under condition of non-removable underground barrier
CN210766953U (en) Urban underground river dredging system
CN203895933U (en) Cable protective sleeve
CN107061865B (en) A kind of new old pipeline of sewage treatment plant's heavy caliber does not stop production the method for meeting and discussing
CN209452010U (en) A kind of mobile crushing station of driven by two energy sources
CN209654048U (en) A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN206997267U (en) Pipeline sundries cleaning device
CN106565021B (en) Pipeline construction method for ecological wetland
CN110756570A (en) Subsurface excavation remediation method for deep polluted soil
CN109914319A (en) A kind of construction site fugitive dust control method based on BIM technology
CN219033359U (en) Underwater excavator
CN214798382U (en) Gate-type waterproof switch box capable of being embedded in end of beam-making pedestal
Cai et al. Innovation and Creativity Proposal for Sha Tin Water Treatment Works in Hong Kong
CN109826643B (en) Pre-buried structure of drainage tunnel shield tunnel portal
CN216075299U (en) Novel equipment is collected to cable pit filler
CN204059330U (en) A kind of channel climbing rolling machine
Gao A emergency power equipment design of direct current full hydraulic tunnel for coal mine
CN201466640U (en) Protection plate of cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 610000 No. 147 Qintai Road, Qingyang District, Chengdu City, Sichuan Province

Applicant after: Chengdu Construction Industry Equipment Installation Co., Ltd.