CN109193467A - Power transmission lines overhauling ladder - Google Patents
Power transmission lines overhauling ladder Download PDFInfo
- Publication number
- CN109193467A CN109193467A CN201811311469.1A CN201811311469A CN109193467A CN 109193467 A CN109193467 A CN 109193467A CN 201811311469 A CN201811311469 A CN 201811311469A CN 109193467 A CN109193467 A CN 109193467A
- Authority
- CN
- China
- Prior art keywords
- struts
- hook
- support rods
- power transmission
- transmission lines
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Ladders (AREA)
Abstract
The invention discloses power transmission lines overhauling ladders, power transmission lines overhauling ladder, including two support rods disposed in parallel, intermediate strut is alongst successively vertically connected between two support rods, the same end of two support rods is connected with cross-arm hook, two gag lever posts disposed in parallel are vertically connected between the other end of two support rods, two struts are connected on the gag lever post of cross-arm hook, the top of two struts is directed towards inclination, the angle between the plane where plane and two support rods where two struts is in 25-30 °, the supporting plate vertical with support rod is connected between the top of two struts, wire hook is equipped on supporting plate, wire hook can be rotated up 360 ° of sides.Maintenance ladder of the invention, conducting wire hanging point can rotate left and right, and are able to carry out left and right adjusting in this way and hang conducting wire on left direction or the right direction, so just can, solve the problems, such as that the problem of because of direction can only carry out the work in one direction.
Description
Technical field
The present invention relates to a kind of maintenance ladders, and in particular to power transmission lines overhauling ladder.
Background technique
Currently, transmission line of electricity in restringing insulator, needs to enter side of wire, all none is effective always
Tool, conventionally employed tool uses with significant limitation, can only be hung in one direction, so just
It can only carry out the work in one direction, the flexibility used is poor.
Summary of the invention
The technical problem to be solved by the present invention is to conventionally employed tools to use with significant limitation, can only
Hung, just can only be carried out the work in one direction so in one direction, the flexibility that uses difference, and it is an object of the present invention to provide
Power transmission lines overhauling ladder, conducting wire hanging point can rotate left and right, and are able to carry out left and right adjusting in this way and hang left direction or the right side
Conducting wire on edge direction, so just can, solve the problems, such as that the problem of because of direction can only carry out the work in one direction.
The present invention is achieved through the following technical solutions:
Power transmission lines overhauling ladder, including two support rods disposed in parallel, between two support rods alongst
It is successively vertically connected with intermediate strut, the same end of two support rods is connected with cross-arm hook, hangs down between the other end of two support rods
It is direct-connected to have two gag lever posts disposed in parallel, two struts, two struts and limit are connected on the gag lever post of cross-arm hook
Angle between bar is 45-60 °, and the top of two struts is directed towards inclination, the plane where two struts and two supports
The angle between plane where bar is in 25-30 °, is connected with the supporting plate vertical with support rod, supporting plate between the top of two struts
On be equipped with wire hook, wire hook can be rotated up 360 ° of sides.
Maintenance ladder of the invention, conducting wire hanging point can rotate left and right, and are able to carry out left and right adjusting in this way and hang the left side
Conducting wire on direction or the right direction, so just can, solve the problems, such as can only to carry out the work in one direction because of direction
Problem.Ladder of the invention when in use, realizes that service personnel carries ladder and climbs to the top end of electric pole, then will be on ladder
Cross-arm be hung on electric pole cross-arm, then wire hook rides upon on the conducting wire of side, and operator passes through ladder
Intermediate strut just can climb to conducting wire the place for needing replacing insulator from the cross-arm of electric pole, again will after the completion of replacement
Ladder is removed from cross-arm;Wire hook can be rotated up 360 ° of sides, in this way in the replacement for completing side wire insulation
Later, wire hook is removed from conducting wire, then rotates 180 ° of wire hook and make hook towards the other side, this energy convenient to both is hung
It is located on the conducting wire of the other side, allows to carry out left and right adjusting by the flexible design of wire hook convenient for being hung on difference
On the conducting wire of side, time of the transmission line of electricity when replacing insulator is shortened;It is to pass through behaviour when ladder to be hung on conducting wire
One end of ladder is lifted as personnel, then vacantly mobile ladder is that wire hook is hung on conducting wire, is easy to hang sky in this way, need more
Operation can just be hung up several times, increase the time hung;Design of the present invention by strut and the plane where two struts
Angle between the plane where two support rods is in 25-30 °, therefore when hanging conducting wire, can be first fastened on conducting wire
In the 25-30 ° of angle formed between strut plane and support rod plane, then to operator direction reverse drawing ladder, lead in this way
Line is just hung on wire hook along the track of strut, is greatly saved conducting wire and is hung the time, improves efficiency.
Further include safety hoop, safety rope and safety belt are connected in safety hoop, the end of safety rope is connected by latch closure
On support rod, the end of safety belt is connected with locking device, and when operator overhauls, safety hoop is mounted on electric wire
On bar, then safety belt is fastened on the waist of operator, is connected in service personnel and ladder, electric pole by safety hoop
Together, the safety in maintenance process is greatly improved.
It is arranged with insulating sheath at the hook of wire hook, reduces the abrasion to conducting wire.
Blocking device is installed on the cross-arm hook, it being capable of more efficient, safety.
Support rod, intermediate strut are all made of aluminum alloy materials and are made, and reduce compared to quality for traditional ladder, light spirit
Living, a people can be with independent operation.
Compared with prior art, the present invention having the following advantages and benefits:
1, power transmission lines overhauling ladder of the present invention, conducting wire hanging point can rotate left and right, and be able to carry out left and right adjusting extension in this way
If the conducting wire on left direction or the right direction, so just can, solve the problems, such as to carry out in one direction because of direction
The problem of work;
2, safety hoop is mounted on electric pole when operator overhauls by power transmission lines overhauling ladder of the present invention
On, then safety belt is fastened on the waist of operator, service personnel and ladder, electric pole are connected in one by safety hoop
It rises, greatly improves the safety in maintenance process;
3, power transmission lines overhauling ladder of the present invention is arranged with insulating sheath at the hook of wire hook, reduces to conducting wire
Abrasion, the cross-arm are linked up with and are equipped with blocking device, can be more efficient, safe, and support rod, intermediate strut are all made of aluminium alloy
Material is made, and reduces compared to quality for traditional ladder, light and flexible a, people can be with independent operation.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application
Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Label and corresponding parts title in attached drawing:
1- support rod, the centre 2- strut, 3- gag lever post, 4- strut, 5- supporting plate, 6- wire hook, 7- safety hoop, 8- peace
Quan Sheng, 9- safety belt, 10- latch closure, 11- cross-arm hook.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment and attached drawing, to this
Invention is described in further detail, and exemplary embodiment of the invention and its explanation for explaining only the invention, are not made
For limitation of the invention.
Embodiment 1
As shown in Figure 1, power transmission lines overhauling ladder of the present invention, including two support rods 1 disposed in parallel, two support rods
Alongst successively vertically it is connected with intermediate strut 2 between 1, the same end of two support rods 1 is connected with cross-arm hook 11, and two
It is vertically connected with two gag lever posts 3 disposed in parallel between the other end of support rod 1, connects on the gag lever post 3 of cross-arm hook 11
There are two struts 4, the angle between two struts 4 and gag lever post 3 is 45-60 °, and the top of two struts 4 is directed towards inclination,
The angle between the plane where plane and two support rods 1 where two struts 4 is in 25-30 °, the top of two struts 4
Between be connected with the supporting plate 5 vertical with support rod 1, wire hook 6 is equipped on supporting plate 5, wire hook 6 can be on 360 ° of directions
Rotation.
Maintenance ladder of the invention, conducting wire hanging point can rotate left and right, and are able to carry out left and right adjusting in this way and hang the left side
Conducting wire on direction or the right direction, so just can, solve the problems, such as can only to carry out the work in one direction because of direction
Problem.Ladder of the invention when in use, realizes that service personnel carries ladder and climbs to the top end of electric pole, then will be on ladder
Cross-arm be hung on electric pole cross-arm, then wire hook rides upon on the conducting wire of side, and operator passes through ladder
Intermediate strut just can climb to conducting wire the place for needing replacing insulator from the cross-arm of electric pole, again will after the completion of replacement
Ladder is removed from cross-arm;Wire hook can be rotated up 360 ° of sides, in this way in the replacement for completing side wire insulation
Later, wire hook is removed from conducting wire, then rotates 180 ° of wire hook and make hook towards the other side, this energy convenient to both is hung
It is located on the conducting wire of the other side, allows to carry out left and right adjusting by the flexible design of wire hook convenient for being hung on difference
On the conducting wire of side, time of the transmission line of electricity when replacing insulator is shortened;It is to pass through behaviour when ladder to be hung on conducting wire
One end of ladder is lifted as personnel, then vacantly mobile ladder is that wire hook is hung on conducting wire, is easy to hang sky in this way, need more
Operation can just be hung up several times, increase the time hung;Design of the present invention by strut and the plane where two struts
Angle between the plane where two support rods is in 25-30 °, therefore when hanging conducting wire, can be first fastened on conducting wire
In the 25-30 ° of angle formed between strut plane and support rod plane, then to operator direction reverse drawing ladder, lead in this way
Line is just hung on wire hook along the track of strut, is greatly saved conducting wire and is hung the time, improves efficiency.
Preferably, further include safety hoop 7, safety rope 8 and safety belt 9 are connected in safety hoop, the end of safety rope is logical
It crosses latch closure 10 to be connected on support rod, the end of safety belt is connected with locking device, and when operator overhauls, safety is embraced
Hoop installation on utility poles, then safety belt is fastened on the waist of operator, by safety hoop by service personnel with climb
Ladder, electric pole connect together, and greatly improve the safety in maintenance process.
Preferably, it is arranged with insulating sheath at the hook of wire hook, reduces the abrasion to conducting wire.
Preferably, blocking device is installed on the cross-arm hook, it being capable of more efficient, safety.
Preferably, support rod, intermediate strut are all made of aluminum alloy materials and are made, and subtract compared to quality for traditional ladder
Small, light and flexible a, people can be with independent operation.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects
It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention
Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include
Within protection scope of the present invention.
Claims (5)
1. power transmission lines overhauling ladder, including two support rods (1) disposed in parallel, along length between two support rods (1)
Direction is successively vertically connected with intermediate strut (2), which is characterized in that and the same end of two support rods (1) is connected with cross-arm hook (11),
Two gag lever posts (3) disposed in parallel are vertically connected between the other end of two support rods (1), close to the limit of cross-arm hook (11)
Two struts (4) are connected on position bar (3), the angle between two struts (4) and gag lever post (3) is 45-60 °, two struts (4)
Top be directed towards inclination, the angle between the plane where plane and two support rods (1) where two struts (4) is in
It 25-30 °, is connected with the supporting plate vertical with support rod (1) (5) between the top of two struts (4), supporting plate is equipped with conducting wire on (5)
It links up with (6), wire hook (6) can be rotated up 360 ° of sides.
2. power transmission lines overhauling ladder according to claim 1, which is characterized in that further include safety hoop (7), safety is embraced
Safety rope (8) and safety belt (9) are connected on hoop (7), the end of safety rope (8) is connected on support rod (1) by latch closure (10),
The end of safety belt (9) is connected with locking device.
3. power transmission lines overhauling ladder according to claim 1, which is characterized in that be arranged at the hook of wire hook (6)
There is insulating sheath.
4. power transmission lines overhauling ladder according to claim 1, which is characterized in that be equipped on the cross-arm hook (11)
Blocking device.
5. power transmission lines overhauling ladder according to claim 1, which is characterized in that support rod (1), intermediate strut (2) are equal
It is made using aluminum alloy materials.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811311469.1A CN109193467B (en) | 2018-11-06 | 2018-11-06 | Transmission line overhauls cat ladder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811311469.1A CN109193467B (en) | 2018-11-06 | 2018-11-06 | Transmission line overhauls cat ladder |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109193467A true CN109193467A (en) | 2019-01-11 |
CN109193467B CN109193467B (en) | 2020-07-07 |
Family
ID=64942015
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811311469.1A Expired - Fee Related CN109193467B (en) | 2018-11-06 | 2018-11-06 | Transmission line overhauls cat ladder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109193467B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110086123A (en) * | 2019-06-18 | 2019-08-02 | 国网四川省电力公司乐山供电公司 | A kind of power transmission lines overhauling replacement auxiliary device |
CN110984833A (en) * | 2019-11-13 | 2020-04-10 | 许继集团有限公司 | Interlayer ladder stand for light-operated converter valve |
CN111810047A (en) * | 2020-07-13 | 2020-10-23 | 安徽省雄峰起重机械有限公司 | Overhauling climbing frame based on crane |
CN114221260A (en) * | 2021-12-21 | 2022-03-22 | 国网河南省电力公司洛阳供电公司 | Insulator maintenance frame of electric power pylon |
WO2022252589A1 (en) * | 2021-05-31 | 2022-12-08 | 青海送变电工程有限公司 | Climbing ladder for power transmission line maintenance |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040222041A1 (en) * | 2002-01-07 | 2004-11-11 | Haverfield Corporation | Helicopter lineman's ladder |
CN202055739U (en) * | 2011-04-28 | 2011-11-30 | 河南省电力公司驻马店供电公司 | Power transmission circuit outgoing line operation horizontal ladder |
CN202888724U (en) * | 2012-11-20 | 2013-04-17 | 山东电力集团公司滨州供电公司 | Special ladder for overhauling concrete pole transmission line |
CN203097699U (en) * | 2012-12-12 | 2013-07-31 | 金华送变电工程有限公司 | Overhead working bridge ladder for power transmission project |
CN204402335U (en) * | 2015-01-20 | 2015-06-17 | 国家电网公司 | A kind of strain insulator Special maintenance tool |
CN204532033U (en) * | 2015-04-14 | 2015-08-05 | 国家电网公司 | The high-altitude line maintenance two hanging ladder of safety |
-
2018
- 2018-11-06 CN CN201811311469.1A patent/CN109193467B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040222041A1 (en) * | 2002-01-07 | 2004-11-11 | Haverfield Corporation | Helicopter lineman's ladder |
CN202055739U (en) * | 2011-04-28 | 2011-11-30 | 河南省电力公司驻马店供电公司 | Power transmission circuit outgoing line operation horizontal ladder |
CN202888724U (en) * | 2012-11-20 | 2013-04-17 | 山东电力集团公司滨州供电公司 | Special ladder for overhauling concrete pole transmission line |
CN203097699U (en) * | 2012-12-12 | 2013-07-31 | 金华送变电工程有限公司 | Overhead working bridge ladder for power transmission project |
CN204402335U (en) * | 2015-01-20 | 2015-06-17 | 国家电网公司 | A kind of strain insulator Special maintenance tool |
CN204532033U (en) * | 2015-04-14 | 2015-08-05 | 国家电网公司 | The high-altitude line maintenance two hanging ladder of safety |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110086123A (en) * | 2019-06-18 | 2019-08-02 | 国网四川省电力公司乐山供电公司 | A kind of power transmission lines overhauling replacement auxiliary device |
CN110984833A (en) * | 2019-11-13 | 2020-04-10 | 许继集团有限公司 | Interlayer ladder stand for light-operated converter valve |
CN111810047A (en) * | 2020-07-13 | 2020-10-23 | 安徽省雄峰起重机械有限公司 | Overhauling climbing frame based on crane |
WO2022252589A1 (en) * | 2021-05-31 | 2022-12-08 | 青海送变电工程有限公司 | Climbing ladder for power transmission line maintenance |
CN114221260A (en) * | 2021-12-21 | 2022-03-22 | 国网河南省电力公司洛阳供电公司 | Insulator maintenance frame of electric power pylon |
CN114221260B (en) * | 2021-12-21 | 2023-07-21 | 国网河南省电力公司洛阳供电公司 | Insulator overhauling frame of electric power tower |
Also Published As
Publication number | Publication date |
---|---|
CN109193467B (en) | 2020-07-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109193467A (en) | Power transmission lines overhauling ladder | |
WO2012088987A1 (en) | Maintenance tool for insulator of direct current transmission line | |
CN107994527A (en) | A kind of high tension electric tower wire insulation buffer unit | |
CN112357847B (en) | Portable lifting auxiliary device for live working | |
CN103441353B (en) | A kind of 110 kilovolts of overhead transmission line anchor support common ground lines | |
CN105398990A (en) | Auxiliary lifting device for electric angle iron tower | |
CN205187730U (en) | Electric power angle -steel tower is with supplementary hoisting device | |
CN102761077B (en) | Insulating hoisting bracket for strain insulator string of 1000kV extra-high alternating current line | |
CN208337014U (en) | A kind of charged for replacement Voltage for Insulators on HV Lines lifting block hanging point heightening device | |
CN105366565A (en) | Auxiliary hoisting device for high-tension cable tower | |
CN203867274U (en) | Installing equipment for double cross arms | |
CN201466574U (en) | Device for isoelectrically replacing insulator and accessory of iron tower of transmission line | |
CN209448333U (en) | A kind of multi-functional unmanned plane seton device for transmission line of electricity | |
CN201332246Y (en) | Large-tonnage conducting wire lifter | |
CN202840363U (en) | Insulated lifting bracket for tension insulator chain of 1000-kV extra-high voltage alternating current circuit | |
CN205489269U (en) | Overhead earth wire hoisting device for high tension transmission line | |
CN110086123A (en) | A kind of power transmission lines overhauling replacement auxiliary device | |
CN209388514U (en) | A kind of live wire repairing real training tool | |
CN209469366U (en) | A kind of new take-off formula conducting wire hanging ladder | |
CN203398638U (en) | Operation ladder for painting insulator string in power transmission line | |
CN202444204U (en) | Traction lifting device for high-altitude circuit tools and appliances | |
CN106159791B (en) | A kind of ADSS optical cables inspection platform | |
CN204391612U (en) | Nacelle device is safeguarded in a kind of high-voltage line high-altitude | |
CN204412656U (en) | A kind of 500kV converting equipment electric cleaning device | |
CN103738860A (en) | Small interval dual-purpose hoisting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200707 Termination date: 20201106 |
|
CF01 | Termination of patent right due to non-payment of annual fee |