CN109098179B - Throwing filling structure system and working method - Google Patents

Throwing filling structure system and working method Download PDF

Info

Publication number
CN109098179B
CN109098179B CN201810929144.3A CN201810929144A CN109098179B CN 109098179 B CN109098179 B CN 109098179B CN 201810929144 A CN201810929144 A CN 201810929144A CN 109098179 B CN109098179 B CN 109098179B
Authority
CN
China
Prior art keywords
control
sandbag
throwing
lifting
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810929144.3A
Other languages
Chinese (zh)
Other versions
CN109098179A (en
Inventor
孙旭亮
随守信
李久春
周林
付光进
王成
付栋
刘强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Harbour Co Ltd
Original Assignee
PowerChina Harbour Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Harbour Co Ltd filed Critical PowerChina Harbour Co Ltd
Priority to CN201810929144.3A priority Critical patent/CN109098179B/en
Publication of CN109098179A publication Critical patent/CN109098179A/en
Application granted granted Critical
Publication of CN109098179B publication Critical patent/CN109098179B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/10Placing gravel or light material under water inasmuch as not provided for elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a throwing and filling structure system and a working method, wherein the throwing and filling structure system mainly comprises a throwing and filling ship, a GPS (global positioning system), an anchor machine, a buoyancy tank, a sandbag control guide frame, a control frame fixing device, a broadside control frame storage device, a control frame lifting system and an operation control box; the floating box is positioned on one side of the throwing filling ship, a moon pool is arranged in the middle of the floating box, and three groups of sandbag control guide frames are placed in the moon pool; the sandbag control guide frame is assembled by a plurality of independent sandbag control frames; the control frame lifting system is composed of four lifting upright columns and used for controlling the movement of the sandbag control guide frame, and the broadside control frame storage device is composed of four storage frames and used for storing the sandbag control guide frame. In a word, the throwing filling structure system can effectively improve the accuracy of the sand bag throwing filling, improve the construction quality and accelerate the construction progress.

Description

Throwing filling structure system and working method
Technical Field
The invention relates to the technical field of river regulation, in particular to a throwing and filling structure system and a working method.
Background
In the engineering for renovating the river channel of the bridge, the water depth of a construction area is 15-30 m, the water flow velocity in the construction period is 0.5-1.5 m/s, the slope of a bank slope is designed to be 1:6, the allowable deviation of slope excavation is +/-250 mm, and a large cutter suction dredger is adopted for dredging the slope; the soil quality is mainly silt and fine sand. The bank slope protective structure mainly comprises 3 layers of 125kg geotextile bag reverse filter layers and 90cm thick stone protection layers, and the foundation trench protective structure comprises 5 layers of 800kg geotextile bag protection layers. The geotextile bags adopt a continuous loose-throwing mode, wherein 1700 thousands of 125kg geotextile bags and 400 ten thousands of 800kg geotextile bags are adopted. The minimum thickness of the throwing filling quality requirement of the geobags meets three layers of 125kg geobags or 5 layers of 800kg geobags, the allowable thickness of the 5 layers of 800kg geobags is 2.0-2.5 m, the allowable thickness of the 3 layers of 125kg geobags is 0.5-0.75 m, the maximum thickness cannot exceed 150% of the designed layer thickness, and the throwing filling precision requirement is extremely high.
Since the start of the geotextile bag throwing filling construction, the Bengal Padema river regulation project always adopts a flat barge as a construction platform, four anchors are used as a positioning basis, positioning is carried out by a GPS, and the throwing filling process is a deck fixed-point stepping throwing filling method, so that the underwater drift and dispersion are very large due to the influence of factors such as water flow, deep water level and different water entering postures of geotextile bags in a construction area, the flatness tolerance of the geotextile bags after throwing filling is large, the unevenness is large, the slope formed after throwing filling is large, the labor intensity is high, the safety is poor, the construction efficiency is low, and the throwing filling process and the throwing filling result cannot be accepted by owners and are recognized by supervision, and the following brief description is given:
the geotextile bags have low throwing and filling precision, and the thrown and filled area has the problem of too high or too low thickness. The earth bag throwing and filling uses a flat barge as a construction platform, dozens of earth bags are thrown and filled into water at one side of the barge according to the measured fixed point position and the required throwing and filling layer number, and then a four-anchor positioning winch is adopted for stepping and throwing and filling the next round; however, when the geotextile bags enter water, the geotextile bags are influenced by water flow in a construction area and turbulence of the geotextile bags impacting the water surface, and the water level in the construction area is relatively deep, so that the geotextile bags are drifted after water enters and are difficult to fall to a preset riverbed throwing and filling place, the drift has relatively high randomness, the final throwing and falling point of the geotextile bags after water enters cannot be controlled, and finally, the thickness of the geotextile bag layers in the throwing and filling area cannot meet the specification requirements (is too high or too low). Supervision requirement: the throwing and filling precision does not approve the next working procedure or the construction of a working face under the condition that the throwing and filling precision does not meet the requirements of technical specifications; removing the filling material with a thickness exceeding a certain thickness, and performing additional polishing if the thickness is not met; the work difficulty of the super-thick removal is larger, and when the supplement and throwing are carried out again, the supplement and throwing geotextile bags are also influenced, so that the geotextile bags are difficult to fall to the low points, and the supplement and throwing effect cannot be achieved. Resulting in repeated and inefficient operation.
Disclosure of Invention
The invention provides a throwing filling structure system and a working method thereof, aiming at improving the construction process of throwing filling of a geotextile bag, improving the construction quality and accelerating the construction progress.
The technical scheme of the invention is that the throwing filling structure system mainly comprises a throwing filling ship, a GPS, an anchor machine, a buoyancy tank, a sandbag control guide frame, a control frame fixing device, a broadside control frame storage device, a control frame lifting system and an operation control box;
the number of the GPS is two, the GPS is respectively positioned at two ends of the buoyancy tank, the number of the anchor machines is four, the anchor machines are respectively positioned at four corners of the throwing and filling ship, and the throwing and filling ship moves to an appointed throwing and filling position through the GPS and the anchor machines;
the floating box is positioned on one side of the throwing filling ship, a moon pool is arranged in the middle of the floating box, the moon pool is in a long strip shape, and three groups of sandbag control guide frames are placed in the moon pool; the buoyancy tank can ensure the modular manufacturing and installation of the added bag throwing control device without reducing the use area of a deck of the throwing filling ship, and the downtime and modification time of the original ship are reduced to the maximum extent in the modification process;
the sandbag control guide frame is assembled by a plurality of independent sandbag control frames, each station of the sandbag control guide frame on the working face side can be opened to form a throwing opening, and the sandbag control frames are used for gradually lifting or dismantling the sandbag control frames according to the water depth condition of a construction operation area so as to realize the adjustment of the water depth of the sandbag control guide frame; the sand bag control guide frame is provided with a special independent lifting beam, and the lifting beam is used for mounting and dismounting the sand bag control guide frame; the sandbag control guide frame can enable the dropped sandbag to accurately fall onto the mud surface of the river bottom, and prevent the sandbag from drifting due to water resistance and water flow in the free falling process;
the control frame lifting system is composed of four lifting stand columns, the four lifting stand columns comprise two lifting stand columns positioned in the middle of the moon pool and two lifting stand columns positioned on two sides of the moon pool, two guide frame lifting winches are respectively arranged on the two lifting stand columns in the middle, one guide frame lifting winch is respectively arranged on the lifting stand columns on the two sides, and the control frame lifting system is used for controlling the lifting of the sandbag control guide frame;
the control frame fixing device is fixed on the moon pools on the inner side and the outer side of the sandbag control guide frame, the control frame fixing device is connected with the lifting lugs on the sandbag control guide frame through chains, and the control frame fixing device is used for fixing the sandbag control guide frame and meeting the requirement that the guide frames on the two sides lift the winch to unhook and change the lifting point when the sandbag control frame is disassembled and assembled, so that the functions of safety and fixation are achieved;
the side control frame storage device is composed of four storage frames, the four storage frames are fixed on the far side face of the floating box at equal intervals, three storage ports are formed by the four storage frames, and the side control frame storage device is used for placing the sandbag control guide frames through the storage ports;
the operation control box is fixed on one side of the floating box and used for operating the control frame lifting system to control the lifting of the guide frame.
Furthermore, every two control frame fixing devices are respectively arranged at the far end and the near end of each group of sandbag control guide frames in a group.
Furthermore, the sandbag control guide frame is assembled by 6 independent sandbag control frames with the height of 4m, and the sandbag control frames are connected through bolts. The installation of hoisting can be convenient.
Furthermore, the sandbag control frame is mainly made of steel pipes, round steel and angle steel, and the inner surface of the sandbag control guide frame is designed to be smooth and free of protrusions. The sand bag control guide frame is prevented from scratching the soil engineering bags to cause the soil engineering bags to lose effect when the soil engineering bags are thrown.
Furthermore, the lifting upright post is arranged on the buoyancy tank in a bolt and electric welding reinforcing mode, and a guide pulley, a lifting hook, a crawling ladder and the like are arranged on the lifting upright post; the top of promotion stand is provided with the maintenance platform, and the follow-up maintenance of the equipment of being convenient for and the fixed and promotion of sand bag control leading truck are provided with the vertical lift support at the top in the promotion stand, and the vertical lift support is used for hanging sand bag control leading truck on promoting the stand through wire rope, prevents to play to rise rocking of in-process sand bag control leading truck, influences the removal of control sand bag control leading truck.
Furthermore, the control frame lifting system is completed by matching lifting points at two ends of the sandbag control guide frame with guide frame lifting winches and guide pulleys on the lifting upright posts, the guide frame lifting winches at the two ends are designed into two-speed or three-speed, two-vehicle linkage and one-vehicle single-action can be realized, and three groups of sandbag control guide frames can be centralized to one control box for control. The whole sandbag control guide frame is heavy after being connected, belongs to a flat box cage body structure, is weak in overall rigidity, and can meet the requirement for lifting two end points by the scheme to realize the lifting of the sandbag control guide frame in a moon pool.
Furthermore, a baffle is arranged on the outer side of the bottom of the sandbag control guide frame. Through the design of baffle, can make the geotechnological bag fall the exit, give the inboard power of geotechnological bag, make the geotechnological bag fill inseparabler, improve efficiency and the quality of throwing filling.
The invention also provides a working method of the throwing filling structure system, which comprises the following steps:
s1, selecting the height of the sandbag control guide frame according to the water depth of the actual construction area, and adding or removing the sandbag control frame by taking the anchor machine as work assistance;
s2, guiding the sandbag control guide frame to move through the operation control box (8), properly lifting and lowering the sandbag control guide frame through the control frame lifting system according to the water depth, and timely adjusting the depth of the sandbag control guide frame according to the throwing and filling depth by a throwing and filling ship operator to avoid that the outlet of the sandbag control guide frame is too far away from the riverbed and cannot play a role and the danger of bottom contact caused by the fact that the outlet is too close to the riverbed is avoided so as to ensure the smooth construction;
s3, after the work is started, an operator knows the coordinate position of the filling ship in real time through four-anchor control and double-GPS computer monitoring on the filling ship, so as to master the positioning accuracy of each filling point;
s4, after filling and bag sewing are completed, each geotextile bag is pushed into a sandbag control guide frame according to a construction instruction, because of the constraint of the sandbag control guide frame, the geotextile bag cannot be influenced by the water flow speed, the water depth and the water entering posture in water, the irregular drifting phenomenon is prevented, the geotextile bags directly fall to a specified place through the sandbag control guide frame, the number of geotextile bags filled at each filling site is strictly controlled, geotextile bag filling is performed according to the preset filling surface density, and joint signature confirmation is immediately performed after each batch of filling is completed, so that the filling precision is greatly improved;
s5, after one round of throwing and filling is finished, determining the throwing and filling number and batch of the next round through GPS measurement, moving the ship through four anchor machines to finish a new round of throwing and filling, and repeating the throwing and filling process; during the moving process of the ship, the underwater position of the guide frame is controlled by paying attention to avoid bottom contact.
The invention has the beneficial effects that:
(1) the invention adopts the design of the buoyancy tank, can ensure the modular manufacturing and installation of the added bag throwing control device without reducing the use area of the deck of the throwing filling ship, furthest reduces the downtime refitting time of the original ship in the refitting process and improves the construction efficiency.
(2) The guide frame is controlled by the sand bag, so that the dropped sand bag can accurately fall on the mud surface of the river bottom, and the drift phenomenon caused by water resistance and water flow in the free falling process of the sand bag is prevented; the throwing and filling construction efficiency is improved, and the safety risk is reduced.
(3) The sandbag control guide frame is assembled by combining the plurality of sandbag control frames, can be disassembled and assembled according to the actual throwing and filling water depth, is suitable for various water depth environments, and has a wider application range.
Drawings
FIG. 1 is a front view of a cast fill structure of the present invention.
FIG. 2 is a top view of the throw fill architecture of the present invention.
Fig. 3 is a sectional view taken along line a-a of fig. 2, particularly a schematic view of a lifting column structure according to the present invention.
FIG. 4 is a sectional view taken along line B-B of FIG. 2, showing the positional relationship between the control frame fixing device and the sandbag control guide frame, wherein a is the first positional relationship, B is the second positional relationship, and c is the third positional relationship.
Fig. 5 is a cross-sectional view taken along line C-C of fig. 2, particularly illustrating the positional relationship and sliding movement of the sandbag control guide frame with respect to the moonpool.
The system comprises a throwing and filling ship 1, an anchor machine 11, a buoyancy tank 2, a GPS21, a moon pool 3, a sand bag control guide frame 4, a sand bag control frame 41, a baffle 42, a lifting lug 43, a lifting upright 5, a guide frame lifting winch 51, a ladder stand 52, a lifting hook 53, a guide pulley 54, a vertical lifting support 55, a storage frame 6, a control frame fixing device 7, an operation control box 8 and a lifting beam 9.
Detailed Description
As shown in fig. 1, a throwing and filling structure system mainly comprises a throwing and filling ship 1, a GPS21, an anchor machine 11, a buoyancy tank 2, a sandbag control guide frame 4, a control frame fixing device 7, a broadside control frame storage device, a control frame lifting system and an operation control box 8; the number of the GPS21 is two, the GPS21 is respectively positioned at two ends of the buoyancy tank 2, the number of the anchor machines 11 is four, the GPS21 is respectively positioned at four corners of the throwing and filling ship 1, and the throwing and filling ship 1 moves to an appointed throwing and filling position through the GPS21 and the anchor machines 11;
as shown in fig. 2, the buoyancy tank 2 is located at one side of the dredger 1, and the buoyancy tank 2 is connected with the dredger 1 through a main deck, fore-aft closure plates and a side structure. Can guarantee the fixing between flotation tank 2 and the throwing and filling ship 1, improve the position precision of throwing and filling simultaneously. A moon pool 3 is arranged in the middle of the buoyancy tank 2, the moon pool 3 is in a strip shape, and three groups of sandbag control guide frames 4 are placed in the moon pool 3; the buoyancy tank 2 can ensure the modular manufacturing and installation of the added bag throwing control device without reducing the use area of the deck of the throwing filling ship 1, and the downtime and the modification time of the original ship are reduced to the maximum extent in the modification process;
as shown in figure 1, the sandbag control guide frame 4 is assembled by 6 independent sandbag control frames 41 with the height of 4m, and the sandbag control frames 41 are connected through bolts. The installation of hoisting can be convenient. The sandbag control frame 41 is mainly made of steel pipes, round steel and angle steel, and the inner surface of the sandbag control guide frame 4 is designed to be smooth and free of protrusions. When the sandbag control guide frame 4 throws the geotextile bags, the geotextile bags are prevented from being scratched by the frame walls to lose the functions of the geotextile bags. The outer side of the bottom of the sandbag control guide frame 4 is provided with a baffle 42. Through the design of baffle 42, can make the geotechnological bag fall the exit, give the geotechnological bag one to the power of inboard, make the geotechnological bag fill inseparabler, improve efficiency and the quality of throwing and filling. Each station of the sandbag control guide frame 4 on the working surface side can be opened to form a throwing opening, and the sandbag control frame 41 is used for gradually lifting or dismantling the sandbag control frame 41 according to the water depth condition of the construction operation area so as to realize the adjustment of the water depth of the sandbag control guide frame 4; the sand bag control guide frame 4 is provided with a special independent hoisting crossbeam 9, and the hoisting crossbeam 9 is used for mounting and dismounting the sand bag control guide frame 4; the sandbag control guide frame 4 can enable the dropped sandbag to accurately fall on the mud surface of the river bottom, and prevent the sandbag from drifting due to water resistance and water flow in the free falling process;
as shown in fig. 1-3, the control frame lifting system is composed of four lifting columns 5, the lifting columns 5 are installed on the buoyancy tank 2 by means of bolts and electric welding reinforcement, and guide pulleys 54, a lifting hook 53, a ladder stand 52 and the like are installed on the lifting columns 5; the top of promotion stand 5 is provided with the maintenance platform, and the subsequent maintenance of the equipment of being convenient for and sand bag control leading truck 4 are fixed and promote, and the top is provided with vertical lifting support 55 in the promotion stand 5, and vertical lifting support 55 is used for hanging sand bag control leading truck 4 on promoting stand 5 through wire rope, prevents to play to rise rocking of in-process sand bag control leading truck 4, influences the removal of control sand bag control leading truck 4. The four lifting columns 5 comprise two lifting columns 5 positioned in the middle of the moon pool 3 and two lifting columns 5 positioned on two sides of the moon pool, two guide frame lifting winches 51 are respectively arranged on the two lifting columns 5 in the middle, one guide frame lifting winch 51 is respectively arranged on the lifting columns 5 on two sides, and the control frame lifting system is used for controlling the lifting of the sandbag control guide frame 4; the control frame lifting system is completed by matching lifting points at two ends of the sandbag control guide frame, guide frame lifting winches on the lifting upright posts and guide pulleys, the guide frame lifting winches at the two ends are designed into two-speed or three-speed, two-vehicle linkage and one-vehicle single-motion can be realized, and three groups of sandbag control guide frames can be centralized to one control box for control. Because the whole sandbag control guide frame 4 is heavy after being connected, belongs to a flat box cage body structure, has weak integral rigidity, and can meet the requirement of lifting two end points by the scheme to realize the lifting of the sandbag control guide frame 4 in the moon pool 3.
As shown in fig. 2, every two control frame fixing devices 7 are fixed on the moon pool 3 at the inner side and the outer side of each group of sandbag control guide frame 4 in a group, the control frame fixing devices 7 are connected with the lifting lugs 43 on the sandbag control guide frames 4 through chains, and the control frame fixing devices 7 are used for fixing the sandbag control guide frames 4 and meeting the requirements of unhooking and replacing lifting points of the guide frame lifting winches 51 of the two sides when the sandbag control frames 41 are disassembled and assembled, so that the functions of safety and fixation are achieved;
as shown in fig. 2, the side control frame storage device is composed of four storage frames 6, the four storage frames 6 are fixed on the far side surface of the buoyancy tank 2 at equal intervals, the four storage frames 6 form three storage ports, and the side control frame storage device is used for placing the sandbag control guide frames 4 through the storage ports;
as shown in fig. 2, the operation control box 8 is fixed to one side of the floating box 2, and is used for operating the control frame lifting system to lift the sandbag control guide frame 4.
As shown in fig. 4, the three kinds of control frame fixing devices 7 are sequentially arranged in the positional relationship with the sandbag control guide frame 4 in the drawings of a, b and c.
As shown in fig. 5, the sandbag control guide 4 is schematically located and slid with respect to the moon pool 3.
The invention also provides a working method of the throwing filling structure system, which comprises the following steps:
s1, selecting the height of the sandbag control guide frame 4 according to the water depth of the actual construction area, and adding or removing the sandbag control frame 41 by taking the anchor machine 11 as work assistance;
s2, guiding the sandbag control guide frame 4 to move through the operation control box 8, properly lifting and lowering the sandbag control guide frame 4 through the control frame lifting system according to the water depth, and timely adjusting the depth of the sandbag control guide frame 4 according to the throwing and filling depth by an operator of the throwing and filling ship 1 to avoid that the outlet of the sandbag control guide frame 4 is too far away from the riverbed and cannot play a role and the danger of bottom contact caused by the outlet being too close to the riverbed is avoided so as to ensure the smooth construction;
s3, after the work is started, an operator knows the coordinate position of the cast-fill ship 1 in real time through four-anchor control and double-GPS computer monitoring on the cast-fill ship 1, and grasps the positioning accuracy of each cast-fill point;
s4, after filling and bag sewing of each geotextile bag are completed, each geotextile bag is pushed into the sandbag control guide frame 4 according to a construction instruction, because of the constraint of the sandbag control guide frame, the geotextile bag cannot be influenced by the water flow velocity, the water depth and the water entering posture in water, the irregular drifting phenomenon is prevented, the geotextile bags control the guide frame 4 to directly fall to a specified place through the sandbag, the number of geotextile bags at each throwing and filling point is strictly controlled, the geotextile bags are thrown and filled according to the preset throwing and filling surface density, and joint signature confirmation is immediately carried out after each batch of throwing and filling is completed, so that the throwing and filling precision is greatly improved;
s5, after one round of throwing and filling is finished, the number and the batch of the next round of throwing and filling are determined through the measurement of the GPS21, the ship is moved through the four anchor machines 11, a new round of throwing and filling is finished, and the throwing and filling process is repeated; during the moving process of the ship, the underwater position of the guide frame 4 is controlled by paying attention to avoid bottoming.
To further illustrate the advantages of the invention, we have implemented a transformation of sandbag throwing and filling vessels: the full-length direction of one side of three 125kg or two 800kg filling flat decks is additionally provided with the floating box 2, the middle position of the floating box 2 is additionally provided with the sandbag control guide frame 4, the control frame lifting system, the control frame fixing device 7, the broadside control frame storage device and other facilities to meet the posture and position control in the sandbag throwing process.
The main structure system is as follows:
1) floating box
The size of the pontoon 2 is calculated from the size of the flat top barge to meet strength and service requirements. And correspondingly increasing the overhanging platform with insufficient size (B16 increases the overhanging platform of the anchor machine 11, so as to ensure the effective rope arrangement distance of the positioning anchor machine 11, which is generally 5-6 times of the length of the roller of the anchor machine 11). The deck and the hull are connected by adopting corner plates and electric welding, the part below the waterline is not treated, the part 200mm above the waterline is connected by adopting a structure, and the bow and the stern are connected by additionally arranging a large T. The deck and the hull are respectively connected through bolts and electric welding, the longitudinal strength requirement of the whole buoyancy tank 2 is guaranteed, a longitudinal moon pool 3 can be formed in the middle of the whole newly-added buoyancy tank 2 after splicing, and the sandbag control guide frame 4 is placed into river water from the moon pool 3. The total height of the sandbag control guide frame 4 is 24 meters, 6 independent sandbag control frames 41 with the height of 4 meters are assembled together, and the sandbag control frames 41 are gradually lifted or removed to move towards a shallow water area according to the water depth condition of a construction operation area.
The buoyancy tank 2 is hauled to a barge position needing to be modified, the barge is positioned on the side of the barge (at the moment, the barge needs to be parked in a relatively flat still water area, and the barge is required to be finally aligned with a main deck of the buoyancy tank 2 to be additionally installed through load adjustment), and the newly-manufactured buoyancy tank 2 is firmly combined with the original ship through the structural connection of the main deck, the fore-aft sealing plate and the side.
2) Sandbag control guide frame
The height of the sand bag control guide frame 4 is designed to be 4m, the requirement of water depth of the sand bag can be met (the operation requirement can be met by lifting or dismounting the sand bag control frame 41 in shallow water operation), the whole sand bag control guide frame 4 can be opened at each station on the working face side to form a throwing opening, three groups of sand bag control guide frames 4 are designed on each 800kg earth bag ship, 7 throwing openings are arranged in the horizontal direction, and 21 sand bags can be thrown and filled on the whole ship. Each ship of 125kg soil engineering bags is provided with three groups of sandbag control guide frames 4, 13 throwing openings are arranged in the horizontal direction, and 39 sandbags can be thrown and filled in the whole ship.
Each section of the sandbag control frame 41 is 4 meters high, the sandbag control frame is divided into an upper layer and a lower layer, each layer is provided with a throwing and filling port, each group of sandbag control frames 41 comprises 6 sections, can be detached at any time, can meet the throwing and filling guide from the water surface to-24 meters, and when the sandbag control frames 41 of 6 sections are hung at the maximum limit, the strength of each group of the sandbag control guide frame 4 can transversely resist 1m/s water flow impact (the transverse direction is vertical to the throwing and filling working face) and can longitudinally resist 2m/s water flow impact (the longitudinal face is parallel to the throwing and filling working face). The construction can not be carried out during the rain season of the mawa side, the water flow velocity reaches 4m/s during the rain season of the main Pardema river channel, the construction can be carried out at the Jajira side all the year round, and the maximum flow velocity does not exceed 2 m/s.
3) Lifting column
After the buoyancy tank 2 is built, in order to facilitate the installation of the subsequent sandbag control frame 41, each throwing and filling ship 1 is provided with 4 sets of special lifting columns 5, the height of each lifting column is about 11 meters, and the lifting columns are installed on the buoyancy tank 2 through a bolt and electric welding reinforcing scheme. A lifting winch 51, a guide pulley 54, a ladder stand 52, a lifting hook 53 and the like are arranged on the special lifting upright post 5, and a maintenance platform is arranged at the top end of the special lifting upright post, so that the subsequent maintenance of the equipment and the fixing and lifting of the sandbag control guide frame 4 are facilitated.
The top of the lifting upright post 5 is provided with a vertical lifting support 55 of the sandbag control guide frame 4, the sandbag control guide frame 4 is suspended on the lifting upright post 5 through a special steel wire rope, and the sandbag control guide frame 4 is lifted or lowered through the cooperation of the guide frame lifting winch 51, the guide pulley 54 and the like according to the actual production water depth.
4) Control frame lifting system
In the scheme, lifting points are arranged at two ends of each group of sandbag control guide frames 4, lifting of the sandbag control guide frames 4 is completed through the guide frame lifting winches 51 and the guide pulleys 54 on the lifting upright posts 5, the lifting winches 51 at the two ends are designed into double speeds, two-vehicle linkage and one-vehicle single-motion can be realized, and three groups of sandbag control guide frames 4 can be controlled by one control box in a centralized mode.
5) Control frame fixing device
When the sandbag control guide frame 4 is in a working state after the position is adjusted, for the purpose of safety, a control frame fixing device 7 is arranged on the floating box and is connected with a lifting lug 43 on the sandbag control guide frame 4 through a chain, so that the functions of safety and fixing are achieved. Meanwhile, the requirement that the guide frame lifting winches 51 on the two sides are unhooked to change the lifting points when the sandbag control frame 41 is disassembled and assembled can be met.
Through practical test use, this structure system of filling and throwing can effectively ensure that the sand bag falls to the river bottom position along the leading truck after entrying accurate, can not be because of the drift condition appears in the rivers influence, and the number of piles is even after filling and throwing, can improve to a great extent and throw the precision, guarantees construction quality, reduces construction volume such as rework and benefit are thrown, throws and fills effectually.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (7)

1. A throwing and filling structure system is characterized by mainly comprising a throwing and filling ship (1), a GPS (21), an anchor machine (11), a buoyancy tank (2), a sandbag control guide frame (4), a control frame fixing device (7), a broadside control frame storage device, a control frame lifting system and an operation control box (8);
the number of the GPS (21) is two, the GPS is respectively positioned at two ends of the buoyancy tank (2), the number of the anchor machines (11) is four, the anchor machines are respectively positioned at four corners of the throwing and filling ship (1), and the throwing and filling ship (1) moves to an appointed throwing and filling position through the GPS (21) and the anchor machines (11);
the floating box (2) is positioned on one side of the throwing filling ship (1), a moon pool (3) is arranged in the middle of the floating box (2), the moon pool (3) is in a strip shape, and three groups of sandbag control guide frames (4) are arranged in the moon pool (3);
the sandbag control guide frame (4) is assembled by a plurality of independent sandbag control frames (41), each station of the sandbag control guide frame (4) on the working surface side can be opened to form a throwing opening, and the sandbag control frames (41) are used for gradually lifting or removing the sandbag control frames (41) according to the water depth condition of a construction operation area so as to realize the adjustment of the water penetration depth of the sandbag control guide frame (4); the sand bag control guide frame (4) is provided with a special independent lifting beam (9), and the lifting beam (9) is used for mounting and dismounting the sand bag control guide frame (4);
the control frame lifting system is composed of four lifting upright columns (5), the four lifting upright columns (5) comprise two lifting upright columns (5) positioned in the middle of the moon pool (3) and two lifting upright columns (5) positioned on two sides of the moon pool, two guide frame lifting winches (51) are respectively arranged on the two lifting upright columns (5) in the middle, one guide frame lifting winch (51) is respectively arranged on each lifting upright column (5) on two sides, and the control frame lifting system is used for controlling the lifting of the sandbag control guide frame (4);
the control frame fixing device (7) is fixed on the moon pools (3) on the inner side and the outer side of the sandbag control guide frame (4), the control frame fixing device (7) is connected with a lifting lug (43) on the sandbag control guide frame (4) through a chain, and the control frame fixing device (7) is used for fixing the sandbag control guide frame (4) and meeting the requirement that the guide frame lifting winches (51) on the two sides are unhooked and the lifting point is changed when the sandbag control frame (41) is disassembled;
the side control frame storage device is composed of four storage frames (6), the four storage frames (6) are fixed on the far side face of the floating box (2) at equal intervals, three storage ports are formed in the four storage frames (6), and the side control frame storage device is used for placing the sandbag control guide frames (4) through the storage ports;
the operation control box (8) is fixed on one side of the floating box (2) and used for operating the control frame lifting system to lift the sandbag control guide frame (4).
2. A cast and fill construction system according to claim 1, c h a r a c t e r i z e d in that said control frame fixing means (7) are arranged in groups of two at each distal and proximal end of each group of sandbag control guides.
3. A cast and fill construction system according to claim 1, c h a r a c t e r i z e d in that the sandbag control guides (4) are assembled from 6 separate sandbag control stands (41) of 4m height, the sandbag control stands (41) being bolted together.
4. A throwing and filling construction system according to claim 3, characterized in that said sandbag control rack (41) is mainly made of steel pipe, round steel and angle steel, and the inner surface of the sandbag control guide rack (4) is designed to be smooth and free of protrusions.
5. A throwing and filling structural system as claimed in claim 1, wherein the lifting columns (5) are installed on the buoyancy tank (2) by means of bolts and electric welding reinforcement, and guide pulleys (54), lifting hooks (53) and ladder stands (52) are installed on the lifting columns (5); the top of the lifting upright post (5) is provided with a maintenance platform, the top of the lifting upright post (5) is provided with a vertical lifting support (55), and the vertical lifting support (55) is used for hanging the sandbag control guide frame (4) on the lifting upright post (5) through a steel wire rope.
6. A throwing and filling construction system according to claim 1, characterized in that the sandbag control guide (4) is provided with a baffle (42) on the outside of the bottom.
7. A method of operating a throw-fill construction system according to any one of claims 1 to 6, comprising the steps of:
s1, selecting the height of the sandbag control guide frame (4) according to the water depth of the actual construction area, and adding or removing the sandbag control frame (41) by taking the anchor machine (11) as work assistance;
s2, guiding the sandbag control guide frame (4) to move through the operation control box (8), properly lifting and lowering the sandbag control guide frame (4) through a control frame lifting system according to the water depth, and timely adjusting the depth of the sandbag control guide frame (4) by an operator of the throwing and filling ship (1) according to the throwing and filling depth to avoid that the outlet of the sandbag control guide frame (4) is too far away from the riverbed and cannot play a role, and avoid that the outlet is too close to the riverbed to cause bottom contact danger so as to ensure the smooth construction;
s3, after the operation starts, an operator knows the coordinate position of the cast-in-situ ship (1) in real time through four-anchor control and double-GPS computer monitoring on the cast-in-situ ship (1) and grasps the positioning accuracy of each cast-in-situ point;
s4, after filling and bag sewing are completed, each geotextile bag is pushed into a sandbag control guide frame (4) according to a construction instruction, the geotextile bags directly fall to a specified place through the sandbag control guide frame (4), the number of geotextile bag throwing and filling of each throwing and filling point is strictly controlled, geotextile bag throwing and filling are performed according to the preset throwing and filling surface density, and after each batch of throwing and filling is completed, combined signature confirmation is immediately performed;
s5, after one round of throwing and filling is finished, the number and the batch of the next round of throwing and filling are determined through the measurement of a GPS (21), the ship is moved through four anchor machines (11), a new round of throwing and filling is finished, and the throwing and filling process is repeated; during the moving process of the ship, the position of the guide frame (4) controlled by the sand bag is noticed, and bottom contact is avoided.
CN201810929144.3A 2018-08-15 2018-08-15 Throwing filling structure system and working method Active CN109098179B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810929144.3A CN109098179B (en) 2018-08-15 2018-08-15 Throwing filling structure system and working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810929144.3A CN109098179B (en) 2018-08-15 2018-08-15 Throwing filling structure system and working method

Publications (2)

Publication Number Publication Date
CN109098179A CN109098179A (en) 2018-12-28
CN109098179B true CN109098179B (en) 2020-06-09

Family

ID=64849904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810929144.3A Active CN109098179B (en) 2018-08-15 2018-08-15 Throwing filling structure system and working method

Country Status (1)

Country Link
CN (1) CN109098179B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8240265B1 (en) * 2007-11-14 2012-08-14 Jon Khachaturian Method and apparatus for salvaging underwater objects
CN202899140U (en) * 2012-09-13 2013-04-24 江苏淮阴船用机械有限公司 Riprap operation device of lifting hopper
CN103924597A (en) * 2013-01-10 2014-07-16 中交第一航务工程局有限公司 Platform type riprap leveling barge and construction method thereof
JP2014136546A (en) * 2013-01-18 2014-07-28 Toyo Constr Co Ltd Door opening control method of barge, and throw-in control system implementing the same
CN105015717A (en) * 2015-07-24 2015-11-04 上海勘测设计研究院有限公司 Box-type deepwater positioning throwing boat and usage method thereof
CN106320344A (en) * 2016-09-22 2017-01-11 中交航局第二工程有限公司 Construction control method for dimension stone deepwater precise throwing and filling
CN207389483U (en) * 2017-11-02 2018-05-22 中国电建集团港航建设有限公司 A kind of deep water high-precision throws bag operation flat-bottomed boat
CN108252306A (en) * 2018-03-20 2018-07-06 中国水利水电第五工程局有限公司 A kind of underwater filler throwing system and construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8240265B1 (en) * 2007-11-14 2012-08-14 Jon Khachaturian Method and apparatus for salvaging underwater objects
CN202899140U (en) * 2012-09-13 2013-04-24 江苏淮阴船用机械有限公司 Riprap operation device of lifting hopper
CN103924597A (en) * 2013-01-10 2014-07-16 中交第一航务工程局有限公司 Platform type riprap leveling barge and construction method thereof
JP2014136546A (en) * 2013-01-18 2014-07-28 Toyo Constr Co Ltd Door opening control method of barge, and throw-in control system implementing the same
CN105015717A (en) * 2015-07-24 2015-11-04 上海勘测设计研究院有限公司 Box-type deepwater positioning throwing boat and usage method thereof
CN106320344A (en) * 2016-09-22 2017-01-11 中交航局第二工程有限公司 Construction control method for dimension stone deepwater precise throwing and filling
CN207389483U (en) * 2017-11-02 2018-05-22 中国电建集团港航建设有限公司 A kind of deep water high-precision throws bag operation flat-bottomed boat
CN108252306A (en) * 2018-03-20 2018-07-06 中国水利水电第五工程局有限公司 A kind of underwater filler throwing system and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
深水域抛填袋装砂筑堤工艺探索;赵国权等;《中国水运》;20130930;第13卷(第9期);第214-217页 *

Also Published As

Publication number Publication date
CN109098179A (en) 2018-12-28

Similar Documents

Publication Publication Date Title
CN201245235Y (en) Deep water jackstone leveling ship
CN102322062B (en) Transportation and installation process of base barrel body of barrel type breakwater
CN1884719A (en) High opening, low edge-foot double-wall steel-cofferdams construction process for coffer without back cover concrete
CN101195407A (en) Boatbuilding system
CN109024525B (en) Artificial island structure considering underground space development and utilization and construction method thereof
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
JP3663693B2 (en) Large structure manufacturing and repair work methods as well as barges used to implement these methods
CN215053031U (en) High-precision environment-friendly riprap leveling ship
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN109098179B (en) Throwing filling structure system and working method
CN107938594A (en) Deep water mixing dike construction method
CN113481883B (en) Reinforcing and reinforcing construction method for bridge underwater structure
CN213625592U (en) Lifting, placing and anchoring device for leveling frame in riprap leveling ship
CN114368456A (en) Process for separating upper floating body and lower floating body of offshore platform
CN114348871A (en) Floating transportation device and transportation method for immersed tube
CN111155540A (en) Construction method of double-wall steel cofferdam
CN216664285U (en) Water dredging platform based on automatic fixed-point operation
CN210263059U (en) Underwater soil layer protection is with throwing bagging apparatus
JP2741076B2 (en) Construction method such as caisson
US1619331A (en) Method of and apparatus for laying protecting coverings
CN114991158B (en) Underwater foundation bed leveling method
CN116378041A (en) Construction method of temporary steel pipe pile in shallow water area
CN116306082B (en) Design method for installation parameters of submarine pipeline in deep sea section
CN218540749U (en) Ship floating platform auxiliary pile foundation structure capable of being movably positioned
CN112779967B (en) Construction method for sea-land connecting section of sewage sea area discharge pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant