CN109209401A - Shield tunnel inner circular support system and its construction method based on brace pre axial force - Google Patents

Shield tunnel inner circular support system and its construction method based on brace pre axial force Download PDF

Info

Publication number
CN109209401A
CN109209401A CN201811137662.8A CN201811137662A CN109209401A CN 109209401 A CN109209401 A CN 109209401A CN 201811137662 A CN201811137662 A CN 201811137662A CN 109209401 A CN109209401 A CN 109209401A
Authority
CN
China
Prior art keywords
steel plate
fashioned iron
arc
support system
screw jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811137662.8A
Other languages
Chinese (zh)
Inventor
杨小兵
马晓波
戴志仁
王博
王立新
贾少春
雷永生
向阳
王崇明
王天明
高志宏
王家乐
王洪波
张海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201811137662.8A priority Critical patent/CN109209401A/en
Publication of CN109209401A publication Critical patent/CN109209401A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to shield tunnel inner circular support system and its construction method based on brace pre axial force, structure includes the fashioned iron and steel plate group zoarium of shield duct piece annular, fashioned iron and the fit support that shield duct piece is provided perpendicular between shield duct piece of steel plate group;Fashioned iron and steel plate group zoarium circumferential direction are divided into more piece, and every section includes arc-shaped fashioned iron, are connected between each pitch circle arc fashioned iron by junction steel plate, and many places screw jack is arranged in joining place.The present invention applies pressure by screw jack, it is transmitted to support, it is evenly distributed on stress on section of jurisdiction, it forms continuous, rigidity, have prestressed integrated support system, to reach to section of jurisdiction formed it is effective reinforce support purpose, prevent segment deformation cracking failure caused by prestressing force caused by the aperture of section of jurisdiction is concentrated at service channel or even safety accident occur.

Description

Shield tunnel inner circular support system and its construction method based on brace pre axial force
Technical field
The invention belongs to Tunnel Engineering technical field of structures, and in particular to a kind of shield tunnel inner circle based on brace pre axial force Shape support system and its construction method.
Background technique
With the continuous development of urban construction, also increasingly increase severely to urban rail transit construction demand.Since project's earlier stage is controlled Moved in earth clearance, pipeline change, the factors such as traffic data process influence, often restrict completion time of project in later period, the contact of tunnel accessory structure The construction of laying a railway track of channel and track is generally existing the case where there are cross-operation.It is needed before Freezing Method for Cross-passage Construction to the place and adjacent of punching Position section of jurisdiction carries out hole inner support, and to prevent segment deformation, cracking failure or even safety accident occurs.Tunnel inner support generallys use Conventional " well " font bracing members, slowly, prestress application is difficult to operate, and dimensional footprint is big, installation for this support installation Personnel are current inconvenient afterwards, and Construction traffic is impassable, and track laying and its construction operation can not be carried out during Freezing Method for Cross-passage Construction, Seriously affect the duration.Therefore, conventional " well " font bracing members are no longer applicable in, and need to be adjusted correspondingly.To guarantee contact Channel is constructed while being carried out with laying a railway track, as soon as giving Construction traffic of laying a railway track " construction channel ", round inner support is particularly important.
Summary of the invention
The object of the present invention is to provide a kind of shield tunnel inner circular support system and its construction party based on brace pre axial force Method, the assembly being welded into using fashioned iron and steel plate by junction steel plate and are bolted, then applying pressure by jack will It forms continuous, rigidity, has prestressed integrated support system, effectively reinforces support purpose to be formed to section of jurisdiction, prevents Segment deformation cracking failure or even generation safety accident caused by only prestressing force caused by the aperture of section of jurisdiction is concentrated at service channel.
The technical scheme adopted by the invention is as follows:
Shield tunnel inner circular support system based on brace pre axial force, it is characterised in that:
Fashioned iron and steel plate group including shield duct piece annular are fit, are provided between fashioned iron and steel plate group zoarium and shield duct piece Perpendicular to the support of shield duct piece;
Fashioned iron and steel plate group zoarium circumferential direction are divided into more piece, and every section includes arc-shaped fashioned iron, pass through between each pitch circle arc fashioned iron Junction steel plate linking, and many places screw jack is set in joining place.
Arc-shaped fashioned iron in fashioned iron and steel plate group zoarium includes inner arc steel plate and the outer arc inside and outside web and web Steel plate;
The inner arc steel plate of each pitch circle arc fashioned iron passes through inner arc steel plate junction steel plate and the fixed linking of bolt on the inside of inner arc steel plate;
The outer arc steel plate junction steel plate and bolt that the outer arc steel plate of each pitch circle arc fashioned iron passes through outer arc steel plate inside, web two sides Fixed linking;
The fixed linking of web junction steel plate and bolt that the web of each pitch circle arc fashioned iron passes through two sides.
At interval of screw jack circumferential at several pitch circle arc fashioned iron setting one, the circular arc adjacent with screw jack Shape fashioned iron end face is provided with end steel plate, and screw jack both ends are fixed on the steel plate of end.
It is fixed on the inside of arc-shaped fashioned iron inner arc steel plate at screw jack by screw jack junction steel plate and bolt Linking.
The web two sides of arc-shaped fashioned iron are evenly arranged the radial reinforcement vertical with web in fashioned iron and steel plate group zoarium Floor.
Support includes the radial support on the inside of bottom plate and bottom plate, and bottom plate abuts shield duct piece inner wall, and is provided with rubber pad Piece.
Fashioned iron and steel plate group zoarium circumferential direction are divided into ten sections, and each section is connected by junction steel plate to be fixed.
At screw jack circumferentially disposed three.
More Pin are longitudinally arranged in parallel along tunnel for fashioned iron and steel plate group zoarium, are done between each Pin by angle steel longitudinally connected.
The construction method of shield tunnel inner circular support system based on brace pre axial force as mentioned, it is characterised in that:
It is realized by following steps:
Step 1: processing:
Blanking is carried out according to tunnel clearance and actual needs size merogenesis, makes web, the outer arc steel of fashioned iron and steel plate group zoarium Plate, inner arc steel plate, deep floor, end steel plate and support become ten piecemeals using welding;Each component process after Ground carries out examination assembling, assembles in tunnel after confirming the errorless number of size;Steel plate, section steel material are Q235B;Welding rod uses E43xx series welding rod, weld seam are continuous weld, and weld bead height is not less than 8mm;
Step 2: installation:
Wherein a nodal pattern steel and steel plate group zoarium it will be placed on tunnel arch bottom, center is overlapped with tunnel middle line;Rubber is encased inside under support Glue gasket is put into appropriate gasket according to gap difference between contact point and section of jurisdiction, makes each contact point uniform force;Successively from tunnel Bottom is symmetrically installed to top, with junction steel plate by the fixation of bolt 10 between each section, segment bolt and injected hole when installation It is auxiliarily fixed;After support installs, real three screw jack in top are started simultaneously at, prestressing force, each screw jack are applied Top power is uniformly arranged, the junction steel plate after prestressing force is met the requirements, at fixed screw jack;In circular support anchor ring and tunnel Axis keeps vertical;
Step 3: construction:
Angle steel is used to do in every tunnel between two Pin pre-loaded support struts longitudinally connected, to ensure the stability of prestress stent; Section of jurisdiction aperture is carried out after meeting the requirements, performs service channel, and construction of laying a railway track carries out therewith.
The invention has the following advantages that
1, the present invention is acted synergistically by fashioned iron and steel plate welding assembly+high-strength bolt+rubber sheet gasket+jack, is had Enough intensity, rigidity, globality and good secret patch performance, can sufficiently apply prestressing force, make in support system and section of jurisdiction Cambered surface is close to, and guarantees aperture section of jurisdiction and adjacent section of jurisdiction without moderate finite deformation.
2, after the installation of this support system, there are enough spaces to meet the current limit requirement of Construction traffic of laying a railway track, can guarantee paving The normal pass of rail Construction traffic, to the influence very little of lay a railway track construction and other construction operations.
3, the installation of this support system is simple, and it is convenient to remove, reusable, saves the duration, investment reduction, conducive to construction Smoothly implement.
4, this support system can be applied in the protection of other shield tunnel projects, be with a wide range of applications.
Detailed description of the invention
Fig. 1 is round steelframe support cross-sectional view of the invention;
Fig. 2 is A connecting node detail drawing of the invention;
Fig. 3 is A connecting node detail drawing C-C sectional view of the invention;
Fig. 4 is B connecting node detail drawing of the invention.
In figure, 1- shield duct piece, 2- web, 3- outer arc steel plate, 4- inner arc steel plate, 5- deep floor, the end 6- steel plate, 7- Outer arc steel plate junction steel plate, 8- web junction steel plate, 9- inner arc steel plate junction steel plate, 10- bolt, 11- support, 12- rubber pad Piece, 13- screw jack junction steel plate, 14- screw jack.
Specific embodiment
The present invention will be described in detail With reference to embodiment.
The present invention relates to a kind of shield tunnel inner circular support system based on brace pre axial force utilizes fashioned iron and steel plate welding At assembly, by junction steel plate and being bolted, then by jack is formed continuous, rigidity, have it is prestressed Integrated support system supports purpose to reach and form effective reinforce to section of jurisdiction.
Structure specifically includes the fashioned iron and steel plate group zoarium of 1 annular of shield duct piece, fashioned iron and steel plate group zoarium and shield The support 11 of shield duct piece 1 is provided perpendicular between section of jurisdiction 1.Fashioned iron and steel plate group zoarium circumferential direction are divided into more piece, and every section wraps Arc-shaped fashioned iron is included, is connected between each pitch circle arc fashioned iron by junction steel plate, and many places screw jack is set in joining place 14。
Arc-shaped fashioned iron in fashioned iron and steel plate group zoarium includes inner arc steel plate 4 inside and outside web 2 and web 2 and outer Arc steel plate 3;The inner arc steel plate junction steel plate 9 and bolt 10 that the inner arc steel plate 4 of each pitch circle arc fashioned iron passes through 4 inside of inner arc steel plate Fixed linking;The outer arc steel plate 3 of each pitch circle arc fashioned iron connects steel by the outer arc steel plate of 3 inside of outer arc steel plate, 2 two sides of web Plate 7 and the fixed linking of bolt 10;The web 2 of each pitch circle arc fashioned iron is fixed by the web junction steel plate 8 and bolt 10 of two sides Linking.
It is adjacent with screw jack 14 at interval of screw jack 14 circumferential at several pitch circle arc fashioned iron setting one Arc-shaped fashioned iron end face is provided with end steel plate 6, and 14 both ends of screw jack are fixed on end steel plate 6.Screw jack 14 Pass through screw jack junction steel plate 13 and the fixed linking of bolt 10 on the inside of the arc-shaped fashioned iron inner arc steel plate 4 at place.
2 two sides of web of arc-shaped fashioned iron are evenly arranged the radial direction vertical with web 2 in fashioned iron and steel plate group zoarium Deep floor 5.
Support 11 includes the radial support on the inside of bottom plate and bottom plate, and bottom plate abuts 1 inner wall of shield duct piece, and is provided with rubber Gasket 12.
Fashioned iron and steel plate group zoarium circumferential direction are divided into ten sections, and each section is connected by junction steel plate to be fixed.14 ring of screw jack To arranging at three.
More Pin are longitudinally arranged in parallel along tunnel for fashioned iron and steel plate group zoarium, are done between each Pin by angle steel longitudinally connected.
The present invention applies pressure by screw jack 14, is transmitted to support 11, is evenly distributed on stress on section of jurisdiction, rubber Glue gasket 12 can be concentrated to avoid stress and cause segment damage.
The construction method of the above-mentioned shield tunnel inner circular support system based on brace pre axial force, is realized by following steps:
Step 1: processing:
Blanking is carried out according to tunnel clearance and actual needs size merogenesis, makes web 2, the outer arc steel of fashioned iron and steel plate group zoarium Plate 3, inner arc steel plate 4, deep floor 5, end steel plate 6 and support 11 become ten piecemeals using welding;Each component processing Examination assembling is carried out on ground after complete, is assembled in tunnel after confirming the errorless number of size;Steel plate, section steel material are Q235B, The related standard of country should be met in relation to chemical component and mechanical property;Welding rod uses E43xx series welding rod, and weld seam is sequential welding Seam, weld bead height are not less than 8mm;
Step 2: installation:
Wherein a nodal pattern steel and steel plate group zoarium it will be placed on tunnel arch bottom, center is overlapped with tunnel middle line;It is encased inside under support 11 Rubber sheet gasket 12 is put into appropriate gasket according to gap difference between contact point and section of jurisdiction, makes each contact point uniform force;Successively from Tunnel bottom is symmetrically installed to top, with junction steel plate by the fixation of bolt 10 between each section, segment bolt and note when installation Slurry hole is auxiliarily fixed;After support installs, real three screw jack 14 in top are started simultaneously at, prestressing force, each spiral are applied Jack 14 pushes up power and is uniformly arranged, the junction steel plate after prestressing force is met the requirements, at fixed screw jack 14;Circular support ring Face is vertical with the holding of tunnel central axes;
Step 3: construction:
Angle steel is used to do in every tunnel between two Pin pre-loaded support struts longitudinally connected, to ensure the stability of prestress stent; Section of jurisdiction aperture is carried out after meeting the requirements, performs service channel, and construction of laying a railway track carries out therewith.
This support system of the present invention is both economical applicable in shield tunnel application, and has installation letter It is single, reusable, highly-safe, save duration, investment reduction the advantages of.Freezing Method for Cross-passage Construction can effectively be solved and intersection of laying a railway track Space occupation problem when operation, Freezing Method for Cross-passage Construction is not interfere with each other with laying a railway track, to save the whole duration.In addition, this circle Bracing members system is also applied in the protection of other shield tunnel projects.
The contents of the present invention are not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, all are covered by the claims of the invention.

Claims (10)

1. the shield tunnel inner circular support system based on brace pre axial force, it is characterised in that:
Fashioned iron and steel plate group including shield duct piece (1) annular are fit, between fashioned iron and steel plate group zoarium and shield duct piece (1) It is provided perpendicular to the support (11) of shield duct piece (1);
Fashioned iron and steel plate group zoarium circumferential direction are divided into more piece, and every section includes arc-shaped fashioned iron, pass through between each pitch circle arc fashioned iron Junction steel plate linking, and many places screw jack (14) are set in joining place.
2. the shield tunnel inner circular support system according to claim 1 based on brace pre axial force, it is characterised in that:
Arc-shaped fashioned iron in fashioned iron and steel plate group zoarium include inner arc steel plate (4) inside and outside web (2) and web (2) and Outer arc steel plate (3);
The inner arc steel plate (4) of each pitch circle arc fashioned iron passes through the inner arc steel plate junction steel plate (9) and bolt on the inside of inner arc steel plate (4) (10) fixed linking;
The outer arc steel plate connection that the outer arc steel plate (3) of each pitch circle arc fashioned iron passes through outer arc steel plate (3) inside, web (2) two sides Steel plate (7) and the fixed linking of bolt (10);
The fixed linking of web junction steel plate (8) and bolt (10) that the web (2) of each pitch circle arc fashioned iron passes through two sides.
3. the shield tunnel inner circular support system according to claim 2 based on brace pre axial force, it is characterised in that:
It is adjacent with screw jack (14) at interval of screw jack (14) circumferential at several pitch circle arc fashioned iron setting one Arc-shaped fashioned iron end face is provided with end steel plate (6), and screw jack (14) both ends are fixed on end steel plate (6).
4. the shield tunnel inner circular support system according to claim 3 based on brace pre axial force, it is characterised in that:
Pass through screw jack junction steel plate (13) and spiral shell on the inside of arc-shaped fashioned iron inner arc steel plate (4) at screw jack (14) The fixed linking of bolt (10).
5. the shield tunnel inner circular support system according to claim 1 based on brace pre axial force, it is characterised in that:
Web (2) two sides of arc-shaped fashioned iron are evenly arranged adding for the radial direction vertical with web (2) in fashioned iron and steel plate group zoarium Strong floor (5).
6. the shield tunnel inner circular support system according to claim 1 based on brace pre axial force, it is characterised in that:
Support (11) includes the radial support on the inside of bottom plate and bottom plate, and bottom plate abuts shield duct piece (1) inner wall, and is provided with rubber Gasket (12).
7. the shield tunnel inner circular support system according to claim 1 based on brace pre axial force, it is characterised in that:
Fashioned iron and steel plate group zoarium circumferential direction are divided into ten sections, and each section is connected by junction steel plate to be fixed.
8. the shield tunnel inner circular support system according to claim 7 based on brace pre axial force, it is characterised in that:
At screw jack (14) circumferentially disposed three.
9. the shield tunnel inner circular support system according to claim 1 based on brace pre axial force, it is characterised in that:
More Pin are longitudinally arranged in parallel along tunnel for fashioned iron and steel plate group zoarium, are done between each Pin by angle steel longitudinally connected.
10. the construction method of the shield tunnel inner circular support system based on brace pre axial force as described in claim 1, feature It is:
It is realized by following steps:
Step 1: processing:
Blanking is carried out according to tunnel clearance and actual needs size merogenesis, makes web (2), the outer arc of fashioned iron and steel plate group zoarium Steel plate (3), inner arc steel plate (4), deep floor (5), end steel plate (6) and support (11), become ten points using welding Block;Each component on ground carries out examination assembling after processing, and assembles in tunnel after confirming the errorless number of size;Steel plate, structural section Material is Q235B;Welding rod uses E43xx series welding rod, and weld seam is continuous weld, and weld bead height is not less than 8mm;
Step 2: installation:
Wherein a nodal pattern steel and steel plate group zoarium it will be placed on tunnel arch bottom, center is overlapped with tunnel middle line;Support (11) underlay Enter rubber sheet gasket (12), appropriate gasket is put into according to gap difference between contact point and section of jurisdiction, makes each contact point uniform force;According to It is secondary to be symmetrically installed from tunnel bottom to top, with junction steel plate by the fixation of bolt 10 between each section, segment bolt when installation And injected hole is auxiliarily fixed;After support installs, real three screw jack (14) in top are started simultaneously at, apply prestressing force, often A screw jack (14) top power is uniformly arranged, the junction steel plate after prestressing force is met the requirements, at fixed screw jack (14); Circular support anchor ring is vertical with the holding of tunnel central axes;
Step 3: construction:
Angle steel is used to do in every tunnel between two Pin pre-loaded support struts longitudinally connected, to ensure the stability of prestress stent; Section of jurisdiction aperture is carried out after meeting the requirements, performs service channel, and construction of laying a railway track carries out therewith.
CN201811137662.8A 2018-09-28 2018-09-28 Shield tunnel inner circular support system and its construction method based on brace pre axial force Pending CN109209401A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811137662.8A CN109209401A (en) 2018-09-28 2018-09-28 Shield tunnel inner circular support system and its construction method based on brace pre axial force

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811137662.8A CN109209401A (en) 2018-09-28 2018-09-28 Shield tunnel inner circular support system and its construction method based on brace pre axial force

Publications (1)

Publication Number Publication Date
CN109209401A true CN109209401A (en) 2019-01-15

Family

ID=64981930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811137662.8A Pending CN109209401A (en) 2018-09-28 2018-09-28 Shield tunnel inner circular support system and its construction method based on brace pre axial force

Country Status (1)

Country Link
CN (1) CN109209401A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110030005A (en) * 2019-03-29 2019-07-19 中铁第一勘察设计院集团有限公司 The light-duty guarantor's circle support system of shield tunnel and its construction method
CN110159300A (en) * 2019-04-29 2019-08-23 同济大学 A kind of shield tunnel repairing and reinforcement platform and reinforcement means
CN110348117A (en) * 2019-07-10 2019-10-18 宁波六希格码建筑科技有限公司 A kind of negative ring structure of steel pipe sheet and its optimization design
CN110953000A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Temporary prestress supporting mechanism of shield tunnel and construction method
CN110952987A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Construction method for side-through bridge pile of stacked porous subway tunnel
CN112502717A (en) * 2020-11-30 2021-03-16 中铁二十局集团第五工程有限公司 Excavation construction method for contact channel between shield zones of water-rich sand layer
CN112502734A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Construction method of shield interval contact channel of water-rich sand layer
CN112502731A (en) * 2020-11-30 2021-03-16 中铁二十局集团第五工程有限公司 Water-rich sand layer shield interval contact channel stratum pre-reinforcing structure and method
CN112502733A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Water-rich sand layer shield interval connection channel hole entering construction method
CN112502732A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Construction method of shield tunnel of water-rich sand layer
CN112523783A (en) * 2019-09-17 2021-03-19 安徽理工大学 Quick assembly type support bracket and support method
CN113944487A (en) * 2021-10-27 2022-01-18 浙江工业大学 Shield constructs contact passageway section of jurisdiction bearing structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120063257A (en) * 2010-12-07 2012-06-15 한국건설기술연구원 Segment structure of shield tunnel making use of a prestressed steel wire and segment lining system fixing the segment therewith
CN206111222U (en) * 2016-08-27 2017-04-19 中国建筑第六工程局有限公司 A annular prestressing force support for preventing circular tunnel deformation of side opening
CN107191210A (en) * 2017-06-16 2017-09-22 中铁第勘察设计院集团有限公司 Shield tunnel anti-floating system and its construction method based on prestress anchorage cable
CN206942782U (en) * 2017-04-25 2018-01-30 中国铁路设计集团有限公司 Hole tunnel inner supporting structure under a kind of overlapping shield section up and down
CN108222978A (en) * 2018-03-08 2018-06-29 中铁建大桥工程局集团第四工程有限公司 A kind of metro shield driving freezes synchronization job belt stress stent system and installation method with service channel
CN209040834U (en) * 2018-09-28 2019-06-28 中铁第一勘察设计院集团有限公司 A kind of shield tunnel inner circular support system based on brace pre axial force

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120063257A (en) * 2010-12-07 2012-06-15 한국건설기술연구원 Segment structure of shield tunnel making use of a prestressed steel wire and segment lining system fixing the segment therewith
CN206111222U (en) * 2016-08-27 2017-04-19 中国建筑第六工程局有限公司 A annular prestressing force support for preventing circular tunnel deformation of side opening
CN206942782U (en) * 2017-04-25 2018-01-30 中国铁路设计集团有限公司 Hole tunnel inner supporting structure under a kind of overlapping shield section up and down
CN107191210A (en) * 2017-06-16 2017-09-22 中铁第勘察设计院集团有限公司 Shield tunnel anti-floating system and its construction method based on prestress anchorage cable
CN108222978A (en) * 2018-03-08 2018-06-29 中铁建大桥工程局集团第四工程有限公司 A kind of metro shield driving freezes synchronization job belt stress stent system and installation method with service channel
CN209040834U (en) * 2018-09-28 2019-06-28 中铁第一勘察设计院集团有限公司 A kind of shield tunnel inner circular support system based on brace pre axial force

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110030005B (en) * 2019-03-29 2023-09-15 中铁第一勘察设计院集团有限公司 Light circular protection supporting system for shield tunnel and construction method thereof
CN110030005A (en) * 2019-03-29 2019-07-19 中铁第一勘察设计院集团有限公司 The light-duty guarantor's circle support system of shield tunnel and its construction method
CN110159300A (en) * 2019-04-29 2019-08-23 同济大学 A kind of shield tunnel repairing and reinforcement platform and reinforcement means
CN110348117A (en) * 2019-07-10 2019-10-18 宁波六希格码建筑科技有限公司 A kind of negative ring structure of steel pipe sheet and its optimization design
CN110348117B (en) * 2019-07-10 2023-10-31 宁波六希格码建筑科技有限公司 Steel pipe sheet negative ring structure and optimal design method thereof
CN112523783A (en) * 2019-09-17 2021-03-19 安徽理工大学 Quick assembly type support bracket and support method
CN112523783B (en) * 2019-09-17 2023-01-06 安徽理工大学 Rapid assembled support bracket and support method
CN110953000A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Temporary prestress supporting mechanism of shield tunnel and construction method
CN110952987A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Construction method for side-through bridge pile of stacked porous subway tunnel
CN110953000B (en) * 2019-12-03 2021-05-07 济南轨道交通集团有限公司 Temporary prestress supporting mechanism of shield tunnel and construction method
CN112502733A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Water-rich sand layer shield interval connection channel hole entering construction method
CN112502732A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Construction method of shield tunnel of water-rich sand layer
CN112502731A (en) * 2020-11-30 2021-03-16 中铁二十局集团第五工程有限公司 Water-rich sand layer shield interval contact channel stratum pre-reinforcing structure and method
CN112502734A (en) * 2020-11-30 2021-03-16 中铁二十局集团有限公司 Construction method of shield interval contact channel of water-rich sand layer
CN112502717A (en) * 2020-11-30 2021-03-16 中铁二十局集团第五工程有限公司 Excavation construction method for contact channel between shield zones of water-rich sand layer
CN113944487A (en) * 2021-10-27 2022-01-18 浙江工业大学 Shield constructs contact passageway section of jurisdiction bearing structure

Similar Documents

Publication Publication Date Title
CN109209401A (en) Shield tunnel inner circular support system and its construction method based on brace pre axial force
CN106088780A (en) The cast-in-place concrete pylon of pre-made void reinforcement bar truss mould plate and construction method thereof
CN112343233A (en) Round roof space pipe truss structure and construction method thereof
CN104594618A (en) Hoop type disassembling operating platform of blast furnace granulated slag steam exhausting barrel
CN204716257U (en) Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction
CN209040834U (en) A kind of shield tunnel inner circular support system based on brace pre axial force
CN108222978A (en) A kind of metro shield driving freezes synchronization job belt stress stent system and installation method with service channel
CN208815426U (en) Steel construction combined platform suitable for Single column pier bearing replacement
CN110242313B (en) Tunnel portal sealing safety structure and construction method
JPH09221760A (en) Temporary coffering structure and method of construction thereof
CN207892631U (en) A kind of metro shield driving freezes synchronization job belt stress stent system with service channel
CN115045686B (en) Method for reinforcing subway shield tunnel by corrugated steel
CN212054717U (en) Circular support system in shield tunnel of contact passageway
JPH08184289A (en) Structure of subway station and construction thereof
CN101749035B (en) Ready-packaged arch timbering steel frame of round tunnel urgent repairing
CN205313984U (en) Heavy steel pipe strutting arrangement of assembled
CN111119948B (en) Construction method of rock burst prevention supporting structure of high-ground-stress hard rock tunnel
CN102562098A (en) Tunnel steel temporary inverted arch with rapid assembly and disassembly
CN113216990A (en) Starting and rapid slag discharging method in limited space of shield tunneling machine
CN107143353B (en) Concrete supporting construction in high temperature tunnel
CN219195981U (en) Easily dismantle combination shaped steel inner support
CN112922641A (en) Circular prestress support system for subway communication channel construction and assembling method
CN205604782U (en) Prefabricate assembled multilayer parking building steel construction system entirely
CN205329554U (en) A diagonal brace for heavy steel pipe strutting arrangement of assembled
CN214590332U (en) Rail-passing pipeline system in railway jacking construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination