CN109208799A - The dedicated cast-in-place reserved plate hole internal model of early demoulding construction method in wafer board structure hole - Google Patents

The dedicated cast-in-place reserved plate hole internal model of early demoulding construction method in wafer board structure hole Download PDF

Info

Publication number
CN109208799A
CN109208799A CN201811265091.6A CN201811265091A CN109208799A CN 109208799 A CN109208799 A CN 109208799A CN 201811265091 A CN201811265091 A CN 201811265091A CN 109208799 A CN109208799 A CN 109208799A
Authority
CN
China
Prior art keywords
plate
arc
cast
hole
upper cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811265091.6A
Other languages
Chinese (zh)
Other versions
CN109208799B (en
Inventor
刘松涛
顾彦杰
唐士飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
NANTONG CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical NANTONG CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201811265091.6A priority Critical patent/CN109208799B/en
Publication of CN109208799A publication Critical patent/CN109208799A/en
Application granted granted Critical
Publication of CN109208799B publication Critical patent/CN109208799B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses the dedicated cast-in-place reserved plate hole internal model of early demoulding construction method, every mold circumferential direction in a kind of wafer board structure hole are assembled by 3 arc formworks, in which: 2 arc length 474mm, 1 arc length 100mm;If upper and lower twice annular transverse flange plate, each piece of arc formwork both sides set vertical flanged plate edge sealing, are bolted between three pieces of arc formworks by vertical flanged plate;Upper cover plate outer diameter is 30mm bigger than aperture by design requirement, and edges of boards milling is bolted at 45o chamfering, upper cover plate with lower part steel mould tool;Two square tube beams are welded on upper cover plate, for adjusting mold installed height mark and levelness.The present invention is easy for construction, construction quality is good.

Description

The dedicated cast-in-place reserved plate hole internal model of early demoulding construction method in wafer board structure hole
The application is application number: 201710462023.8, the applying date: 2017-06-19, title " clear-water concrete wafer board The divisional application of early demoulding construction method in structure hole ".
Technical field
The present invention relates to demoulding construction methods early in a kind of clear-water concrete wafer board structure hole.
Background technique
Wafer board refers to Large area reinforced concrete structure floor plates with holes, constructs as high-level cleaning shop return air, It is required with meeting the clean of general electronic workshop, can be applied in the very big workshop of the investments such as photoelectricity, electronic chip.Usually In the case of wafer board be with FRP(fiber glass epoxy) do plate bed die and hole interior bucket mould is poured and smash, bucket template after the completion of pouring It is not removed as bed die and casement.
Due to technique or fire-fighting requirements, wafer board need to use clear-water concrete structure for some plant designings, and when construction does not adopt It needs to remove with expoxy glass steel form, or using FRP template.FRP(fiber glass epoxy) template strength is high, construct thickness It is thin, should not demoulding be used in turn.Clear-water concrete waffle plate bed die uses multi-plywood template under normal conditions, and hole internal model is adopted Use steel form.And when adopting in hole with steel form, how to accomplish quickly to remove, not only constructing operation is convenient, but also improves casement It is used in turn speed, is to ensure that the construction quality, construction speed, the key of save the cost of wafer board structure construction.
Summary of the invention
The purpose of the present invention is to provide in a kind of clear-water concrete wafer board structure hole easy for construction, construction quality is good Early demoulding construction method.
The technical solution of the invention is as follows:
Early demoulding construction method in a kind of clear-water concrete wafer board structure hole, it is characterized in that: including the following steps:
1) after the completion of wafer board unit plate lifts, there are cast-in-site stripe between two pieces of prefabricated wafer boards, cast-in-site stripe is equipped with China Husband's plate preformed hole, specification and arrangement are consistent with prefabricated board;
2) after prefabricated wafer board lifting is completed, reinforcing bar in preformed groove is bound, cast-in-place reserved plate hole internal model is propped up, then pours cast-in-place Band concrete removes hole inner template after waiting concrete to have some strength;
The cast-in-place reserved plate hole internal model is by structure steel fabrication, and every mold circumferential direction is assembled by 3 arc formworks, in which: 2 Piece arc length 474mm, 1 arc length 100mm;If upper and lower twice annular transverse flange plate, each piece of arc formwork both sides set vertical method Blue plate edge sealing is bolted between three pieces of arc formworks by vertical flanged plate;Upper cover plate outer diameter is bigger than aperture by design requirement 30mm, edges of boards milling are bolted at 45o chamfering, upper cover plate with lower part steel mould tool;Two square tube cross are welded on upper cover plate Beam, for adjusting mold installed height mark and levelness;
3) 1 piece of 3 arc formwork China and foreign countries surface arc length 100mm, wedge shaped shape, interior annular transverse flange plate arc length 125mm, vertical flanged plate and arc radial line are dismantled convenient for piece template when demoulding into drum at 27.09o angle.
Upper cover plate side milling at 15*15mm 45o chamfering.
The present invention is easy for construction, construction quality is good.Entire mold is divided into three pieces composition, and wherein width is lesser a piece of in water The wedge shaped shape of flat cutting faces is convenient for assembly and disassembly, is tightened by vertical flanged plate with bolt between three sheet molds, just piece is closed Smoothly;
The smaller die blade of width is first torn open after the completion of concreting, because the die blade horizontal profile designs and produces wedgewise block, is torn open After the connection bolt for releasing vertical flanged plate when unloading, by die blade into hole direction gently agitate it is i.e. dismountable, when die blade is torn open After removing, another two panels mold can be easy to remove.
Three pieces bucket wall mould is fixed on entirety by lamina tecti, has not only met the requirement of design aperture chamfered edge, but also is capable of fixing three pieces mould Tool prevents from deforming;
The two horizontal square tubes welded on lamina tecti, the top mark height and sag of adjustable mold, and the fixed party can be passed through Pipe is to prevent die shift.
Entire mold is formed using welding for steel structure, and bolt is assembled, firm to be unlikely to deform, and is repeated turnover up to a hundred times and is not necessarily to Trimming;
Mold outer surface is handled by polishing, and concrete surface can reach the perception requirement of clear-water concrete after demoulding.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is the structural schematic diagram of the cast-in-place reserved plate hole internal model of the present invention.
Fig. 2 is the top view of Fig. 1.
Fig. 3 is wedge shape die blade structural map.
Specific embodiment
Early demoulding construction method in a kind of clear-water concrete wafer board structure hole, including the following steps:
1) after the completion of wafer board unit plate lifts, there are cast-in-site stripe between two pieces of prefabricated wafer boards, cast-in-site stripe is equipped with China Husband's plate preformed hole, specification and arrangement are consistent with prefabricated board;
2) after prefabricated wafer board lifting is completed, reinforcing bar in preformed groove is bound, cast-in-place reserved plate hole internal model is propped up, then pours cast-in-place Band concrete removes hole inner template after waiting concrete to have some strength;
For the cast-in-place reserved plate hole internal model by structure steel fabrication, every mold circumferential direction is assembled by 3 arc formworks, in which: Wherein 21,2 arc length are 474mm, another 13 arc length 100mm;If upper and lower twice annular transverse flange plate, each piece of arc formwork Both sides set vertical flanged plate edge sealing, are bolted between three pieces of arc formworks by vertical flanged plate;Upper cover plate outer diameter is by design It is required that 30mm bigger than aperture, edges of boards milling is bolted at 45o chamfering, upper cover plate with lower part steel mould tool;It is welded on upper cover plate Two square tube beams 4,5 are connect, for adjusting mold installed height mark and levelness;
3) 1 piece of 3 arc formwork China and foreign countries surface arc length 100mm, wedge shaped shape, interior annular transverse flange plate arc length 125mm, vertical flanged plate and arc radial line are dismantled convenient for piece template when demoulding into drum at 27.09o angle.
Upper cover plate side milling at 15*15mm 45o chamfering.

Claims (2)

1. the dedicated cast-in-place reserved plate hole internal model of early demoulding construction method in a kind of wafer board structure hole, it is characterized in that: the waffle Early demoulding construction method includes the following steps: in plate structure hole
1) after the completion of wafer board unit plate lifts, there are cast-in-site stripe between two pieces of prefabricated wafer boards, cast-in-site stripe is equipped with China Husband's plate preformed hole, specification and arrangement are consistent with prefabricated board;
2) after prefabricated wafer board lifting is completed, reinforcing bar in preformed groove is bound, cast-in-place reserved plate hole internal model is propped up, then pours cast-in-place Band concrete removes hole inner template after waiting concrete to have some strength;
Cast-in-place reserved plate hole internal model is by structure steel fabrication, and every mold circumferential direction is assembled by 3 arc formworks, in which: 2 arcs Long 474mm, 1 arc length 100mm;If upper and lower twice annular transverse flange plate, each piece of arc formwork both sides set vertical flanged plate Edge sealing is bolted between three pieces of arc formworks by vertical flanged plate;Upper cover plate outer diameter is 30mm bigger than aperture by design requirement, Edges of boards milling is bolted at 45o chamfering, upper cover plate with lower part steel mould tool;Two square tube beams are welded on upper cover plate, are used In adjustment mold installed height mark and levelness;1 piece of 3 arc formwork China and foreign countries surface arc length 100mm, wedge shaped shape, inside Annular transverse flange plate arc length 125mm, vertical flanged plate and arc radial line at 27.09o angle, when being convenient for demoulding the piece template to Disassembly in drum.
2. the dedicated cast-in-place reserved plate hole internal model of early demoulding construction method in wafer board structure hole according to claim 1, Be characterized in: upper cover plate side milling at 15*15mm 45o chamfering.
CN201811265091.6A 2017-06-19 2017-06-19 Construction method for early formwork removal in structure hole of waffle slab Active CN109208799B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811265091.6A CN109208799B (en) 2017-06-19 2017-06-19 Construction method for early formwork removal in structure hole of waffle slab

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710462023.8A CN107060173B (en) 2017-06-19 2017-06-19 Early demoulding construction method in clear-water concrete wafer board structure hole
CN201811265091.6A CN109208799B (en) 2017-06-19 2017-06-19 Construction method for early formwork removal in structure hole of waffle slab

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710462023.8A Division CN107060173B (en) 2017-06-19 2017-06-19 Early demoulding construction method in clear-water concrete wafer board structure hole

Publications (2)

Publication Number Publication Date
CN109208799A true CN109208799A (en) 2019-01-15
CN109208799B CN109208799B (en) 2020-05-19

Family

ID=59594186

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201811265091.6A Active CN109208799B (en) 2017-06-19 2017-06-19 Construction method for early formwork removal in structure hole of waffle slab
CN201710462023.8A Active CN107060173B (en) 2017-06-19 2017-06-19 Early demoulding construction method in clear-water concrete wafer board structure hole

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201710462023.8A Active CN107060173B (en) 2017-06-19 2017-06-19 Early demoulding construction method in clear-water concrete wafer board structure hole

Country Status (1)

Country Link
CN (2) CN109208799B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112092154A (en) * 2019-06-17 2020-12-18 陕西晟泰源水泥制品有限公司 Prefabricated inspection well preformed hole forming device and forming method
CN112681382A (en) * 2021-01-13 2021-04-20 郑州美东工程科技有限公司 Template connection assembly for working well construction

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203834627U (en) * 2014-03-28 2014-09-17 中国一冶集团有限公司 Novel combined steel die plate for shaping water drainage well bore
CN206957201U (en) * 2017-06-19 2018-02-02 南通建工集团股份有限公司 Early form removal in clear-water concrete wafer board structure hole

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU727665B3 (en) * 1999-07-19 2000-12-21 Sydney Waffle Pods Pty Limited A void former for a waffle slab foundation
CA2321241A1 (en) * 2000-09-27 2002-03-27 Runhorn Pretech Engineering Co., Ltd. The prefabrication of the waffle slab in wafer foundry (fab)
CN103225397A (en) * 2013-04-08 2013-07-31 中国葛洲坝集团股份有限公司 Integral assembling and disassembling template and method for round well pipe concrete lining
CN105452577B (en) * 2013-06-05 2018-07-24 F·帕罗蒂 The method and apparatus for forming the template for concrete slab
CN205857715U (en) * 2016-07-14 2017-01-04 中国建筑第二工程局有限公司 Easy-to-detach type waffle slab cover plate and waffle slab structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203834627U (en) * 2014-03-28 2014-09-17 中国一冶集团有限公司 Novel combined steel die plate for shaping water drainage well bore
CN206957201U (en) * 2017-06-19 2018-02-02 南通建工集团股份有限公司 Early form removal in clear-water concrete wafer board structure hole

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112092154A (en) * 2019-06-17 2020-12-18 陕西晟泰源水泥制品有限公司 Prefabricated inspection well preformed hole forming device and forming method
CN112681382A (en) * 2021-01-13 2021-04-20 郑州美东工程科技有限公司 Template connection assembly for working well construction

Also Published As

Publication number Publication date
CN107060173B (en) 2018-12-11
CN107060173A (en) 2017-08-18
CN109208799B (en) 2020-05-19

Similar Documents

Publication Publication Date Title
CN109707173B (en) Construction method of assembly type laminated beam plate installation auxiliary device
CN203712840U (en) Small box girder concrete pouring mold
CN109989525B (en) Y-shaped composite supporting structure and construction method thereof
CN105952148A (en) Easy-to-demount inner aluminum form support system for narrow deformation joint and construction method
CN102383593A (en) Support formwork device and construction method for one-step formed flange concrete in kitchens and toilets
CN107143076A (en) A kind of Prefabricated stacking floor with side flanging and its construction method for being used to drop plate region
CN107060173B (en) Early demoulding construction method in clear-water concrete wafer board structure hole
CN107419904B (en) Chute mounting structure for concrete column pouring and using method thereof
CN111730738A (en) Prefabricated box girder diaphragm plate connecting structure and construction method thereof
CN106285002A (en) Cast-in-place walls difference of height tool-type hoisting die construction method
KR100402436B1 (en) The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack
KR100949785B1 (en) Mold for manufacturing PC beam
CN207177286U (en) Add region mould after fabricated shear wall is reserved
CN206957201U (en) Early form removal in clear-water concrete wafer board structure hole
CN211114798U (en) Kitchen and bathroom board descending and shaping die
CN202064636U (en) Closed stair formwork erecting device
CN111441576A (en) Method and structure for pouring concrete beam post-cast strip by adopting inflatable template
CN215969285U (en) Mould for manufacturing concrete fence plate
CN110761562A (en) Auxiliary tool for pouring concrete and using method
CN207244961U (en) A kind of Prefabricated stacking floor with side flanging for being used to drop plate region
CN214739890U (en) Steel form for concrete constructional column construction
CN201024666Y (en) Groove template for concrete casting for door window hole moulding
CN109914571B (en) Basement drainage ditch formwork system, pouring system and construction method
CN214725110U (en) Stair mould
CN210738077U (en) Waterproof reverse-edge aluminum alloy hanging die

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant