CN109179217A - Super High vertical high voltage cable laying construction technology - Google Patents

Super High vertical high voltage cable laying construction technology Download PDF

Info

Publication number
CN109179217A
CN109179217A CN201811237945.XA CN201811237945A CN109179217A CN 109179217 A CN109179217 A CN 109179217A CN 201811237945 A CN201811237945 A CN 201811237945A CN 109179217 A CN109179217 A CN 109179217A
Authority
CN
China
Prior art keywords
cable
lifting
high voltage
construction technology
laying construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811237945.XA
Other languages
Chinese (zh)
Other versions
CN109179217B (en
Inventor
孙军
杨泓斌
盖守超
隋新春
齐鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Bozhilin Robot Co Ltd
Original Assignee
Building Dream High Tech Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Building Dream High Tech Construction Co Ltd filed Critical Building Dream High Tech Construction Co Ltd
Priority to CN201811237945.XA priority Critical patent/CN109179217B/en
Publication of CN109179217A publication Critical patent/CN109179217A/en
Application granted granted Critical
Publication of CN109179217B publication Critical patent/CN109179217B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C15/00Safety gear
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/16Applications of indicating, registering, or weighing devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/46Position indicators for suspended loads or for crane elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C15/00Safety gear
    • B66C15/02Safety gear for retaining load-engaging elements in the event of rope or cable breakage
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses Super High vertical high voltage cable laying construction technologies, belong to ultra-high layer cable laying field, Super High vertical high voltage cable laying construction technology, the following steps are included: S1: measuring electrical well head, S2: establishment cable arrangement table, S3: selecting and installs lifting equipment and each group fixture, S4: selects main suspender and auxiliary lifting appliance, S5: carrying out examination and hang work, and S6: lifting is completed and removes each lifting apparatus.The measurement work of the electric shaft mouth is used to determine the installation site of each group fixture.It can be effectively prevented economic loss caused by due to wirerope is surprisingly broken, cable installation cost can be reduced to a certain extent, and it is capable of the lifting process of real-time monitoring cable, improve safety guarantee when lifting, the position of cable head-end can also be accurately positioned, and send its location information to computer and be compared, effectively increase the installation accuracy rate and installation effectiveness of cable.

Description

Super High vertical high voltage cable laying construction technology
Technical field
The present invention relates to ultra-high layer cables to lay field, applies more specifically to Super High vertical high voltage cable laying Work technique.
Background technique
Ultra-high layer cable laying technique refers to a kind of method of the laying installation cable in skyscraper, in skyscraper In, the length of cable vertical section increases, and voltage drop also increases, and in power supply process, electric energy loss is also bigger, existing super In high-rise cable laying technique, it can not be effectively prevented economic loss caused by due to wirerope is surprisingly broken, will increase electricity Cable laying installation cost, and can not real-time monitoring cable lifting process, reduce safety guarantee when lifting, can't It is enough that the position of cable head-end is accurately positioned, the installation accuracy rate and installation effectiveness of cable can be reduced.
Summary of the invention
1. technical problems to be solved
Aiming at the problems existing in the prior art, the purpose of the present invention is to provide Super High vertical high voltage cable layings to apply Work technique, it may be implemented to be effectively prevented economic loss caused by due to wirerope is surprisingly broken, can drop to a certain extent Low cable installation cost, and it is capable of the lifting process of real-time monitoring cable, improve safety guarantee when lifting, additionally it is possible to electricity The position at cable beginning is accurately positioned, and is sent its location information to computer and be compared, and cable is effectively increased Accuracy rate and installation effectiveness are installed.
2. technical solution
To solve the above problems, the present invention adopts the following technical scheme that.
Super High vertical high voltage cable laying construction technology, comprising the following steps:
S1: after electric shaft meets lifting condition, each electric shaft mouth is measured, and record each well head Measurement data, the electric shaft mouth to width less than 400mm make mark;
S2: working out cable arrangement table according to the actual conditions of project distribution system, determines beginning, the end position of each group cable It sets and horizontal segment, vertical section length data, and enters data into computer;
S3: lifting equipment is selected according to calculated result, and lifting equipment and fixed frame are installed to the highest of electric shaft Flooring more than mechanical floor or highest mechanical floor is arranged as the leading block of cable horizontal segment guiding, most on the ground Antihunting positioning fixture is installed in the electric shaft mouth of low mechanical floor, retaining fixture is installed in the two sides of each electric shaft mouth;
S4: according to requiring to select main suspender and auxiliary lifting appliance, GPS positioning chip is installed in the inside of main suspender, is being hung The lower end for filling disk is installed by high-definition camera;
S5: main suspender is fixed on the suspension hook of top pulleys, is carried out examination and is hung work, confirms that each link, can without mistaking Formal lifting;
S6: in formal hoisting process, with the promotion of lifting equipment, the beginning of cable slowly rises, cable vertical section Length constantly increase, upper horizontal segment cable, which steps into, is horizontally mounted layer, when slinger completes, successively remove each group hang Tool, fixture and lifting equipment and fixed frame etc..
Further, the measurement work of the electric shaft mouth is used to determine the installation site of each group fixture.
Further, the computer is used to integrate the parameter and the entire work progress of real-time monitoring of each group cable.
Further, the calculated result is the Force Calculation result to lifting equipment and wirerope.
Further, the auxiliary lifting appliance is used to make the vertical section uniform force of cable, and the antihunting positioning fixture is used In preventing the excessive damage cable of cable amplitude of fluctuation during lifting.
Further, the suspension hook is connected by wirerope and lifting disk, the beginning of the lifting disk and cable End is connected.
Further, the GPS positioning chip and high-definition camera are connected to a computer by wireless network, and described Heavy equipment is connected to a computer by programmable controller.
Further, the vertical section of the cable sequentially passes through the antihunting positioning of each elevator shaft mouth during lifting Fixture and retaining fixture.
Further, the GPS positioning chip is used to determine that the real time position of cable head-end, the high-definition camera to be used for The entire hoisting process of real-time monitoring.
Further, the retaining fixture falls downwards for fracture cable after preventing wirerope from accident occur.
3. beneficial effect
Compared with the prior art, the present invention has the advantages that
The construction technology of this programme is more scientific and reasonable, caused by capable of being effectively prevented due to wirerope is surprisingly broken Economic loss can reduce cable installation cost to a certain extent, and be capable of the lifting process of real-time monitoring cable, improve Safety guarantee when hanging, additionally it is possible to the position of cable head-end is accurately positioned, and send its location information to computer It is compared, effectively increases the installation accuracy rate and installation effectiveness of cable.
Detailed description of the invention
Fig. 1 is construction process schematic diagram of the invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description;Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments, is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the instruction such as term " on ", "lower", "inner", "outside", " top/bottom end " Orientation or positional relationship be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description the present invention and simplification retouch It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.In addition, term " first ", " second " are used for description purposes only, and cannot understand For indication or suggestion relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation " " is set Be equipped with ", " be arranged/connect ", " connection " etc., shall be understood in a broad sense, such as " connection ", may be a fixed connection, be also possible to removable Connection is unloaded, or is integrally connected, can be mechanical connection, is also possible to be electrically connected, can be directly connected, it can also be in Between medium be indirectly connected, can be the connection inside two elements, for the ordinary skill in the art, can be specific Situation understands the concrete meaning of above-mentioned term in the present invention.
Embodiment 1:
Referring to Fig. 1, Super High vertical high voltage cable laying construction technology, comprising the following steps:
S1: after electric shaft meets lifting condition, each electric shaft mouth is measured, and record each well head Measurement data, the electric shaft mouth to width less than 400mm make mark, and electric shaft mouth of the degree less than 400mm should not be installed Each group fixture;
S2: working out cable arrangement table according to the actual conditions of project distribution system, determines beginning, the end position of each group cable It sets and horizontal segment, vertical section length data, and enters data into computer, which is common laptop;
S3: lifting equipment is selected according to calculated result, and lifting equipment and fixed frame are installed to the highest of electric shaft Flooring more than mechanical floor or highest mechanical floor is arranged as the leading block of cable horizontal segment guiding, most on the ground Antihunting positioning fixture is installed, antihunting positioning fixture is for preventing cable in lifting process in the electric shaft mouth of low mechanical floor The middle excessive damage cable of amplitude of fluctuation installs retaining fixture in the two sides of each electric shaft mouth, and retaining fixture is for preventing steel Fracture cable falls downwards after accident occurs in cord;
S4: according to requiring to select main suspender and auxiliary lifting appliance, auxiliary lifting appliance is used to make the vertical section uniform force of cable, GPS positioning chip is installed in the inside of main suspender, is used in the lower end installation high-definition camera GPS positioning chip of lifting disk true Determine the real time position of cable head-end, high-definition camera is used for the entire hoisting process of real-time monitoring;
S5: main suspender is fixed on the suspension hook of top pulleys, is carried out examination and is hung work, confirms that each link, can without mistaking Formal lifting;
S6: in formal hoisting process, with the promotion of lifting equipment, the beginning of cable slowly rises, cable it is vertical Section sequentially passes through the antihunting positioning fixture and retaining fixture of each elevator shaft mouth, the length of cable vertical section during lifting Constantly increase, upper horizontal segment cable, which steps into, is horizontally mounted layer, when slinger completes, successively removes each group suspender, fixture And lifting equipment and fixed frame etc..
The measurement work of electric shaft mouth is used to determine the installation site of each group fixture, and width is electrical perpendicular less than 400mm Well head should not install each group fixture;Computer is used to integrate the parameter and the entire work progress of real-time monitoring of each group cable;Meter Calculating result is the Force Calculation result to lifting equipment and wirerope;Auxiliary lifting appliance is for keeping the vertical section stress of cable equal Even, antihunting positioning fixture is for preventing the excessive damage cable of cable amplitude of fluctuation during lifting, and retaining fixture is for preventing Fracture cable falls downwards after only accident occurs in wirerope;Suspension hook is connected by wirerope and lifting disk, lifts disk It is connected with the beginning of cable;GPS positioning chip and high-definition camera are connected to a computer by wireless network, GPS positioning Chip is used to determine that the real time position of cable head-end, high-definition camera to be used for the entire hoisting process of real-time monitoring, and lifting equipment is logical The programmable controller for crossing model DVP60ES200R is connected to a computer;The vertical section of cable during lifting successively Across the antihunting positioning fixture and retaining fixture of each elevator shaft mouth.
In conclusion construction technology of the invention is more scientific and reasonable, can be effectively prevented because wirerope surprisingly breaks Split and caused by economic loss, cable installation cost can be reduced to a certain extent, and be capable of the lifting of real-time monitoring cable Journey improves safety guarantee when lifting, additionally it is possible to be accurately positioned to the position of cable head-end, and its location information is passed It gives computer to be compared, effectively increases the installation accuracy rate and installation effectiveness of cable.
The foregoing is intended to be a preferred embodiment of the present invention;But scope of protection of the present invention is not limited thereto. Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its It improves design and is subject to equivalent substitution or change, should be covered by the scope of protection of the present invention.

Claims (10)

1. Super High vertical high voltage cable laying construction technology, which comprises the following steps:
S1: after electric shaft meets lifting condition, each electric shaft mouth is measured, and record the measurement of each well head Data, the electric shaft mouth to width less than 400mm make mark;
S2: according to the actual conditions of project distribution system work out cable arrange table, determine beginning, the terminal position of each group cable with And horizontal segment, vertical section length data, and enter data into computer;
S3: lifting equipment is selected according to calculated result, and lifting equipment and fixed frame are installed to the highest equipment of electric shaft Flooring more than layer or highest mechanical floor is arranged as the leading block of cable horizontal segment guiding on the ground, sets minimum Antihunting positioning fixture is installed in the electric shaft mouth of standby layer, retaining fixture is installed in the two sides of each electric shaft mouth;
S4: according to requiring to select main suspender and auxiliary lifting appliance, GPS positioning chip is installed in the inside of main suspender, is justified in lifting The lower end of disk is installed by high-definition camera;
S5: main suspender is fixed on the suspension hook of top pulleys, is carried out examination and is hung work, confirms that each link, can be formal without mistaking Lifting;
S6: in formal hoisting process, with the promotion of lifting equipment, the beginning of cable slowly rises, the length of cable vertical section Degree constantly increases, and upper horizontal segment cable, which steps into, is horizontally mounted layer, when slinger completes, successively removes each group suspender, card Tool and lifting equipment and fixed frame etc..
2. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: described electrical perpendicular The measurement work of well head is used to determine the installation site of each group fixture.
3. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the computer The entire work progress of parameter and real-time monitoring for integrating each group cable.
4. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the calculating knot Fruit is the Force Calculation result to lifting equipment and wirerope.
5. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the auxiliary hanging Has the vertical section uniform force for making cable, the antihunting positioning fixture is for preventing cable amplitude of fluctuation during lifting Spend big damage cable.
6. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the suspension hook is logical It crosses wirerope to connect with lifting disk, the lifting disk is connected with the beginning of cable.
7. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the GPS is fixed Position chip and high-definition camera are connected to a computer by wireless network, and the lifting equipment passes through programmable controller and meter Calculation machine is connected.
8. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the cable Vertical section sequentially passes through the antihunting positioning fixture and retaining fixture of each elevator shaft mouth during lifting.
9. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the GPS is fixed Position chip is used to determine that the real time position of cable head-end, the high-definition camera to be used for the entire hoisting process of real-time monitoring.
10. Super High vertical high voltage cable laying construction technology according to claim 1, it is characterised in that: the retaining Fixture falls downwards for fracture cable after preventing wirerope from accident occur.
CN201811237945.XA 2018-10-23 2018-10-23 Super high-rise vertical high-voltage cable laying construction process Active CN109179217B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811237945.XA CN109179217B (en) 2018-10-23 2018-10-23 Super high-rise vertical high-voltage cable laying construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811237945.XA CN109179217B (en) 2018-10-23 2018-10-23 Super high-rise vertical high-voltage cable laying construction process

Publications (2)

Publication Number Publication Date
CN109179217A true CN109179217A (en) 2019-01-11
CN109179217B CN109179217B (en) 2020-04-07

Family

ID=64942923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811237945.XA Active CN109179217B (en) 2018-10-23 2018-10-23 Super high-rise vertical high-voltage cable laying construction process

Country Status (1)

Country Link
CN (1) CN109179217B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115207837A (en) * 2022-07-11 2022-10-18 中国建筑第二工程局有限公司 Overhead cable laying method and safety protection auxiliary device thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002078165A (en) * 2000-08-25 2002-03-15 Sanki Eng Co Ltd Cable locking apparatus
US20040239133A1 (en) * 2003-05-29 2004-12-02 Yakov Kushnir Gripping device
JP2005221012A (en) * 2004-02-05 2005-08-18 Sumori Kogyo Kk Building ready for maintenance, pulley for supporting piping, wiring, etc., piping/wiring executing method, and piping/wiring replacing method
CN201171147Y (en) * 2007-12-18 2008-12-24 上海市安装工程有限公司 Clamp for vertically mounting ultra-high layer cable
CN101728790A (en) * 2009-12-29 2010-06-09 广东省工业设备安装公司 Method for laying vertical cables for extra-high building
CN205304103U (en) * 2015-11-30 2016-06-08 中国建筑第八工程局有限公司 Dynamic positioning device is prevented putting by cable
CN205791261U (en) * 2016-07-11 2016-12-07 青岛博海建设集团有限公司 Big specification cable-laying gear in a kind of high-rise building vertical shaft
CN107359550A (en) * 2017-08-25 2017-11-17 中国十七冶集团有限公司 A kind of big cable of converter oxygen gun main motor colligation laying method on the way
CN108462117A (en) * 2018-03-02 2018-08-28 北京利华消防工程有限公司 A kind of skyscraper cable-laying gear and its application method
CN108516464A (en) * 2018-04-28 2018-09-11 上海市安装工程集团有限公司 A kind of accompanying cable vertical lifting system of wirerope and its construction method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002078165A (en) * 2000-08-25 2002-03-15 Sanki Eng Co Ltd Cable locking apparatus
US20040239133A1 (en) * 2003-05-29 2004-12-02 Yakov Kushnir Gripping device
JP2005221012A (en) * 2004-02-05 2005-08-18 Sumori Kogyo Kk Building ready for maintenance, pulley for supporting piping, wiring, etc., piping/wiring executing method, and piping/wiring replacing method
CN201171147Y (en) * 2007-12-18 2008-12-24 上海市安装工程有限公司 Clamp for vertically mounting ultra-high layer cable
CN101728790A (en) * 2009-12-29 2010-06-09 广东省工业设备安装公司 Method for laying vertical cables for extra-high building
CN205304103U (en) * 2015-11-30 2016-06-08 中国建筑第八工程局有限公司 Dynamic positioning device is prevented putting by cable
CN205791261U (en) * 2016-07-11 2016-12-07 青岛博海建设集团有限公司 Big specification cable-laying gear in a kind of high-rise building vertical shaft
CN107359550A (en) * 2017-08-25 2017-11-17 中国十七冶集团有限公司 A kind of big cable of converter oxygen gun main motor colligation laying method on the way
CN108462117A (en) * 2018-03-02 2018-08-28 北京利华消防工程有限公司 A kind of skyscraper cable-laying gear and its application method
CN108516464A (en) * 2018-04-28 2018-09-11 上海市安装工程集团有限公司 A kind of accompanying cable vertical lifting system of wirerope and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
丁锐等: "上海环球金融中心10kV垂吊式高压电缆吊装敷设技术", 《施工技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115207837A (en) * 2022-07-11 2022-10-18 中国建筑第二工程局有限公司 Overhead cable laying method and safety protection auxiliary device thereof

Also Published As

Publication number Publication date
CN109179217B (en) 2020-04-07

Similar Documents

Publication Publication Date Title
CN107338733B (en) Hoisting device and hoisting method for adjusting and positioning overhead posture of steel box arch rib
CN102185265B (en) Construction method for replacing cross arm of 35kV line linear rod
CN103683088A (en) Line bracing tool
CN109179217A (en) Super High vertical high voltage cable laying construction technology
CN203367865U (en) Auxiliary bracket for maintaining power transmission line
CN105932601B (en) Disconnected strand of overhead grounding wire method for repairing and mending
CN205296844U (en) Precast box girder steel strand wires hoisting point
CN105514867A (en) Method for replacing V-shaped insulator string of power transmission line pole
CN111697490A (en) Electric power iron tower wiring device based on Internet of things equipment and use method
CN102623927B (en) Charged for replacement 220kV circuit multiloop double bundle conductor insulator tool and method
CN102832571B (en) Cable bending radius controller and cable bending method
CN201466574U (en) Device for isoelectrically replacing insulator and accessory of iron tower of transmission line
CN101692548A (en) Tool for live replacing of hanging bottle string of drainage wire
CN204216502U (en) Drag and make Cable holder for distribution
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN102684088B (en) Transformer assembly and disassembly methods
CN102983517A (en) Integral installation device for transformer test bench
CN104218493B (en) ± 800kV UHVDC Transmission Lines live-line replacing strain hard tube mother's wire jumper insulator technique
CN102290738A (en) Construction method for replacing 35kV line tension pole cross arm
CN207498840U (en) The bridge hanging basket that can be broken the barriers
CN104377598A (en) Straightening device for double-insulator-suspended yoke plates on electric transmission line
CN212462602U (en) Electric power iron tower stringing device based on internet of things equipment
CN203683010U (en) High-altitude working electric conveying device
CN105591318B (en) A kind of block method of U-shaped net
CN204980888U (en) Electric block controlling means

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190930

Address after: 528300 East Office Building 201-11, No. 11 Junye East Road, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Applicant after: Guangdong Bozhilin Robot Co., Ltd.

Address before: 519000 -44144, 105 room 6, Baohua Road, Hengqin New District, Zhuhai, Guangdong (centralized office area)

Applicant before: Building dream high tech Construction Company Limited

GR01 Patent grant
GR01 Patent grant