CN109087035A - Engineering construction plan creating method and system and electronic equipment - Google Patents
Engineering construction plan creating method and system and electronic equipment Download PDFInfo
- Publication number
- CN109087035A CN109087035A CN201811237613.1A CN201811237613A CN109087035A CN 109087035 A CN109087035 A CN 109087035A CN 201811237613 A CN201811237613 A CN 201811237613A CN 109087035 A CN109087035 A CN 109087035A
- Authority
- CN
- China
- Prior art keywords
- information
- date
- project
- entry condition
- parameter information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000000034 method Methods 0.000 title claims abstract description 411
- 238000010276 construction Methods 0.000 title claims abstract description 97
- 230000008569 process Effects 0.000 claims abstract description 321
- 238000003860 storage Methods 0.000 claims description 17
- 238000004590 computer program Methods 0.000 claims description 5
- 238000012545 processing Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 description 45
- 230000006870 function Effects 0.000 description 5
- 230000007774 longterm Effects 0.000 description 5
- 238000007726 management method Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000012986 modification Methods 0.000 description 4
- 230000004048 modification Effects 0.000 description 4
- 230000003287 optical effect Effects 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 230000008878 coupling Effects 0.000 description 3
- 238000010168 coupling process Methods 0.000 description 3
- 238000005859 coupling reaction Methods 0.000 description 3
- 230000005611 electricity Effects 0.000 description 3
- 238000009472 formulation Methods 0.000 description 3
- 239000000203 mixture Substances 0.000 description 3
- 238000012163 sequencing technique Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000012217 deletion Methods 0.000 description 2
- 230000037430 deletion Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 230000014759 maintenance of location Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- 230000001195 anabolic effect Effects 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000012512 characterization method Methods 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000008014 freezing Effects 0.000 description 1
- 238000007710 freezing Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000035800 maturation Effects 0.000 description 1
- 238000004393 prognosis Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- General Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Biodiversity & Conservation Biology (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The embodiment of the application provides a method, a system and electronic equipment for creating an engineering construction plan, wherein the method comprises the following steps: acquiring project plan parameter information of a target project; determining a procedure which accords with starting conditions in the target project from a preset date according to the project plan parameter information; and determining the operation date of each process meeting the starting condition. The creation method can timely, accurately and comprehensively acquire the project plan parameter information of the target project, avoids the problems of untimely information updating, asymmetric information or incomplete information, determines the operation date of each process according to the acquired project plan parameter information, further works out the operation plan of the whole project, greatly overcomes the problem that the made operation plan is seriously inconsistent with the actual condition due to experience difference of project managers, ensures that each process can complete operation within the expected operation date in actual work, and can efficiently and reasonably utilize each construction resource.
Description
Technical field
This application involves the technical fields of creation engineering construction plan, specifically, the present invention relates to engineering construction plans
Creation method, system and electronic equipment.
Background technique
In engineering construction field, reasonable engineering construction plan can effectively shorten item efficiently using every resource
The mesh period reduces project cost, brings higher economy return.
By taking the construction project on wind-power electricity generation airport as an example, as wind-power market is from past growth form market to emerging economies
Body transfer, wind-powered electricity generation increase field newly and focus primarily upon the southern market for comparing not yet maturation and more otherness, this passes wind field
System the mode of project construction is unable to satisfy the engineering construction demand of new markets.In the current project implementation process, " work order is generallyd use
The mode of management+project manager's experience " formulates production plan.However, process involved in project is more, made using above-mentioned formulation
When the mode of industry plan, be easy because of information update not in time, information asymmetry, information is not comprehensive or subjective factor of people is (such as item
The experience difference of mesh manager) etc. reasons and cause the production plan formulated and generation the case where actual conditions grave fault.
In conclusion the method for formulating production plan in the prior art haves the defects that accuracy is low.
Summary of the invention
This application provides a kind of creation method of engineering construction plan, device, electronic equipment and computer-readable storages
Medium, the method for solving that formulation production plan exists in the prior art have the defects that the technical issues of accuracy is low.
In a first aspect, the embodiment of the present application provides a kind of creation method of engineering construction plan, comprising: obtain target item
Purpose project plan parameter information;According to project plan parameter information, determine to open from meeting in destination item the default date
The process of dynamic condition;Determine the job date of each process for meeting entry condition.
Second aspect, the embodiment of the present application provide a kind of creation system of engineering construction plan, comprising:
Module is obtained, for obtaining the project plan parameter information of destination item;First judgment module, for according to project
Plan parameters information is determined from the process for meeting entry condition the default date in destination item;Execution module is determined every
The job date of a process for meeting entry condition.
The third aspect, the embodiment of the present application provide a kind of electronic equipment comprising:
Processor;And
Memory is configured to storage machine readable instructions, instructs when executed by the processor, so that processor executes sheet
Apply for the creation method for the engineering construction plan that embodiment first aspect provides.
Fourth aspect, the embodiment of the present application provide a kind of computer readable storage medium, are stored thereon with computer journey
Sequence, which is characterized in that the program realizes the engineering construction plan that the embodiment of the present application first aspect provides when being executed by processor
Creation method.
Technical solution provided by the embodiments of the present application has the benefit that
In the creation method of engineering construction plan provided by the embodiments of the present application, can in time, it is accurate and comprehensively obtain
To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks
Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project
Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not
The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work
It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band
Carry out higher economy return.
Detailed description of the invention
In order to more clearly explain the technical solutions in the embodiments of the present application, institute in being described below to the embodiment of the present application
Attached drawing to be used is needed to be briefly described.
Fig. 1 is a kind of flow diagram of the creation method for engineering construction plan that the embodiment of the present application one provides;
Fig. 2 is the flow diagram of the creation method for another engineering construction plan that the embodiment of the present application two provides;
Fig. 3 is a kind of structural schematic diagram of the prediction meanss for operation window phase that the embodiment of the present application five provides;
Fig. 4 is the structural schematic diagram for a kind of electronic equipment that the embodiment of the present application six provides.
Specific embodiment
Embodiments herein is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end
Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached
The embodiment of figure description is exemplary, and is only used for explaining the application, and is not construed as limiting the claims.
Those skilled in the art of the present technique are appreciated that unless expressly stated, singular " one " used herein, " one
It is a ", " described " and "the" may also comprise plural form.It is to be further understood that being arranged used in the description of the present application
Diction " comprising " refer to that there are the feature, integer, step, operation, element and/or component, but it is not excluded that in the presence of or addition
Other one or more features, integer, step, operation, element, component and/or their group.It should be understood that when we claim member
Part is " connected " or when " coupled " to another element, it can be directly connected or coupled to other elements, or there may also be
Intermediary element.In addition, " connection " used herein or " coupling " may include being wirelessly connected or wirelessly coupling.It is used herein to arrange
Diction "and/or" includes one or more associated wholes for listing item or any cell and all combinations.
To keep the purposes, technical schemes and advantages of the application clearer, below in conjunction with attached drawing to the application embodiment party
Formula is described in further detail.
The creation method of engineering construction plan provided by the embodiments of the present application, can be used for formulating short-term production plan and length
Phase production plan.Wherein, short-term production plan refers to the production plan formulated for the project for going into operation or having gone into operation in the recent period, long
Phase production plan refers to the production plan of the project formulation for going into operation after the long period or still in the business meeting stage.
In short-term planning, since project goes into operation or has gone into operation in the recent period, the basic information and item of project
Purpose plan parameters information can be formulated directly according to the plan parameters information of the known project corresponding known to being usually
Production plan;And in forward planning, it is gone into operation after extended periods due to project or is still in the business meeting stage, because
It is known that this, which only has less basic information, and project plan parameter information is usually unknown, it is therefore desirable to pass through project
Basic information determine project plan parameter information, formulate corresponding production plan further according to plan parameters information.
In order to realize the creation method of engineering construction plan provided by the embodiments of the present application, the embodiment of the present application provides one
Software systems are covered, which uses B/S (Browser/Server, browser and server) framework of standard criterion, real
A series of functions such as existing data displaying, service logic, data access separation.System is made of each Service Component, is adjusted according to request
With corresponding Service Component, make that the whole system degree of coupling is low, modularization is strong, and for user provide conveniently, it is accurate, quickly, it is friendly
Service, while software systems can be supported integrated with other system specified modularizations, have good practicability and extension
Property.
Above-mentioned software systems include foreground and backstage, and foreground provides human-computer interaction function, for user's creation, editor, inquiry
Or corresponding information is deleted, foreground includes homepage module, information module, planned allocation module and system configuration module etc., wherein
Homepage module is divided according to user role, and role includes client service center, division department manager and project manager etc., the homepage mould
Block be mainly used for the distribution of display project, policy implication region, unit capacity statistics, go into operation prompting etc. summary informations;Information module
For the nucleus module of entire software systems, the functions such as data interaction, data operation are realized, return the result with background model collection, it will
Corresponding information visualization shows user;Planned allocation module is for configuring make a plan required data information, such as machine
Type information, supplier information etc.;System configuration module is for configuring system permission, management role relation etc..After software systems
Platform is integrated with every module of the creation method of performance of work construction plan, and foreground cooperates with backstage realizes that the embodiment of the present application mentions
Every step of the creation method of the engineering construction plan of confession, each module on backstage are full for calculating as system operations core
The plan arrangement of parameter set under sufficient different business scene, and carrier of the software systems as each module, for receiving or safeguarding phase
Necessary information is closed to support the measuring and calculating process of each module on backstage, further enhances operability, the availability for formulating construction plan
And ease for use.
How the technical solution of the application and the technical solution of the application are solved with specifically embodiment below above-mentioned
Technical problem is described in detail.These specific embodiments can be combined with each other below, for the same or similar concept
Or process may repeat no more in certain embodiments.Below in conjunction with attached drawing, embodiments herein is described.
Embodiment one
The embodiment of the present application one provides a kind of creation method of engineering construction plan, as shown in Figure 1, this method comprises:
S1: the project plan parameter information of destination item is obtained.
S2: it according to project plan parameter information, determines from the work for meeting entry condition the default date in destination item
Sequence.
S3: the job date of each process for meeting entry condition is determined.
The creation method for the engineering construction plan that the embodiment of the present application one provides, can in time, it is accurate and comprehensively obtain
To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks
Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project
Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not
The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work
It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band
Carry out higher economy return.
In addition, the method for the embodiment of the present application is to letter compared to the mode of traditional " workform management+project manager's experience "
The feedback speed for ceasing variation faster, can carry out dynamic adjustment, the production plan of renewal item according to the variation of information in real time.
Optionally, in the S1 of the embodiment of the present application one, when obtaining the project plan parameter information of destination item, packet
It includes: obtaining the project plan parameter information of destination item and the basic information of destination item.The step be applicable in go into operation in the near future or
The creation method of the construction plan of the project to have gone into operation, that is, the method for creating short-term production plan, in the method, target item
Purpose basic information and project plan parameter information be it is determining, can directly acquire to obtain.
Alternatively, the project plan parameter information for obtaining destination item can also include: the basic information for obtaining destination item,
The history item to match with destination item is determined according to basic information;Joined according to the project plan of the history item to match
Number information, determines the project plan parameter information of destination item.The step is suitable for going into operation or still locating after extended periods
In the creation method of the construction plan of the project in business meeting stage, that is, the method for creating long-term operation plan, in the method,
Only less basic information is known, and project plan parameter information is usually unknown, it is therefore desirable to pass through project
Basic information determines project plan parameter information, formulates corresponding production plan further according to plan parameters information.
It, being capable of not sympathizing with for destination item in the creation method for the engineering construction plan that the embodiment of the present application one provides
Condition provides the corresponding method for obtaining project plan parameter, makes short-term production plan and long-term operation plan, meets not
With the destination item of application scenarios.
Optionally, the creation method for the engineering construction plan that the embodiment of the present application one provides, further includes: join according to the project plan
Number information is determined from there is no when the process for meeting entry condition in destination item the default date, it is determined whether exist not
The process for being determined job date;If so, determining the target item from next default date according to project plan parameter information
The process for meeting entry condition in mesh determines the job date of each process for meeting entry condition.
In the creation method for the engineering construction plan that the embodiment of the present application one provides, meet when all from the default date
After job date is determined in the process of entry condition, is re-executed on next default date and be determined for compliance with entry condition
Process and the step of determine the job date of each process for meeting entry condition, process circulation executes, until determining
There is no the processes for not being determined job date, show that job date has been determined in all process steps in project at this time,
The construction plan of the project has created completion.The above process can determine destination item all process steps in a very short period of time
Job date, the construction plan being quickly obtained in the whole cycle of destination item.
Optionally, the creation method for the engineering construction plan that the embodiment of the present application one provides, further includes: every by what is determined
The information of the job date of a process for meeting entry condition is uploaded to appointing system.
Can be with specified in time by information in the creation method for the engineering construction plan that the embodiment of the present application one provides
System or platform coordination sharing, avoid information from losing, and the effective experience information of destination item can be inherited, and are subsequent project
Experience is instructed in offer.
Embodiment two
The embodiment of the present application two provides the creation method of another engineering construction plan, as shown in Fig. 2, this method packet
It includes:
S11: the basic information and project plan parameter information of destination item are obtained.
The embodiment of the present application two provides the creation side of the construction plan for the project for going into operation or having gone into operation in the recent period
Method, that is, the method for creating short-term production plan, in the method, the basic information and project plan parameter information of destination item are
Determining, it can directly acquire to obtain.It specifically, can be according to basic information, previously described including foreground and backstage
In software systems, corresponding project plan parameter information is transferred.
The creation method for the engineering construction plan that the embodiment of the present application two provides can be applied in wind energy project construction project
In, below by taking wind energy project construction project as an example, specifically introduce basic information and project plan parameter information.
Basic information includes the characteristic information of destination item, for example, characteristic information may include project name, number, wind
Power generator pool-size, wind-driven generator set type, wind power generating set quantity, province where project, project site contour and
The transportation range of the components such as longitude and latitude, pylon and master hang quantity etc..
Project plan parameter information includes resource equipment information in wind energy project construction project, and resource equipment information can wrap
Include working sources information and component resource information.
Wherein, working sources information includes working sources total amount and each process needed for project and required construction
The corresponding relationship of resource, working sources include all types of construction teams, as road construction team, foundation construction team, lifting construction team,
It is main to hang team and auxiliary hang team etc..
Component resource information includes each base part of wind power generating set, such as pylon, cabin, impeller, generator,
In, impeller includes wheel hub and blade, and component resource information can characterize the corresponding relationship of each process Yu required component resource, also
The current state of each base part resource can be characterized, such as whether component resource has been consumed.
Project plan parameter information includes the process the constraint relationship information in wind energy project construction project, process the constraint relationship
The sequence of operation in information representation project between each process.Process the constraint relationship information includes blower topological constraints relationship letter
Breath, single machine process the constraint relationship information and global process the constraint relationship information.
The constraint of the sequence of operation in blower topological constraints relation information characterization project between each wind power generating set is closed
System, can know each wind power generating set should be in which wind power generating set by the blower topological constraints relation information
Operation is carried out after or before construction.For example, table 1 is shown in which a kind of blower topological constraints relationship, as shown in table 1, some
Wind power plant needs to build 15 wind power generating sets, and number is respectively FJ01 to FJ15.This 15 wind power generating sets are divided into three
Item builds route, from the point of view of table 1 is divided into three column, first build route be FJ01 to FJ05, second build route be FJ06 extremely
FJ10, it is FJ11 to FJ15 that third, which builds route,.
Each wind power generating set in route is built for same, is needed according to the sequence of operation between each unit about
Beam relationship sequentially construction operation.For example, building route for first, need sequentially successively to carry out wind power generating set FJ01 extremely
The operation of FJ05 after the completion of the operation of one wind power generating set, then carries out the operation of next wind power generating set.
Route is built for above-mentioned three, needs sequentially to apply according to the constraint relationship for the sequence of operation respectively built between route
Work industry.Above-mentioned three sequences of operation for building route include at least following several:
(1) operation in route is sequentially successively respectively built.For example, carrying out the first each wind-force built in route at first
The operation of generating set carries out after the completion of the operation that first builds the last one wind power generating set in route, then successively
Second builds route and third builds the operation of each wind power generating set in route.Those skilled in the art can manage
Solution, three sequencings for building route are adjustable, for example, it is also possible to which route is built in progress second at first or third builds line
The operation of each wind power generating set in road.
(2) operation for building route is first carried out, then carries out other two operations for building route simultaneously.For example, first
The operation for carrying out each wind power generating set that first builds in route, builds the last one wind-power electricity generation in route first
After the completion of the operation of unit, while route is built in progress second and third builds the work of each wind power generating set in route
Industry.It will be understood to those skilled in the art that three sequencings for building route are adjustable, for example, it is also possible to first carry out
Second builds route or third builds the operation of each wind power generating set in route.
(3) two first are carried out simultaneously and builds the operation of route, then carry out remaining one operation for building route.For example,
Carry out first simultaneously and build route and second to build the operation of each wind power generating set in route, first build route or
Second builds after the completion of the operation of the last one wind power generating set in route, then carries out each wind that third is built in route
The operation of power generator group.It will be understood to those skilled in the art that three sequencings for building route are adjustable, example
Such as, it can also first carry out second and build route and third builds the operation of each wind power generating set in route, carry out afterwards
One builds the operation of each wind power generating set in route.
(4) three operations for building route are carried out simultaneously.First is carried out simultaneously to build route, second build route and the
Three build the operation of each wind power generating set in route, it can be understood as, wind power generating set FJ01, FJ06 and FJ011
It goes into operation simultaneously.
It should also be noted that, it is also not necessary to wait upper one to repair in above-mentioned 4 kinds of sequence of operation for building route
The operation completion for building route can start to carry out the next operation for building route.For example, the operation provided for (1) is suitable
Sequence, can be after the completion of first builds the operation of wind power generating set FJ03 in route, it can starts progress second and builds line
The operation on road.The above builds each sequence of operation of route, to those of ordinary skill in the art, is not departing from
Under the premise of the application principle, several improvements and modifications can also be made, these improvements and modifications also should be regarded as the guarantor of the application
Protect range.
FJ01 | FJ02 | FJ03 | FJ04 | FJ05 |
FJ06 | FJ07 | FJ08 | FJ09 | FJ10 |
FJ11 | FJ12 | FJ13 | FJ14 | FJ15 |
Table 1
Table 2 is meteorological allocation list provided by the embodiments of the present application, and meteorology configuration, which indicates, builds single wind-driven generator
Process and process involved in group can operation meteorological condition, single machine process constraint information characterizes in single wind power generating set
The sequence of operation of each process, for example, lifting the stage the sequence of operation be " tower hoisting --- cabin lifting --- generator hanger
Dress --- wheel hub, leaf blade hanging ".According to the difference of sessions, all process steps in table 2 are divided into the level-one process of three types,
Level-one process include early period process, the supply of material process and lifting process;Each level-one process further includes multiple second level processes, for example,
Process early period includes two second level processes, respectively constructing road process and foundation construction process;Further, each second level is also
Including three-level process, builds single wind power generating set and need 35 three-level processes altogether, for example, foundation construction process includes
Three-level process has foundation ring procedure for preparation, foundation excavation process, basis backfill process etc..In engineering provided by the embodiments of the present application
In the creation method of construction plan, the job date of each process for meeting entry condition is determined, which refers to wind power plant
The three-level process of the wind power generating set of required construction.
Table 2
S12: it according to project plan parameter information, determines from the work for meeting entry condition the default date in destination item
Sequence.
Optionally, for the destination item not gone into operation, the default date can be the starting date of destination item, i.e., first
The job date of process, thus the production plan for all process steps after making starting date;For the mesh to have gone into operation
Mark project, default date can be set to some day in the project cycle, make not finishing after the date for all
The production plan of process, for example, can be the current date by default date default setting for the destination item to have gone into operation.
In the embodiment of the present application, the starting date of destination item can be determined according to global process the constraint relationship information,
As shown in table 3, table 3 is global process the constraint relationship information table provided by the embodiments of the present application, global process the constraint relationship information
The information of the process of involved every preparation before going into operation including destination item, for example, formality information is (such as country
Check and approve plan information etc.), targeted message (such as host contract signing information), drawing information, road survey information, build information (such as
The information of over-the-counter constructing road situation) and information of showing up, information of showing up refers to that resource equipment is shown up the information of situation, such as road
The case where unit in charge of construction shows up etc..The starting date of destination item can be determined according to above- mentioned information, certainly, gone into operation in determination
Also need to consider the influence of policy information when the date, policy information includes policy of obligating, elastic restraint policy (such as local political affairs
Plan etc.).
Level-one process | Second level process | Coding |
Formality | Country checks and approves plan | qj_01 |
Formality | System of project approval gives an written reply (provincial reply) | qj_02 |
Formality | Environmental impact assessment reply | qj_03 |
Formality | Expropriation of land formality | qj_04 |
Formality | Access reply | qj_05 |
Formality | Forest land reply | qj_06 |
Formality | Logging management | qj_07 |
Calibration | Host contract signing | qj_08 |
Calibration | The calibration of foundation ring factory | qj_09 |
Calibration | The calibration of pylon factory | qj_10 |
Calibration | The calibration of road construction unit | qj_11 |
Calibration | The calibration of foundation construction unit | qj_12 |
Calibration | Lifting construction unit calibrates (installation unit calibration) | qj_13 |
Calibration | The calibration of line construction unit | qj_14 |
Calibration | The calibration of booster stations unit in charge of construction | qj_15 |
Drawing | The review of road drawing | qj_16 |
Road is surveyed | Completion is surveyed on road | qj_17 |
It builds | Over-the-counter constructing road | qj_18 |
It builds | Stockyard is established | qj_19 |
It shows up | Road construction unit is shown up | qj_20 |
It shows up | Foundation construction unit is shown up | qj_21 |
It shows up | Lifting construction unit is shown up | qj_22 |
It shows up | Main hang is shown up | qj_23 |
It shows up | Auxiliary hang is shown up | qj_24 |
Table 3
Optionally, it according to project plan parameter information and basic information, determines not complete on the default date in destination item
The process of knot;From the process not finished respectively, the process for meeting entry condition is determined.
Optionally, in the embodiment of the present application two, according to project plan parameter information and basic information, destination item is determined
In the process that does not finish on the default date, specific implementation step may include: according to the process in project plan parameter information
The starting day of the first process of destination item in the net operating time information and basic information of the constraint relationship information and each process
Phase is determined to end the process not finished into default date destination item.
The net operating time of process in the embodiment of the present application, refer to process not by any disturbance factor (such as meteorological condition,
Holiday or other enchancement factors) under the influence of, normal implement duration used in process content.
It should be noted that directly first process can be determined as not when the starting date of process headed by the default date
The process to finish, then executes subsequent step.For the other processes after first process, then need to be believed according to process the constraint relationship
The sequence of operation of each process in breath is successively added to default from the starting date for process that the net operating time of each process is confessed one's crime
Date ends the process not finished as to default date, the process that net operating time is not cumulatively added.
Optionally, in the embodiment of the present application two, from the process not finished respectively, the process for meeting entry condition is determined,
Its specific implementation step may include: according to the process the constraint relationship information in project plan parameter information, determine it is each not
The preposition process of the process to finish;According to the net operating time information and basic information of process each in project plan parameter information
The starting date of the first process of middle destination item, judge to end the process not finished each to the default date preposition process whether
It finishes;The corresponding resource equipment of process not finished each according to the resource equipment information in project plan parameter information, judgement
It whether is all serviceable condition;It has finished for preposition process and resource equipment is all the process of serviceable condition not finished,
Determine that the process meets entry condition.
It should be noted that each process is needed according to the preset order successively operation in process the constraint relationship information, only
There is the operation that subsequent handling can be just carried out after the completion of preposition process.Determine that multiple processes not finished may include, it should
Multiple processes not finished are also required to construct according to preset order, such as the process A not finished and work for determining
Sequence B, process A are the preposition process of process B, and the preposition process of process A has finished, then it is further contemplated that carrying out process A
Operation, and since process A at this time does not finish also, process B does not just meet entry condition.Meanwhile each process is made
Corresponding working sources are needed when industry, only when resource equipment is serviceable condition, process can just carry out operation.Therefore,
For process A, after the preposition process for determining process A has finished, it is also necessary to determine the corresponding working sources of process A whether be
State to be used, for example, determining whether the corresponding working sources of process A are idle, and whether the corresponding component resource of process B reaches item
Mesh scene.Only the preposition process of process A has finished and when resource equipment is all serviceable condition, can just determine that process A is accorded with
Close entry condition.
Optionally, it in the embodiment of the present application two, determines the process to finish in destination item on the default date, releases
The corresponding resource equipment of the process of knot.Optionally, it according to project plan parameter information and basic information, determines in destination item
In the process that the default date has finished, the corresponding resource equipment of process to have finished is discharged.
It should be noted that the corresponding resource equipment of process that release finishes includes: the work that this in resource equipment finishes
The corresponding working sources of sequence (such as foundation construction team) are set as state to be used, so that other processes that do not finish continue to use;
It sets the corresponding component resource of the process to have finished (pylon and cabin of such as wind power generating set) in resource equipment to
Consumption state.
S13: the job date of each process for meeting entry condition is determined.
Optionally, according to target in the net operating time information and basic information of process each in project plan parameter information
The starting date of the first process of project determines the basic job date for each meeting the process of entry condition.
Process for meeting entry condition, according to the sequence of operation of each process in process the constraint relationship information, by the work
The net operating time of each process before sequence confess one's crime process the starting date from be successively added to some date, opened meeting
The starting date of the process of dynamic condition was arranged after the date, according to the net operating time for the process for meeting entry condition, pushed away
Calculating finishes the date, and starting the date section between date and the date of finishing is that this meets the basic operation of the process of entry condition
Date.
Present inventor it is considered that in the operation process of process, may because of weather, holiday or it is other with
Machine factor causes operation process discontinuous, and the duration of process actual basic job date may be more than net operating time.Example
Such as, the net operating time of process A is 3 days, and the starting date is August 1, and the date that theoretically finishes is August 3, however due to day
Gas reason cause August No. 2 and No. 3 can not operation, cause process A finish the date be August 5, the basic operation of process A at this time
Date is August No. 1 to August 5.
Based on above-mentioned consideration, optionally, in the embodiment of the present application two, each process for meeting entry condition is determined
Job date, further includes: according to the operation window phase information in project plan parameter information, to each work for meeting entry condition
The basic job date of sequence is modified, and obtains out the plan job date for each meeting the process of entry condition.Operation window
Phase information, which refers to process within a preset time period, can carry out the date of operation, from the starting date of process, according to process
Net operating time, date of operation can be carried out sequentially in time by choosing, until determining finishing the date for process, this is opened
Date section between dynamic date and the date that finishes is that this meets the plan job date of the process of entry condition.
Present invention is it is considered that influence the process factor that whether can carry out operation on a certain date main
Have: the meteorological condition of this day whether meet process can operating condition and this day whether be can not operation holiday, because
This, can filter out that meteorological condition meets process operating condition and can be not belonging to date of holiday, as making for process
Industry day.
Based on above-mentioned consideration, optionally, in the embodiment of the present application two, according to the gathering hole in project plan parameter information
Mouth phase information, is modified the basic job date of each process for meeting entry condition, obtains out each meeting trip bar
The plan job date of the process of part, comprising: according to the routine work window phase information in operation window phase information, to each symbol
The basic job date for closing the process of entry condition is modified, and obtains out the plan operation for each meeting the process of entry condition
Date.
Routine work window phase information refers to the process determined according to meteorological condition and holiday in the preset period
The interior date that can carry out operation, from the starting date of process, according to the net operating time and routine work window phase of process
Information, date of operation can be carried out sequentially in time by choosing, until determine finishing the date for process, the starting date and
Date section between the date that finishes is that this meets the plan job date of the process of entry condition.
The acquisition process of routine work window phase information may include steps of a)-c):
A): acquisition can operation meteorological condition, weather information over the years and holiday information.
It should be noted that each process have respectively it is respective can operation meteorological condition obtained in the embodiment of the present application two
Take can operation meteorological condition include different processes can operation meteorological condition.
Optionally, shown in table 2 each three-level process can operation meteorological condition, including wind friction velocity, rainfall, drop
Snowfall, temperature condition and can fishing time, for example, constructing road can operation meteorological condition are as follows: without rainfall, without snowfall, gas
Temperature between subzero 5 degrees Celsius to 40 degrees Celsius above freezing and wind speed be less than 10m/s, can fishing time be daytime.
The weather information over the years obtained can be the weather information in past one period or a time, be also possible to
The weather information in multiple times in past, concrete condition can be decided according to the actual requirements.For example, current time point is 2018
January 1, then weather information or annual weather information in 2017 in available 2017 in certain time, it can also
To obtain the weather information of weather information or these three times whole in 2015 to 2017 in certain time.The application
The weather information over the years that embodiment provides, spatial accuracy can achieve as unit of the region of 81 sq-kms, time precision
It can achieve as unit of hour, i.e. the weather information over the years meteorology hourly over the years that is capable of providing certain unit area
Data.
The holiday information of acquisition includes national legal festivals and holidays, the local (folk customs and culture festival of such as ethnic group legal festivals and holidays
Day, church festival) or the lay day set by occasion etc..
B): according to can operation meteorological condition and weather information over the years, determine that the basis of every process can operation day.It will go through
In year weather information meet can operation meteorological condition date, the basis in the current construction year as project can operation day, for example,
What the August weather information ordered on the 1st in 2017 met process A can operation meteorological condition, it is determined that August 1st in 2018 is A work
It the basis of sequence can operation day.
C): determining whether the basis of each process can belong to the holiday in holiday information operation day, from each process
Basis can in operation day, reject belong to holiday basis can operation day, determine each process first amendment can operation
Day, according to the first of each process amendment can operation day, determine routine work window phase information.
The embodiment of the present application can be based on weather history information and holiday information, determine routine work window phase information,
It is modified, is planned according to the basic job date that net operating time of the routine work window phase information to process is determined
Job date, the plan job date have taken into account the influence of meteorological condition and holiday to process construction speed, so that process
Starting date and the date that finishes are more accurate, further reduced the production plan of process and the probability that actual conditions are not inconsistent.
It should be noted that during project carries out, to the process Weather Forecast Information started in a short time compared with subject to
Really, have higher reference value, therefore can also further correct routine work window phase information according to Weather Forecast Information.
Weather Forecast Information can use existing Predictive meteorological methods and obtain, and can also pass through third-party weather prognosis
Using or meteorological official website in obtain.For example, the Weather Forecast Information in somewhere may include 3 days, 7 days or 15 days following
Meteorological data.
After step c, determine each process it is each first amendment can operation day Weather Forecast Information, if meet should
Process can operation meteorological condition;By meet the process can operation meteorological condition first amendment can operation day, as the work
Sequence second amendment can operation day, by be unsatisfactory for the process can operation meteorological condition first amendment can operation day reject.Root
According to each process second amendment can operation day, determine more accurate routine work window phase information.
In actual operation process, some random factors can also be delayed the job scheduling of process, therefore, optionally,
In the embodiment of the present application two, according to the operation window phase information in project plan parameter information, meet entry condition to each
Basic job date of process be modified, obtain out the plan job date for each meeting the process of entry condition, also wrap
It includes: according to the random operation window phase information in operation window phase information, the basis of each process for meeting entry condition being made
The industry date is modified, and obtains out the plan job date for each meeting the process of entry condition.
After random operation window phase information refers to the date rejected and can not constructed by enchancement factor, obtained process can
Job date, random operation window phase can be determined by rule of thumb data.In the embodiment of the present application two, the plan of process
Job date after having taken into account the influence of meteorological condition and holiday to process construction speed, has also taken into account random factor to work
The influence of sequence job scheduling further improves the accuracy of the plan job date of process.
Optionally, in the S13 of the embodiment of the present application two further include:, will be each when determining the process for meeting entry condition
The corresponding resource equipment of process for meeting entry condition is set as occupied state.Meet the corresponding resource machine of process of entry condition
Tool is set as occupied state, then shows that other processes can not at least make within the basic job date for the process for meeting entry condition
With this part resource equipment, avoid same resource equipment causes construction to be counted on the identical date by two processes while occupancy
Mark existing conflict.
Implement to determine multiple processes for meeting entry condition in S12, therefore, S13's is specific in two in the application
Step may include: that a process is randomly selected in multiple processes for meeting entry condition, determine each to meet trip bar
The corresponding resource equipment of the process for meeting entry condition is set occupied state by the job date of the process of part.
At this point, workable resource equipment is reduced compared with the S12 before the case where.Under the premise of this, for
The remaining process for meeting entry condition may be no longer complies with entry condition, therefore can hold again since resource equipment is reduced
Row S12 and S13, the process for determining new symbol entry condition in these processes determine the new work for meeting entry condition
The new corresponding resource equipment of the process for meeting entry condition is set occupied state by the job date of sequence.The above process follows
Ring executes, until determining from all processes for meeting entry condition in destination item the default date.
Optionally, in the embodiment of the present application two, after the job date for determining each process for meeting entry condition,
The information for each of determining the job date for the process for meeting entry condition is uploaded to appointing system.
S14: it according to project plan parameter information, determines from there is no meet trip bar in destination item the default date
The process of part.
Optionally it is determined that going out from the process to have finished in destination item the default date;The process that has been finished according to these,
And determined in S13 from all processes for meeting entry condition in destination item the default date, determine in this step
Out from the process for not meeting entry condition in destination item the default date and not finishing.
S15: the process for not being determined job date is determined whether there is;The process for not being determined job date if it exists,
Execute S16;Otherwise terminate this process.
S16: it according to project plan parameter information, determines from meeting trip bar in destination item next default date
The process of part determines the job date of each process for meeting entry condition.
Optionally, in the embodiment of the present application two, after the job date for determining each process for meeting entry condition,
The information for each of determining the job date for the process for meeting entry condition is uploaded to appointing system.
Can be with specified in time by information in the creation method for the engineering construction plan that the embodiment of the present application two provides
System or platform coordination sharing, prevent loss of data, and the effective posterior infromation of destination item can be inherited, and are subsequent project
Experience is instructed in offer.
It will be understood to those skilled in the art that S16, which is equivalent to, re-executes S12 to S15 on next default date, it should
Process circulation executes, until determining under each default date all there is no the process for not being determined job date, shows item at this time
Job date has been determined in all process steps in mesh, and the construction plan of the project has created completion.
Embodiment three
The embodiment of the present application three provides the creation method of another engineering construction plan, the method for the embodiment of the present application three
Process is by the S11 replacement in the method flow of above-described embodiment two are as follows: the basic information for obtaining destination item, according to basis letter
Breath determines the history item to match with destination item;According to the project plan parameter information of the history item to match, really
Make the project plan parameter information of destination item.
The embodiment of the present application three provides the item for being directed to and going into operation after extended periods or being still in the business meeting stage
The creation method of purpose construction plan, that is, the method for creating long-term operation plan, in the method, only less basic information
It is known, and project plan parameter information is usually unknown, it is therefore desirable to project is determined by the basic information of project
Plan parameters information formulates corresponding production plan further according to plan parameters information.
In the embodiment of the present application three, basic information includes the characteristic information of the destination item, for example, may include project
Title, number, unit capacity, machine set type, unit quantity, province where project, project site contour and longitude and latitude, pylon etc.
The transportation range of component and master hang quantity etc..According to features described above information, project matching algorithm based on a specified, in history item
It is matched to the history item most like with destination item in library, the every terms of information of destination item, example are determined according to the history item
The resource equipment information and process the constraint relationship information in the project plan parameter information of destination item are such as determined, according to above-mentioned
The information determined executes subsequent step, and the subsequent step of the embodiment of the present application three can be with S12 to S16 in above-described embodiment two
Unanimously, details are not described herein again.
The creation method for the engineering construction plan that the embodiment of the present application three provides, for going into operation or still locating after the long period
In the project in business meeting stage, it is capable of under a large amount of deletion conditions of relevant information of elementary item and formulates more accurately construction meter
It draws, which can promote the competitiveness in business meeting of enterprise, help to guide clients investment intention.
Example IV
The embodiment of the present application four provides the creation method of another engineering construction plan, compared with above-described embodiment,
The embodiment of the present application four the difference is that: the operation restrictive condition of destination item is set;According to the project plan parameter
Information, determine from the process for meeting entry condition the default date in destination item, determines each entry condition that meets
The job date of process, comprising: according to the operation restrictive condition of project plan parameter information and destination item, determine from default
The process for meeting entry condition from date in destination item determines the job date of each process for meeting entry condition.
As shown in the input process in following table 4, the operation restrictive condition of destination item includes time restriction, resource constraint
With planned outcome restrict.Time restriction refers to the duty cycle of limited target project, the i.e. operation of destination item all process steps
Complete the occupied period.The duty cycle of limited target project includes limit starting time, limit end time, or is opened with the time limit
Dynamic time and end time.Resource constraint refers to the resource equipment that limited target project needs.Resource equipment can be limited to
Fixed resource, the i.e. total amount of resource equipment are fixed;Resource equipment can also be limited to dynamic resource, i.e. resource equipment
Total amount can according to need floating.
Planned outcome restrict refers to the difference that demand it is expected according to project, limits the type of production plan.The project phase
Prestige demand includes: that the duration is most short, cost is minimum and optimal balance.Planned outcome restrict be the duration it is most short refer to, referring to
In the combination of fixed time restriction and resource constraint, in all possible production plans, duration shortest operation meter is exported
It draws;Out result restrict be the duration it is most short refer to, at the appointed time limit and resource constraint combination in, all can
In the production plan of energy, the minimum production plan of output cost;Result restrict refers to out for optimal balance, when specified
Between limitation and resource constraint combination in, in all possible production plans, export the production plan of optimal balance, it is optimal
Balance refers to that duration and cost reach desired equalization point.
As shown in the anabolic process in table 4, different types of time restriction and resource constraint be can be combined with each other, at every kind
In combination, demand it is expected according to different projects, exports different production plans.Combination 1 indicates, is limited beginning in time restriction
Time and resource constraint are that export planned outcome restrict respectively be respectively that the duration is most short, cost under the combination of fixed resource
Minimum and optimal balance production plan.In table 4, plan1 indicates that planned outcome restrict is duration shortest production plan,
Plan2 indicates that planned outcome restrict is the minimum production plan of cost, and plan3 indicates that planned outcome restrict is optimal
The production plan of balance.In table 4, time restriction and resource constraint share six kinds of combinations, and every kind is combined according to planned outcome about
The difference of beam limitation can export three kinds of production plans, therefore the creation of the engineering construction plan of the offer of the embodiment of the present application four
Method can export 18 kinds of production plans.
Table 4
Embodiment five
The embodiment of the present application provides a kind of creation system of engineering construction plan, as shown in figure 3, the engineering construction plan
Creation system 200 include: to obtain module 201, first judgment module 202 and execution module 203.
Wherein, the project plan parameter information that module 201 is used to obtain destination item is obtained.
First judgment module 202 is used to be determined according to project plan parameter information from the default date in destination item
Meet the process of entry condition.
Execution module 203 is used to determine the job date of each process for meeting entry condition.
Optionally, in embodiments herein five, for short-term production plan, module 201 is obtained for obtaining target
The project plan parameter information of project and the basic information of destination item.
For long-term operation plan, the basic information that module 201 is used to obtain destination item is obtained, it is true according to basic information
The history item to match with destination item is made, according to the project plan parameter information of the history item to match, is determined
The project plan parameter information of destination item.
Optionally, the creation system of the engineering construction plan provided in embodiments herein five further include: the second judgement
Module 204.
Second judgment module 204 is used to be determined according to project plan parameter information from the default date in destination item
There is no when the process for meeting entry condition, it is determined whether there is the process for not being determined job date;If so, first judges mould
Block 202 is determined according to project plan parameter information from the work for meeting entry condition next default date in destination item
Sequence, execution module 203 determine the job date of each process for meeting entry condition.
Embodiment six
The embodiment of the present application provides a kind of electronic equipment, as shown in figure 4, electronic equipment shown in Fig. 4 300 includes: place
Manage device 301 and memory 302.
Memory 302 is configured to storage machine readable instructions, instructs when executed by the processor, so that processor executes
The creation method for the engineering construction plan that application embodiment one to example IV any embodiment provides.
Memory 302 in the embodiment of the present application can be ROM (Read-Only Memory, read-only memory) or can deposit
Store up static information and instruction other kinds of static storage device, can be RAM (Random Access Memory, at random
Access memory) or the other kinds of dynamic memory of information and instruction can be stored, it is also possible to EEPROM
(Electrically Erasable Programmable Read Only Memory, Electrically Erasable Programmable Read-Only Memory),
CD-ROM (Compact Disc Read-Only Memory, CD-ROM) or other optical disc storages, optical disc storage (including pressure
Contracting optical disc, laser disc, optical disc, Digital Versatile Disc, Blu-ray Disc etc.), magnetic disk storage medium or other magnetic storage apparatus or
Person can be used in the desired program code of carrying or storage with instruction or data structure form and can be by computer access
Any other medium, but not limited to this.
Processor 301 in the embodiment of the present application can be CPU (Central Processing Unit, central processing
Device), general processor, DSP (Digital Signal Processor, data signal processor), ASIC (Application
Specific Integrated Circuit, specific integrated circuit), FPGA (Field-Programmable Gate
Array, field programmable gate array) either other programmable logic device, transistor logic, hardware component or its
Meaning combination.Its may be implemented or execute combine present disclosure described in various illustrative logic blocks, module and
Circuit.Processor 301 be also possible to realize computing function combination, such as comprising one or more microprocessors combine, DSP and
The combination etc. of microprocessor.
Those skilled in the art of the present technique are appreciated that the pre- measurement equipment of engineering construction plan provided by the embodiments of the present application can
Think required purpose and specially design and manufacture, or also may include the known device in general purpose computer.These equipment
With the computer program being stored in it, these computer programs are selectively activated or are reconstructed.Such computer program
It can be stored in equipment (for example, computer) readable medium or be stored in and be suitable for storage e-command and be coupled to respectively
In any kind of medium of bus.
The pre- measurement equipment of engineering construction plan provided by the embodiments of the present application has identical with mentioned-above each embodiment
Inventive concept and identical beneficial effect, details are not described herein.
Embodiment seven
The embodiment of the present application provides a kind of computer readable storage medium, is stored on the computer readable storage medium
Computer program, the program realize the work that the embodiment of the present application one is provided to example IV any embodiment when being executed by processor
The creation method of journey construction plan.
The computer-readable medium include but is not limited to any kind of disk (including floppy disk, hard disk, CD, CD-ROM and
Magneto-optic disk), (Erasable Programmable Read-Only Memory, erasable programmable are read-only by ROM, RAM, EPROM
Memory), EEPROM, flash memory, magnetic card or light card.It is, readable medium includes by equipment (for example, computer)
With any medium for the form storage or transmission information that can be read.
Computer readable storage medium provided by the embodiments of the present application, with mentioned-above each embodiment hair having the same
Bright design and identical beneficial effect, details are not described herein.
Using embodiments herein, at least may be implemented it is following the utility model has the advantages that
1, the creation method of engineering construction plan provided by the embodiments of the present application, can in time, it is accurate and comprehensively obtain
To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks
Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project
Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not
The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work
It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band
Carry out higher economy return.
In addition, the method for the embodiment of the present application is to letter compared to the mode of traditional " workform management+project manager's experience "
The feedback speed for ceasing variation faster, can carry out dynamic adjustment, the production plan of renewal item according to the variation of information in real time.
2, after job date is determined in all processes for meeting entry condition from the default date, next pre-
If the date re-executes the process for being determined for compliance with entry condition and determines the operation day of each process for meeting entry condition
The step of phase, process circulation execute, until determining there is no the process for not being determined job date, show in project at this time
Job date has been determined in all process steps, and the construction plan of the project has created completion.The above process can be in pole
The job date that all process steps are determined in the short time, the construction plan being quickly obtained in the whole cycle of project.
3, can be with specified in time by information in the creation method of engineering construction plan provided by the embodiments of the present application
System or platform coordination sharing, avoid information from losing, project effective experience information can be inherited, and provide finger for subsequent project
Lead experience.
4, the creation method of engineering construction plan provided by the embodiments of the present application can be directed to the different situations of destination item
The corresponding method for obtaining project plan parameter is provided, short-term production plan and long-term operation plan is made, meets difference
The destination item of application scenarios.
5, the creation method of engineering construction plan provided by the embodiments of the present application originally can take into account process net duration information,
Process is made in influence and random factor of influence, holiday of the meteorological condition to process construction speed to process construction speed
Job date of process is corrected in the influence of industry progress, further reduced the production plan of process and that actual conditions are not inconsistent is general
Rate.
6, in the creation method of engineering construction plan provided by the embodiments of the present application, for going into operation after the long period or still
Project in the business meeting stage is capable of to formulate under a large amount of deletion conditions of relevant information of elementary item and more accurately be built
Plan, the construction plan can promote the competitiveness in business meeting of enterprise, help to guide clients investment intention.
It should be understood that although each step in the flow chart of attached drawing is successively shown according to the instruction of arrow,
These steps are not that the inevitable sequence according to arrow instruction successively executes.Unless expressly stating otherwise herein, these steps
Execution there is no stringent sequences to limit, can execute in the other order.Moreover, at least one in the flow chart of attached drawing
Part steps may include that perhaps these sub-steps of multiple stages or stage are not necessarily in synchronization to multiple sub-steps
Completion is executed, but can be executed at different times, execution sequence, which is also not necessarily, successively to be carried out, but can be with other
At least part of the sub-step or stage of step or other steps executes in turn or alternately.
The above is only some embodiments of the invention, it is noted that for the ordinary skill people of the art
For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered
It is considered as protection scope of the present invention.
Claims (18)
1. a kind of creation method of engineering construction plan characterized by comprising
Obtain the project plan parameter information of destination item;
According to the project plan parameter information, the work for meeting entry condition from destination item described the default date is determined
Sequence;
Determine the job date of each process for meeting entry condition.
2. the method according to claim 1, wherein in the project plan parameter information for obtaining destination item
When, further includes: obtain the basic information of the destination item;
Alternatively, the project plan parameter information for obtaining destination item, comprising: the basic information of the destination item is obtained,
The history item to match with the destination item is determined according to the basic information;According to the history item to match
Project plan parameter information, determine the project plan parameter information of the destination item.
3. according to the method described in claim 2, determining it is characterized in that, described according to the project plan parameter information
Meet the process of entry condition from destination item described the default date, comprising:
According to the project plan parameter information and basic information, determine presetting what the date did not finished in the destination item
Process;
From each process not finished, the process for meeting entry condition is determined.
4. according to the method described in claim 3, it is characterized in that, the basic information includes the feature letter of the destination item
Breath;
And/or the project plan parameter information includes process the constraint relationship information and the resource in wind energy project construction project
Equipment information;
And/or the resource equipment information includes working sources information and component resource information;
And/or the process the constraint relationship information include blower topological constraints relation information, single machine process the constraint relationship information and
Global process the constraint relationship information.
5. according to the method described in claim 4, it is characterized in that, described believe according to the project plan parameter information and basis
Breath determines the process not finished in the destination item on the default date, comprising:
According to the net operating time information of process the constraint relationship information and each process in the project plan parameter information, with
And the starting date of the first process of destination item described in the basic information, determine cut-off to mesh described in the default date
The process not finished in mark project.
6. according to the method described in claim 4, determining institute it is characterized in that, described from each process not finished
State the process for meeting entry condition, comprising:
According to the process the constraint relationship information in the project plan parameter information, each process not finished is determined
Preposition process;
According to mesh described in the net operating time information of each process in the project plan parameter information and the basic information
The starting date of the first process of mark project judges to end described preposition to each process not finished of the default date
Whether process finishes;
According to the resource equipment information in the project plan parameter information, each corresponding money of process not finished is judged
Whether source equipment is all serviceable condition;
It has finished for preposition process and resource equipment is all the process not finished described in serviceable condition, determined that the process accords with
Close entry condition.
7. according to the method described in claim 4, it is characterized by further comprising:
It is described determine it is described when meeting the process of entry condition, by each corresponding resource of process for meeting entry condition
Equipment is set as occupied state;
And/or determine the process to finish in the destination item on the default date, the process to finish described in release is corresponding
Resource equipment.
8. according to the method described in claim 2, it is characterized in that, described determine each process for meeting entry condition
Job date, comprising:
According to mesh described in the net operating time information of each process in the project plan parameter information and the basic information
The starting date of the first process of mark project determines the basic job date of each process for meeting entry condition.
9. according to the method described in claim 8, it is characterized in that, described determine each process for meeting entry condition
Job date, further includes:
According to the operation window phase information in the project plan parameter information, to each process for meeting entry condition
Basic job date is modified, and obtains the plan job date of each process for meeting entry condition.
10. according to the method described in claim 9, it is characterized in that, the work according in the project plan parameter information
Industry window phase information is modified the basic job date of each process for meeting entry condition, obtains each described
Meet the plan job date of the process of entry condition, comprising:
According to the routine work window phase information in the operation window phase information, to each process for meeting entry condition
Basic job date be modified, obtain the plan job date of each process for meeting entry condition;
And/or according to the random operation window phase information in the operation window phase information, described meet entry condition to each
Basic job date of process be modified, obtain the plan job date of each process for meeting entry condition.
11. the method according to claim 1, wherein further include:
According to the project plan parameter information, determine that there is no meet trip bar from destination item described the default date
When the process of part, it is determined whether there is the process for not being determined the job date;
If so, according to the project plan parameter information, determine from meeting in the destination item next default date
The process of entry condition determines the job date of each process for meeting entry condition.
12. the method according to claim 1, wherein further include:
The information for each of determining the job date of the process for meeting entry condition is uploaded to appointing system.
13. the method according to claim 1, wherein further include: the operation limitation item of the destination item is set
Part;
And it is described according to the project plan parameter information, it determines to meet from destination item described the default date and open
The process of dynamic condition determines the job date of each process for meeting entry condition, comprising: according to the project plan
The operation restrictive condition of parameter information and the destination item is determined to meet starting from destination item described the default date
The process of condition determines the job date of each process for meeting entry condition.
14. a kind of creation system of engineering construction plan characterized by comprising
Module is obtained, for obtaining the project plan parameter information of destination item;
First judgment module, for determining the destination item from the default date according to the project plan parameter information
In meet the process of entry condition;
Execution module determines the job date of each process for meeting entry condition.
15. creation system according to claim 14, which is characterized in that
The basic information for obtaining module and being used to obtain the project plan parameter information and the destination item of destination item;Or
Person obtains the basic information of the destination item, determines to go through with what the destination item matched according to the basic information
History project determines the project meter of the destination item according to the project plan parameter information of the history item to match
Draw parameter information.
16. creation system according to claim 14, which is characterized in that further include:
Second judgment module, for determining the destination item from the default date according to the project plan parameter information
In there is no meet entry condition process when, it is determined whether there is the process for not being determined the job date;
If so, the first judgment module according to the project plan parameter information, determines the institute from next default date
The process for meeting entry condition in destination item is stated, the execution module determines each process for meeting entry condition
Job date.
17. a kind of electronic equipment, characterized in that it comprises:
Processor;And
Memory is configured to storage machine readable instructions, and described instruction by the processor when being executed, so that the processing
The creation method of the device perform claim requirement described in any item engineering construction plans of 1-13.
18. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that the program is by processor
The creation method of the described in any item engineering construction plans of claim 1-13 is realized when execution.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811237613.1A CN109087035A (en) | 2018-10-23 | 2018-10-23 | Engineering construction plan creating method and system and electronic equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811237613.1A CN109087035A (en) | 2018-10-23 | 2018-10-23 | Engineering construction plan creating method and system and electronic equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109087035A true CN109087035A (en) | 2018-12-25 |
Family
ID=64843925
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811237613.1A Withdrawn CN109087035A (en) | 2018-10-23 | 2018-10-23 | Engineering construction plan creating method and system and electronic equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109087035A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110175781A (en) * | 2019-05-29 | 2019-08-27 | 国家电网有限公司 | A kind of industry expansion power supply plan self-learning type formulating method |
CN110766292A (en) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | Ship block resource scheduling method, device, equipment and storage medium |
CN111738538A (en) * | 2020-01-06 | 2020-10-02 | 业达建设管理有限公司 | Engineering project management system, management method, APP and storage medium |
CN112561361A (en) * | 2020-12-22 | 2021-03-26 | 深圳市九州建设技术股份有限公司 | BIM-based project supervision informatization management method and system and storage medium |
CN113158306A (en) * | 2021-04-02 | 2021-07-23 | 中国建筑第二工程局有限公司 | Tower crane parametric design method based on Revit metric system conventional model |
CN113283879A (en) * | 2021-06-21 | 2021-08-20 | 华电重工股份有限公司 | Method and device for determining construction amount, electronic equipment and readable storage medium |
CN117114922A (en) * | 2023-10-24 | 2023-11-24 | 天津广正建设项目咨询股份有限公司 | Consultation service and evaluation method and system based on whole process engineering consultation |
-
2018
- 2018-10-23 CN CN201811237613.1A patent/CN109087035A/en not_active Withdrawn
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110175781A (en) * | 2019-05-29 | 2019-08-27 | 国家电网有限公司 | A kind of industry expansion power supply plan self-learning type formulating method |
CN110175781B (en) * | 2019-05-29 | 2021-03-19 | 国家电网有限公司 | Self-learning formulation method for business expansion power supply scheme |
CN110766292A (en) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | Ship block resource scheduling method, device, equipment and storage medium |
CN111738538A (en) * | 2020-01-06 | 2020-10-02 | 业达建设管理有限公司 | Engineering project management system, management method, APP and storage medium |
CN112561361A (en) * | 2020-12-22 | 2021-03-26 | 深圳市九州建设技术股份有限公司 | BIM-based project supervision informatization management method and system and storage medium |
CN112561361B (en) * | 2020-12-22 | 2024-04-09 | 深圳市九州建设技术股份有限公司 | BIM-based engineering supervision informatization management method, system and storage medium |
CN113158306A (en) * | 2021-04-02 | 2021-07-23 | 中国建筑第二工程局有限公司 | Tower crane parametric design method based on Revit metric system conventional model |
CN113283879A (en) * | 2021-06-21 | 2021-08-20 | 华电重工股份有限公司 | Method and device for determining construction amount, electronic equipment and readable storage medium |
CN117114922A (en) * | 2023-10-24 | 2023-11-24 | 天津广正建设项目咨询股份有限公司 | Consultation service and evaluation method and system based on whole process engineering consultation |
CN117114922B (en) * | 2023-10-24 | 2024-01-26 | 天津广正建设项目咨询股份有限公司 | Consultation service and evaluation method and system based on whole process engineering consultation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109087035A (en) | Engineering construction plan creating method and system and electronic equipment | |
US20140129272A1 (en) | System and method for managing service restoration in a utility network | |
JP6445909B2 (en) | Power demand forecasting system | |
US8024205B2 (en) | System and method for calculating damage as a result of natural catastrophes | |
CN104732298A (en) | Method for achieving EMS load prediction based on decision tree and linear regression | |
CN113282684A (en) | Prediction method and device for seasonal classification of flight and machine readable medium | |
Zou et al. | A Biobjective Optimization Model for Deadline Satisfaction in Line‐of‐Balance Scheduling with Work Interruptions Consideration | |
CN108846488A (en) | The maintenance dispatching method and device of wind power plant | |
CN113255996B (en) | Method, device, equipment and storage medium for managing tagged electric charge balance | |
WO2011061970A1 (en) | Inventory plan creation device, inventory plan creation method and inventory plan creation program | |
CN106779439A (en) | A kind of task distribution method and device | |
US20200327627A1 (en) | Methods and systems of a blockchain for distributed-energy-project management | |
CN106786533A (en) | The acquisition methods and device of electric dispatching plan data | |
CN116385124A (en) | Agricultural socialization integrated service cloud platform based on big data analysis traceability | |
CN116307547A (en) | Linkage method, device and equipment for emergency handling of overseas oil and gas pipeline accidents | |
Jia et al. | Setting scheduled trip time based on AVL data | |
Tang et al. | Short-term work team scheduling models for effective road repair and management | |
CN101464873A (en) | Material list establishing method and system | |
CN110059839A (en) | A kind of method that need-based extracts unmet demand | |
Zhao | Strategic enterprise management in the age of energy transition: a roadmap for sustainable business practices | |
CN111311037A (en) | Method for compiling custom construction plan, progress summarizing and data analysis | |
CN110322185A (en) | A kind of logistics management-control method based on GIS and GPS | |
ES2401880B1 (en) | PROCEDURE AND SYSTEM FOR OPTIMIZING MAINTENANCE OPERATIONS IN AIRCRAFTERS AND WIND FARMS. | |
CN111126652B (en) | Hotel tail room intelligent prediction distribution system and method | |
Kumar et al. | Socio-economic aspects of PV roof-top installations for residential colonies |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181225 |