CN109113059A - Cast-in-situ bored pile breaks a processing method - Google Patents
Cast-in-situ bored pile breaks a processing method Download PDFInfo
- Publication number
- CN109113059A CN109113059A CN201811008918.5A CN201811008918A CN109113059A CN 109113059 A CN109113059 A CN 109113059A CN 201811008918 A CN201811008918 A CN 201811008918A CN 109113059 A CN109113059 A CN 109113059A
- Authority
- CN
- China
- Prior art keywords
- hole
- interlayer
- grouting pipe
- concrete
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/64—Repairing piles
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to bored concrete pile technology fields more particularly to a kind of cast-in-situ bored pile to break a processing method, comprising the following steps: Step 1: verifying the interlayer position of bored concrete pile;Step 2: the depth in hole is up to the position of interlayer in one hole of centre drill of bored concrete pile;Step 3: going deep into a Grouting Pipe into hole, it is equipped with a sealing ring, the inner wall tight fit of sealing ring and the hole front ring week of the Grouting Pipe, Grouting Pipe is deep into interlayer, high pressure concrete is injected into interlayer, high pressure concrete squeezes out mud from interlayer;Step 4: being lifted up Grouting Pipe, while high pressure concrete is injected into hole, the final solidifying soil of high nip drum seals hole.It this method effective solution the problem of interlayer is broken in the prior art, is not influenced by pile diameter, so that it may complete the work of piling.
Description
Technical field
The present invention relates to anchor pole clearance technique fields more particularly to a kind of cast-in-situ bored pile to break a processing method.
Background technique
Currently, bored concrete pile usually carries out in the following way in production, first makes a hole on the ground, place into reinforcing bar
Concrete is driven into steel reinforcement cage finally by Grouting Pipe, Grouting Pipe is usually first deep into the bottommost in hole, slowly by cage
Mention upwards, for the concrete in Grouting Pipe from the bottom in hole as Grouting Pipe promotion is injected into hole, the mud in hole can quilt
Concrete is upward out.But in practice of construction, if Grouting Pipe promotion is too fast, mud will be mixed between concrete,
Or Grouting Pipe is broken in lifting process, can all mud be caused to enter between concrete, there have been the folders of concrete for this
Layer, which is mud, leads to the weakened of entire bored concrete pile, and such case occurs in general unit in charge of construction, is all weight
A stake is newly played, this cost is relatively high, and also a kind of mode is to make a hole on bored concrete pile after solidification, then be put into hole
A piece reinforcing bar, reinjects concrete, to play the role of connecting two parts above and below interlayer, this mode to diameter compared with
Small bored concrete pile is also possible that but bored concrete pile more than one meter in diameter is not appropriate for that must need very thick reinforcing bar, because
And the program and unrealistic.
Summary of the invention
It is an object of the invention to overcome the shortcomings of above-mentioned technology, and provide a kind of cast-in-situ bored pile drawing broken pile treatment side
Method.
To achieve the above object, using following technical scheme: a kind of cast-in-situ bored pile breaks a processing method to the present invention,
It is characterized in that: the following steps are included:
Step 1: verifying the interlayer position of bored concrete pile;
Step 2: the depth in hole is up to the position of interlayer in one hole of centre drill of bored concrete pile;
Step 3: go deep into a Grouting Pipe into hole, be equipped with a sealing ring front ring week of the Grouting Pipe, sealing ring with
The inner wall in the hole is fitted close, and Grouting Pipe is deep into interlayer, injects high pressure concrete into interlayer, and high pressure concrete is by mud
Slurry is squeezed out from interlayer;
Step 4: being lifted up Grouting Pipe, while high pressure concrete is injected into hole, final high nip drum is solidifying native by Kong Mi
Envelope.
Preferably, the diameter in the hole is 110mm-120mm.
Preferably, in step 1, using the position of ultrasonic equipment detection interlayer.
Preferably, the sealing ring is rubber material.
The beneficial effects of the present invention are: compared with the existing technology, interlayer is disconnected in the prior art for this method effective solution
The problem of splitting, by making a hole on bored concrete pile, the diameter in the hole is very small, can be adapted for diameter at one meter or more
The effect for acting on hole in the prior art of the work of bored concrete pile piling, hole is different, and the application mesoporous is as connection interlayer
Channel, and one sealing ring, the side wall tight fit of the sealing ring and hole are set in the front of Grouting Pipe, such interlayer is exactly
The space of one sealing, then high pressure concrete is injected into Grouting Pipe, high pressure concrete enters backward in interlayer from Grouting Pipe
Surrounding squeezes mud, and the originally position of mud will be accounted for by high pressure concrete into mud is expressed into the sky of surrounding from interlayer
Between, after high pressure concrete fills full interlayer, realize the pile extension of upper and lower ends bored concrete pile, finally as Grouting Pipe is lifted up,
High pressure concrete fills hole.
Detailed description of the invention
Fig. 1 is that the structural schematic diagram of interlayer occurs in bored concrete pile in the present invention;
Fig. 2 is the structural schematic diagram for injecting high pressure concrete in the present invention into interlayer;
Fig. 3 is state diagram when Grouting Pipe is lifted up in the present invention.
Specific embodiment
With reference to the accompanying drawing and the preferred embodiment specific embodiment that the present invention will be described in detail.As shown in Figure 1-3, a kind of
Cast-in-situ bored pile breaks a processing method, comprising the following steps:
Step 1: verifying 1 position of interlayer of bored concrete pile;Using the position of ultrasonic equipment detection interlayer.
Step 2: the depth in hole is up to the position of interlayer in one hole 2 of centre drill of bored concrete pile;In the straight of the hole
Diameter is 110mm-120mm.The diameter of mesoporous of the present invention can be beaten very small, not limited by pile diameter, and cost is very
It is low.
Step 3: going deep into a Grouting Pipe 3 into hole, the front ring week of the Grouting Pipe is equipped with a sealing ring 4, described close
Seal ring is rubber material.Sealing ring and the inner wall in the hole are fitted close, and Grouting Pipe is deep into interlayer, are injected into interlayer high
Concrete 5 is pressed, high pressure concrete squeezes out mud 6 from interlayer;Due to all loosening the soil around general bored concrete pile, so high pressure is mixed
Mud can be easily extruded into the loosening the soil of surrounding by solidifying soil.
Step 4: being lifted up Grouting Pipe, while high pressure concrete is injected into hole, final high nip drum is solidifying native by Kong Mi
Envelope.This method can be linked together the bored concrete pile of fracture with the concrete of same specification, and intensity was with being identical in the past
's.
By making a hole on bored concrete pile, the diameter in the hole is very small, can be adapted for diameter at one meter or more
The effect for acting on hole in the prior art of the work of bored concrete pile piling, hole is different, and the application mesoporous is as connection interlayer
Channel, and one sealing ring, the side wall tight fit of the sealing ring and hole are set in the front of Grouting Pipe, such interlayer is exactly
The space of one sealing, then high pressure concrete is injected into Grouting Pipe, high pressure concrete enters backward in interlayer from Grouting Pipe
Surrounding squeezes mud, and the originally position of mud will be accounted for by high pressure concrete into mud is expressed into the sky of surrounding from interlayer
Between, after high pressure concrete fills full interlayer, realize the pile extension of upper and lower ends bored concrete pile, finally as Grouting Pipe is lifted up,
High pressure concrete fills hole.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered
It is considered as protection scope of the present invention.
Claims (4)
1. a kind of cast-in-situ bored pile breaks a processing method, it is characterised in that: the following steps are included:
Step 1: verifying the interlayer position of bored concrete pile;
Step 2: the depth in hole is up to the position of interlayer in one hole of centre drill of bored concrete pile;
Step 3: go deep into a Grouting Pipe into hole, be equipped with a sealing ring front ring week of the Grouting Pipe, sealing ring with it is described
The inner wall in hole is fitted close, and Grouting Pipe is deep into interlayer, injects high pressure concrete into interlayer, high pressure concrete by mud from
It is squeezed out in interlayer;
Step 4: being lifted up Grouting Pipe, while high pressure concrete is injected into hole, the final solidifying soil of high nip drum seals hole.
2. cast-in-situ bored pile according to claim 1 breaks a processing method, it is characterised in that: the diameter in the hole is
110mm-120mm。
3. cast-in-situ bored pile according to claim 1 breaks a processing method, it is characterised in that: in step 1, use
The position of ultrasonic equipment detection interlayer.
4. cast-in-situ bored pile according to claim 1 breaks a processing method, it is characterised in that: the sealing ring is rubber
Material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811008918.5A CN109113059A (en) | 2018-08-31 | 2018-08-31 | Cast-in-situ bored pile breaks a processing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811008918.5A CN109113059A (en) | 2018-08-31 | 2018-08-31 | Cast-in-situ bored pile breaks a processing method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109113059A true CN109113059A (en) | 2019-01-01 |
Family
ID=64861721
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811008918.5A Pending CN109113059A (en) | 2018-08-31 | 2018-08-31 | Cast-in-situ bored pile breaks a processing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109113059A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110016941A (en) * | 2019-04-23 | 2019-07-16 | 谢定茂 | The reinforcement means of pile foundation |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101413266A (en) * | 2008-11-28 | 2009-04-22 | 广东省长大公路工程有限公司 | Processing method of interlayer defect injection concrete of drill filling pile |
CN102041814A (en) * | 2010-12-31 | 2011-05-04 | 郭红军 | Novel composite pile (ground) foundation and application method thereof |
KR20170040602A (en) * | 2015-10-05 | 2017-04-13 | 김동욱 | Grouting device using a reinforced network is equipped with a small steel pipe |
-
2018
- 2018-08-31 CN CN201811008918.5A patent/CN109113059A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101413266A (en) * | 2008-11-28 | 2009-04-22 | 广东省长大公路工程有限公司 | Processing method of interlayer defect injection concrete of drill filling pile |
CN102041814A (en) * | 2010-12-31 | 2011-05-04 | 郭红军 | Novel composite pile (ground) foundation and application method thereof |
KR20170040602A (en) * | 2015-10-05 | 2017-04-13 | 김동욱 | Grouting device using a reinforced network is equipped with a small steel pipe |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110016941A (en) * | 2019-04-23 | 2019-07-16 | 谢定茂 | The reinforcement means of pile foundation |
CN110016941B (en) * | 2019-04-23 | 2021-01-26 | 武汉科诚基础工程有限责任公司 | Pile foundation reinforcing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104234055B (en) | A kind of prefabricated pile post-grouting device and technique thereof | |
CN104389314B (en) | A kind of shallow clay grouting and reinforcing device and method | |
CN105386433B (en) | A kind of microorganism soil-fixing CFG pile composite foundations and construction method | |
CN102926770A (en) | Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas | |
CN103924987B (en) | A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof | |
CN110258538B (en) | Soil nail reinforced buffer type manual hole digging pile and construction method thereof | |
CN104131556A (en) | Soft-and-hard interlayer alternation foundation drainage prestressed pipe pile and construction method | |
CN106761918A (en) | A kind of tunnel solution cavity and Groundwater Comprehensive administer construction and construction method | |
CN203200746U (en) | High-pressure jet grouting hollow reinforced tubular pile | |
CN210562157U (en) | Post-grouting composite pile | |
CN109083135A (en) | Miniature steel pipe pile construction method | |
CN106907157B (en) | A kind of shield machine normal pressure opens the cabin operation construction method | |
CN102852141A (en) | Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation | |
CN109680675A (en) | A kind of Stabilizing Grout method that can dynamically control grouting amount and harden opportunity | |
CN108385715A (en) | A kind of assembled stake arch combination retaining wall and its construction method | |
CN103498478B (en) | Rock curtain grouting in foundation of dam construction method | |
CN103161151A (en) | Construction method of high pressure jet grouting hollow strengthening tubular pile and high pressure jet grouting hollow strengthening tubular pile | |
CN109113059A (en) | Cast-in-situ bored pile breaks a processing method | |
CN110230314A (en) | A kind of piling strtucture and its construction method | |
CN206753653U (en) | A kind of tunnel solution cavity and Groundwater Comprehensive administer construction | |
CN206289627U (en) | A kind of post jacking pile tube | |
CN110685272B (en) | Method for treating soft foundation settlement overrun by utilizing inclined-hole cloth bag pile | |
CN107938640A (en) | A kind of microorganism fixing the handles device and its construction technology for sand-layer foundation | |
CN208472716U (en) | Crack geology mortar leakage prevention drill-pouring pilework | |
CN202430728U (en) | Water blocking equipment for water bursting control |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190101 |
|
RJ01 | Rejection of invention patent application after publication |