CN109098278A - The connecting structure and construction method of prefabricated beam column - Google Patents

The connecting structure and construction method of prefabricated beam column Download PDF

Info

Publication number
CN109098278A
CN109098278A CN201811134623.2A CN201811134623A CN109098278A CN 109098278 A CN109098278 A CN 109098278A CN 201811134623 A CN201811134623 A CN 201811134623A CN 109098278 A CN109098278 A CN 109098278A
Authority
CN
China
Prior art keywords
prefabricated
column
fiber
concrete
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811134623.2A
Other languages
Chinese (zh)
Inventor
赵秋
缪钰婷
黄金局
许家斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201811134623.2A priority Critical patent/CN109098278A/en
Publication of CN109098278A publication Critical patent/CN109098278A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to the connecting structure and construction method of a kind of prefabricated beam column, including prefabricated components and beam-column connection, prefabricated components are precast beam, prefabricated post, the beam-column connection is the intersection point of precast beam and prefabricated post, precast beam, prefabricated post is linked into an integrated entity by the cast-in-place concrete at beam-column connection, if the precast beam and prefabricated post end face at beam-column connection bury dry fibers, a part embedment precast beam of fiber, in prefabricated post, the other end of fiber protrudes into the cast-in-place concrete at beam-column connection, structure is reasonable for this, intensity is high, convenient construction, it can effectively avoid precast beam and the less reliable problem of prefabricated post junction intensity, assembled integral building system " strong shear capacity and weak bending capacity is fully ensured that, the design concept of stronger node ", be conducive to the development and popularization of assembled architecture system.

Description

The connecting structure and construction method of prefabricated beam column
Technical field
The present invention relates to the connecting structure and construction method of a kind of prefabricated beam column.
Background technique
Assembled architecture becomes the mode of construction based on site operation based on factory's production, is that building industry modernizes Important content, be building move towards the industrialization, an information-based vital step.Assembled architecture, which has, to be improved quality, shortens work Phase, it is energy saving, reduce consumption, clean manufacturing many advantages, such as.Currently, with China's rapid economic development, assembled architecture Widely promoted.Assembled monolithic concrete structure is current China with a kind of most assembled forms, and " equivalent original Then " be assembled monolithic concrete structure use a big core.Doctrine of equivalents is i.e.: assembled monolithic concrete structure should be basic Reach or approach the effects equivalent of the effect being equal with cast-in-place concrete structure, especially connection type.The component of factory's production It is superior, accomplish that the intensity of prefabricated components is equivalent easy with cast-in-place concrete, but the guarantee of connecting node intensity is one big Problem.
It is poured based on " wet seam ", that is, after passing through in the connection type of assembled integral building structure used at present Concrete makes to link together between prefabricated components.Although wet seam overall performance is good, exist in construction work many not true Qualitative, construction quality is difficult to ensure.And node was the weak part in building structure originally, once it goes wrong, it is possible to Catastrophic failure occurs.From stress, the power of connecting node needs directly to transmit by rear pouring concrete region, although new and old Concrete linkage interface sets rough surface, but its power transmission effect is poor, and power is transmitted mainly by various dowel, pre-buried weldment. Its stress performance reliability is not easy to guarantee especially under course under cyclic loading, and in earthquake territory, the application of fabricated construction receives greatly greatly Limit, therefore only solve the problems, such as that assembling type node connection could allow assembled architecture to be promoted.
Summary of the invention
The present invention proposes the connecting structure and construction method of a kind of prefabricated beam column.
The solution adopted by the present invention to solve the technical problem is that a kind of connecting structure of prefabricated beam column, including it is pre- Component and beam-column connection processed, the prefabricated components are precast beam, prefabricated post, and the beam-column connection is for precast beam and in advance The intersection point of column processed, precast beam, prefabricated post are linked into an integrated entity by the cast-in-place concrete at beam-column connection, beam-to-column joint section If dry fibers are buried in the precast beam at point place and prefabricated post end face, a part of fiber is embedded to precast beam, in prefabricated post, fiber The other end protrudes into the cast-in-place concrete at beam-column connection.
Further, fiber insertion precast beam, 0.3-0.6 times that the length in prefabricated post is fiber total length, fibre Direction and concrete linkage interface normal direction angle are tieed up less than 20 °.
Further, the fiber is appointing in steel fibre, glass fibre, polypropylene fibre, plant fiber or carbon fiber It anticipates one kind.
Further, concrete material cast-in-place at the beam-column connection is mixed using ultra-high performance concrete or fiber Solidifying soil.
Further, the prefabricated post includes prefabricated lower prop, prefabricated upper prop, under beam-column connection is precast beam and is prefabricated The intersection point of column, prefabricated upper prop, precast beam, prefabricated lower prop connect to form matrix by the cast-in-place concrete at beam-column connection, Matrix is starched by column pedestal to be connected with prefabricated upper prop.
Further, the cubic compressive strength for the mortar material that the column pedestal slurry uses is higher than prefabricated components concrete Cubic compressive strength.
Further, the precast beam, prefabricated column end are equipped with keyway.
Further, the position of beam-column connection is arranged at girder position or secondary beam position.
A kind of construction method of the connecting structure of prefabricated beam column, comprising the following steps:
1) prefabricated components are made: carrying out the prefabricated of beam and column by design requirement, the template of precast beam and prefabricated post is installed respectively, is hung Enter manufactured steel reinforcement cage, while placing respective built-in fitting, then the casting concrete in precast-concrete form, and carries out Maintenance, is respectively formed precast beam and prefabricated post, wherein being inserted into fiber in its end in the molding process of prefabricated components, and prefabricated Component carries out the dabbing of the concrete surface of rough surface during storing;
2) hoisting prefabricated column: surveying setting-out determines member position, carries out column muscle aligning, steel plate washer is levelling, for example top layer Prefabricated post is then lifted to the corresponding position of design by hoist cable, suspender, installs prefabricated post after reinforcing bar contraposition, such as by beam-to-column joint For the beam-to-column joint of middle layer, then prefabricated lower prop is lifted to by the corresponding position of design by hoist cable, suspender, pacified after reinforcing bar contraposition Prefabricated lower prop is filled, and after step (4), increased step (5);
3) precast beam: surveying setting-out is installed, precast beam is lifted into corresponding position using suspender and installed by arrangement support;
4) node connection construction: carrying out the reinforcing bar binding at beam-column connection, and set aside pre-embedded part installs stock mould at node Plate pours after inspection is errorless and smashes concrete at node, the form removal after it reaches 70% or more normal intensity, in node concrete Before ot-yet-hardened, by the insertion concrete of fiber partial-length, the length of fiber spacing and fiber is determined according to design;
5) install prefabricated upper prop: in corresponding column bottom position, seat is starched, and carries out column muscle aligning, by hoist cable, suspender will be prefabricated on Column is lifted to the corresponding position of design, installs prefabricated lower prop after reinforcing bar contraposition.
In step (1), the pre-buried fiber in prefabricated components end face at beam-column connection can be formed by two methods;
First method are as follows: spile to prefabricated components end face template is formed by fiber design spacing, in precast beam section concrete Fiber partial-length is inserted into green concrete by aperture before unhardened;
Second method are as follows: by the fiber connecting plate of part injection along its length, then by connecting plate without fiber it is exposed one Side is tightly attached on the inside of the template for pouring prefabricated components end, and the template and connection at seam interface are removed after concreting and maintenance Plate makes the fiber of injection connecting plate be exposed to seam interface.
Compared with prior art, the invention has the following advantages: should structure is reasonable, intensity is high, convenient construction, It can effectively avoid precast beam and the less reliable problem of prefabricated post junction intensity, fully ensured that assembled integral building system The design concept of " strong shear capacity and weak bending capacity, stronger node ", is conducive to the development and popularization of assembled architecture system.
Detailed description of the invention
The invention patent is further illustrated with reference to the accompanying drawing.
Fig. 1 is top layer beam, column end bay attachment structure schematic diagram;
Fig. 2 is top layer beam, column centre mid-span structural schematic diagram;
Fig. 3 is middle layer beam, column end bay attachment structure schematic diagram;
Fig. 4 is middle layer beam, column centre mid-span schematic diagram;
In figure:
1- precast beam;2- prefabricated post;The prefabricated lower prop of 201-;The prefabricated upper prop of 202-;3- connecting node;4- fiber;5- keyway;6- connects Connect reinforcing bar.
Specific embodiment
The present invention is further described with reference to the accompanying drawings and detailed description.
As shown in Figs 1-4, a kind of connecting structure of prefabricated beam column, including prefabricated components and beam-column connection, The prefabricated components are precast beam, prefabricated post, and the beam-column connection is the intersection point of precast beam and prefabricated post, precast beam, pre- Column processed is linked into an integrated entity by the cast-in-place concrete at beam-column connection, precast beam and prefabricated styletable at beam-column connection If dry fibers are buried in face, in a part embedment precast beam of fiber, prefabricated post, the other end of fiber protrudes into beam-column connection In the cast-in-place concrete at place, it is connected to fiber between new-old concrete interface.
In the present embodiment, fiber insertion precast beam, the 0.3-0.6 that the length in prefabricated post is fiber total length Times, less than 20, the length of fiber spacing and fiber is true according to design for machine direction and concrete linkage interface normal direction angle It is fixed.
In the present embodiment, be improve after-pouring part anchor force, the non-intrusive end of fiber be provided with hook portion, bulb or For waveform;Or radially spaced several annular grooves of setting on fiber.
In the present embodiment, the fiber is in steel fibre, glass fibre, polypropylene fibre, plant fiber or carbon fiber Any one, if fiber be straight steel fibre, the part of the after-pouring of fiber should be longer than insertion portion, so that fiber is preceding Phase pour with the later period pour in anchor force it is balanced.
In the present embodiment, concrete material cast-in-place at the beam-column connection uses ultra-high performance concrete or fibre Tie up concrete.
In the present embodiment, the prefabricated post includes prefabricated lower prop, prefabricated upper prop, and beam-column connection is for precast beam and in advance The intersection point of lower prop processed, prefabricated upper prop, precast beam, prefabricated lower prop connect to form base by the cast-in-place concrete at beam-column connection Body, matrix is starched by column pedestal to be connected with prefabricated upper prop.
In middle layer frame structure, the connection of prefabricated beam column component is divided into two parts, respectively precast beam and it is prefabricated under The connection of column and the connection of prefabricated upper prop;First part are as follows: the connection of precast beam and prefabricated lower prop.By at connecting node Cast-in-place concrete precast beam and prefabricated upper prop are linked into an integrated entity.It is pre- in cast-in-place node upper surface and upper prop corresponding position simultaneously Bury partial-length fiber;Second part are as follows: the connection of prefabricated upper prop.This is carried out after the completion of being connected to first part's connection, is passed through It is starched in column pedestal, prefabricated upper prop is installed.
In the present embodiment, the cubic compressive strength for the mortar material that the column pedestal slurry uses is mixed higher than prefabricated components Solidifying soil cubic compressive strength.
In the present embodiment, the precast beam, prefabricated column end are equipped with keyway, and keyway size is determined by design.
In the present embodiment, the position of beam-column connection is arranged at girder position or secondary beam position, presses at node Connection lengthwise rib is set according to design requirement, mechanical connection can be used in the connection type of connection lengthwise rib, sleeve grouting is connected, welded, taking The modes such as connect.
A kind of construction method of the connecting structure of prefabricated beam column, comprising the following steps:
1) prefabricated components are made: carrying out the prefabricated of beam and column by design requirement, the template of precast beam and prefabricated post is installed respectively, is hung Enter manufactured steel reinforcement cage, while placing respective built-in fitting, then the casting concrete in precast-concrete form, and carries out Maintenance, is respectively formed precast beam and prefabricated post, wherein being inserted into fiber in its end in the molding process of prefabricated components, and prefabricated Component carries out the dabbing of the concrete surface of rough surface during storing;
2) hoisting prefabricated column: surveying setting-out determines member position, carries out column muscle aligning, steel plate washer is levelling, for example top layer Prefabricated post is then lifted to the corresponding position of design by hoist cable, suspender, installs prefabricated post after reinforcing bar contraposition, such as by beam-to-column joint For the beam-to-column joint of middle layer, then prefabricated lower prop is lifted to by the corresponding position of design by hoist cable, suspender, pacified after reinforcing bar contraposition Prefabricated lower prop is filled, and after step (4), increased step (5);
3) precast beam: surveying setting-out is installed, precast beam is lifted into corresponding position using suspender and installed by arrangement support;
4) node connection construction: carrying out the reinforcing bar binding at beam-column connection, and set aside pre-embedded part installs stock mould at node Plate pours after inspection is errorless and smashes concrete at node, the form removal after it reaches 70% or more normal intensity, in node concrete Before ot-yet-hardened, by the insertion concrete of fiber partial-length, the length of fiber spacing and fiber is determined according to design;
5) install prefabricated upper prop: in corresponding column bottom position, seat is starched, and carries out column muscle aligning, by hoist cable, suspender will be prefabricated on Column is lifted to the corresponding position of design, installs prefabricated lower prop after reinforcing bar contraposition.
In step (1), the pre-buried fiber in prefabricated components end face at beam-column connection can be formed by two methods;
First method are as follows: spile to prefabricated components end face template is formed by fiber design spacing, in precast beam section concrete Fiber partial-length is inserted into green concrete by aperture before unhardened;
Second method are as follows: by the fiber connecting plate of part injection along its length, then by connecting plate without fiber it is exposed one Side is tightly attached on the inside of the template for pouring prefabricated components end, and the template and connection at seam interface are removed after concreting and maintenance Plate makes the fiber of injection connecting plate be exposed to seam interface.
Above-listed preferred embodiment, has been further described the object, technical solutions and advantages of the present invention, is answered Understand, the foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of connecting structure of prefabricated beam column, including prefabricated components and beam-column connection, it is characterised in that: described Prefabricated components are precast beam, prefabricated post, and the beam-column connection is the intersection point of precast beam and prefabricated post, precast beam, prefabricated post It is linked into an integrated entity by the cast-in-place concrete at beam-column connection, the precast beam and prefabricated post end face at beam-column connection bury If a part embedment precast beam of fiber, in prefabricated post, the other end of fiber protrudes at beam-column connection if dry fibers In cast-in-place concrete.
2. the connecting structure of prefabricated beam column according to claim 1, it is characterised in that: the fiber insertion is prefabricated Length in beam, prefabricated post is 0.3-0.6 times of fiber total length, machine direction and concrete linkage interface normal direction angle Less than 20 °.
3. the connecting structure of prefabricated beam column according to claim 2, it is characterised in that: the fiber is that steel is fine Any one in dimension, glass fibre, polypropylene fibre, plant fiber or carbon fiber.
4. the connecting structure of prefabricated beam column according to claim 1, it is characterised in that: the beam-column connection Locate cast-in-place concrete material using ultra-high performance concrete or fiber concrete.
5. the connecting structure of prefabricated beam column according to claim 1, it is characterised in that: the prefabricated post includes pre- Lower prop processed, prefabricated upper prop, beam-column connection are the intersection point of precast beam and prefabricated lower prop, prefabricated upper prop, precast beam, prefabricated lower prop It connects to form matrix by the cast-in-place concrete at beam-column connection, matrix is starched by column pedestal to be connected with prefabricated upper prop.
6. the connecting structure of prefabricated beam column according to claim 5, it is characterised in that: the column pedestal slurry uses Mortar material cubic compressive strength be higher than prefabricated components compressive strength of concrete.
7. the connecting structure of prefabricated beam column according to claim 1, it is characterised in that: the precast beam, prefabricated Column end is equipped with keyway.
8. the connecting structure of prefabricated beam column according to claim 1, it is characterised in that: the position of beam-column connection It installs at girder position or secondary beam position.
9. a kind of construction method of the connecting structure of prefabricated beam column, using as claimed in claim 5 prefabricated The connecting structure of beam column, which comprises the following steps:
1) prefabricated components are made: carrying out the prefabricated of beam and column by design requirement, the template of precast beam and prefabricated post is installed respectively, is hung Enter manufactured steel reinforcement cage, while placing respective built-in fitting, then the casting concrete in precast-concrete form, and carries out Maintenance, is respectively formed precast beam and prefabricated post, wherein being inserted into fiber in its end in the molding process of prefabricated components, and prefabricated Component carries out the dabbing of the concrete surface of rough surface during storing;
2) hoisting prefabricated column: surveying setting-out determines member position, carries out column muscle aligning, steel plate washer is levelling, for example top layer Prefabricated post is then lifted to the corresponding position of design by hoist cable, suspender, installs prefabricated post after reinforcing bar contraposition, such as by beam-to-column joint For the beam-to-column joint of middle layer, then prefabricated lower prop is lifted to by the corresponding position of design by hoist cable, suspender, pacified after reinforcing bar contraposition Prefabricated lower prop is filled, and after step (4), increased step (5);
3) precast beam: surveying setting-out is installed, precast beam is lifted into corresponding position using suspender and installed by arrangement support;
4) node connection construction: carrying out the reinforcing bar binding at beam-column connection, and set aside pre-embedded part installs stock mould at node Plate pours after inspection is errorless and smashes concrete at node, the form removal after it reaches 70% or more normal intensity, in node concrete Before ot-yet-hardened, by the insertion concrete of fiber partial-length, the length of fiber spacing and fiber is determined according to design;
5) install prefabricated upper prop: in corresponding column bottom position, seat is starched, and carries out column muscle aligning, by hoist cable, suspender will be prefabricated on Column is lifted to the corresponding position of design, installs prefabricated lower prop after reinforcing bar contraposition.
10. the construction method of the connecting structure of prefabricated beam column according to claim 1, it is characterised in that:
In step (1), the pre-buried fiber in prefabricated components end face at beam-column connection can be formed by two methods;
First method are as follows: spile to prefabricated components end face template is formed by fiber design spacing, in precast beam section concrete Fiber partial-length is inserted into green concrete by aperture before unhardened;
Second method are as follows: by the fiber connecting plate of part injection along its length, then by connecting plate without fiber it is exposed one Side is tightly attached on the inside of the template for pouring prefabricated components end, and the template and connection at seam interface are removed after concreting and maintenance Plate makes the fiber of injection connecting plate be exposed to seam interface.
CN201811134623.2A 2018-09-28 2018-09-28 The connecting structure and construction method of prefabricated beam column Pending CN109098278A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811134623.2A CN109098278A (en) 2018-09-28 2018-09-28 The connecting structure and construction method of prefabricated beam column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811134623.2A CN109098278A (en) 2018-09-28 2018-09-28 The connecting structure and construction method of prefabricated beam column

Publications (1)

Publication Number Publication Date
CN109098278A true CN109098278A (en) 2018-12-28

Family

ID=64867383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811134623.2A Pending CN109098278A (en) 2018-09-28 2018-09-28 The connecting structure and construction method of prefabricated beam column

Country Status (1)

Country Link
CN (1) CN109098278A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130487A (en) * 2019-05-24 2019-08-16 广东中建新型建筑构件有限公司 A kind of prefabricated primary and secondary beam connecting node and connection method
CN110616803A (en) * 2019-07-19 2019-12-27 三一筑工科技有限公司 Fabricated building structure system and construction method
CN110847355A (en) * 2019-12-11 2020-02-28 山东海龙建筑科技有限公司 Novel efficient mounting node assembly integral beam column and production design method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061296A (en) * 2000-08-15 2002-02-28 Taisei Corp Structure of joint and construction method therefor
AU2003204314B1 (en) * 2003-05-25 2004-11-18 Bendtsen, Bo Mr Precast spanning floor system using steel fibre reinforced concrete
CN105863047A (en) * 2016-05-10 2016-08-17 上海理工大学 Prefabricated concrete beam column joint and construction method
CN107060117A (en) * 2017-04-25 2017-08-18 福州大学 The continuous construction method of seam crossing fiber is realized in concrete gradation casting process
CN108396637A (en) * 2018-04-28 2018-08-14 福州大学 Based on short-line prefabrication assembly girder construction and its construction method
CN208934108U (en) * 2018-09-28 2019-06-04 福州大学 The connecting structure of prefabricated beam column

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061296A (en) * 2000-08-15 2002-02-28 Taisei Corp Structure of joint and construction method therefor
AU2003204314B1 (en) * 2003-05-25 2004-11-18 Bendtsen, Bo Mr Precast spanning floor system using steel fibre reinforced concrete
CN105863047A (en) * 2016-05-10 2016-08-17 上海理工大学 Prefabricated concrete beam column joint and construction method
CN107060117A (en) * 2017-04-25 2017-08-18 福州大学 The continuous construction method of seam crossing fiber is realized in concrete gradation casting process
CN108396637A (en) * 2018-04-28 2018-08-14 福州大学 Based on short-line prefabrication assembly girder construction and its construction method
CN208934108U (en) * 2018-09-28 2019-06-04 福州大学 The connecting structure of prefabricated beam column

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130487A (en) * 2019-05-24 2019-08-16 广东中建新型建筑构件有限公司 A kind of prefabricated primary and secondary beam connecting node and connection method
CN110130487B (en) * 2019-05-24 2024-01-16 广东中建新型建筑构件有限公司 Prefabricated main and secondary beam connecting node and connecting method
CN110616803A (en) * 2019-07-19 2019-12-27 三一筑工科技有限公司 Fabricated building structure system and construction method
CN110616803B (en) * 2019-07-19 2024-03-19 三一筑工科技股份有限公司 Assembled building structure system and construction method
CN110847355A (en) * 2019-12-11 2020-02-28 山东海龙建筑科技有限公司 Novel efficient mounting node assembly integral beam column and production design method thereof

Similar Documents

Publication Publication Date Title
CN108049498A (en) The prefabricated post and Prefabricated beam connection structure and method of assembled architecture frame structure
CN201339250Y (en) Stiffness structure framework beam preformed steel reinforcement framework structure
CN106592440B (en) A kind of construction method of prefabricated subsection type bridge pier
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN108035438A (en) A kind of concrete assembled frame structure system of high-strength high ductility and connection method
CN109555151A (en) Precast concrete column combines connecting structure and construction method with the steel reinforced concrete of cushion cap
CN207919748U (en) A kind of high ductility concrete beam and column node of assembled
CN108035437A (en) A kind of prefabricated node of the high-strength high concrete assembled frame of ductility and connection method
CN109098278A (en) The connecting structure and construction method of prefabricated beam column
CN207919746U (en) A kind of prefabricated node of high-strength high concrete assembled frame of ductility
CN106013432A (en) Joint connecting structure in high-ductility assembled integrated frame and construction method
CN108265824A (en) A kind of high ductility concrete beam and column node of assembled and connection method
CN108582465A (en) After pour canopy, precast reinforced concrete frame beam and after pour canopy manufacturing method
CN206408515U (en) Precast pier section assembling structure
CN109914589B (en) Vertical connecting structure of prestressed reinforced concrete precast column and construction method thereof
CN208934108U (en) The connecting structure of prefabricated beam column
CN207919747U (en) A kind of high-strength high concrete assembled frame structure system of ductility
CN110005053A (en) One kernel texture assembly assembling frame structure and its method of construction
CN212295248U (en) Prefabricated building member
CN209779987U (en) one-way superimposed sheet bottom plate of piece pre-compaction
CN105951984A (en) High-ductility assembled integral type frame exterior joint connection structure and construction method thereof
CN109098279A (en) The connecting structure and construction method of prefabricated girder and secondary beam
CN206233359U (en) A kind of assembled architecture reinforced concrete member
CN209227763U (en) The connecting structure of prefabricated girder and secondary beam
CN211286164U (en) Self-compaction regeneration block concrete superimposed shear wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181228