CN109149565A - Electric integrated management-control method, system, server and storage medium - Google Patents

Electric integrated management-control method, system, server and storage medium Download PDF

Info

Publication number
CN109149565A
CN109149565A CN201811030220.3A CN201811030220A CN109149565A CN 109149565 A CN109149565 A CN 109149565A CN 201811030220 A CN201811030220 A CN 201811030220A CN 109149565 A CN109149565 A CN 109149565A
Authority
CN
China
Prior art keywords
information
data
electric
level
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811030220.3A
Other languages
Chinese (zh)
Inventor
周翔
陈功林
于晶
张敏
柳毅德
江嘉鹏
杨苇菁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811030220.3A priority Critical patent/CN109149565A/en
Publication of CN109149565A publication Critical patent/CN109149565A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/001Methods to deal with contingencies, e.g. abnormalities, faults or failures
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Quality & Reliability (AREA)
  • Power Engineering (AREA)
  • Operations Research (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a kind of electric integrated management-control method, system, server and storage mediums, the method generates electric network synthetic control figure by obtaining power production management data, geodata and the operational monitoring data of multiple electric system, according to the power production management data, the geodata and each operational monitoring data;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;In the current electric grid real-time running data exception, abnormality alarming information is generated;Power off notifying information is pushed to target terminal user according to the abnormality alarming information, pass through the various data of synthesis, keep the operating status of current electric grid high-visible, improve power system monitor efficiency, it is alerted in time when grid operation data occurs abnormal, electric network emergency first-aid repair efficiency is improved, and pushes power off notifying to user, the user experience is improved.

Description

Electric integrated management-control method, system, server and storage medium
Technical field
The present invention relates to power domains more particularly to a kind of electric integrated management-control method, system, server and storage to be situated between Matter.
Background technique
Electric service is one of important process of power grid enterprises, he through safety in production, marketing service, power grid construction, The links such as power regulation and department are that the emphasis of power grid enterprises' integrated management level embodies, with power system reform, especially It is to propose acid test to the electric service competitiveness of power grid enterprises, electric service is horizontal after sales market is decontroled Have to be hoisted.But due to distribution net work structure complexity, automation coverage rate is not complete, and system is numerous, is that limitation good service is horizontal The basic place promoted.
Particular problem is mainly reflected in the following aspects:
First is that fault point can not be accurately positioned when high-tension line or low-voltage platform area failure occurs, it can not with commanding is robbed Accurately know user information in power supply interrupted district, can not can only pass through in advance to user's sending fault message in scope of power outage is related to Work order or grid phone passive service.Stand-line-change-family relationship confusion largely effects on robbing working efficiency.
Second is that the data for being related to user are dispersed in each system, can only be by cumbersome when generation low voltage failure is reported for repairment Inquiry and where user itself describes discriminating fault types and problem, the intermediate link of service needs further to be simplified, and right It can only be contacted by phone in scene rush to repair personnel, grasp repairing situation in real time, be completely in blind tune.
Third is that each system has accumulated a large amount of grid operation data in conventional operational, these data are not divided deeply Analysis, causes resource to waste significantly.
Summary of the invention
The main purpose of the present invention is to provide a kind of electric integrated management-control method, system, server and storage medium, purports Solving the technical issues of a large amount of grid operation data wastes cause difficult power failure repairing, inefficiency in the prior art.
To achieve the above object, the present invention provides a kind of electric integrated management-control method, the electric integrated management-control method packet Include following steps:
Power production management data, geodata and the operational monitoring data of multiple electric system are obtained, according to the electricity Power production management data, the geodata and each operational monitoring data generate electric network synthetic control figure;
Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;
In the current electric grid real-time running data exception, abnormality alarming information is generated;
Power off notifying information is pushed to target terminal user according to the abnormality alarming information.
Preferably, after the control figure acquisition current electric grid real-time running data according to the electric network synthetic, the electricity Power comprehensive control method further include:
In the troublshooting number for receiving target user, searched out in real time according to the electric network synthetic control figure and institute State the corresponding troublshooting user information of troublshooting number;
Troublshooting work order is generated according to the troublshooting user information, and institute is obtained according to the troublshooting work order State load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and the affiliated platform area real time execution of target user Status information;
It is real-time according to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area Running state information determines emergency first-aid repair scheme;
Breakdown repair is carried out according to the emergency first-aid repair scheme.
Preferably, described that breakdown repair is carried out according to the emergency first-aid repair scheme, it specifically includes:
According to the emergency first-aid repair scheme determine the target vehicle for handling the troublshooting work order, target rush repair equipment and Target repair personnel;
The troublshooting work order is sent on the mobile terminal of the target repair personnel, so that the target is repaired Personnel carry out breakdown repair using the target vehicle and the target rush repair equipment.
Preferably, described in the current electric grid real-time running data exception, it is described after generating abnormality alarming information Electric integrated management-control method further include:
Obtain the abnormal rank of the abnormality alarming information;
When the abnormal rank is default first level, level-one is generated according to the abnormality alarming information and repairs work order;
Work order, which is repaired, according to the level-one determines level-one repairing group, level-one recovery vehicle and level-one rush repair equipment;
Level-one repairing work order is sent on the mobile terminal of level-one repairing group, so that the level-one is repaired Group is handled level-one repairing work order using the level-one recovery vehicle and level-one rush repair equipment.
Preferably, on the mobile terminal that level-one repairing work order is sent to level-one repairing group, so that The level-one repairing group is handled level-one repairing work order using the level-one recovery vehicle and level-one rush repair equipment Later, the electric integrated management-control method further include:
Receive the scene rush to repair video information that the mobile terminal of level-one repairing group uploads in real time;
Resource is dispatched according to the scene rush to repair video information to support level-one repairing group.
It is preferably, described to obtain power production management data, geodata and the operational monitoring data of multiple electric system, Electric network synthetic control figure is generated according to the power production management data, the geodata and each operational monitoring data, specifically Include:
Obtain power production management data, geodata and the operational monitoring data of multiple electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, It is established between the power production management data, geodata and the operational monitoring data of multiple electric system based on the analysis results Target mapping relations;
According to the fortune of the target mapping relations and the power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic control figure.
Preferably, described that power off notifying information is pushed to target terminal user according to the abnormality alarming information, it is specific to wrap It includes:
Macro or mass analysis is carried out to the abnormality alarming information, is obtained belonging to the corresponding fault zone of the abnormality alarming information Platform area;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, stop to target terminal user push Electric notification information.
In addition, to achieve the above object, the present invention also proposes that a kind of server, the server include: memory, processing Device and the electric integrated control program that is stored on the memory and can run on the processor, the electric integrated pipe The step of control program is arranged for carrying out electric integrated management-control method as described above.
In addition, to achieve the above object, the present invention also proposes a kind of storage medium, electric power is stored on the storage medium Integrated control program, the electric integrated control program realize electric integrated control side as described above when being executed by processor The step of method.
In addition, to achieve the above object, the present invention also provides a kind of electric integrated managing and control system, the electric integrated control System includes:
Figure generation module is managed, for obtaining the operation of power production management data, geodata and multiple electric system Monitoring data generate electric network synthetic pipe according to the power production management data, the geodata and each operational monitoring data Control figure;
Real time data acquisition module obtains current electric grid real-time running data for managing figure according to the electric network synthetic;
Alarm module, for generating abnormality alarming information in the current electric grid real-time running data exception;
Notification module, for pushing power off notifying information to target terminal user according to the abnormality alarming information.
Electric integrated management-control method proposed by the present invention, by obtaining power production management data, geodata and multiple The operational monitoring data of electric system, according to the power production management data, the geodata and each operational monitoring data Generate electric network synthetic control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;Described current When power grid real-time running data exception, abnormality alarming information is generated;It is pushed away according to the abnormality alarming information to target terminal user Power off notifying information is sent, by the various data of synthesis, keeps the operating status of current electric grid high-visible, improves power system monitor effect Rate alerts in time when grid operation data occurs abnormal, improves electric network emergency first-aid repair efficiency, and push and have a power failure to user Notice, the user experience is improved.
Detailed description of the invention
Fig. 1 is the server architecture schematic diagram for the hardware running environment that the embodiment of the present invention is related to;
Fig. 2 is the flow diagram of the electric integrated management-control method first embodiment of the present invention;
Fig. 3 is the flow diagram of the electric integrated management-control method second embodiment of the present invention;
Fig. 4 is the flow diagram of the electric integrated management-control method 3rd embodiment of the present invention;
Fig. 5 is the functional block diagram of the electric integrated managing and control system first embodiment of the present invention.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The solution of the embodiment of the present invention is mainly: by obtaining power production management data, geodata and multiple The operational monitoring data of electric system, according to the power production management data, the geodata and each operational monitoring data Generate electric network synthetic control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;Described current When power grid real-time running data exception, abnormality alarming information is generated;It is pushed away according to the abnormality alarming information to target terminal user Power off notifying information is sent, by the various data of synthesis, keeps the operating status of current electric grid high-visible, improves power system monitor effect Rate alerts in time when grid operation data occurs abnormal, improves electric network emergency first-aid repair efficiency, and push and have a power failure to user Notice, the user experience is improved, solve a large amount of grid operation datas waste in the prior art cause power failure repairing it is difficult, The technical issues of inefficiency.
Referring to Fig.1, Fig. 1 is the server architecture schematic diagram for the hardware running environment that the embodiment of the present invention is related to.
As shown in Figure 1, the server may include: processor 1001, such as CPU, communication bus 1002, user's end interface 1003, network interface 1004, memory 1005.Wherein, communication bus 1002 is for realizing the connection communication between these components. User's end interface 1003 may include display screen (Display), input unit such as keyboard (Keyboard), optional user's termination Mouth 1003 can also include standard wireline interface and wireless interface.Network interface 1004 optionally may include the wired of standard Interface, wireless interface (such as WI-FI interface).Memory 1005 can be high speed RAM memory, be also possible to stable memory (non-volatile memory), such as magnetic disk storage.Memory 1005 optionally can also be independently of aforementioned processor 1001 storage device.
It will be understood by those skilled in the art that server architecture shown in Fig. 1 does not constitute the restriction to the server, It may include perhaps combining certain components or different component layouts than illustrating more or fewer components.
As shown in Figure 1, as may include operating system, network communication mould in a kind of memory 1005 of storage medium Block, user terminal interface module and electric integrated control program.
Server of the present invention calls the electric integrated control program stored in memory 1005 by processor 1001, and holds The following operation of row:
Power production management data, geodata and the operational monitoring data of multiple electric system are obtained, according to the electricity Power production management data, the geodata and each operational monitoring data generate electric network synthetic control figure;
Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;
In the current electric grid real-time running data exception, abnormality alarming information is generated;
Power off notifying information is pushed to target terminal user according to the abnormality alarming information.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
In the troublshooting number for receiving target user, searched out in real time according to the electric network synthetic control figure and institute State the corresponding troublshooting user information of troublshooting number;
Troublshooting work order is generated according to the troublshooting user information, and institute is obtained according to the troublshooting work order State load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and the affiliated platform area real time execution of target user Status information;
It is real-time according to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area Running state information determines emergency first-aid repair scheme;
Breakdown repair is carried out according to the emergency first-aid repair scheme.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
According to the emergency first-aid repair scheme determine the target vehicle for handling the troublshooting work order, target rush repair equipment and Target repair personnel;
The troublshooting work order is sent on the mobile terminal of the target repair personnel, so that the target is repaired Personnel carry out breakdown repair using the target vehicle and the target rush repair equipment.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
Obtain the abnormal rank of the abnormality alarming information;
When the abnormal rank is default first level, level-one is generated according to the abnormality alarming information and repairs work order;
Work order, which is repaired, according to the level-one determines level-one repairing group, level-one recovery vehicle and level-one rush repair equipment;
Level-one repairing work order is sent on the mobile terminal of level-one repairing group, so that the level-one is repaired Group is handled level-one repairing work order using the level-one recovery vehicle and level-one rush repair equipment.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
Receive the scene rush to repair video information that the mobile terminal of level-one repairing group uploads in real time;
Resource is dispatched according to the scene rush to repair video information to support level-one repairing group.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
Obtain power production management data, geodata and the operational monitoring data of multiple electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, It is established between the power production management data, geodata and the operational monitoring data of multiple electric system based on the analysis results Target mapping relations;
According to the fortune of the target mapping relations and the power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic control figure.
Further, processor 1001 can call the electric integrated control program stored in memory 1005, also execute It operates below:
Macro or mass analysis is carried out to the abnormality alarming information, is obtained belonging to the corresponding fault zone of the abnormality alarming information Platform area;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, stop to target terminal user push Electric notification information.
The present embodiment through the above scheme, passes through acquisition power production management data, geodata and multiple electric system Operational monitoring data, according to the power production management data, the geodata and each operational monitoring data generate power grid Integrated control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;It is real-time in the current electric grid When operation data exception, abnormality alarming information is generated;Had a power failure according to the abnormality alarming information to target terminal user push and is led to Know information, by the various data of synthesis, keeps the operating status of current electric grid high-visible, power system monitor efficiency is improved, in electricity Net operation data alerts in time when occurring abnormal, improves electric network emergency first-aid repair efficiency, and push power off notifying to user, mentions User experience is risen.
Based on above-mentioned hardware configuration, the electric integrated management-control method embodiment of the present invention is proposed.
Referring to Fig. 2, Fig. 2 is the flow diagram of the electric integrated management-control method first embodiment of the present invention.
In the first embodiment, the electric integrated management-control method the following steps are included:
Step S10, power production management data, geodata and the operational monitoring data of multiple electric system, root are obtained Electric network synthetic control figure is generated according to the power production management data, the geodata and each operational monitoring data.
It should be noted that the power production management data are power engineering production management system (Power Production Management System, PMS) in the management data in relation to power generation, the geodata be geography Geographical location information number in relation to power grid overlay area in information system (Geographic Information System, GIS) According to the operational monitoring data are multiple electric system, such as OPEN3000, Open3200 distribution automation of production scheduling All kinds of distribution operation datas, fault recorder data and the monitoring of platform area in system, teletransmission type fault recording system and platform area monitoring system Operational monitoring data in the various electric system such as data;It can certainly be the operation number of other more or less electric system According to the present embodiment is without restriction to this.
It is understood that by by the power production management data, geodata and the operation of multiple electric system Monitoring data are integrated, and electric network synthetic control figure can be generated, the electric network synthetic control figure can be to various operation datas Carry out real-time centralized displaying, can be similar to keyword by way of quickly check route, power supply unit, counting equipment with The monitoring efficiency of power grid can be greatly improved in user information, the foundation of the electric network synthetic control figure.
Further, the step S10 specifically includes the following steps:
Obtain power production management data, geodata and the operational monitoring data of multiple electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, It is established between the power production management data, geodata and the operational monitoring data of multiple electric system based on the analysis results Target mapping relations;
According to the fortune of the target mapping relations and the power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic control figure.
It should be understood that by the power production management data, geodata and the operation of multiple electric system Monitoring data are analyzed, can be analyzed as a result, according to the analysis result establish the power production management data, The target mapping relations between data and the operational monitoring data of multiple electric system are managed, wherein the operational monitoring data include But it is not limited to: real time monitoring main transformer data, track data, distribution transformer load data, bus and line voltage distribution data, route actual time line It damages data, each branch switch and distribution transforming status data and stops power transmission information and heavy-overload situation data, by closing each data Connection gets up, and can determine the target mapping relations, thus according to the target mapping relations and the power production management number Electric network synthetic control figure is generated according to, geodata and the operational monitoring data of multiple electric system, may be implemented to various indexs The centralized displaying of data reaches the real time monitoring to bottom data, advantageously forms complete supervisor's rectification mechanism, is conducive to electricity The promotion of net quality monitoring and monitoring efficiency.
In the concrete realization, by the power production management data, geodata and the operation of multiple electric system Monitoring data are analyzed, using the data of long-term running generation, to personnel, equipment, portfolio state, all kinds of power grid constructions The historical data of economy counted, large database concept can be formed and then carry out targetedly analysis, be subsequent power grid Construction and maintenance work provide data supporting foundation.
Step S20, figure is managed according to the electric network synthetic and obtains current electric grid real-time running data.
It can be with quick search to the key message pair for wanting inquiry it is understood that managing figure by the electric network synthetic The operation data answered, by real-time grid integrated control figure in addition to current electric grid real-time running data can be inquired, moreover it is possible to return The grid operation data of query history of tracing back set period;In general, can by keyword query to corresponding basic data with And current electric grid operation data, be conducive to improve power system monitor speed and efficiency.
Step S30, in the current electric grid real-time running data exception, abnormality alarming information is generated.
It should be understood that by the way that current electric grid real-time running data to be compared with default grid operation data, it can To judge whether real-time current electric grid real-time running data is abnormal, default grid operation data is pre-set various in real time The preset threshold range set of basic data, when different data not relative to preset threshold range in when, i.e., judgement work as Preceding power grid real-time running data is abnormal, generates abnormality alarming information in time at this time, and be sent to command and control center, carries out next Step processing;The data exception can be the exception of track data, is also possible to the exception of device data, can also be at system Manage the exception of data, naturally it is also possible to be the exception of other data, the present embodiment is without restriction to this.
Step S40, power off notifying information is pushed to target terminal user according to the abnormality alarming information.
It is understood that the abnormality alarming information can be line anomalies warning information, it is also possible to unit exception Warning information, can also be other kinds of abnormality alarming information, and the present embodiment is without restriction to this;Obtaining abnormality alarming It, can be according to the corresponding target terminal user of the abnormality alarming acquisition of information, thus in time to the target user after information Terminal pushes power off notifying information, improves the electricity consumption experience of user.
Further, the step S40 is specifically included:
Macro or mass analysis is carried out to the abnormality alarming information, is obtained belonging to the corresponding fault zone of the abnormality alarming information Platform area;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, stop to target terminal user push Electric notification information.
It should be understood that the abnormality alarming can be obtained by carrying out Macro or mass analysis to the abnormality alarming information The corresponding fault zone of information, to determine affiliated platform area according to the fault zone;The abnormality alarming information is converged Bulk analysis, which can be, periodically carries out Macro or mass analysis to a plurality of abnormality alarming information, is also possible in real time believe different abnormality alarmings Breath carries out Macro or mass analysis, naturally it is also possible to be to carry out Macro or mass analysis, the present embodiment pair to abnormality alarming information by other means This is without restriction;The corresponding use in the affiliated platform area in the fault zone can be quickly found by the electric network synthetic control figure Family information list, for example, tripping of breaking down abnormality alarming information when, can quickly determine abnormality alarming information it is corresponding therefore Hinder region, and then determine the affiliated platform area in fault zone and user information list, so that command and control center be facilitated accurately to grasp Fault coverage, thus in fault coverage user terminal and the corresponding user terminal of the user information list as target User terminal, and power off notifying information is pushed to target terminal user.
In the concrete realization, when having monitored abnormality alarming information, fault zone can be quickly determined, and rob people to matching Member, i.e., the staff of handling failure mobile terminal show fault zone range, scope of power outage Nei Tai area's information and User information list, it is described fault zone to be understood by mobile terminal at the first time with the personnel that rob, in system to faulty section Domain is isolated, and after continuing power supply to non-faulting region, breakdown repair can be carried out, at the first time so as to further contract The power off time of short fault zone improves the electricity consumption experience of user.
The present embodiment through the above scheme, passes through acquisition power production management data, geodata and multiple electric system Operational monitoring data, according to the power production management data, the geodata and each operational monitoring data generate power grid Integrated control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;It is real-time in the current electric grid When operation data exception, abnormality alarming information is generated;Had a power failure according to the abnormality alarming information to target terminal user push and is led to Know information, by the various data of synthesis, keeps the operating status of current electric grid high-visible, power system monitor efficiency is improved, in electricity Net operation data alerts in time when occurring abnormal, improves electric network emergency first-aid repair efficiency, and push power off notifying to user, mentions User experience is risen.
Further, Fig. 3 is the flow diagram of the electric integrated management-control method second embodiment of the present invention, as shown in figure 3, It is proposed the electric integrated management-control method second embodiment of the present invention based on first embodiment, in the present embodiment, the step S20 it Afterwards, affiliated electric integrated management-control method is further comprising the steps of:
Step S21, it in the troublshooting number for receiving target user, is searched in real time according to the electric network synthetic control figure Rope goes out troublshooting user information corresponding with the troublshooting number.
It is understood that receive target user report incoming call for repairment after, record corresponding troublshooting number, it is described Electric network synthetic control figure searches out troublshooting user information corresponding with the troublshooting number, the troublshooting in real time User information can include but is not limited to: reporting personnel's name, address and Customs Assigned Number for repairment, certainly can also include other kinds of User information, the present embodiment are without restriction to this;It can be looked for by the electric network synthetic control figure according to these essential informations To corresponding related information, to prepare for consequent malfunction repairing;It can certainly be that system is somewhither matched in monitoring When accident hinders, fault repairing information is actively generated in time, and then is distributed corresponding failure and reported work order for repairment to corresponding repair personnel's hand In, carry out repairing processing.
Step S22, troublshooting work order is generated according to the troublshooting user information, and according to the troublshooting work Single load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area for obtaining the target user Real-time running state information.
Step S23, according to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated Platform area real-time running state information determines emergency first-aid repair scheme.
Step S24, breakdown repair is carried out according to the emergency first-aid repair scheme.
It is understood that corresponding troublshooting work order can be generated according to the troublshooting user information, thus The load nature of electricity consumed information, ammeter status information, payment information, institute of the target user are found by the electric network synthetic control figure Belong to line information and affiliated platform area real-time running state information, according to these associations corresponding with the troublshooting user information Information can determine the emergency first-aid repair scheme of breakdown repair, that is, pass through these passes corresponding with the troublshooting user information Connection information can determine the time for the equipment and repairing that the scale of repairing and repairing need, thus targetedly repaired, By to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area real time execution shape The analysis of state information can fast and accurately find failure combined symptoms, so that accurate reasonable arrangement repairing strength, is robbed according to emergency Repair the rapid rush-repair that scheme carries out failure.
In the concrete realization, the load nature of electricity consumed letter that work order obtains the corresponding target user is reported for repairment by real time fail Breath, ammeter status information, payment information, affiliated line information and affiliated platform area real-time running state information, can pass through in time Vehicle administrating system, individual soldier carry out Data Integration application with the systems such as terminal, emergency materials control are robbed, and report work for repairment for real time fail Single targetedly offer emergency first-aid repair scheme quickly solves failure to improve the efficiency of emergency first-aid repair, improves user's body It tests.
Further, the step S24 specifically includes the following steps:
According to the emergency first-aid repair scheme determine the target vehicle for handling the troublshooting work order, target rush repair equipment and Target repair personnel;
The troublshooting work order is sent on the mobile terminal of the target repair personnel, so that the target is repaired Personnel carry out breakdown repair using the target vehicle and the target rush repair equipment.
It should be understood that after determining the emergency first-aid repair scheme, can be determined according to the emergency first-aid repair scheme at The target vehicle, target rush repair equipment and target repair personnel of the troublshooting work order are managed, in general, vehicle pipe can be passed through Control system, individual soldier push with the system datas integration application such as terminal and emergency materials control is robbed to corresponding target repair personnel Corresponding troublshooting work order, thus make the target repair personnel using the target vehicle and the target rush repair equipment into Row breakdown repair, under the premise of comprehensive and accurate in the troublshooting work order information, determining emergency first-aid repair scheme being capable of needle To repairing the corresponding failure of the troublshooting work order for property, significant increase breakdown repair speed and efficiency.
In the concrete realization, when by the electric network synthetic manage graph discovery have data exception need to carry out troublshooting or When reporting number for repairment of user is received, the type of troublshooting is analyzed, different troublshootings determines different emergency Rush Repair Scheme can search client by keyword for example, reporting for repairment for the low voltage failure that number determines of reporting for repairment that user provides Essential information and affiliated common transformer and dedicated transformer data, work order or grid phone report for repairment record, affiliated platform area, Line status, meter parameter, address, whether arrearage and payment record, affiliated distribution transforming the information such as have a power failure, and realize caller client Accurate anticipation, in addition can be shifted to an earlier date by system information warning function and actively be made a phone call to failed subs criber, photos and sending messages informing mutually concerns feeling Condition, it is ensured that effectively accurately linked up with user at the first time, promote user power utilization experience;For high-tension line and low-voltage platform area event Barrier, can by the electric network synthetic manage figure to corresponding monitoring data carry out centralized displaying, the monitoring data include but Be not limited to: load, electricity, distribution presence, real-time line loss, stop the data such as power transmission number, repair ticket at reliability in time, lead to It crosses to platform zone state real-time monitoring, is immediately generated warning information when platform area breaks down, to quickly be carried out to abnormal failure Processing.
The present embodiment through the above scheme, by the troublshooting number for receiving target user, according to the electricity Net integrated control figure searches out troublshooting user information corresponding with the troublshooting number in real time;According to the failure report It repairs user information and generates troublshooting work order, and believed according to the load nature of electricity consumed that the troublshooting work order obtains the target user Breath, ammeter status information, payment information, affiliated line information and affiliated platform area real-time running state information;According to the electricity consumption Property information, ammeter status information, payment information, affiliated line information and affiliated platform area real-time running state information determine emergency Rush Repair Scheme;Breakdown repair is carried out according to the emergency first-aid repair scheme, timely quick response can be carried out to troublshooting, ensured The good service of electric power maintenance, improves the speed and efficiency of electric power first-aid, improves the electricity consumption experience of user.
Further, Fig. 4 is the flow diagram of the electric integrated management-control method 3rd embodiment of the present invention, as shown in figure 4, It is proposed the electric integrated management-control method 3rd embodiment of the present invention based on second embodiment, in the present embodiment, the step S30 it Afterwards, the electric integrated management-control method is further comprising the steps of:
Step S31, the abnormal rank of the abnormality alarming information is obtained.
It should be noted that the abnormal rank of the abnormality alarming information is the corresponding failure of real-time abnormality alarming information Rank can determine different repairing strategies, that is, decompose the exception by the abnormal rank of the determination abnormality alarming information The different Rush Repair Scheme of the different classes of determination of warning information uses different emergency first-aid repairs for the failure of different abnormal ranks Scheme, such as simple troubleshooting can be handled with worksheet processing people, and for large-scale troubleshooting, it needs to send corresponding Processing team and corresponding corollary equipment are targetedly handled.
Step S32, when the abnormal rank is default first level, level-one is generated according to the abnormality alarming information and is robbed Repair work order.
Step S33, work order is repaired according to the level-one and determines that level-one repairing group, level-one recovery vehicle and level-one repairing are set It is standby.
It is understood that the default first level is pre-set rank, it is corresponding to can be large-scale repairing work Rank, be also possible to the work more more complicated than general family's breakdown repair for rank, naturally it is also possible to be other types Corresponding rank, the present embodiment are without restriction to this;Level-one can be generated by the abnormality alarming information and repair work order, into And the corresponding repairing group of work order matching, vehicle and equipment are repaired according to the level-one.
Step S34, level-one repairing work order is sent on the mobile terminal of level-one repairing group, so that described Level-one is repaired group and is handled using the level-one recovery vehicle and level-one rush repair equipment level-one repairing work order.
It should be understood that determine level-one repairing work order corresponding level-one repairing group, level-one recovery vehicle and After level-one rush repair equipment, the level-one can be repaired to work order and be sent on the mobile terminal of level-one repairing group in time, To make level-one repairing group using the level-one recovery vehicle and level-one rush repair equipment to the level-one repair work order into Row processing.
In the concrete realization, whole with the system datas such as terminal and emergency materials control are robbed by vehicle administrating system, individual soldier Application is closed, can be realized the push level-one repairing work order on the mobile terminal of level-one repairing group, so that the level-one be made to repair Group obtains the corresponding accurate information of failure, is targetedly handled failure in time, the electric power of fast quick-recovery fault zone Supply.
Further, after the step S34, the electric integrated management-control method further include:
Receive the scene rush to repair video information that the mobile terminal of level-one repairing group uploads in real time;
Resource is dispatched according to the scene rush to repair video information to support level-one repairing group.
It is understood that level-one repairing group can also upload in real time fault in-situ by the mobile terminal of carrying Repairing video information, the scene rush to repair video information in addition to can by the level-one repair group mobile terminal it is real-time It outside uploading, can also be uploaded in real time by vehicle-mounted individual soldier's camera, and be interacted with live level-one repairing group, to realize The Real time visible call of command and control these and repairing scene, entire breakdown repair process are more intuitively changed, can be to scene Level-one repairing group is commanded and is supported, and be can further ensure that the safety of breakdown repair, is guaranteed the efficient of work quality With it is reliable
The present embodiment through the above scheme, passes through the abnormal rank of the acquisition abnormality alarming information;In the abnormal grade When Wei not preset first level, level-one is generated according to the abnormality alarming information and repairs work order;Work order is repaired according to the level-one Determine level-one repairing group, level-one recovery vehicle and level-one rush repair equipment;Level-one repairing work order is sent to the level-one On the mobile terminal of repairing group, so that level-one repairing group utilizes the level-one recovery vehicle and level-one rush repair equipment pair Level-one repairing work order is handled, and can carry out specific aim processing to failure, it is ensured that the accuracy of troubleshooting and in time Property, it has ensured the good service of electric power maintenance, has improved the speed and efficiency of electric power first-aid, improved the electricity consumption experience of user.
The present invention further provides a kind of electric integrated managing and control systems.
Referring to Fig. 5, Fig. 5 is the functional block diagram of the electric integrated managing and control system first embodiment of the present invention.
In the electric integrated managing and control system first embodiment of the present invention, which includes:
Figure generation module 10 is managed, for obtaining the fortune of power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic according to the power production management data, the geodata and each operational monitoring data Control figure.
It should be noted that the power production management data are power engineering production management system (Power Production Management System, PMS) in the management data in relation to power generation, the geodata be geography Geographical location information number in relation to power grid overlay area in information system (Geographic Information System, GIS) According to the operational monitoring data are multiple electric system, such as OPEN3000, Open3200 distribution automation of production scheduling All kinds of distribution operation datas, fault recorder data and the monitoring of platform area in system, teletransmission type fault recording system and platform area monitoring system Operational monitoring data in the various electric system such as data;It can certainly be the operation number of other more or less electric system According to the present embodiment is without restriction to this.
It is understood that by by the power production management data, geodata and the operation of multiple electric system Monitoring data are integrated, and electric network synthetic control figure can be generated, the electric network synthetic control figure can be to various operation datas Carry out real-time centralized displaying, can be similar to keyword by way of quickly check route, power supply unit, counting equipment with The monitoring efficiency of power grid can be greatly improved in user information, the foundation of the electric network synthetic control figure.
Further, the control figure generation module 10 is also used to obtain power production management data, geodata and more The operational monitoring data of a electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, It is established between the power production management data, geodata and the operational monitoring data of multiple electric system based on the analysis results Target mapping relations;
According to the fortune of the target mapping relations and the power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic control figure.
It should be understood that by the power production management data, geodata and the operation of multiple electric system Monitoring data are analyzed, can be analyzed as a result, according to the analysis result establish the power production management data, The target mapping relations between data and the operational monitoring data of multiple electric system are managed, wherein the operational monitoring data include But it is not limited to: real time monitoring main transformer data, track data, distribution transformer load data, bus and line voltage distribution data, route actual time line It damages data, each branch switch and distribution transforming status data and stops power transmission information and heavy-overload situation data, by closing each data Connection gets up, and can determine the target mapping relations, thus according to the target mapping relations and the power production management number Electric network synthetic control figure is generated according to, geodata and the operational monitoring data of multiple electric system, may be implemented to various indexs The centralized displaying of data reaches the real time monitoring to bottom data, advantageously forms complete supervisor's rectification mechanism, is conducive to electricity The promotion of net quality monitoring and monitoring efficiency.
In the concrete realization, by the power production management data, geodata and the operation of multiple electric system Monitoring data are analyzed, using the data of long-term running generation, to personnel, equipment, portfolio state, all kinds of power grid constructions The historical data of economy counted, large database concept can be formed and then carry out targetedly analysis, be subsequent power grid Construction and maintenance work provide data supporting foundation.
Real time data acquisition module 20 obtains current electric grid real time execution number for managing figure according to the electric network synthetic According to.
It can be with quick search to the key message pair for wanting inquiry it is understood that managing figure by the electric network synthetic The operation data answered, by real-time grid integrated control figure in addition to current electric grid real-time running data can be inquired, moreover it is possible to return The grid operation data of query history of tracing back set period;In general, can by keyword query to corresponding basic data with And current electric grid operation data, be conducive to improve power system monitor speed and efficiency.
Alarm module 30, for generating abnormality alarming information in the current electric grid real-time running data exception.
It should be understood that by the way that current electric grid real-time running data to be compared with default grid operation data, it can To judge whether real-time current electric grid real-time running data is abnormal, default grid operation data is pre-set various in real time The preset threshold range set of basic data, when different data not relative to preset threshold range in when, i.e., judgement work as Preceding power grid real-time running data is abnormal, generates abnormality alarming information in time at this time, and be sent to command and control center, carries out next Step processing;The data exception can be the exception of track data, is also possible to the exception of device data, can also be at system Manage the exception of data, naturally it is also possible to be the exception of other data, the present embodiment is without restriction to this.
Notification module 40, for pushing power off notifying information to target terminal user according to the abnormality alarming information.
It is understood that the abnormality alarming information can be line anomalies warning information, it is also possible to unit exception Warning information, can also be other kinds of abnormality alarming information, and the present embodiment is without restriction to this;Obtaining abnormality alarming It, can be according to the corresponding target terminal user of the abnormality alarming acquisition of information, thus in time to the target user after information Terminal pushes power off notifying information, improves the electricity consumption experience of user.Further, the notification module 40, is also used to institute It states abnormality alarming information and carries out Macro or mass analysis, obtain the affiliated platform area in the corresponding fault zone of the abnormality alarming information;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, stop to target terminal user push Electric notification information.
It should be understood that the abnormality alarming can be obtained by carrying out Macro or mass analysis to the abnormality alarming information The corresponding fault zone of information, to determine affiliated platform area according to the fault zone;The abnormality alarming information is converged Bulk analysis, which can be, periodically carries out Macro or mass analysis to a plurality of abnormality alarming information, is also possible in real time believe different abnormality alarmings Breath carries out Macro or mass analysis, naturally it is also possible to be to carry out Macro or mass analysis, the present embodiment pair to abnormality alarming information by other means This is without restriction;The corresponding use in the affiliated platform area in the fault zone can be quickly found by the electric network synthetic control figure Family information list, for example, tripping of breaking down abnormality alarming information when, can quickly determine abnormality alarming information it is corresponding therefore Hinder region, and then determine the affiliated platform area in fault zone and user information list, so that command and control center be facilitated accurately to grasp Fault coverage, thus in fault coverage user terminal and the corresponding user terminal of the user information list as target User terminal, and power off notifying information is pushed to target terminal user.
In the concrete realization, when having monitored abnormality alarming information, fault zone can be quickly determined, and rob people to matching Member, i.e., the staff of handling failure mobile terminal show fault zone range, scope of power outage Nei Tai area's information and User information list, it is described fault zone to be understood by mobile terminal at the first time with the personnel that rob, in system to faulty section Domain is isolated, and after continuing power supply to non-faulting region, breakdown repair can be carried out, at the first time so as to further contract The power off time of short fault zone improves the electricity consumption experience of user.
The present embodiment through the above scheme, passes through acquisition power production management data, geodata and multiple electric system Operational monitoring data, according to the power production management data, the geodata and each operational monitoring data generate power grid Integrated control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;It is real-time in the current electric grid When operation data exception, abnormality alarming information is generated;Had a power failure according to the abnormality alarming information to target terminal user push and is led to Know information, by the various data of synthesis, keeps the operating status of current electric grid high-visible, power system monitor efficiency is improved, in electricity Net operation data alerts in time when occurring abnormal, improves electric network emergency first-aid repair efficiency, and push power off notifying to user, mentions User experience is risen.
In addition, the embodiment of the present invention also proposes a kind of storage medium, electric integrated control is stored on the storage medium Program realizes following operation when the electric integrated control program is executed by processor:
Power production management data, geodata and the operational monitoring data of multiple electric system are obtained, according to the electricity Power production management data, the geodata and each operational monitoring data generate electric network synthetic control figure;
Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;
In the current electric grid real-time running data exception, abnormality alarming information is generated;
Power off notifying information is pushed to target terminal user according to the abnormality alarming information.
Further, following operation is also realized when the electric integrated control program is executed by processor:
In the troublshooting number for receiving target user, searched out in real time according to the electric network synthetic control figure and institute State the corresponding troublshooting user information of troublshooting number;
Troublshooting work order is generated according to the troublshooting user information, and institute is obtained according to the troublshooting work order State load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and the affiliated platform area real time execution of target user Status information;
It is real-time according to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area Running state information determines emergency first-aid repair scheme;
Breakdown repair is carried out according to the emergency first-aid repair scheme.
Further, following operation is also realized when the electric integrated control program is executed by processor:
According to the emergency first-aid repair scheme determine the target vehicle for handling the troublshooting work order, target rush repair equipment and Target repair personnel;
The troublshooting work order is sent on the mobile terminal of the target repair personnel, so that the target is repaired Personnel carry out breakdown repair using the target vehicle and the target rush repair equipment.
Further, following operation is also realized when the electric integrated control program is executed by processor:
Obtain the abnormal rank of the abnormality alarming information;
When the abnormal rank is default first level, level-one is generated according to the abnormality alarming information and repairs work order;
Work order, which is repaired, according to the level-one determines level-one repairing group, level-one recovery vehicle and level-one rush repair equipment;
Level-one repairing work order is sent on the mobile terminal of level-one repairing group, so that the level-one is repaired Group is handled level-one repairing work order using the level-one recovery vehicle and level-one rush repair equipment.
Further, following operation is also realized when the electric integrated control program is executed by processor:
Receive the scene rush to repair video information that the mobile terminal of level-one repairing group uploads in real time;
Resource is dispatched according to the scene rush to repair video information to support level-one repairing group.
Further, following operation is also realized when the electric integrated control program is executed by processor:
Obtain power production management data, geodata and the operational monitoring data of multiple electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, It is established between the power production management data, geodata and the operational monitoring data of multiple electric system based on the analysis results Target mapping relations;
According to the fortune of the target mapping relations and the power production management data, geodata and multiple electric system Row monitoring data generate electric network synthetic control figure.
Further, following operation is also realized when the electric integrated control program is executed by processor:
Macro or mass analysis is carried out to the abnormality alarming information, is obtained belonging to the corresponding fault zone of the abnormality alarming information Platform area;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, stop to target terminal user push Electric notification information.
The present embodiment through the above scheme, passes through acquisition power production management data, geodata and multiple electric system Operational monitoring data, according to the power production management data, the geodata and each operational monitoring data generate power grid Integrated control figure;Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;It is real-time in the current electric grid When operation data exception, abnormality alarming information is generated;Had a power failure according to the abnormality alarming information to target terminal user push and is led to Know information, by the various data of synthesis, keeps the operating status of current electric grid high-visible, power system monitor efficiency is improved, in electricity Net operation data alerts in time when occurring abnormal, improves electric network emergency first-aid repair efficiency, and push power off notifying to user, mentions User experience is risen.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or the system that include a series of elements not only include those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or system institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including being somebody's turn to do There is also other identical elements in the process, method of element, article or system.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
The above is only a preferred embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (10)

1. a kind of electric integrated management-control method, which is characterized in that the electric integrated management-control method includes:
Power production management data, geodata and the operational monitoring data of multiple electric system are obtained, it is raw according to the electric power It produces management data, the geodata and each operational monitoring data and generates electric network synthetic control figure;
Figure, which is managed, according to the electric network synthetic obtains current electric grid real-time running data;
In the current electric grid real-time running data exception, abnormality alarming information is generated;
Power off notifying information is pushed to target terminal user according to the abnormality alarming information.
2. electric integrated management-control method as described in claim 1, which is characterized in that described managed according to the electric network synthetic is schemed After obtaining current electric grid real-time running data, the electric integrated management-control method further include:
In the troublshooting number for receiving target user, searched out in real time and the event according to the electric network synthetic control figure Barrier reports the corresponding troublshooting user information of number for repairment;
Troublshooting work order is generated according to the troublshooting user information, and the mesh is obtained according to the troublshooting work order Mark load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and the affiliated platform area real-time running state of user Information;
According to the load nature of electricity consumed information, ammeter status information, payment information, affiliated line information and affiliated platform area real time execution Status information determines emergency first-aid repair scheme;
Breakdown repair is carried out according to the emergency first-aid repair scheme.
3. electric integrated management-control method as claimed in claim 2, which is characterized in that it is described according to the emergency first-aid repair scheme into Row breakdown repair, specifically includes:
Target vehicle, target rush repair equipment and the target for handling the troublshooting work order are determined according to the emergency first-aid repair scheme Repair personnel;
The troublshooting work order is sent on the mobile terminal of the target repair personnel, so that the target repair personnel Breakdown repair is carried out using the target vehicle and the target rush repair equipment.
4. electric integrated management-control method as claimed in claim 3, which is characterized in that described in the current electric grid real time execution When data exception, after generating abnormality alarming information, the electric integrated management-control method further include:
Obtain the abnormal rank of the abnormality alarming information;
When the abnormal rank is default first level, level-one is generated according to the abnormality alarming information and repairs work order;
Work order, which is repaired, according to the level-one determines level-one repairing group, level-one recovery vehicle and level-one rush repair equipment;
Level-one repairing work order is sent on the mobile terminal of level-one repairing group, so that the level-one repairs group Level-one repairing work order is handled using the level-one recovery vehicle and level-one rush repair equipment.
5. electric integrated management-control method as claimed in claim 4, which is characterized in that described to send level-one repairing work order To the mobile terminal of level-one repairing group, so that level-one repairing group utilizes the level-one recovery vehicle and level-one After rush repair equipment handles level-one repairing work order, the electric integrated management-control method further include:
Receive the scene rush to repair video information that the mobile terminal of level-one repairing group uploads in real time;
Resource is dispatched according to the scene rush to repair video information to support level-one repairing group.
6. electric integrated management-control method according to any one of claims 1 to 5, which is characterized in that the acquisition power generation Data, the operational monitoring data of geodata and multiple electric system are managed, according to power production management data, described It manages data and each operational monitoring data generates electric network synthetic control figure, specifically include:
Obtain power production management data, geodata and the operational monitoring data of multiple electric system;
The power production management data, geodata and the operational monitoring data of multiple electric system are analyzed, according to Analysis result establishes the mesh between the power production management data, geodata and the operational monitoring data of multiple electric system Mark mapping relations;
It is supervised according to the operation of the target mapping relations and the power production management data, geodata and multiple electric system Measured data generates electric network synthetic control figure.
7. the electric integrated management-control method as described in claim 1-5, which is characterized in that described to be believed according to the abnormality alarming It ceases to target terminal user and pushes power off notifying information, specifically include:
Macro or mass analysis is carried out to the abnormality alarming information, obtains the corresponding affiliated platform in fault zone of the abnormality alarming information Area;
Obtain the corresponding user information list in the affiliated platform area in the fault zone;
Using the corresponding user terminal of the user information list as target terminal user, have a power failure to target terminal user push logical Know information.
8. a kind of electric integrated managing and control system, which is characterized in that the electric integrated managing and control system includes:
Figure generation module is managed, for obtaining the operational monitoring of power production management data, geodata and multiple electric system Data generate electric network synthetic control figure according to the power production management data, the geodata and each operational monitoring data;
Real time data acquisition module obtains current electric grid real-time running data for managing figure according to the electric network synthetic;
Alarm module, for generating abnormality alarming information in the current electric grid real-time running data exception;
Notification module, for pushing power off notifying information to target terminal user according to the abnormality alarming information.
9. a kind of server, which is characterized in that the server includes: memory, processor and is stored on the memory And the electric integrated control program that can be run on the processor, the electric integrated control program are arranged for carrying out such as right It is required that the step of electric integrated management-control method described in any one of 1 to 7.
10. a kind of storage medium, which is characterized in that be stored with electric integrated control program, the electric power on the storage medium Realizing the electric integrated management-control method as described in any one of claims 1 to 7 when integrated control program is executed by processor Step.
CN201811030220.3A 2018-09-04 2018-09-04 Electric integrated management-control method, system, server and storage medium Pending CN109149565A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811030220.3A CN109149565A (en) 2018-09-04 2018-09-04 Electric integrated management-control method, system, server and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811030220.3A CN109149565A (en) 2018-09-04 2018-09-04 Electric integrated management-control method, system, server and storage medium

Publications (1)

Publication Number Publication Date
CN109149565A true CN109149565A (en) 2019-01-04

Family

ID=64826931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811030220.3A Pending CN109149565A (en) 2018-09-04 2018-09-04 Electric integrated management-control method, system, server and storage medium

Country Status (1)

Country Link
CN (1) CN109149565A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110460051A (en) * 2019-09-25 2019-11-15 广东稳峰电力科技有限公司 A kind of medium voltage distribution network contact method and system based on net capability
CN110458713A (en) * 2019-07-05 2019-11-15 中国平安人寿保险股份有限公司 Model Monitoring method, apparatus, computer equipment and storage medium
CN110807287A (en) * 2019-11-05 2020-02-18 广东电网有限责任公司 Construction method for dividing service grids in emergency repair point arrangement scene based on finite element grids
CN111126971A (en) * 2020-03-27 2020-05-08 国网山东省电力公司青州市供电公司 Power supply network, marketing and distribution through integrated display platform and equipment
CN111582549A (en) * 2020-04-14 2020-08-25 广东卓维网络有限公司 Power station monitoring and rush-repair system based on GIS
CN111582550A (en) * 2020-04-14 2020-08-25 广东卓维网络有限公司 Power station fault first-aid repair quick response system based on GIS
CN111913147A (en) * 2020-08-05 2020-11-10 国网甘肃省电力公司营销服务中心 Monitoring method and device of power metering device based on Internet of things, server and storage medium
CN111983383A (en) * 2020-08-17 2020-11-24 海南电网有限责任公司信息通信分公司 Power system fault first-aid repair method and system
CN112101815A (en) * 2020-09-25 2020-12-18 贵州电网有限责任公司 Construction management visualization system for capital construction distribution network project
CN112269859A (en) * 2020-11-16 2021-01-26 国网山东省电力公司聊城供电公司 Power supply and distribution data optimization rapid processing system, equipment and readable storage medium
CN112688435A (en) * 2021-01-15 2021-04-20 广东电网有限责任公司广州供电局 Power grid comprehensive monitoring method, device, control system and storage medium
CN112838947A (en) * 2020-12-23 2021-05-25 广州体育职业技术学院 Construction method of power communication scheduling system
CN113128719A (en) * 2021-04-27 2021-07-16 国网河北省电力有限公司石家庄供电分公司 Power line repair management method
CN113381872A (en) * 2020-03-10 2021-09-10 北京科东电力控制***有限责任公司 Partition-based electric power system abnormal alarm processing method and system
CN113408943A (en) * 2021-07-13 2021-09-17 国网上海市电力公司 User power failure information interactive intelligent management system and management method
CN113780869A (en) * 2021-09-22 2021-12-10 南方电网数字电网研究院有限公司 Power grid data comprehensive processing system based on big data storage
CN114152835A (en) * 2020-09-08 2022-03-08 韦渊 Power utilization safety monitoring system
CN115411839A (en) * 2022-09-26 2022-11-29 四川君诚互动科技有限公司 Network distribution dispatching platform for power grid

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008287444A (en) * 2007-05-16 2008-11-27 Chugoku Electric Power Co Inc:The Repair staff calling system, method and program
CN103714437A (en) * 2014-01-09 2014-04-09 海南电网公司信息通信分公司 Power line repair commanding method based on CIS and movable operation
CN104077641A (en) * 2013-03-28 2014-10-01 国家电网公司 Power grid operation and emergency command method and power commanding system
CN104091231A (en) * 2014-06-30 2014-10-08 国家电网公司 Distribution network fault repairing commanding and processing system and method
CN107276041A (en) * 2017-05-16 2017-10-20 国网山东省电力公司临清市供电公司 Power distribution network rushes to repair maneuvering platform
CN108267670A (en) * 2017-12-29 2018-07-10 国家电网公司 A kind of Distribution Network Failure studies and judges early warning system and its implementation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008287444A (en) * 2007-05-16 2008-11-27 Chugoku Electric Power Co Inc:The Repair staff calling system, method and program
CN104077641A (en) * 2013-03-28 2014-10-01 国家电网公司 Power grid operation and emergency command method and power commanding system
CN103714437A (en) * 2014-01-09 2014-04-09 海南电网公司信息通信分公司 Power line repair commanding method based on CIS and movable operation
CN104091231A (en) * 2014-06-30 2014-10-08 国家电网公司 Distribution network fault repairing commanding and processing system and method
CN107276041A (en) * 2017-05-16 2017-10-20 国网山东省电力公司临清市供电公司 Power distribution network rushes to repair maneuvering platform
CN108267670A (en) * 2017-12-29 2018-07-10 国家电网公司 A kind of Distribution Network Failure studies and judges early warning system and its implementation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蔡高升: ""浅谈配网抢修标准化建设"", 《科技经济导刊》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110458713A (en) * 2019-07-05 2019-11-15 中国平安人寿保险股份有限公司 Model Monitoring method, apparatus, computer equipment and storage medium
CN110458713B (en) * 2019-07-05 2023-10-13 中国平安人寿保险股份有限公司 Model monitoring method, device, computer equipment and storage medium
CN110460051A (en) * 2019-09-25 2019-11-15 广东稳峰电力科技有限公司 A kind of medium voltage distribution network contact method and system based on net capability
CN110807287A (en) * 2019-11-05 2020-02-18 广东电网有限责任公司 Construction method for dividing service grids in emergency repair point arrangement scene based on finite element grids
CN113381872A (en) * 2020-03-10 2021-09-10 北京科东电力控制***有限责任公司 Partition-based electric power system abnormal alarm processing method and system
CN111126971A (en) * 2020-03-27 2020-05-08 国网山东省电力公司青州市供电公司 Power supply network, marketing and distribution through integrated display platform and equipment
CN111582549A (en) * 2020-04-14 2020-08-25 广东卓维网络有限公司 Power station monitoring and rush-repair system based on GIS
CN111582550A (en) * 2020-04-14 2020-08-25 广东卓维网络有限公司 Power station fault first-aid repair quick response system based on GIS
CN111913147A (en) * 2020-08-05 2020-11-10 国网甘肃省电力公司营销服务中心 Monitoring method and device of power metering device based on Internet of things, server and storage medium
CN111983383A (en) * 2020-08-17 2020-11-24 海南电网有限责任公司信息通信分公司 Power system fault first-aid repair method and system
CN114152835A (en) * 2020-09-08 2022-03-08 韦渊 Power utilization safety monitoring system
CN112101815A (en) * 2020-09-25 2020-12-18 贵州电网有限责任公司 Construction management visualization system for capital construction distribution network project
CN112269859A (en) * 2020-11-16 2021-01-26 国网山东省电力公司聊城供电公司 Power supply and distribution data optimization rapid processing system, equipment and readable storage medium
CN112838947A (en) * 2020-12-23 2021-05-25 广州体育职业技术学院 Construction method of power communication scheduling system
CN112688435A (en) * 2021-01-15 2021-04-20 广东电网有限责任公司广州供电局 Power grid comprehensive monitoring method, device, control system and storage medium
CN113128719A (en) * 2021-04-27 2021-07-16 国网河北省电力有限公司石家庄供电分公司 Power line repair management method
CN113408943A (en) * 2021-07-13 2021-09-17 国网上海市电力公司 User power failure information interactive intelligent management system and management method
CN113780869A (en) * 2021-09-22 2021-12-10 南方电网数字电网研究院有限公司 Power grid data comprehensive processing system based on big data storage
CN115411839A (en) * 2022-09-26 2022-11-29 四川君诚互动科技有限公司 Network distribution dispatching platform for power grid

Similar Documents

Publication Publication Date Title
CN109149565A (en) Electric integrated management-control method, system, server and storage medium
CN100466416C (en) Intelligent decision support system for urban power grid accidents
CN102646230B (en) A kind of infosystem realizing the management of distribution network failure fast power restoration
CN105564465B (en) A kind of railway electric signal plant maintenance operation control system and method
CN111007433B (en) Intelligent electricity utilization safety supervision system based on Internet of things
CN106990328A (en) The analysis of distribution repairing abnormal data, fault location system and method
CN105871605A (en) Operation and maintenance monitoring platform based on big power marketing data
CN103558818A (en) Cable 10kV high voltage ring main unit remote monitoring and control system
CN109784508A (en) A kind of power grid panorama monitoring operation management method and system based on cloud platform
CN104077641A (en) Power grid operation and emergency command method and power commanding system
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN104124756A (en) Province-level power distribution network operation monitoring system based on network-wide data
CN107920111A (en) A kind of integral intelligent collecting method and platform based on surface weather observation
Hu et al. Research and application of capability maturity model for Chinese intelligent manufacturing
CN108267670B (en) Distribution network fault study and judgment early warning system and implementation method thereof
CN101267359A (en) Optical cable monitoring device
CN106355357A (en) Power distribution network fault processing method and information processing system
CN103279830A (en) Transformer substation or converter station accident handling cloud terminal remote support decision-making method and system
CN110928254A (en) Environment-friendly monitoring method and system for operation of pollution control equipment produced by pollution discharge enterprise
CN111756581A (en) Power distribution network operation fault processing method and device, computer equipment and storage medium
CN112987632A (en) Intelligent operation and maintenance system for equipment based on Internet of things
CN111667076A (en) Tracking method for processing power failure fault
CN108539856A (en) Power distribution network complete perception operation monitoring power distribution rush-repair system
CN117714260A (en) Remote centralized operation and maintenance method for distributed resource edge gateway under cloud edge fusion architecture
CN113064399A (en) Industrial monitoring software prediction maintenance system based on big data distributed programming framework

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104