CN109162209A - The quick-replaceable construction method of half-through and half/through arch bridge suspender - Google Patents

The quick-replaceable construction method of half-through and half/through arch bridge suspender Download PDF

Info

Publication number
CN109162209A
CN109162209A CN201811025150.2A CN201811025150A CN109162209A CN 109162209 A CN109162209 A CN 109162209A CN 201811025150 A CN201811025150 A CN 201811025150A CN 109162209 A CN109162209 A CN 109162209A
Authority
CN
China
Prior art keywords
sunpender
suspender
interim
tensioning
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811025150.2A
Other languages
Chinese (zh)
Other versions
CN109162209B (en
Inventor
肖开军
罗小聪
吴志淋
杨文甫
张长利
李鸿彬
陈俊
易学锋
何嘉强
杜波
黄明海
戴春洋
成莉
朱燕萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Heli Transportation Maintenance Technology Co.,Ltd.
Original Assignee
Guangdong Heli Civil Engineering Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Heli Civil Engineering Ltd filed Critical Guangdong Heli Civil Engineering Ltd
Priority to CN201811025150.2A priority Critical patent/CN109162209B/en
Publication of CN109162209A publication Critical patent/CN109162209A/en
Application granted granted Critical
Publication of CN109162209B publication Critical patent/CN109162209B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the quick-replaceable construction methods of a kind of half-through and half/through arch bridge suspender, including step 1: installing the operating platform, prepares measurement monitoring;Step 2: interim pocket crane system is installed;Step 3: the interim pocket crane system of tensioning cuts off old sunpender;Step 4: old sunpender is removed;Step 5: installation and the new sunpender of tensioning realize the replacement of sunpender;Step 6: interim pocket crane system, new the adjusting of suspender power are removed.The construction method can be under conditions of the interim sunpender of less investment, operating personnel and machinery, achieve the purpose that the old sunpender of quick-replaceable, especially in half-through and the half/through arch bridge suspender replacement construction for being suitable for early stage for sunpender and being anchored at arch rib or crossbeam, the construction method is more efficient.

Description

The quick-replaceable construction method of half-through and half/through arch bridge suspender
Technical field
The present invention relates to the quick of the replacing options of arch bridge suspender, in particular to a kind of half-through and half/through arch bridge suspender Replace construction method.
Background technique
Due to arched bridge pre-stressed boom beautiful design, span ability is big, is generally built in urban road, becomes the beautiful wind together in city Scape line improves city image, however urban road wagon flow is intensive, and runway is again limited, and suspender replacement generally requires full-bridge envelope It closes or enclosure portion lane, is affected to civil plantation.General authorities are the influence reduced to traffic, are wanted to the duration Ask stringent.
Sunpender is anchored at arch rib or crossbeam in design and construction, the anchoring shape by the half-through and lower bearing arch bridge of early stage Formula is limitation based on technology at that time and the selection made to the deficient long-range nature of late maintaining, replacement, can prevent arch rib and The corrosion of the exposed sunpender steel wire of header portion, while sunpender and arch rib and header portion being made to form unified rigid body, it improves Its globality, increases the anchor force of sunpender and arch rib and crossbeam, however causes influence factor when later period suspender replacement more, technology It is required that high, complicated construction technique, replacement difficulty is big, causes to replace inefficiency, according to suspender replacement technical characterstic at this stage, such as Fruit will accelerate suspender replacement progress, have and the mode of only increase input interim sunpender, operating personnel and machinery, this is not only A kind of waste, and more sunpenders are replaced will lead to that structure stress is increasingly complex simultaneously, and the risk of suspender replacement is increased.
Arch bridge suspender replacement main technique is to install the operating platform, and measurement monitoring prepares, installs interim pocket crane system, tensioning Interim pocket crane system cuts off old sunpender, removes former sunpender, installation and the new sunpender of tensioning, removes interim pocket crane system, sunpender rope The processes such as power adjustment determine the pass of suspender replacement speed in the case where not increasing interim sunpender and operating personnel's machinery is put into Dismounting of the key node process for anchoring section above and below time-consuming longest old sunpender, data statistic analysis, sunpender take anchor head and remove Anchor head working hour accounts for 33.7%, 24.5% when suspender replacement chief engineer respectively, and the sum of working hour accounts for 58.2% when suspender replacement chief engineer, Steel wire and cement slurry consolidation are integral in anchoring section embedded steel tube above and below arch rib and crossbeam for sunpender, between embedded steel tube and steel wire Spacing is small, and under and efficiency time-consuming using other modes removing cement slurry is very low, and high-pressure water jet is to the fragmentation of material Predominantly water jet acts on the fricting shearing of the impact of particle and water wedge effect, particle between each other and between particle and tube wall Deng.Because steel pipe and steel wire are homogeneous solid materials, when setting specified water pressure, high-pressure water jet is not to pre-buried steel Steel wire causes to impact in managing, and is only purged to the cement slurry between embedded steel tube and steel wire, therefore high-pressure water jet will not damage Evil arrives other steel constructions such as steel wire and steel pipe.Reinforced concrete technology is abolished using high-pressure water jet, can be grasped using computer Equipment is controlled, process is abolished and carries out under program, is constructed safer reliable.
Summary of the invention
The object of the present invention is to provide the quick-replaceable construction method of a kind of half-through and half/through arch bridge suspender, the constructions Method can achieve the purpose that the old sunpender of quick-replaceable under conditions of the interim sunpender of less investment, operating personnel and machinery, special It is not in half-through and the half/through arch bridge suspender replacement construction for being suitable in early days being anchored at sunpender arch rib or crossbeam, the construction Method is more efficient.
Above-mentioned purpose of the invention is achieved through the following technical solutions: a kind of half-through and half/through arch bridge suspender it is fast Speed replacement construction method, it is characterised in that: the construction method includes the following steps:
Step 1: installing the operating platform, and prepares measurement monitoring;
Step 2: interim pocket crane system is installed;
Step 3: the interim pocket crane system of tensioning cuts off old sunpender;
Step 4: old sunpender is removed;
Step 5: installation and the new sunpender of tensioning realize the replacement of sunpender;
Step 6: interim pocket crane system, new the adjusting of suspender power are removed.
In the present invention, the step 1 is installed the operating platform, and prepares measurement monitoring, and concrete processing procedure is as follows:
(1) there are two the operating platforms installed, one is the operating platform set up on arch rib with frame pipe, for sunpender Tensioning is used, and be can also be used as new hanger erection and is used, the other is using construction to hang indigo plant as operating platform, for supplying in downrod lower end Construction personnel installs lower anchor head and tensioning equipment;
(2) traverse point control net is established, above and below each sunpender under existing high-precision total station survey dead load state Space coordinate and floor elevation between anchor plate, the benchmark as process control high in construction.
In the present invention, the step 2 installs interim pocket crane system, and concrete processing procedure is as follows:
(1) interim long sunpender is transported on arch rib, interim long sunpender is pre- from anchor point on four outrigger ends of tensioning platform It boxes out and wears, each preformed hole wears an interim long sunpender, according to physical length spreading;
(2) interim pocket crane system is installed in bridge floor, interim pocket crane system includes conversion beam, stringer, crossbeam, lower joist and arch Upper conversion beam and jack, stringer, crossbeam, lower joist and the upper conversion beam of arch are the original structure of arch bridge, and conversion beam is horizontal It is arranged on stringer, installing four jack pairs altogether at conversion beam, temporarily long sunpender carries out tensioning, is then put into lower joist Beam bottom is fixed temporarily lower joist with interim short steeve cucurbit;
(3) preformed hole that interim short steeve is passed through to conversion beam and lower joist by lower joist and is encircleed using interim short steeve The longitudinal and cross beam of bridge is connected.
In the present invention, the step 3, the interim pocket crane system of tensioning cuts off old sunpender, concrete processing procedure is as follows:
(1) cement in the embedded steel tube being located between arch rib and crossbeam or more anchoring section is removed using high-pressure water jet Slurry, so that embedded steel tube is separated with the steel wire in pipe;
(2) measurement by monitoring to suspender force, obtains force value in the dead load of every sunpender, is added step by step using existing The Suo Li of original sunpender is gradually transferred on interim long sunpender by the method for carrying and discharging internal force;
(3) to the progress grading tension control of interim sunpender power in system conversion process: grading tension control respectively 0 → 20% → 40% → 60% → 80% → 100%, while old sunpender steel wire is cut off by same Suo Li, at the high 1.5m of bridge floor, point It cuts off twice, and controls floor elevation changing value within the scope of ± 5mm in the stretching process of every level-one.
In the present invention, the step 4 removes old sunpender, and concrete processing procedure is as follows:
After old sunpender cutting, upper anchor head, the lower anchor head of arch bridge are directly taken out old anchor head using drawing mode, and drawing is filled Set and be mounted under bridge floor, with hydraulic tensioning jack provide driving force, using high-strength bolt as jack tension part, high-strength bolt and It is fixedly connected between the old sunpender anchor head of arch bridge by connector, using the steel of the whole old sunpender of beam drawing arch bridge of hydraulic tensioning jack Silk or stranded wire anchor head finally carry out borehole cleaning to removing after old sunpender drawing.
In the present invention, the step 5 is installed and the new sunpender of tensioning, concrete processing procedure is as follows:
(1) former sunpender embedded steel tube cleans out, and after processing anchor plate repairing, installs new sunpender;
(2) suspender tension equipment is installed, suspender tension equipment uses existing equipment, including suspender tension connector, tensioning Support foot, jack, tension rod and tensioning nut, and adjust centering;
(3) tensioning being carried out to new sunpender according to the stretching rope force value of design, absolute altitude control, tensioning classification is loaded, point Grade releases interim suspender force;
(4) new suspender tension is to builder's tonnage, after Pass line adjustment is suitable, tightening nut and locking nut, and removal sunpender Draw equipment.
In the present invention, the step 6 removes interim pocket crane system, new the adjusting of suspender power, and concrete processing procedure is as follows:
After the completion of full-bridge new suspender replacement, interim pocket crane system, the new suspender force of measurement full-bridge and bridge floor control are removed Point absolute altitude, determines whether new suspender force and floor elevation reach design requirement by calculating analysis, if there is deviation, then New suspender force is further adjusted, design requirement is reached, surveys a Suo Li and absolute altitude again to full-bridge tune Suo Wanhou, as applying Work record is saved.
Construction method of the invention is solved in existing suspender replacement technology and can only be increased input to accelerate construction efficiency The mode of interim sunpender, operating personnel and machinery, avoids more sunpenders while replacement causes structure stress increasingly complex and increases The risk added, has prevented security-hidden trouble.
Construction method speed of application of the invention is fast, construction risk is low, strong operability.
Compared with prior art, the present invention has following remarkable result:
(1) uniqueness that the present invention has using high-pressure water jet is quickly removed and calculates depth in sunpender embedded steel tube Cement slurry removes in embedded steel tube pipe fast 10 times of cement slurry or more than tradition, is 5 times of common solution efficiency.
(2) for the present invention after sunpender power is transferred to pocket crane system, upper and lower anchor head will by the way of hydraulic jack drawing Old anchor head takes out.
(3) present invention changes the original stress of bridge structure smaller, and construction is simple, operation side is small, replacement Period is smaller to the traffic impact of bridge, can accomplish uninterrupted traffic under reasonable arrangement, and speed of application is fast, high-efficient.
Detailed description of the invention
The present invention is described in further details with reference to the accompanying drawings and detailed description.
Fig. 1 is operation of the present invention platform schematic diagram;
Fig. 2 is interim pocket crane system schematic diagram of the invention;
Fig. 3 is sunpender cutting schematic diagram of the present invention;
Fig. 4 is that the present invention removes former sunpender schematic diagram;
Fig. 5 is that the present invention installs new sunpender schematic diagram.
Description of symbols
1, old sunpender 2, arch rib
3, operating platform 4, interim long sunpender
5, interim short steeve 6, conversion beam
7, lower joist 8, conversion beam on arch
9, jack 10, stringer
11, crossbeam 12, high-pressure water jet
13, embedded steel tube 14, cement slurry
15, the old sunpender steel wire of steel wire 16
17, upper anchor head 18, lower anchor head
19, draw-off gear 20, new sunpender.
Specific embodiment
As shown in Figures 1 to 5, the quick-replaceable construction method of a kind of half-through of the present invention and half/through arch bridge suspender, packet Include following steps:
Step 1: installing the operating platform, and prepares measurement monitoring, and concrete processing procedure is as follows:
(1) there are two the operating platforms 3 installed, one is the operating platform set up on arch rib 2 with frame pipe, is mainly used It is used in the tensioning of sunpender, can also be used as the new installation of sunpender 20 and use.The other is it is blue as operation to use construction to hang in downrod lower end Platform, for installing lower anchor head 18 and tensioning equipment for construction personnel;
(2) traverse point control net is established, above and below each sunpender under existing high-precision total station survey dead load state Space coordinate and floor elevation between anchor plate, the benchmark as process control high in construction.
Step 2 installs interim pocket crane system, and concrete processing procedure is as follows:
(1) interim long sunpender 4 is transported on arch rib 2, interim long sunpender 4 is from anchor point on four outrigger ends of tensioning platform Preformed hole is worn, and each preformed hole wears an interim long sunpender 4, according to physical length spreading;
(2) interim pocket crane system is installed in bridge floor, interim pocket crane system includes conversion beam 6, stringer 10, crossbeam 11, subiculum Beam 7 and the upper conversion beam 8 of arch and jack 9, stringer 10, crossbeam 11, lower joist 7 and the upper conversion beam 8 of arch are the original of arch bridge Structure, conversion beam 6 are horizontally set on stringer 10, are installed four jack 9 altogether at conversion beam 6 and are carried out to interim long sunpender 4 Then lower joist 7 is put into beam bottom by tensioning, the interim short steeve cucurbit made of fining twisted steel is fixed temporarily lower joist 7;
(3) preformed hole that interim short steeve 5 is passed through to conversion beam 6 and lower joist 7, using interim short steeve 5 by lower joist 7 It is connected with the stringer 10 of arch bridge and crossbeam 11.
Step 3, the interim pocket crane system of tensioning, cuts off old sunpender 1;Concrete processing procedure is as follows:
(1) it is removed using high-pressure water jet 12 in the embedded steel tube 13 being located between arch rib 2 and crossbeam or more anchoring section Cement slurry, high-pressure water jet spray gun use existing equipment, screw around sunpender or so, will be pre-buried using the impact force of high-pressure water jet Cement slurry 14 in steel pipe 13 is broken and goes out, so that embedded steel tube 13 is separated with the steel wire 15 in pipe;
(2) measurement by monitoring to suspender force, obtains force value in the dead load of every sunpender, is added step by step using existing The Suo Li of original sunpender is gradually transferred on interim long sunpender 4 by the method for carrying and discharging internal force;
(3) to the progress grading tension control of interim sunpender power in system conversion process: grading tension control respectively 0 → 20% → 40% → 60% → 80% → 100%, while old sunpender steel wire 16 is cut off by same Suo Li, in the high about 1.5m of bridge floor Place, cuts off in two times, and controls floor elevation changing value within the scope of ± 5mm in the stretching process of every level-one.
Step 4 removes old sunpender 1, and concrete processing procedure is as follows:
After old sunpender cutting, upper anchor head 17, the lower anchor head 18 of arch bridge are directly taken out old anchor head using drawing mode, will be drawn Pulling device 19 is mounted under bridge floor, and draw-off gear 19 uses existing equipment, includes high-strength bolt and connector, with hydraulic tensioning thousand 9 offer driving force of jin top passes through connection between high-strength bolt and the old sunpender anchor head of arch bridge using high-strength bolt as jack tension part Device is fixedly connected, and using the steel wire or stranded wire anchor head of the whole old sunpender of beam drawing arch bridge of hydraulic tensioning jack, is drawn old sunpender 1 It is removed after pulling out, finally carries out borehole cleaning.
Step 5, installation and the new sunpender 20 of tensioning, realize the replacement of sunpender, concrete processing procedure is as follows:
(1) former sunpender embedded steel tube 13 cleans out, and after processing anchor plate repairing, installs new sunpender 20;
(2) suspender tension equipment is installed, suspender tension equipment uses existing equipment, including suspender tension connector, tensioning Support foot, jack, tension rod and tensioning nut, and adjust centering;
(3) tensioning being carried out to new sunpender 20 according to the stretching rope force value of design, absolute altitude control, tensioning classification is loaded, The interim suspender force of unranking;
(4) new 20 tensioning of sunpender is to builder's tonnage, after Pass line adjustment is suitable, tightening nut and locking nut, and removal sunpender Tensioning equipment.
Step 6, removes interim pocket crane system, new the adjusting of suspender power, and concrete processing procedure is as follows:
After the completion of the new sunpender 20 of full-bridge is replaced, interim pocket crane system, the new suspender force of measurement full-bridge and bridge floor control are removed A system point absolute altitude, by calculating analysis determines whether new suspender force and floor elevation reach design requirement, if there is deviation, It then needs further to adjust new suspender force, reaches design requirement.
Specific the adjusting of suspender power mode is similar with the method for suspender tension.A Suo Li is surveyed again to full-bridge tune Suo Wanhou And absolute altitude, it is saved as construction record.
Half-through and half/through arch bridge suspender quick-replaceable construction method of the invention solves existing suspender replacement technology In can only increase input the mode of interim sunpender, operating personnel and machinery to accelerate construction efficiency, it is same to avoid more sunpenders Shi Genghuan leads to the increasingly complex and increased risk of structure stress, has prevented security-hidden trouble.
Construction method speed of application of the invention is fast, construction risk is low, strong operability.
Application example
Case history 1
The brilliant old bridge of bridge was built in 1989, and bridge site is located at provincial highway extensively on high line S113, and East and West direction crosses over the Xijiang River, belongs to A Very Large Bridge on the mainstream of the Xijiang River, is the traffic main artery of the external communications and transportation in Gaoming District, bridge overall length 1092.1m, two-way 4 Lane, across footpath group are combined into (78.5+4 × 82.6) deck type reinforced concrete ribbed arch bridge+(2 × 110) half-through steel tube concrete Native arched bridge pre-stressed boom+(5 × 79+68.2) m deck type reinforced concrete ribbed arch bridge, bridge floor beam overall are 13.35m, reinforced concrete bridge Face.Xijiang River navigation channel is I grade of inland river navigation channel at brilliant bridge, and current 3000t seagoing vessel, open the navigation or air flight clear height 22m, Designed Highest Navigable Stage 8.01m (pearl base).Full-bridge sunpender quantity is 36, and old sunpender specification is 5-109 steel wire, intensity of steel wire 1600Mpa, Fracture Force For 349.2t.It is reported according to conventional detection in 2011, the 5# suspender force in the 6th hole downstream side changes compared with last time detection 6.23t, amplitude of variation 11%.Service life has been basically reached in view of most sunpenders simultaneously, therefore has replaced whole sunpenders.2016 It 2 months, tests 2 and uses this engineering method, during entire suspender replacement, bridge structure stress is controlled in permissible range, Entire bridge structure is not affected by new damage, and efficiency is 5 times of common engineering method.
Case history 2
Foshan City's Fochen Bridge is open to the traffic in 1994, bridge long 883.84m, main span 115.80m.Spanning combination are as follows: (15 × 16) m prestressed cored slab+(3 × 28.3) m reinforced concrete continuous beam+112.8m base-supporting concrete-filled steel tube tied arch+(3 × 28.3) m reinforced concrete continuous beam+(18 × 16) m prestressed cored slab, totally 40 across.42 sunpenders are set on main bridge both sides of the chest altogether, Away from 5m.Sunpender is all made of SNS/S-85 × 7mm zinc-coated wire and extrudes double sheath knob line type finished guy cables, and the upper end uses LZM85IJ-7 type cold cast upset head anchor anchor is on anchor slab, lower end then uses the bulb-end anchorage anchor of designed, designed in crossbeam in arch rib upper tube It is interior.It tests 6 and uses this engineering method in April, 2017, during entire suspender replacement, the control of bridge structure stress is being held Perhaps in range, entire bridge structure is not affected by new damage, and efficiency is 5 times of common engineering method.
The above embodiment of the present invention is not limiting the scope of the present invention, and embodiments of the present invention are not limited to This, all this kind above content according to the present invention is not departing from this according to the ordinary technical knowledge and customary means of this field Modification, replacement or change under the premise of inventing above-mentioned basic fundamental thought, to other diversified forms that above structure of the present invention is made More, it should all fall within the scope and spirit of the invention.

Claims (7)

1. the quick-replaceable construction method of a kind of half-through and half/through arch bridge suspender, it is characterised in that: the construction method includes Following steps:
Step 1: installing the operating platform, and prepares measurement monitoring;
Step 2: interim pocket crane system is installed;
Step 3: the interim pocket crane system of tensioning cuts off old sunpender;
Step 4: old sunpender is removed;
Step 5: installation and the new sunpender of tensioning realize the replacement of sunpender;
Step 6: interim pocket crane system, new the adjusting of suspender power are removed.
2. the quick-replaceable construction method of half-through according to claim 1 and half/through arch bridge suspender, it is characterised in that: The step 1, installs the operating platform, and prepares measurement monitoring, and concrete processing procedure is as follows:
(1) there are two the operating platforms installed, one is the operating platform set up on arch rib with frame pipe, the tensioning for sunpender With can also be used as new hanger erection and use, the other is it is blue as operating platform use construction to hang in downrod lower end, be used for for constructing Personnel install lower anchor head and tensioning equipment;
(2) traverse point control net is established, the pad that casts anchor on each sunpender under existing high-precision total station survey dead load state is utilized Space coordinate and floor elevation between plate, the benchmark as process control high in construction.
3. half-through according to claim 2 and half/through arch bridge suspender quickly replace construction method, it is characterised in that: The step 2 installs interim pocket crane system, and concrete processing procedure is as follows:
(1) interim long sunpender is transported on arch rib, interim long sunpender is from anchor point preformed hole on four outrigger ends of tensioning platform It wears, each preformed hole wears an interim long sunpender, according to physical length spreading;
(2) interim pocket crane system is installed in bridge floor, interim pocket crane system includes turning on conversion beam, stringer, crossbeam, lower joist and arch Beam and jack are changed, stringer, crossbeam, lower joist and the upper conversion beam of arch are the original structure of arch bridge, and conversion beam is horizontally disposed On stringer, installing four jack pairs altogether at conversion beam, temporarily long sunpender carries out tensioning, and lower joist is then put into beam bottom, Lower joist is fixed temporarily with interim short steeve cucurbit;
(3) preformed hole that interim short steeve is passed through to conversion beam and lower joist, using interim short steeve by lower joist and arch bridge Longitudinal and cross beam is connected.
4. the quick-replaceable construction method of half-through according to claim 3 and half/through arch bridge suspender, it is characterised in that: The step 3, the interim pocket crane system of tensioning, cuts off old sunpender, concrete processing procedure is as follows:
(1) cement slurry in the embedded steel tube being located between arch rib and crossbeam or more anchoring section is removed using high-pressure water jet, is made Embedded steel tube is obtained to separate with the steel wire in pipe;
(2) by measurement of the monitoring to suspender force, obtain force value in the dead load of every sunpender, using existing multistage loadings and The Suo Li of original sunpender is gradually transferred on interim long sunpender by the method for discharging internal force;
(3) to the progress grading tension control of interim sunpender power in system conversion process: grading tension control respectively 0 → 20% → 40% → 60% → 80% → 100%, while old sunpender steel wire is cut off by same Suo Li, at the high 1.5m of bridge floor, cut in two times It is disconnected, and floor elevation changing value is controlled within the scope of ± 5mm in the stretching process of every level-one.
5. the quick-replaceable construction method of half-through according to claim 4 and half/through arch bridge suspender, it is characterised in that: The step 4 removes old sunpender, and concrete processing procedure is as follows:
After old sunpender cutting, upper anchor head, the lower anchor head of arch bridge are directly taken out old anchor head using drawing mode, and draw-off gear is pacified Under bridge floor, driving force is provided with hydraulic tensioning jack, using high-strength bolt as jack tension part, high-strength bolt and arch bridge Be fixedly connected between old sunpender anchor head by connector, using the whole old sunpender of beam drawing arch bridge of hydraulic tensioning jack steel wire or Stranded wire anchor head finally carries out borehole cleaning to removing after old sunpender drawing.
6. the quick-replaceable construction method of half-through according to claim 5 and half/through arch bridge suspender, it is characterised in that: The step 5, installation and the new sunpender of tensioning, concrete processing procedure are as follows:
(1) former sunpender embedded steel tube cleans out, and after processing anchor plate repairing, installs new sunpender;
(2) install suspender tension equipment, suspender tension equipment use existing equipment, including suspender tension connector, tensioning support foot, Jack, tension rod and tensioning nut, and adjust centering;
(3) tensioning is carried out to new sunpender according to the stretching rope force value of design, absolute altitude control, tensioning classification is loaded, classification solution Except interim suspender force;
(4) new suspender tension is to builder's tonnage, and after Pass line adjustment is suitable, tightening nut and locking nut, removal suspender tension are set It is standby.
7. the quick-replaceable construction method of half-through according to claim 6 and half/through arch bridge suspender, it is characterised in that: The step 6, removes interim pocket crane system, new the adjusting of suspender power, and concrete processing procedure is as follows:
After the completion of full-bridge new suspender replacement, interim pocket crane system, the new suspender force of measurement full-bridge and bridge floor control point mark are removed Height determines whether new suspender force and floor elevation reach design requirement by calculating analysis, if there is deviation, then into one Step renewing suspender force, reaches design requirement, surveys a Suo Li and absolute altitude again to full-bridge tune Suo Wanhou, records as construction Record is saved.
CN201811025150.2A 2018-09-04 2018-09-04 Quick replacement construction method for half-through type and through type arch bridge suspenders Active CN109162209B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811025150.2A CN109162209B (en) 2018-09-04 2018-09-04 Quick replacement construction method for half-through type and through type arch bridge suspenders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811025150.2A CN109162209B (en) 2018-09-04 2018-09-04 Quick replacement construction method for half-through type and through type arch bridge suspenders

Publications (2)

Publication Number Publication Date
CN109162209A true CN109162209A (en) 2019-01-08
CN109162209B CN109162209B (en) 2021-06-01

Family

ID=64894091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811025150.2A Active CN109162209B (en) 2018-09-04 2018-09-04 Quick replacement construction method for half-through type and through type arch bridge suspenders

Country Status (1)

Country Link
CN (1) CN109162209B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853352A (en) * 2019-01-30 2019-06-07 中铁大桥局第七工程有限公司 Rib-lifting section operation platform and its setting method
CN111119075A (en) * 2019-12-31 2020-05-08 山西省交通新技术发展有限公司 Replacement construction method for suspender of super-large half-through arch bridge
CN111597614A (en) * 2020-05-13 2020-08-28 广西交科集团有限公司 Bridge deck displacement control method for replacing arch bridge suspender based on actual measurement displacement correction
CN113107211A (en) * 2021-03-31 2021-07-13 中冶(上海)钢结构科技有限公司 Temporary reinforcing method for replacing equipment anchorage device in tensioning and lifting construction
CN113152313A (en) * 2021-04-19 2021-07-23 南京润华建设集团有限公司 Suspender replacing structure of tied arch bridge and construction method thereof
CN113605251A (en) * 2021-09-16 2021-11-05 广西大学 Arch bridge cable adjusting method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003020618A (en) * 2001-07-06 2003-01-24 Nkk Corp Existing bridge reinforcing method, and reinforced existing bridge
CN103046466A (en) * 2012-12-29 2013-04-17 广东省公路勘察规划设计院股份有限公司 Detectable, replaceable and adjustable arch bridge suspender system and method for constructing same
CN204112242U (en) * 2014-09-03 2015-01-21 武汉二航路桥特种工程有限责任公司 A kind of Concrete Filled Steel-tube Truss Arch Bridge suspender replacement special tool boom system
CN105507167A (en) * 2015-12-30 2016-04-20 杭州市市政工程集团有限公司 Construction method for replacing suspender of tied-arch bridge by PLC (Programmable Logic Controller) synchronous tensioning
CN106087767A (en) * 2016-08-11 2016-11-09 柳州欧维姆工程有限公司 The whole bundle draw-off gear assembly in the clear hole of suspender replacement and remove steel wire and the clear hole method of the old suspension rod of arch bridge
CN106758883A (en) * 2017-03-02 2017-05-31 柳州欧维姆工程有限公司 For the interim pocket device for hoisting of steel wire rope of steel pipe truss concrete arch-type bridge suspender replacement and its method for suspender replacement
CN106758882A (en) * 2017-02-16 2017-05-31 柳州欧维姆工程有限公司 For the hood type automatic leveling anchor and its method for suspender replacement of CFST Arch Bridge suspender replacement
CN206418414U (en) * 2016-12-13 2017-08-18 上海浦东新区公路建设发展有限公司 Derrick type arch bridge suspender replacing device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003020618A (en) * 2001-07-06 2003-01-24 Nkk Corp Existing bridge reinforcing method, and reinforced existing bridge
CN103046466A (en) * 2012-12-29 2013-04-17 广东省公路勘察规划设计院股份有限公司 Detectable, replaceable and adjustable arch bridge suspender system and method for constructing same
CN204112242U (en) * 2014-09-03 2015-01-21 武汉二航路桥特种工程有限责任公司 A kind of Concrete Filled Steel-tube Truss Arch Bridge suspender replacement special tool boom system
CN105507167A (en) * 2015-12-30 2016-04-20 杭州市市政工程集团有限公司 Construction method for replacing suspender of tied-arch bridge by PLC (Programmable Logic Controller) synchronous tensioning
CN106087767A (en) * 2016-08-11 2016-11-09 柳州欧维姆工程有限公司 The whole bundle draw-off gear assembly in the clear hole of suspender replacement and remove steel wire and the clear hole method of the old suspension rod of arch bridge
CN206418414U (en) * 2016-12-13 2017-08-18 上海浦东新区公路建设发展有限公司 Derrick type arch bridge suspender replacing device
CN106758882A (en) * 2017-02-16 2017-05-31 柳州欧维姆工程有限公司 For the hood type automatic leveling anchor and its method for suspender replacement of CFST Arch Bridge suspender replacement
CN106758883A (en) * 2017-03-02 2017-05-31 柳州欧维姆工程有限公司 For the interim pocket device for hoisting of steel wire rope of steel pipe truss concrete arch-type bridge suspender replacement and its method for suspender replacement

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱妍等: "轨道交通某拱桥吊杆锚头取出试验研究", 《城市道桥与防洪》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853352A (en) * 2019-01-30 2019-06-07 中铁大桥局第七工程有限公司 Rib-lifting section operation platform and its setting method
CN111119075A (en) * 2019-12-31 2020-05-08 山西省交通新技术发展有限公司 Replacement construction method for suspender of super-large half-through arch bridge
CN111597614A (en) * 2020-05-13 2020-08-28 广西交科集团有限公司 Bridge deck displacement control method for replacing arch bridge suspender based on actual measurement displacement correction
CN111597614B (en) * 2020-05-13 2022-09-16 广西交科集团有限公司 Bridge deck displacement control method for replacing arch bridge suspender based on actual measurement displacement correction
CN113107211A (en) * 2021-03-31 2021-07-13 中冶(上海)钢结构科技有限公司 Temporary reinforcing method for replacing equipment anchorage device in tensioning and lifting construction
CN113152313A (en) * 2021-04-19 2021-07-23 南京润华建设集团有限公司 Suspender replacing structure of tied arch bridge and construction method thereof
CN113605251A (en) * 2021-09-16 2021-11-05 广西大学 Arch bridge cable adjusting method
CN113605251B (en) * 2021-09-16 2022-11-29 广西大学 Arch bridge cable adjusting method

Also Published As

Publication number Publication date
CN109162209B (en) 2021-06-01

Similar Documents

Publication Publication Date Title
CN109162209A (en) The quick-replaceable construction method of half-through and half/through arch bridge suspender
CN106677070B (en) A kind of high-altitude long-span heavy duty construction of beam bracket and construction method
CN109137744B (en) Asymmetric construction method and control method for main truss of large-span flexible suspension bridge
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN108060636B (en) The construction method of overall assembled composite beam bridge
CN108193607B (en) Fabricated prestressed truss for reinforcement and construction method thereof
CN105507167A (en) Construction method for replacing suspender of tied-arch bridge by PLC (Programmable Logic Controller) synchronous tensioning
CN106012872B (en) Continuous rigid frame bridge without dorsal funciculus oblique pull reinforcement system and construction method
CN110552296A (en) Cable-stayed bridge dismantling construction method
CN107165039A (en) Encorbelment mass concrete construction prestress anchoraging angle-table bracket and its construction method
CN109183783B (en) Breaking-free separated pile head of concrete filling pile
CN102108748B (en) Quadrilateral endless rope chord supporting structure and construction process
CN110847041A (en) Temporary anchoring structure and anchoring method for segmental prefabricated assembled concrete box girder
CN110184948A (en) A kind of Bridge beam construction method
CN112252212A (en) Method for dismantling prestressed concrete variable cross-section continuous beam bridge
CN100545353C (en) Adopt external eccentric prestress system to carry out steel girder cantilever erection construction method
CN104763161A (en) Beam-adding reinforced structure of a reinforced concrete floor with an opening and construction method
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN106499211B (en) Newly-increased outrigger frame Baogang anchor daraf(reciprocal of farad) structure
CN206503378U (en) Newly-increased outrigger constructing structure
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN115679844A (en) Integrated dismantling method for steel pipe concrete arch bridge
CN109098395A (en) A kind of installation method of the prefabricated piping lane of assembly concrete
CN113944114A (en) Dismantling construction method for large-span prestressed concrete cable-stayed bridge
CN212714601U (en) Cantilever structure stabilizing device after conversion of truss type combined arch bridge system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 510400 4-6 / F, 1161 Panyu Avenue North, Donghuan street, Panyu District, Guangzhou City, Guangdong Province

Patentee after: Guangdong Heli Transportation Maintenance Technology Co.,Ltd.

Country or region after: China

Address before: 510400 4-6 / F, 1161 Panyu Avenue North, Donghuan street, Panyu District, Guangzhou City, Guangdong Province

Patentee before: GUANGDONG HELI CIVIL ENGINEERING Ltd.

Country or region before: China

CP03 Change of name, title or address