CN109087035A - Engineering construction plan creating method and system and electronic equipment - Google Patents

Engineering construction plan creating method and system and electronic equipment Download PDF

Info

Publication number
CN109087035A
CN109087035A CN201811237613.1A CN201811237613A CN109087035A CN 109087035 A CN109087035 A CN 109087035A CN 201811237613 A CN201811237613 A CN 201811237613A CN 109087035 A CN109087035 A CN 109087035A
Authority
CN
China
Prior art keywords
information
date
project
entry condition
parameter information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201811237613.1A
Other languages
Chinese (zh)
Inventor
陆恒
严斌
王曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Original Assignee
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Goldwind Science and Creation Windpower Equipment Co Ltd filed Critical Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority to CN201811237613.1A priority Critical patent/CN109087035A/en
Publication of CN109087035A publication Critical patent/CN109087035A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • General Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the application provides a method, a system and electronic equipment for creating an engineering construction plan, wherein the method comprises the following steps: acquiring project plan parameter information of a target project; determining a procedure which accords with starting conditions in the target project from a preset date according to the project plan parameter information; and determining the operation date of each process meeting the starting condition. The creation method can timely, accurately and comprehensively acquire the project plan parameter information of the target project, avoids the problems of untimely information updating, asymmetric information or incomplete information, determines the operation date of each process according to the acquired project plan parameter information, further works out the operation plan of the whole project, greatly overcomes the problem that the made operation plan is seriously inconsistent with the actual condition due to experience difference of project managers, ensures that each process can complete operation within the expected operation date in actual work, and can efficiently and reasonably utilize each construction resource.

Description

Creation method, system and the electronic equipment of engineering construction plan
Technical field
This application involves the technical fields of creation engineering construction plan, specifically, the present invention relates to engineering construction plans Creation method, system and electronic equipment.
Background technique
In engineering construction field, reasonable engineering construction plan can effectively shorten item efficiently using every resource The mesh period reduces project cost, brings higher economy return.
By taking the construction project on wind-power electricity generation airport as an example, as wind-power market is from past growth form market to emerging economies Body transfer, wind-powered electricity generation increase field newly and focus primarily upon the southern market for comparing not yet maturation and more otherness, this passes wind field System the mode of project construction is unable to satisfy the engineering construction demand of new markets.In the current project implementation process, " work order is generallyd use The mode of management+project manager's experience " formulates production plan.However, process involved in project is more, made using above-mentioned formulation When the mode of industry plan, be easy because of information update not in time, information asymmetry, information is not comprehensive or subjective factor of people is (such as item The experience difference of mesh manager) etc. reasons and cause the production plan formulated and generation the case where actual conditions grave fault.
In conclusion the method for formulating production plan in the prior art haves the defects that accuracy is low.
Summary of the invention
This application provides a kind of creation method of engineering construction plan, device, electronic equipment and computer-readable storages Medium, the method for solving that formulation production plan exists in the prior art have the defects that the technical issues of accuracy is low.
In a first aspect, the embodiment of the present application provides a kind of creation method of engineering construction plan, comprising: obtain target item Purpose project plan parameter information;According to project plan parameter information, determine to open from meeting in destination item the default date The process of dynamic condition;Determine the job date of each process for meeting entry condition.
Second aspect, the embodiment of the present application provide a kind of creation system of engineering construction plan, comprising:
Module is obtained, for obtaining the project plan parameter information of destination item;First judgment module, for according to project Plan parameters information is determined from the process for meeting entry condition the default date in destination item;Execution module is determined every The job date of a process for meeting entry condition.
The third aspect, the embodiment of the present application provide a kind of electronic equipment comprising:
Processor;And
Memory is configured to storage machine readable instructions, instructs when executed by the processor, so that processor executes sheet Apply for the creation method for the engineering construction plan that embodiment first aspect provides.
Fourth aspect, the embodiment of the present application provide a kind of computer readable storage medium, are stored thereon with computer journey Sequence, which is characterized in that the program realizes the engineering construction plan that the embodiment of the present application first aspect provides when being executed by processor Creation method.
Technical solution provided by the embodiments of the present application has the benefit that
In the creation method of engineering construction plan provided by the embodiments of the present application, can in time, it is accurate and comprehensively obtain To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band Carry out higher economy return.
Detailed description of the invention
In order to more clearly explain the technical solutions in the embodiments of the present application, institute in being described below to the embodiment of the present application Attached drawing to be used is needed to be briefly described.
Fig. 1 is a kind of flow diagram of the creation method for engineering construction plan that the embodiment of the present application one provides;
Fig. 2 is the flow diagram of the creation method for another engineering construction plan that the embodiment of the present application two provides;
Fig. 3 is a kind of structural schematic diagram of the prediction meanss for operation window phase that the embodiment of the present application five provides;
Fig. 4 is the structural schematic diagram for a kind of electronic equipment that the embodiment of the present application six provides.
Specific embodiment
Embodiments herein is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached The embodiment of figure description is exemplary, and is only used for explaining the application, and is not construed as limiting the claims.
Those skilled in the art of the present technique are appreciated that unless expressly stated, singular " one " used herein, " one It is a ", " described " and "the" may also comprise plural form.It is to be further understood that being arranged used in the description of the present application Diction " comprising " refer to that there are the feature, integer, step, operation, element and/or component, but it is not excluded that in the presence of or addition Other one or more features, integer, step, operation, element, component and/or their group.It should be understood that when we claim member Part is " connected " or when " coupled " to another element, it can be directly connected or coupled to other elements, or there may also be Intermediary element.In addition, " connection " used herein or " coupling " may include being wirelessly connected or wirelessly coupling.It is used herein to arrange Diction "and/or" includes one or more associated wholes for listing item or any cell and all combinations.
To keep the purposes, technical schemes and advantages of the application clearer, below in conjunction with attached drawing to the application embodiment party Formula is described in further detail.
The creation method of engineering construction plan provided by the embodiments of the present application, can be used for formulating short-term production plan and length Phase production plan.Wherein, short-term production plan refers to the production plan formulated for the project for going into operation or having gone into operation in the recent period, long Phase production plan refers to the production plan of the project formulation for going into operation after the long period or still in the business meeting stage.
In short-term planning, since project goes into operation or has gone into operation in the recent period, the basic information and item of project Purpose plan parameters information can be formulated directly according to the plan parameters information of the known project corresponding known to being usually Production plan;And in forward planning, it is gone into operation after extended periods due to project or is still in the business meeting stage, because It is known that this, which only has less basic information, and project plan parameter information is usually unknown, it is therefore desirable to pass through project Basic information determine project plan parameter information, formulate corresponding production plan further according to plan parameters information.
In order to realize the creation method of engineering construction plan provided by the embodiments of the present application, the embodiment of the present application provides one Software systems are covered, which uses B/S (Browser/Server, browser and server) framework of standard criterion, real A series of functions such as existing data displaying, service logic, data access separation.System is made of each Service Component, is adjusted according to request With corresponding Service Component, make that the whole system degree of coupling is low, modularization is strong, and for user provide conveniently, it is accurate, quickly, it is friendly Service, while software systems can be supported integrated with other system specified modularizations, have good practicability and extension Property.
Above-mentioned software systems include foreground and backstage, and foreground provides human-computer interaction function, for user's creation, editor, inquiry Or corresponding information is deleted, foreground includes homepage module, information module, planned allocation module and system configuration module etc., wherein Homepage module is divided according to user role, and role includes client service center, division department manager and project manager etc., the homepage mould Block be mainly used for the distribution of display project, policy implication region, unit capacity statistics, go into operation prompting etc. summary informations;Information module For the nucleus module of entire software systems, the functions such as data interaction, data operation are realized, return the result with background model collection, it will Corresponding information visualization shows user;Planned allocation module is for configuring make a plan required data information, such as machine Type information, supplier information etc.;System configuration module is for configuring system permission, management role relation etc..After software systems Platform is integrated with every module of the creation method of performance of work construction plan, and foreground cooperates with backstage realizes that the embodiment of the present application mentions Every step of the creation method of the engineering construction plan of confession, each module on backstage are full for calculating as system operations core The plan arrangement of parameter set under sufficient different business scene, and carrier of the software systems as each module, for receiving or safeguarding phase Necessary information is closed to support the measuring and calculating process of each module on backstage, further enhances operability, the availability for formulating construction plan And ease for use.
How the technical solution of the application and the technical solution of the application are solved with specifically embodiment below above-mentioned Technical problem is described in detail.These specific embodiments can be combined with each other below, for the same or similar concept Or process may repeat no more in certain embodiments.Below in conjunction with attached drawing, embodiments herein is described.
Embodiment one
The embodiment of the present application one provides a kind of creation method of engineering construction plan, as shown in Figure 1, this method comprises:
S1: the project plan parameter information of destination item is obtained.
S2: it according to project plan parameter information, determines from the work for meeting entry condition the default date in destination item Sequence.
S3: the job date of each process for meeting entry condition is determined.
The creation method for the engineering construction plan that the embodiment of the present application one provides, can in time, it is accurate and comprehensively obtain To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band Carry out higher economy return.
In addition, the method for the embodiment of the present application is to letter compared to the mode of traditional " workform management+project manager's experience " The feedback speed for ceasing variation faster, can carry out dynamic adjustment, the production plan of renewal item according to the variation of information in real time.
Optionally, in the S1 of the embodiment of the present application one, when obtaining the project plan parameter information of destination item, packet It includes: obtaining the project plan parameter information of destination item and the basic information of destination item.The step be applicable in go into operation in the near future or The creation method of the construction plan of the project to have gone into operation, that is, the method for creating short-term production plan, in the method, target item Purpose basic information and project plan parameter information be it is determining, can directly acquire to obtain.
Alternatively, the project plan parameter information for obtaining destination item can also include: the basic information for obtaining destination item, The history item to match with destination item is determined according to basic information;Joined according to the project plan of the history item to match Number information, determines the project plan parameter information of destination item.The step is suitable for going into operation or still locating after extended periods In the creation method of the construction plan of the project in business meeting stage, that is, the method for creating long-term operation plan, in the method, Only less basic information is known, and project plan parameter information is usually unknown, it is therefore desirable to pass through project Basic information determines project plan parameter information, formulates corresponding production plan further according to plan parameters information.
It, being capable of not sympathizing with for destination item in the creation method for the engineering construction plan that the embodiment of the present application one provides Condition provides the corresponding method for obtaining project plan parameter, makes short-term production plan and long-term operation plan, meets not With the destination item of application scenarios.
Optionally, the creation method for the engineering construction plan that the embodiment of the present application one provides, further includes: join according to the project plan Number information is determined from there is no when the process for meeting entry condition in destination item the default date, it is determined whether exist not The process for being determined job date;If so, determining the target item from next default date according to project plan parameter information The process for meeting entry condition in mesh determines the job date of each process for meeting entry condition.
In the creation method for the engineering construction plan that the embodiment of the present application one provides, meet when all from the default date After job date is determined in the process of entry condition, is re-executed on next default date and be determined for compliance with entry condition Process and the step of determine the job date of each process for meeting entry condition, process circulation executes, until determining There is no the processes for not being determined job date, show that job date has been determined in all process steps in project at this time, The construction plan of the project has created completion.The above process can determine destination item all process steps in a very short period of time Job date, the construction plan being quickly obtained in the whole cycle of destination item.
Optionally, the creation method for the engineering construction plan that the embodiment of the present application one provides, further includes: every by what is determined The information of the job date of a process for meeting entry condition is uploaded to appointing system.
Can be with specified in time by information in the creation method for the engineering construction plan that the embodiment of the present application one provides System or platform coordination sharing, avoid information from losing, and the effective experience information of destination item can be inherited, and are subsequent project Experience is instructed in offer.
Embodiment two
The embodiment of the present application two provides the creation method of another engineering construction plan, as shown in Fig. 2, this method packet It includes:
S11: the basic information and project plan parameter information of destination item are obtained.
The embodiment of the present application two provides the creation side of the construction plan for the project for going into operation or having gone into operation in the recent period Method, that is, the method for creating short-term production plan, in the method, the basic information and project plan parameter information of destination item are Determining, it can directly acquire to obtain.It specifically, can be according to basic information, previously described including foreground and backstage In software systems, corresponding project plan parameter information is transferred.
The creation method for the engineering construction plan that the embodiment of the present application two provides can be applied in wind energy project construction project In, below by taking wind energy project construction project as an example, specifically introduce basic information and project plan parameter information.
Basic information includes the characteristic information of destination item, for example, characteristic information may include project name, number, wind Power generator pool-size, wind-driven generator set type, wind power generating set quantity, province where project, project site contour and The transportation range of the components such as longitude and latitude, pylon and master hang quantity etc..
Project plan parameter information includes resource equipment information in wind energy project construction project, and resource equipment information can wrap Include working sources information and component resource information.
Wherein, working sources information includes working sources total amount and each process needed for project and required construction The corresponding relationship of resource, working sources include all types of construction teams, as road construction team, foundation construction team, lifting construction team, It is main to hang team and auxiliary hang team etc..
Component resource information includes each base part of wind power generating set, such as pylon, cabin, impeller, generator, In, impeller includes wheel hub and blade, and component resource information can characterize the corresponding relationship of each process Yu required component resource, also The current state of each base part resource can be characterized, such as whether component resource has been consumed.
Project plan parameter information includes the process the constraint relationship information in wind energy project construction project, process the constraint relationship The sequence of operation in information representation project between each process.Process the constraint relationship information includes blower topological constraints relationship letter Breath, single machine process the constraint relationship information and global process the constraint relationship information.
The constraint of the sequence of operation in blower topological constraints relation information characterization project between each wind power generating set is closed System, can know each wind power generating set should be in which wind power generating set by the blower topological constraints relation information Operation is carried out after or before construction.For example, table 1 is shown in which a kind of blower topological constraints relationship, as shown in table 1, some Wind power plant needs to build 15 wind power generating sets, and number is respectively FJ01 to FJ15.This 15 wind power generating sets are divided into three Item builds route, from the point of view of table 1 is divided into three column, first build route be FJ01 to FJ05, second build route be FJ06 extremely FJ10, it is FJ11 to FJ15 that third, which builds route,.
Each wind power generating set in route is built for same, is needed according to the sequence of operation between each unit about Beam relationship sequentially construction operation.For example, building route for first, need sequentially successively to carry out wind power generating set FJ01 extremely The operation of FJ05 after the completion of the operation of one wind power generating set, then carries out the operation of next wind power generating set.
Route is built for above-mentioned three, needs sequentially to apply according to the constraint relationship for the sequence of operation respectively built between route Work industry.Above-mentioned three sequences of operation for building route include at least following several:
(1) operation in route is sequentially successively respectively built.For example, carrying out the first each wind-force built in route at first The operation of generating set carries out after the completion of the operation that first builds the last one wind power generating set in route, then successively Second builds route and third builds the operation of each wind power generating set in route.Those skilled in the art can manage Solution, three sequencings for building route are adjustable, for example, it is also possible to which route is built in progress second at first or third builds line The operation of each wind power generating set in road.
(2) operation for building route is first carried out, then carries out other two operations for building route simultaneously.For example, first The operation for carrying out each wind power generating set that first builds in route, builds the last one wind-power electricity generation in route first After the completion of the operation of unit, while route is built in progress second and third builds the work of each wind power generating set in route Industry.It will be understood to those skilled in the art that three sequencings for building route are adjustable, for example, it is also possible to first carry out Second builds route or third builds the operation of each wind power generating set in route.
(3) two first are carried out simultaneously and builds the operation of route, then carry out remaining one operation for building route.For example, Carry out first simultaneously and build route and second to build the operation of each wind power generating set in route, first build route or Second builds after the completion of the operation of the last one wind power generating set in route, then carries out each wind that third is built in route The operation of power generator group.It will be understood to those skilled in the art that three sequencings for building route are adjustable, example Such as, it can also first carry out second and build route and third builds the operation of each wind power generating set in route, carry out afterwards One builds the operation of each wind power generating set in route.
(4) three operations for building route are carried out simultaneously.First is carried out simultaneously to build route, second build route and the Three build the operation of each wind power generating set in route, it can be understood as, wind power generating set FJ01, FJ06 and FJ011 It goes into operation simultaneously.
It should also be noted that, it is also not necessary to wait upper one to repair in above-mentioned 4 kinds of sequence of operation for building route The operation completion for building route can start to carry out the next operation for building route.For example, the operation provided for (1) is suitable Sequence, can be after the completion of first builds the operation of wind power generating set FJ03 in route, it can starts progress second and builds line The operation on road.The above builds each sequence of operation of route, to those of ordinary skill in the art, is not departing from Under the premise of the application principle, several improvements and modifications can also be made, these improvements and modifications also should be regarded as the guarantor of the application Protect range.
FJ01 FJ02 FJ03 FJ04 FJ05
FJ06 FJ07 FJ08 FJ09 FJ10
FJ11 FJ12 FJ13 FJ14 FJ15
Table 1
Table 2 is meteorological allocation list provided by the embodiments of the present application, and meteorology configuration, which indicates, builds single wind-driven generator Process and process involved in group can operation meteorological condition, single machine process constraint information characterizes in single wind power generating set The sequence of operation of each process, for example, lifting the stage the sequence of operation be " tower hoisting --- cabin lifting --- generator hanger Dress --- wheel hub, leaf blade hanging ".According to the difference of sessions, all process steps in table 2 are divided into the level-one process of three types, Level-one process include early period process, the supply of material process and lifting process;Each level-one process further includes multiple second level processes, for example, Process early period includes two second level processes, respectively constructing road process and foundation construction process;Further, each second level is also Including three-level process, builds single wind power generating set and need 35 three-level processes altogether, for example, foundation construction process includes Three-level process has foundation ring procedure for preparation, foundation excavation process, basis backfill process etc..In engineering provided by the embodiments of the present application In the creation method of construction plan, the job date of each process for meeting entry condition is determined, which refers to wind power plant The three-level process of the wind power generating set of required construction.
Table 2
S12: it according to project plan parameter information, determines from the work for meeting entry condition the default date in destination item Sequence.
Optionally, for the destination item not gone into operation, the default date can be the starting date of destination item, i.e., first The job date of process, thus the production plan for all process steps after making starting date;For the mesh to have gone into operation Mark project, default date can be set to some day in the project cycle, make not finishing after the date for all The production plan of process, for example, can be the current date by default date default setting for the destination item to have gone into operation.
In the embodiment of the present application, the starting date of destination item can be determined according to global process the constraint relationship information, As shown in table 3, table 3 is global process the constraint relationship information table provided by the embodiments of the present application, global process the constraint relationship information The information of the process of involved every preparation before going into operation including destination item, for example, formality information is (such as country Check and approve plan information etc.), targeted message (such as host contract signing information), drawing information, road survey information, build information (such as The information of over-the-counter constructing road situation) and information of showing up, information of showing up refers to that resource equipment is shown up the information of situation, such as road The case where unit in charge of construction shows up etc..The starting date of destination item can be determined according to above- mentioned information, certainly, gone into operation in determination Also need to consider the influence of policy information when the date, policy information includes policy of obligating, elastic restraint policy (such as local political affairs Plan etc.).
Level-one process Second level process Coding
Formality Country checks and approves plan qj_01
Formality System of project approval gives an written reply (provincial reply) qj_02
Formality Environmental impact assessment reply qj_03
Formality Expropriation of land formality qj_04
Formality Access reply qj_05
Formality Forest land reply qj_06
Formality Logging management qj_07
Calibration Host contract signing qj_08
Calibration The calibration of foundation ring factory qj_09
Calibration The calibration of pylon factory qj_10
Calibration The calibration of road construction unit qj_11
Calibration The calibration of foundation construction unit qj_12
Calibration Lifting construction unit calibrates (installation unit calibration) qj_13
Calibration The calibration of line construction unit qj_14
Calibration The calibration of booster stations unit in charge of construction qj_15
Drawing The review of road drawing qj_16
Road is surveyed Completion is surveyed on road qj_17
It builds Over-the-counter constructing road qj_18
It builds Stockyard is established qj_19
It shows up Road construction unit is shown up qj_20
It shows up Foundation construction unit is shown up qj_21
It shows up Lifting construction unit is shown up qj_22
It shows up Main hang is shown up qj_23
It shows up Auxiliary hang is shown up qj_24
Table 3
Optionally, it according to project plan parameter information and basic information, determines not complete on the default date in destination item The process of knot;From the process not finished respectively, the process for meeting entry condition is determined.
Optionally, in the embodiment of the present application two, according to project plan parameter information and basic information, destination item is determined In the process that does not finish on the default date, specific implementation step may include: according to the process in project plan parameter information The starting day of the first process of destination item in the net operating time information and basic information of the constraint relationship information and each process Phase is determined to end the process not finished into default date destination item.
The net operating time of process in the embodiment of the present application, refer to process not by any disturbance factor (such as meteorological condition, Holiday or other enchancement factors) under the influence of, normal implement duration used in process content.
It should be noted that directly first process can be determined as not when the starting date of process headed by the default date The process to finish, then executes subsequent step.For the other processes after first process, then need to be believed according to process the constraint relationship The sequence of operation of each process in breath is successively added to default from the starting date for process that the net operating time of each process is confessed one's crime Date ends the process not finished as to default date, the process that net operating time is not cumulatively added.
Optionally, in the embodiment of the present application two, from the process not finished respectively, the process for meeting entry condition is determined, Its specific implementation step may include: according to the process the constraint relationship information in project plan parameter information, determine it is each not The preposition process of the process to finish;According to the net operating time information and basic information of process each in project plan parameter information The starting date of the first process of middle destination item, judge to end the process not finished each to the default date preposition process whether It finishes;The corresponding resource equipment of process not finished each according to the resource equipment information in project plan parameter information, judgement It whether is all serviceable condition;It has finished for preposition process and resource equipment is all the process of serviceable condition not finished, Determine that the process meets entry condition.
It should be noted that each process is needed according to the preset order successively operation in process the constraint relationship information, only There is the operation that subsequent handling can be just carried out after the completion of preposition process.Determine that multiple processes not finished may include, it should Multiple processes not finished are also required to construct according to preset order, such as the process A not finished and work for determining Sequence B, process A are the preposition process of process B, and the preposition process of process A has finished, then it is further contemplated that carrying out process A Operation, and since process A at this time does not finish also, process B does not just meet entry condition.Meanwhile each process is made Corresponding working sources are needed when industry, only when resource equipment is serviceable condition, process can just carry out operation.Therefore, For process A, after the preposition process for determining process A has finished, it is also necessary to determine the corresponding working sources of process A whether be State to be used, for example, determining whether the corresponding working sources of process A are idle, and whether the corresponding component resource of process B reaches item Mesh scene.Only the preposition process of process A has finished and when resource equipment is all serviceable condition, can just determine that process A is accorded with Close entry condition.
Optionally, it in the embodiment of the present application two, determines the process to finish in destination item on the default date, releases The corresponding resource equipment of the process of knot.Optionally, it according to project plan parameter information and basic information, determines in destination item In the process that the default date has finished, the corresponding resource equipment of process to have finished is discharged.
It should be noted that the corresponding resource equipment of process that release finishes includes: the work that this in resource equipment finishes The corresponding working sources of sequence (such as foundation construction team) are set as state to be used, so that other processes that do not finish continue to use; It sets the corresponding component resource of the process to have finished (pylon and cabin of such as wind power generating set) in resource equipment to Consumption state.
S13: the job date of each process for meeting entry condition is determined.
Optionally, according to target in the net operating time information and basic information of process each in project plan parameter information The starting date of the first process of project determines the basic job date for each meeting the process of entry condition.
Process for meeting entry condition, according to the sequence of operation of each process in process the constraint relationship information, by the work The net operating time of each process before sequence confess one's crime process the starting date from be successively added to some date, opened meeting The starting date of the process of dynamic condition was arranged after the date, according to the net operating time for the process for meeting entry condition, pushed away Calculating finishes the date, and starting the date section between date and the date of finishing is that this meets the basic operation of the process of entry condition Date.
Present inventor it is considered that in the operation process of process, may because of weather, holiday or it is other with Machine factor causes operation process discontinuous, and the duration of process actual basic job date may be more than net operating time.Example Such as, the net operating time of process A is 3 days, and the starting date is August 1, and the date that theoretically finishes is August 3, however due to day Gas reason cause August No. 2 and No. 3 can not operation, cause process A finish the date be August 5, the basic operation of process A at this time Date is August No. 1 to August 5.
Based on above-mentioned consideration, optionally, in the embodiment of the present application two, each process for meeting entry condition is determined Job date, further includes: according to the operation window phase information in project plan parameter information, to each work for meeting entry condition The basic job date of sequence is modified, and obtains out the plan job date for each meeting the process of entry condition.Operation window Phase information, which refers to process within a preset time period, can carry out the date of operation, from the starting date of process, according to process Net operating time, date of operation can be carried out sequentially in time by choosing, until determining finishing the date for process, this is opened Date section between dynamic date and the date that finishes is that this meets the plan job date of the process of entry condition.
Present invention is it is considered that influence the process factor that whether can carry out operation on a certain date main Have: the meteorological condition of this day whether meet process can operating condition and this day whether be can not operation holiday, because This, can filter out that meteorological condition meets process operating condition and can be not belonging to date of holiday, as making for process Industry day.
Based on above-mentioned consideration, optionally, in the embodiment of the present application two, according to the gathering hole in project plan parameter information Mouth phase information, is modified the basic job date of each process for meeting entry condition, obtains out each meeting trip bar The plan job date of the process of part, comprising: according to the routine work window phase information in operation window phase information, to each symbol The basic job date for closing the process of entry condition is modified, and obtains out the plan operation for each meeting the process of entry condition Date.
Routine work window phase information refers to the process determined according to meteorological condition and holiday in the preset period The interior date that can carry out operation, from the starting date of process, according to the net operating time and routine work window phase of process Information, date of operation can be carried out sequentially in time by choosing, until determine finishing the date for process, the starting date and Date section between the date that finishes is that this meets the plan job date of the process of entry condition.
The acquisition process of routine work window phase information may include steps of a)-c):
A): acquisition can operation meteorological condition, weather information over the years and holiday information.
It should be noted that each process have respectively it is respective can operation meteorological condition obtained in the embodiment of the present application two Take can operation meteorological condition include different processes can operation meteorological condition.
Optionally, shown in table 2 each three-level process can operation meteorological condition, including wind friction velocity, rainfall, drop Snowfall, temperature condition and can fishing time, for example, constructing road can operation meteorological condition are as follows: without rainfall, without snowfall, gas Temperature between subzero 5 degrees Celsius to 40 degrees Celsius above freezing and wind speed be less than 10m/s, can fishing time be daytime.
The weather information over the years obtained can be the weather information in past one period or a time, be also possible to The weather information in multiple times in past, concrete condition can be decided according to the actual requirements.For example, current time point is 2018 January 1, then weather information or annual weather information in 2017 in available 2017 in certain time, it can also To obtain the weather information of weather information or these three times whole in 2015 to 2017 in certain time.The application The weather information over the years that embodiment provides, spatial accuracy can achieve as unit of the region of 81 sq-kms, time precision It can achieve as unit of hour, i.e. the weather information over the years meteorology hourly over the years that is capable of providing certain unit area Data.
The holiday information of acquisition includes national legal festivals and holidays, the local (folk customs and culture festival of such as ethnic group legal festivals and holidays Day, church festival) or the lay day set by occasion etc..
B): according to can operation meteorological condition and weather information over the years, determine that the basis of every process can operation day.It will go through In year weather information meet can operation meteorological condition date, the basis in the current construction year as project can operation day, for example, What the August weather information ordered on the 1st in 2017 met process A can operation meteorological condition, it is determined that August 1st in 2018 is A work It the basis of sequence can operation day.
C): determining whether the basis of each process can belong to the holiday in holiday information operation day, from each process Basis can in operation day, reject belong to holiday basis can operation day, determine each process first amendment can operation Day, according to the first of each process amendment can operation day, determine routine work window phase information.
The embodiment of the present application can be based on weather history information and holiday information, determine routine work window phase information, It is modified, is planned according to the basic job date that net operating time of the routine work window phase information to process is determined Job date, the plan job date have taken into account the influence of meteorological condition and holiday to process construction speed, so that process Starting date and the date that finishes are more accurate, further reduced the production plan of process and the probability that actual conditions are not inconsistent.
It should be noted that during project carries out, to the process Weather Forecast Information started in a short time compared with subject to Really, have higher reference value, therefore can also further correct routine work window phase information according to Weather Forecast Information.
Weather Forecast Information can use existing Predictive meteorological methods and obtain, and can also pass through third-party weather prognosis Using or meteorological official website in obtain.For example, the Weather Forecast Information in somewhere may include 3 days, 7 days or 15 days following Meteorological data.
After step c, determine each process it is each first amendment can operation day Weather Forecast Information, if meet should Process can operation meteorological condition;By meet the process can operation meteorological condition first amendment can operation day, as the work Sequence second amendment can operation day, by be unsatisfactory for the process can operation meteorological condition first amendment can operation day reject.Root According to each process second amendment can operation day, determine more accurate routine work window phase information.
In actual operation process, some random factors can also be delayed the job scheduling of process, therefore, optionally, In the embodiment of the present application two, according to the operation window phase information in project plan parameter information, meet entry condition to each Basic job date of process be modified, obtain out the plan job date for each meeting the process of entry condition, also wrap It includes: according to the random operation window phase information in operation window phase information, the basis of each process for meeting entry condition being made The industry date is modified, and obtains out the plan job date for each meeting the process of entry condition.
After random operation window phase information refers to the date rejected and can not constructed by enchancement factor, obtained process can Job date, random operation window phase can be determined by rule of thumb data.In the embodiment of the present application two, the plan of process Job date after having taken into account the influence of meteorological condition and holiday to process construction speed, has also taken into account random factor to work The influence of sequence job scheduling further improves the accuracy of the plan job date of process.
Optionally, in the S13 of the embodiment of the present application two further include:, will be each when determining the process for meeting entry condition The corresponding resource equipment of process for meeting entry condition is set as occupied state.Meet the corresponding resource machine of process of entry condition Tool is set as occupied state, then shows that other processes can not at least make within the basic job date for the process for meeting entry condition With this part resource equipment, avoid same resource equipment causes construction to be counted on the identical date by two processes while occupancy Mark existing conflict.
Implement to determine multiple processes for meeting entry condition in S12, therefore, S13's is specific in two in the application Step may include: that a process is randomly selected in multiple processes for meeting entry condition, determine each to meet trip bar The corresponding resource equipment of the process for meeting entry condition is set occupied state by the job date of the process of part.
At this point, workable resource equipment is reduced compared with the S12 before the case where.Under the premise of this, for The remaining process for meeting entry condition may be no longer complies with entry condition, therefore can hold again since resource equipment is reduced Row S12 and S13, the process for determining new symbol entry condition in these processes determine the new work for meeting entry condition The new corresponding resource equipment of the process for meeting entry condition is set occupied state by the job date of sequence.The above process follows Ring executes, until determining from all processes for meeting entry condition in destination item the default date.
Optionally, in the embodiment of the present application two, after the job date for determining each process for meeting entry condition, The information for each of determining the job date for the process for meeting entry condition is uploaded to appointing system.
S14: it according to project plan parameter information, determines from there is no meet trip bar in destination item the default date The process of part.
Optionally it is determined that going out from the process to have finished in destination item the default date;The process that has been finished according to these, And determined in S13 from all processes for meeting entry condition in destination item the default date, determine in this step Out from the process for not meeting entry condition in destination item the default date and not finishing.
S15: the process for not being determined job date is determined whether there is;The process for not being determined job date if it exists, Execute S16;Otherwise terminate this process.
S16: it according to project plan parameter information, determines from meeting trip bar in destination item next default date The process of part determines the job date of each process for meeting entry condition.
Optionally, in the embodiment of the present application two, after the job date for determining each process for meeting entry condition, The information for each of determining the job date for the process for meeting entry condition is uploaded to appointing system.
Can be with specified in time by information in the creation method for the engineering construction plan that the embodiment of the present application two provides System or platform coordination sharing, prevent loss of data, and the effective posterior infromation of destination item can be inherited, and are subsequent project Experience is instructed in offer.
It will be understood to those skilled in the art that S16, which is equivalent to, re-executes S12 to S15 on next default date, it should Process circulation executes, until determining under each default date all there is no the process for not being determined job date, shows item at this time Job date has been determined in all process steps in mesh, and the construction plan of the project has created completion.
Embodiment three
The embodiment of the present application three provides the creation method of another engineering construction plan, the method for the embodiment of the present application three Process is by the S11 replacement in the method flow of above-described embodiment two are as follows: the basic information for obtaining destination item, according to basis letter Breath determines the history item to match with destination item;According to the project plan parameter information of the history item to match, really Make the project plan parameter information of destination item.
The embodiment of the present application three provides the item for being directed to and going into operation after extended periods or being still in the business meeting stage The creation method of purpose construction plan, that is, the method for creating long-term operation plan, in the method, only less basic information It is known, and project plan parameter information is usually unknown, it is therefore desirable to project is determined by the basic information of project Plan parameters information formulates corresponding production plan further according to plan parameters information.
In the embodiment of the present application three, basic information includes the characteristic information of the destination item, for example, may include project Title, number, unit capacity, machine set type, unit quantity, province where project, project site contour and longitude and latitude, pylon etc. The transportation range of component and master hang quantity etc..According to features described above information, project matching algorithm based on a specified, in history item It is matched to the history item most like with destination item in library, the every terms of information of destination item, example are determined according to the history item The resource equipment information and process the constraint relationship information in the project plan parameter information of destination item are such as determined, according to above-mentioned The information determined executes subsequent step, and the subsequent step of the embodiment of the present application three can be with S12 to S16 in above-described embodiment two Unanimously, details are not described herein again.
The creation method for the engineering construction plan that the embodiment of the present application three provides, for going into operation or still locating after the long period In the project in business meeting stage, it is capable of under a large amount of deletion conditions of relevant information of elementary item and formulates more accurately construction meter It draws, which can promote the competitiveness in business meeting of enterprise, help to guide clients investment intention.
Example IV
The embodiment of the present application four provides the creation method of another engineering construction plan, compared with above-described embodiment, The embodiment of the present application four the difference is that: the operation restrictive condition of destination item is set;According to the project plan parameter Information, determine from the process for meeting entry condition the default date in destination item, determines each entry condition that meets The job date of process, comprising: according to the operation restrictive condition of project plan parameter information and destination item, determine from default The process for meeting entry condition from date in destination item determines the job date of each process for meeting entry condition.
As shown in the input process in following table 4, the operation restrictive condition of destination item includes time restriction, resource constraint With planned outcome restrict.Time restriction refers to the duty cycle of limited target project, the i.e. operation of destination item all process steps Complete the occupied period.The duty cycle of limited target project includes limit starting time, limit end time, or is opened with the time limit Dynamic time and end time.Resource constraint refers to the resource equipment that limited target project needs.Resource equipment can be limited to Fixed resource, the i.e. total amount of resource equipment are fixed;Resource equipment can also be limited to dynamic resource, i.e. resource equipment Total amount can according to need floating.
Planned outcome restrict refers to the difference that demand it is expected according to project, limits the type of production plan.The project phase Prestige demand includes: that the duration is most short, cost is minimum and optimal balance.Planned outcome restrict be the duration it is most short refer to, referring to In the combination of fixed time restriction and resource constraint, in all possible production plans, duration shortest operation meter is exported It draws;Out result restrict be the duration it is most short refer to, at the appointed time limit and resource constraint combination in, all can In the production plan of energy, the minimum production plan of output cost;Result restrict refers to out for optimal balance, when specified Between limitation and resource constraint combination in, in all possible production plans, export the production plan of optimal balance, it is optimal Balance refers to that duration and cost reach desired equalization point.
As shown in the anabolic process in table 4, different types of time restriction and resource constraint be can be combined with each other, at every kind In combination, demand it is expected according to different projects, exports different production plans.Combination 1 indicates, is limited beginning in time restriction Time and resource constraint are that export planned outcome restrict respectively be respectively that the duration is most short, cost under the combination of fixed resource Minimum and optimal balance production plan.In table 4, plan1 indicates that planned outcome restrict is duration shortest production plan, Plan2 indicates that planned outcome restrict is the minimum production plan of cost, and plan3 indicates that planned outcome restrict is optimal The production plan of balance.In table 4, time restriction and resource constraint share six kinds of combinations, and every kind is combined according to planned outcome about The difference of beam limitation can export three kinds of production plans, therefore the creation of the engineering construction plan of the offer of the embodiment of the present application four Method can export 18 kinds of production plans.
Table 4
Embodiment five
The embodiment of the present application provides a kind of creation system of engineering construction plan, as shown in figure 3, the engineering construction plan Creation system 200 include: to obtain module 201, first judgment module 202 and execution module 203.
Wherein, the project plan parameter information that module 201 is used to obtain destination item is obtained.
First judgment module 202 is used to be determined according to project plan parameter information from the default date in destination item Meet the process of entry condition.
Execution module 203 is used to determine the job date of each process for meeting entry condition.
Optionally, in embodiments herein five, for short-term production plan, module 201 is obtained for obtaining target The project plan parameter information of project and the basic information of destination item.
For long-term operation plan, the basic information that module 201 is used to obtain destination item is obtained, it is true according to basic information The history item to match with destination item is made, according to the project plan parameter information of the history item to match, is determined The project plan parameter information of destination item.
Optionally, the creation system of the engineering construction plan provided in embodiments herein five further include: the second judgement Module 204.
Second judgment module 204 is used to be determined according to project plan parameter information from the default date in destination item There is no when the process for meeting entry condition, it is determined whether there is the process for not being determined job date;If so, first judges mould Block 202 is determined according to project plan parameter information from the work for meeting entry condition next default date in destination item Sequence, execution module 203 determine the job date of each process for meeting entry condition.
Embodiment six
The embodiment of the present application provides a kind of electronic equipment, as shown in figure 4, electronic equipment shown in Fig. 4 300 includes: place Manage device 301 and memory 302.
Memory 302 is configured to storage machine readable instructions, instructs when executed by the processor, so that processor executes The creation method for the engineering construction plan that application embodiment one to example IV any embodiment provides.
Memory 302 in the embodiment of the present application can be ROM (Read-Only Memory, read-only memory) or can deposit Store up static information and instruction other kinds of static storage device, can be RAM (Random Access Memory, at random Access memory) or the other kinds of dynamic memory of information and instruction can be stored, it is also possible to EEPROM (Electrically Erasable Programmable Read Only Memory, Electrically Erasable Programmable Read-Only Memory), CD-ROM (Compact Disc Read-Only Memory, CD-ROM) or other optical disc storages, optical disc storage (including pressure Contracting optical disc, laser disc, optical disc, Digital Versatile Disc, Blu-ray Disc etc.), magnetic disk storage medium or other magnetic storage apparatus or Person can be used in the desired program code of carrying or storage with instruction or data structure form and can be by computer access Any other medium, but not limited to this.
Processor 301 in the embodiment of the present application can be CPU (Central Processing Unit, central processing Device), general processor, DSP (Digital Signal Processor, data signal processor), ASIC (Application Specific Integrated Circuit, specific integrated circuit), FPGA (Field-Programmable Gate Array, field programmable gate array) either other programmable logic device, transistor logic, hardware component or its Meaning combination.Its may be implemented or execute combine present disclosure described in various illustrative logic blocks, module and Circuit.Processor 301 be also possible to realize computing function combination, such as comprising one or more microprocessors combine, DSP and The combination etc. of microprocessor.
Those skilled in the art of the present technique are appreciated that the pre- measurement equipment of engineering construction plan provided by the embodiments of the present application can Think required purpose and specially design and manufacture, or also may include the known device in general purpose computer.These equipment With the computer program being stored in it, these computer programs are selectively activated or are reconstructed.Such computer program It can be stored in equipment (for example, computer) readable medium or be stored in and be suitable for storage e-command and be coupled to respectively In any kind of medium of bus.
The pre- measurement equipment of engineering construction plan provided by the embodiments of the present application has identical with mentioned-above each embodiment Inventive concept and identical beneficial effect, details are not described herein.
Embodiment seven
The embodiment of the present application provides a kind of computer readable storage medium, is stored on the computer readable storage medium Computer program, the program realize the work that the embodiment of the present application one is provided to example IV any embodiment when being executed by processor The creation method of journey construction plan.
The computer-readable medium include but is not limited to any kind of disk (including floppy disk, hard disk, CD, CD-ROM and Magneto-optic disk), (Erasable Programmable Read-Only Memory, erasable programmable are read-only by ROM, RAM, EPROM Memory), EEPROM, flash memory, magnetic card or light card.It is, readable medium includes by equipment (for example, computer) With any medium for the form storage or transmission information that can be read.
Computer readable storage medium provided by the embodiments of the present application, with mentioned-above each embodiment hair having the same Bright design and identical beneficial effect, details are not described herein.
Using embodiments herein, at least may be implemented it is following the utility model has the advantages that
1, the creation method of engineering construction plan provided by the embodiments of the present application, can in time, it is accurate and comprehensively obtain To the project plan parameter information of destination item, avoid information update not in time, information asymmetry or information is incomplete asks Topic, the job date of each process is determined according to the project plan parameter information of acquisition, and then make the operation of entire project Plan largely overcomes the production plan for leading to formulate because of the experience difference of project manager and actual conditions seriously not The problem of symbol, improves the accuracy rate of production plan, ensure that each process can be within desired job date in real work It fulfils assignment, every working sources can be utilized effectively and rationally, and the project cycle is effectively shortened, and reduce project cost, band Carry out higher economy return.
In addition, the method for the embodiment of the present application is to letter compared to the mode of traditional " workform management+project manager's experience " The feedback speed for ceasing variation faster, can carry out dynamic adjustment, the production plan of renewal item according to the variation of information in real time.
2, after job date is determined in all processes for meeting entry condition from the default date, next pre- If the date re-executes the process for being determined for compliance with entry condition and determines the operation day of each process for meeting entry condition The step of phase, process circulation execute, until determining there is no the process for not being determined job date, show in project at this time Job date has been determined in all process steps, and the construction plan of the project has created completion.The above process can be in pole The job date that all process steps are determined in the short time, the construction plan being quickly obtained in the whole cycle of project.
3, can be with specified in time by information in the creation method of engineering construction plan provided by the embodiments of the present application System or platform coordination sharing, avoid information from losing, project effective experience information can be inherited, and provide finger for subsequent project Lead experience.
4, the creation method of engineering construction plan provided by the embodiments of the present application can be directed to the different situations of destination item The corresponding method for obtaining project plan parameter is provided, short-term production plan and long-term operation plan is made, meets difference The destination item of application scenarios.
5, the creation method of engineering construction plan provided by the embodiments of the present application originally can take into account process net duration information, Process is made in influence and random factor of influence, holiday of the meteorological condition to process construction speed to process construction speed Job date of process is corrected in the influence of industry progress, further reduced the production plan of process and that actual conditions are not inconsistent is general Rate.
6, in the creation method of engineering construction plan provided by the embodiments of the present application, for going into operation after the long period or still Project in the business meeting stage is capable of to formulate under a large amount of deletion conditions of relevant information of elementary item and more accurately be built Plan, the construction plan can promote the competitiveness in business meeting of enterprise, help to guide clients investment intention.
It should be understood that although each step in the flow chart of attached drawing is successively shown according to the instruction of arrow, These steps are not that the inevitable sequence according to arrow instruction successively executes.Unless expressly stating otherwise herein, these steps Execution there is no stringent sequences to limit, can execute in the other order.Moreover, at least one in the flow chart of attached drawing Part steps may include that perhaps these sub-steps of multiple stages or stage are not necessarily in synchronization to multiple sub-steps Completion is executed, but can be executed at different times, execution sequence, which is also not necessarily, successively to be carried out, but can be with other At least part of the sub-step or stage of step or other steps executes in turn or alternately.
The above is only some embodiments of the invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (18)

1. a kind of creation method of engineering construction plan characterized by comprising
Obtain the project plan parameter information of destination item;
According to the project plan parameter information, the work for meeting entry condition from destination item described the default date is determined Sequence;
Determine the job date of each process for meeting entry condition.
2. the method according to claim 1, wherein in the project plan parameter information for obtaining destination item When, further includes: obtain the basic information of the destination item;
Alternatively, the project plan parameter information for obtaining destination item, comprising: the basic information of the destination item is obtained, The history item to match with the destination item is determined according to the basic information;According to the history item to match Project plan parameter information, determine the project plan parameter information of the destination item.
3. according to the method described in claim 2, determining it is characterized in that, described according to the project plan parameter information Meet the process of entry condition from destination item described the default date, comprising:
According to the project plan parameter information and basic information, determine presetting what the date did not finished in the destination item Process;
From each process not finished, the process for meeting entry condition is determined.
4. according to the method described in claim 3, it is characterized in that, the basic information includes the feature letter of the destination item Breath;
And/or the project plan parameter information includes process the constraint relationship information and the resource in wind energy project construction project Equipment information;
And/or the resource equipment information includes working sources information and component resource information;
And/or the process the constraint relationship information include blower topological constraints relation information, single machine process the constraint relationship information and Global process the constraint relationship information.
5. according to the method described in claim 4, it is characterized in that, described believe according to the project plan parameter information and basis Breath determines the process not finished in the destination item on the default date, comprising:
According to the net operating time information of process the constraint relationship information and each process in the project plan parameter information, with And the starting date of the first process of destination item described in the basic information, determine cut-off to mesh described in the default date The process not finished in mark project.
6. according to the method described in claim 4, determining institute it is characterized in that, described from each process not finished State the process for meeting entry condition, comprising:
According to the process the constraint relationship information in the project plan parameter information, each process not finished is determined Preposition process;
According to mesh described in the net operating time information of each process in the project plan parameter information and the basic information The starting date of the first process of mark project judges to end described preposition to each process not finished of the default date Whether process finishes;
According to the resource equipment information in the project plan parameter information, each corresponding money of process not finished is judged Whether source equipment is all serviceable condition;
It has finished for preposition process and resource equipment is all the process not finished described in serviceable condition, determined that the process accords with Close entry condition.
7. according to the method described in claim 4, it is characterized by further comprising:
It is described determine it is described when meeting the process of entry condition, by each corresponding resource of process for meeting entry condition Equipment is set as occupied state;
And/or determine the process to finish in the destination item on the default date, the process to finish described in release is corresponding Resource equipment.
8. according to the method described in claim 2, it is characterized in that, described determine each process for meeting entry condition Job date, comprising:
According to mesh described in the net operating time information of each process in the project plan parameter information and the basic information The starting date of the first process of mark project determines the basic job date of each process for meeting entry condition.
9. according to the method described in claim 8, it is characterized in that, described determine each process for meeting entry condition Job date, further includes:
According to the operation window phase information in the project plan parameter information, to each process for meeting entry condition Basic job date is modified, and obtains the plan job date of each process for meeting entry condition.
10. according to the method described in claim 9, it is characterized in that, the work according in the project plan parameter information Industry window phase information is modified the basic job date of each process for meeting entry condition, obtains each described Meet the plan job date of the process of entry condition, comprising:
According to the routine work window phase information in the operation window phase information, to each process for meeting entry condition Basic job date be modified, obtain the plan job date of each process for meeting entry condition;
And/or according to the random operation window phase information in the operation window phase information, described meet entry condition to each Basic job date of process be modified, obtain the plan job date of each process for meeting entry condition.
11. the method according to claim 1, wherein further include:
According to the project plan parameter information, determine that there is no meet trip bar from destination item described the default date When the process of part, it is determined whether there is the process for not being determined the job date;
If so, according to the project plan parameter information, determine from meeting in the destination item next default date The process of entry condition determines the job date of each process for meeting entry condition.
12. the method according to claim 1, wherein further include:
The information for each of determining the job date of the process for meeting entry condition is uploaded to appointing system.
13. the method according to claim 1, wherein further include: the operation limitation item of the destination item is set Part;
And it is described according to the project plan parameter information, it determines to meet from destination item described the default date and open The process of dynamic condition determines the job date of each process for meeting entry condition, comprising: according to the project plan The operation restrictive condition of parameter information and the destination item is determined to meet starting from destination item described the default date The process of condition determines the job date of each process for meeting entry condition.
14. a kind of creation system of engineering construction plan characterized by comprising
Module is obtained, for obtaining the project plan parameter information of destination item;
First judgment module, for determining the destination item from the default date according to the project plan parameter information In meet the process of entry condition;
Execution module determines the job date of each process for meeting entry condition.
15. creation system according to claim 14, which is characterized in that
The basic information for obtaining module and being used to obtain the project plan parameter information and the destination item of destination item;Or Person obtains the basic information of the destination item, determines to go through with what the destination item matched according to the basic information History project determines the project meter of the destination item according to the project plan parameter information of the history item to match Draw parameter information.
16. creation system according to claim 14, which is characterized in that further include:
Second judgment module, for determining the destination item from the default date according to the project plan parameter information In there is no meet entry condition process when, it is determined whether there is the process for not being determined the job date;
If so, the first judgment module according to the project plan parameter information, determines the institute from next default date The process for meeting entry condition in destination item is stated, the execution module determines each process for meeting entry condition Job date.
17. a kind of electronic equipment, characterized in that it comprises:
Processor;And
Memory is configured to storage machine readable instructions, and described instruction by the processor when being executed, so that the processing The creation method of the device perform claim requirement described in any item engineering construction plans of 1-13.
18. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that the program is by processor The creation method of the described in any item engineering construction plans of claim 1-13 is realized when execution.
CN201811237613.1A 2018-10-23 2018-10-23 Engineering construction plan creating method and system and electronic equipment Withdrawn CN109087035A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811237613.1A CN109087035A (en) 2018-10-23 2018-10-23 Engineering construction plan creating method and system and electronic equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811237613.1A CN109087035A (en) 2018-10-23 2018-10-23 Engineering construction plan creating method and system and electronic equipment

Publications (1)

Publication Number Publication Date
CN109087035A true CN109087035A (en) 2018-12-25

Family

ID=64843925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811237613.1A Withdrawn CN109087035A (en) 2018-10-23 2018-10-23 Engineering construction plan creating method and system and electronic equipment

Country Status (1)

Country Link
CN (1) CN109087035A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110175781A (en) * 2019-05-29 2019-08-27 国家电网有限公司 A kind of industry expansion power supply plan self-learning type formulating method
CN110766292A (en) * 2019-09-29 2020-02-07 广船国际有限公司 Ship block resource scheduling method, device, equipment and storage medium
CN111738538A (en) * 2020-01-06 2020-10-02 业达建设管理有限公司 Engineering project management system, management method, APP and storage medium
CN112561361A (en) * 2020-12-22 2021-03-26 深圳市九州建设技术股份有限公司 BIM-based project supervision informatization management method and system and storage medium
CN113158306A (en) * 2021-04-02 2021-07-23 中国建筑第二工程局有限公司 Tower crane parametric design method based on Revit metric system conventional model
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium
CN117114922A (en) * 2023-10-24 2023-11-24 天津广正建设项目咨询股份有限公司 Consultation service and evaluation method and system based on whole process engineering consultation

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110175781A (en) * 2019-05-29 2019-08-27 国家电网有限公司 A kind of industry expansion power supply plan self-learning type formulating method
CN110175781B (en) * 2019-05-29 2021-03-19 国家电网有限公司 Self-learning formulation method for business expansion power supply scheme
CN110766292A (en) * 2019-09-29 2020-02-07 广船国际有限公司 Ship block resource scheduling method, device, equipment and storage medium
CN111738538A (en) * 2020-01-06 2020-10-02 业达建设管理有限公司 Engineering project management system, management method, APP and storage medium
CN112561361A (en) * 2020-12-22 2021-03-26 深圳市九州建设技术股份有限公司 BIM-based project supervision informatization management method and system and storage medium
CN112561361B (en) * 2020-12-22 2024-04-09 深圳市九州建设技术股份有限公司 BIM-based engineering supervision informatization management method, system and storage medium
CN113158306A (en) * 2021-04-02 2021-07-23 中国建筑第二工程局有限公司 Tower crane parametric design method based on Revit metric system conventional model
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium
CN117114922A (en) * 2023-10-24 2023-11-24 天津广正建设项目咨询股份有限公司 Consultation service and evaluation method and system based on whole process engineering consultation
CN117114922B (en) * 2023-10-24 2024-01-26 天津广正建设项目咨询股份有限公司 Consultation service and evaluation method and system based on whole process engineering consultation

Similar Documents

Publication Publication Date Title
CN109087035A (en) Engineering construction plan creating method and system and electronic equipment
US20140129272A1 (en) System and method for managing service restoration in a utility network
JP6445909B2 (en) Power demand forecasting system
US8024205B2 (en) System and method for calculating damage as a result of natural catastrophes
CN104732298A (en) Method for achieving EMS load prediction based on decision tree and linear regression
CN113282684A (en) Prediction method and device for seasonal classification of flight and machine readable medium
Zou et al. A Biobjective Optimization Model for Deadline Satisfaction in Line‐of‐Balance Scheduling with Work Interruptions Consideration
CN108846488A (en) The maintenance dispatching method and device of wind power plant
CN113255996B (en) Method, device, equipment and storage medium for managing tagged electric charge balance
WO2011061970A1 (en) Inventory plan creation device, inventory plan creation method and inventory plan creation program
CN106779439A (en) A kind of task distribution method and device
US20200327627A1 (en) Methods and systems of a blockchain for distributed-energy-project management
CN106786533A (en) The acquisition methods and device of electric dispatching plan data
CN116385124A (en) Agricultural socialization integrated service cloud platform based on big data analysis traceability
CN116307547A (en) Linkage method, device and equipment for emergency handling of overseas oil and gas pipeline accidents
Jia et al. Setting scheduled trip time based on AVL data
Tang et al. Short-term work team scheduling models for effective road repair and management
CN101464873A (en) Material list establishing method and system
CN110059839A (en) A kind of method that need-based extracts unmet demand
Zhao Strategic enterprise management in the age of energy transition: a roadmap for sustainable business practices
CN111311037A (en) Method for compiling custom construction plan, progress summarizing and data analysis
CN110322185A (en) A kind of logistics management-control method based on GIS and GPS
ES2401880B1 (en) PROCEDURE AND SYSTEM FOR OPTIMIZING MAINTENANCE OPERATIONS IN AIRCRAFTERS AND WIND FARMS.
CN111126652B (en) Hotel tail room intelligent prediction distribution system and method
Kumar et al. Socio-economic aspects of PV roof-top installations for residential colonies

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20181225