CN109066738B - Dynamic load balance-based tie line absorption amount calculation method and system - Google Patents

Dynamic load balance-based tie line absorption amount calculation method and system Download PDF

Info

Publication number
CN109066738B
CN109066738B CN201811141651.7A CN201811141651A CN109066738B CN 109066738 B CN109066738 B CN 109066738B CN 201811141651 A CN201811141651 A CN 201811141651A CN 109066738 B CN109066738 B CN 109066738B
Authority
CN
China
Prior art keywords
value
voltage direct
direct current
extra
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811141651.7A
Other languages
Chinese (zh)
Other versions
CN109066738A (en
Inventor
向萌
左剑
胡臻
柳永妍
呙虎
张可人
沈阳武
崔挺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811141651.7A priority Critical patent/CN109066738B/en
Publication of CN109066738A publication Critical patent/CN109066738A/en
Application granted granted Critical
Publication of CN109066738B publication Critical patent/CN109066738B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method and a system for calculating the tie line absorption amount based on dynamic load balance, wherein the method comprises the following steps of S1: constructing a short-term dynamic load balance model based on power grid load balance; s2: calculating an upper limit value and a lower limit value of a planned absorption value of the extra-high voltage direct-current connecting line at each moment to be researched based on the constructed short-term dynamic load balance model and a planned starting mode of a local unit of the power grid; s3: and obtaining the sectional curve of the ultrahigh voltage direct current tie line absorption plan value based on the sectional mode of the pre-stored ultrahigh voltage direct current tie line plan curve and the upper limit value and the lower limit value of the ultrahigh voltage direct current tie line absorption plan value at each time to be researched. The method measures the planned value of the consumption of the extra-high voltage direct current tie line, so that the sectional curve of the planned value of the consumption of the extra-high voltage direct current tie line is applied to a dispatching mechanism in the follow-up process, and the consumption proportion of clean energy is improved.

Description

Dynamic load balance-based tie line absorption amount calculation method and system
Technical Field
The invention belongs to the field of power grid dispatching, and particularly relates to a dynamic load balance-based tie line consumption calculation method and a dynamic load balance-based tie line consumption calculation system.
Background
With the unique advantages of the power grid tie line plan, the optimized allocation of energy resources is realized in the power trading nationwide, the situation that the defects and the pits coexist is effectively solved, the increasingly tight connection between each large area and the provincial power grid and the power transmission capacity of the tie line are improved in a hardware manner, and the more firm foundation is realized on the optimized allocation of the energy resources. However, the current grid structure and the current situation of water, fire and electricity resources restrict large-scale consumption of clean energy, how to fully adjust various adjustment means of a power grid, and fully consume the extra-high voltage direct current power mainly generated by the clean energy, have important significance for reducing the power grid fire and electricity ratio, optimizing the energy structure, reducing the electricity purchasing average price and realizing energy conservation and emission reduction, and are also the problems to be solved urgently at present. Therefore, obtaining the consumption of the extra-high voltage direct current electric power mainly generated by clean energy to guide a scheduling mechanism to specify a day-ahead plan, and preferentially considering the extra-high voltage direct current connecting line is a crucial link for solving the problems when performing real-time balance calculation. However, the prior art lacks a reliable and fast way to obtain the consumption of the extra-high voltage dc link mainly based on clean energy power generation.
Disclosure of Invention
The invention aims to provide a connecting line consumption calculation method and a system thereof based on short-term dynamic load balance, which are reliable to realize, quickly acquire the consumption of an extra-high voltage direct current connecting line mainly based on clean energy power generation, and provide scheduling data for a scheduling mechanism, so that the system can maximally consume the extra-high voltage direct current connecting line mainly based on clean energy under the condition of meeting safe and stable operation.
In one aspect, the invention provides a method for calculating a tie line budget based on short-term dynamic load balancing, comprising the following steps:
s1: constructing a short-term dynamic load balance model based on power grid load balance;
Dt=GL,t+Gr,t+Lh,t+Lother,t
in the formula, DtRepresenting the load value, G, of the grid at time tL,tRepresenting the value of the output of the local set of the grid at time t, Gr,tRepresenting the output value L of the clean energy of the power grid at the moment th,tRepresenting the planned value, L, of the line at time t of the UHV DC lineother,tRepresenting the sum of planned values of the connecting lines of other connecting lines except the extra-high voltage direct current connecting line at the time t;
s2: calculating an upper limit value and a lower limit value of a planned absorption value of the extra-high voltage direct-current connecting line at each moment to be researched based on the constructed short-term dynamic load balance model and a planned starting mode of a local unit of the power grid;
s3: obtaining a sectional curve of the extra-high voltage direct current tie line absorption plan value based on a sectional mode of a pre-stored extra-high voltage direct current tie line plan curve and upper limit values and lower limit values of the extra-high voltage direct current tie line absorption plan value at each time to be researched;
the sectional intervals on the sectional curve of the ultrahigh voltage direct current tie line absorption plan value correspond to the sectional intervals of the ultrahigh voltage direct current tie line absorption plan value one by one, a group of absorption plan value maximum values and minimum values exist in each sectional interval in the sectional curve of the ultrahigh voltage direct current tie line absorption plan value correspondingly, and the calculation formula is as follows:
Figure BDA0001815947100000021
in the formula (I), the compound is shown in the specification,
Figure BDA0001815947100000022
andL(Ti) Respectively, in the time period TiThe extra-high voltage direct current connecting line in the system absorbs the maximum value and the minimum value of the planned value,
Figure BDA0001815947100000023
and
Figure BDA0001815947100000024
respectively representing the upper limit value and the lower limit value of a planned value of the consumption on the extra-high voltage direct current connecting line at the time T, Ti、TnRespectively representing the ith subsection interval and the time period corresponding to the nth subsection interval in the plan curve of the extra-high voltage direct current tie line, wherein n is the number of the subsection intervals of the plan curve of the extra-high voltage direct current tie line.
It should be understood that the extra-high voltage dc link in the field is mainly based on clean energy. According to the method, when the consumption capacity of the extra-high voltage direct current connecting line is considered, loads, local main-regulating water-fire power generation output, clean energy and other connecting lines are comprehensively analyzed, a short-term dynamic load balance model is further constructed, intra-provincial balance and trans-provincial power balance are considered, the consumption of the extra-high voltage direct current connecting line is calculated based on the short-term dynamic load balance model, and the extra-high voltage connecting line which mainly uses clean energy is consumed by the system under the condition that safe and stable operation is met. Therefore, the sectional curve of the extra-high voltage direct current tie line absorption plan value obtained by the invention can be applied to a scheduling mechanism to make a day-ahead plan, and the extra-high voltage direct current tie line is prioritized when real-time balance calculation is carried out.
From the above formula of S3, in the time period TiMaximum value of inner extra-high voltage direct current connecting line absorption plan value
Figure BDA00018159471000000210
In the time period TiThe minimum value of the maximum values of the digestion plan values at all the moments to be researched; in a time period TiMinimum value of inner extra-high voltage direct current connecting line absorption plan valueL(Ti) In the time period TiThe maximum value of the minimum values of the planned values is consumed at all times to be studied.
Preferably, in step S2, the calculation formulas of the upper limit value and the lower limit value of the extra-high voltage dc link accommodation plan value at each time to be studied are as follows:
Figure BDA0001815947100000025
in the formula (I), the compound is shown in the specification,
Figure BDA0001815947100000026
and
Figure BDA0001815947100000027
upper and lower limit values respectively representing the sum of all tie-line accommodation plan values at time t, where the upper limit value of the sum of all tie-line accommodation plan values at time t
Figure BDA0001815947100000028
And lower limit value
Figure BDA0001815947100000029
The calculation formula of (a) is as follows:
Figure BDA0001815947100000031
in the formula, Dt' denotes the predicted value of load at time t, Gr,tRepresents the predicted value of the clean energy at time t,
Figure BDA0001815947100000032
and respectively representing the output upper limit and the output lower limit of the local unit of the power grid at the moment t.
Preferably, the output upper limit of the local unit of the power grid at the time t
Figure BDA0001815947100000033
The output lower limit of the local unit of the power grid at the time t is 100 percent of the starting capacity
Figure BDA0001815947100000034
50% of the boot capacity.
Preferably, the time to be studied selected in S2 is a time point of an interval period of 15 min.
The study time was substantially 96 points, i.e., 15 minutes per day.
On the other hand, the invention also provides a measuring and calculating system based on the method, which comprises a balance model building module and a processing module;
the system comprises a balance model construction module, a load balance module and a load balance module, wherein the balance model construction module is used for constructing a short-term dynamic load balance model based on power grid load balance;
the processing module is used for calculating the upper limit value and the lower limit value of the extra-high voltage direct current connecting line absorption plan value at each time to be researched;
and the processing module is used for calculating the maximum value and the minimum value of the ultrahigh voltage direct current tie line absorption plan value of each subsection interval so as to obtain a subsection curve of the ultrahigh voltage direct current tie line absorption plan value.
Advantageous effects
1. The invention provides a brand-new measuring and calculating method for obtaining the consumption of an extra-high voltage direct current connecting line, which is characterized in that an upper limit value and a lower limit value of a planned value of the extra-high voltage direct current connecting line at each time to be researched are calculated by constructing a short-term dynamic load balance model, and a sectional curve of the planned value of the extra-high voltage direct current connecting line is obtained according to a conventional sectional mode of the planned curve of the extra-high voltage direct current connecting line.
2. According to the method, when the consumption capacity of the extra-high voltage direct current connecting line is considered, loads, local general regulating water and fire power generation output, clean energy and other connecting lines are comprehensively analyzed, a short-term dynamic load balance model is further constructed, intra-provincial balance is considered, trans-provincial power balance is also considered, the consumption of the extra-high voltage direct current connecting line is calculated based on the short-term dynamic load balance model, a reliable consumption plan quantity result is obtained, the system can consume the extra-high voltage connecting line mainly comprising the clean energy under the condition that safe and stable operation is met, and the obtained section curve of the consumption plan value is executed by local scheduling, so that the safety and stability of operation of a power grid are improved.
Drawings
Fig. 1 is a flowchart of a new measuring and calculating method for obtaining the consumption of the extra-high voltage dc link according to the present invention.
Detailed Description
The present invention will be further described with reference to the following examples.
As shown in fig. 1, the method for calculating the tie line budget based on short-term dynamic load balancing according to the present invention includes the following steps:
s1: and constructing a short-term dynamic load balancing model based on the power grid load balancing. Based on the load balance of the power grid, the short-term dynamic load balance model needs to satisfy the following formula:
Dt=GL,t+Gr,t+Lh,t+Lother,t
in the formula, DtRepresenting the load value, G, of the grid at time tL,tRepresenting the value of the output of the local set of the grid at time t, Gr,tRepresenting the output value L of the clean energy of the power grid at the moment th,tRepresenting the planned value, L, of the line at time t of the UHV DC lineother,tAnd represents the sum of planned values of the links at the time t of other links except the extra-high voltage direct current link.
S2: and calculating the upper limit value and the lower limit value of the absorption plan value at each 96 points on the extra-high voltage direct current connecting line based on the constructed short-term dynamic load balance model and the planned starting mode of the local unit of the power grid.
Firstly, obtaining the lower output limit of the local unit at 96 points according to the starting mode plan of the local unit of the power grid
Figure BDA0001815947100000041
And upper limit of output
Figure BDA0001815947100000042
In this embodiment, since other tie line plans are set to be unchanged and the local start-stop mode is set to be unchanged, the lower limit of the output at each time is set
Figure BDA0001815947100000043
All are 50% of the starting capacity and the upper limit of the output
Figure BDA0001815947100000044
Are all 100% of the boot capacity.
From the short-term dynamic load balancing model in step S1, the calculation formula for obtaining the sum of planned values of the consumption of all links at time t is as follows:
Lall,t=Dt′-(GL,t+Gr,t)
in the formula, Lall,tRepresenting the sum of all tie-line accommodation plan values at time t, Dt' denotes the predicted value of load at time t, Gr,tAnd the predicted value of the clean energy at the time t is shown. Thus limiting the output at 96 points to a lower limit
Figure BDA0001815947100000045
And upper limit of output
Figure BDA0001815947100000046
Substituting this equation can calculate the upper and lower limits of the sum of the planned values for the consumption at 96 points for all links as follows:
Figure BDA0001815947100000047
in the formula (I), the compound is shown in the specification,
Figure BDA0001815947100000048
and
Figure BDA0001815947100000049
an upper limit value and a lower limit value representing the sum of all tie line accommodation plan values at time t, respectively. Therefore, the upper limit value and the lower limit value of the planned value for the absorption at each 96 points on the extra-high voltage direct current communication line are as follows:
Figure BDA00018159471000000410
in the formula (I), the compound is shown in the specification,
Figure BDA00018159471000000411
and
Figure BDA00018159471000000412
respectively representing the upper limit value and the lower limit value of the planned value of the consumption on the extra-high voltage direct current connecting line at the time point t (at each 96 points). The maximum curve and the lower limit value formed by the upper limit value of the absorption plan value at the 96 point of the extra-high voltage direct current connecting line can be obtained through the calculation
Figure BDA0001815947100000051
The minimum curve formed.
S3: and obtaining the sectional curve of the ultrahigh voltage direct current tie line absorption plan value based on the sectional mode of the pre-stored ultrahigh voltage direct current tie line plan curve and the upper limit value and the lower limit value of the ultrahigh voltage direct current tie line absorption plan value at each time to be researched.
The curve type of the plan curve of the extra-high voltage direct current link is generally in a step-by-step mode, so that the curve of the planned value of the extra-high voltage direct current link absorption in a period of time consists of a plurality of straight lines. By processing the consumption plan values of 96 points in each time interval, the curve can be divided into n sections T by assuming that the planned value curve of the extra-high voltage direct current connecting line consists of n stepsi∈{T1,T2,…Tn}. In each time interval, the sectional curve of the extra-high voltage direct current tie line absorption plan value is represented as follows:
Figure BDA0001815947100000052
in the formula (I), the compound is shown in the specification,
Figure BDA0001815947100000053
andL(Ti) Respectively, in the time period TiThe extra-high voltage direct current connecting line in the system absorbs the maximum value and the minimum value of the planned value. From the above formulaIn a time period TiMaximum value of inner extra-high voltage direct current connecting line absorption plan value
Figure BDA0001815947100000054
In the time period TiAll 96 points within the total take-up plan value maximum; in a time period TiMinimum value of inner extra-high voltage direct current connecting line absorption plan valueL(Ti) In the time period TiAll 96 points within the plot value take up the maximum of the minimum values of the plot value.
On the other hand, the invention also provides a measuring and calculating system based on the method, which comprises a balance model building module and a processing module;
the system comprises a balance model construction module, a load balance module and a load balance module, wherein the balance model construction module is used for constructing a short-term dynamic load balance model based on power grid load balance;
the processing module is used for calculating the upper limit value and the lower limit value of the extra-high voltage direct current connecting line absorption plan value at each time to be researched;
and the processing module is used for calculating the maximum value and the minimum value of the ultrahigh voltage direct current tie line absorption plan value of each subsection interval so as to obtain a subsection curve of the ultrahigh voltage direct current tie line absorption plan value.
The above-mentioned division of the modules is a functional division, and in some embodiments, some modules may be combined or disassembled, which is not specifically limited by the present invention.
According to the method, when the consumption capacity of the extra-high voltage direct current connecting line is considered, loads, local main-regulating water-fire power generation output, clean energy and other connecting lines are comprehensively analyzed, a short-term dynamic load balance model is further constructed, intra-provincial balance and trans-provincial power balance are considered, the consumption of the extra-high voltage direct current connecting line is calculated based on the short-term dynamic load balance model, and the extra-high voltage connecting line which mainly uses clean energy is consumed by the system under the condition that safe and stable operation is met.
It should be emphasized that the examples described herein are illustrative and not restrictive, and thus the invention is not to be limited to the examples described herein, but rather to other embodiments that may be devised by those skilled in the art based on the teachings herein, and that various modifications, alterations, and substitutions are possible without departing from the spirit and scope of the present invention.

Claims (5)

1. A tie line absorption amount calculation method based on dynamic load balance is characterized in that; the method comprises the following steps:
s1: constructing a short-term dynamic load balance model based on power grid load balance;
Dt=GL,t+Gr,t+Lh,t+Lother,t
in the formula, DtRepresenting the load value, G, of the grid at time tL,tRepresenting the value of the output of the local set of the grid at time t, Gr,tRepresenting the output value L of the clean energy of the power grid at the moment th,tRepresenting the planned value, L, of the line at time t of the UHV DC lineother,tRepresenting the sum of planned values of the connecting lines of other connecting lines except the extra-high voltage direct current connecting line at the time t;
s2: calculating an upper limit value and a lower limit value of a planned absorption value of the extra-high voltage direct-current connecting line at each moment to be researched based on the constructed short-term dynamic load balance model and a planned starting mode of a local unit of the power grid;
s3: obtaining a sectional curve of the extra-high voltage direct current tie line absorption plan value based on a sectional mode of a pre-stored extra-high voltage direct current tie line plan curve and upper limit values and lower limit values of the extra-high voltage direct current tie line absorption plan value at each time to be researched;
the sectional intervals on the sectional curve of the ultrahigh voltage direct current tie line absorption plan value correspond to the sectional intervals of the ultrahigh voltage direct current tie line absorption plan value one by one, a group of absorption plan value maximum values and minimum values exist in each sectional interval in the sectional curve of the ultrahigh voltage direct current tie line absorption plan value correspondingly, and the calculation formula is as follows:
Figure FDA0002970136860000011
in the formula (I), the compound is shown in the specification,
Figure FDA0002970136860000012
andL(Ti) Respectively, in the time period TiThe extra-high voltage direct current connecting line in the system absorbs the maximum value and the minimum value of the planned value,
Figure FDA0002970136860000013
and
Figure FDA0002970136860000014
respectively representing the upper limit value and the lower limit value of a planned value of the consumption on the extra-high voltage direct current connecting line at the time T, Ti、TnRespectively representing the ith subsection interval and the time period corresponding to the nth subsection interval in the plan curve of the extra-high voltage direct current tie line, wherein n is the number of the subsection intervals of the plan curve of the extra-high voltage direct current tie line.
2. The dynamic load balancing-based tie line budget calculation method according to claim 1, wherein: in step S2, the calculation formulas of the upper limit value and the lower limit value of the planned absorption value of the extra-high voltage dc link at each time to be studied are as follows:
Figure FDA0002970136860000015
in the formula (I), the compound is shown in the specification,
Figure FDA0002970136860000016
and
Figure FDA0002970136860000017
upper and lower limit values respectively representing the sum of all tie-line accommodation plan values at time t, where the upper limit value of the sum of all tie-line accommodation plan values at time t
Figure FDA0002970136860000018
And lower limit value
Figure FDA0002970136860000019
The calculation formula of (a) is as follows:
Figure FDA00029701368600000110
in formula (II) to'tDenotes a predicted value of load at time t, G'r,tRepresents the predicted value of the clean energy at time t,
Figure FDA00029701368600000111
and respectively representing the output upper limit and the output lower limit of the local unit of the power grid at the moment t.
3. The dynamic load balancing-based tie line budget calculation method according to claim 2, wherein: output upper limit of local unit of power grid at time t
Figure FDA0002970136860000021
The output lower limit of the local unit of the power grid at the time t is 100 percent of the starting capacity
Figure FDA0002970136860000022
50% of the boot capacity.
4. The dynamic load balancing-based tie line budget calculation method according to claim 1, wherein: the time to be studied selected in S2 is a time point with an interval period of 15 min.
5. A system for calculating the tie line budget based on the dynamic load balancing calculation method according to any one of claims 1 to 4, wherein: the system comprises a balance model building module and a processing module;
the system comprises a balance model construction module, a load balance module and a load balance module, wherein the balance model construction module is used for constructing a short-term dynamic load balance model based on power grid load balance;
the processing module is used for calculating the upper limit value and the lower limit value of the extra-high voltage direct current connecting line absorption plan value at each time to be researched;
and the processing module is used for calculating the maximum value and the minimum value of the ultrahigh voltage direct current tie line absorption plan value of each subsection interval so as to obtain a subsection curve of the ultrahigh voltage direct current tie line absorption plan value.
CN201811141651.7A 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system Active CN109066738B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811141651.7A CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811141651.7A CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Publications (2)

Publication Number Publication Date
CN109066738A CN109066738A (en) 2018-12-21
CN109066738B true CN109066738B (en) 2021-04-23

Family

ID=64766474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811141651.7A Active CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Country Status (1)

Country Link
CN (1) CN109066738B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN104578183A (en) * 2015-01-28 2015-04-29 国家电网公司 Tie-line power transmission plan optimization method for improving low-carbon level of electric system
CN105470956A (en) * 2015-12-29 2016-04-06 中国电力科学研究院 Optimal dispatching method for inter-provincial interconnecting line for production analogue simulation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN104578183A (en) * 2015-01-28 2015-04-29 国家电网公司 Tie-line power transmission plan optimization method for improving low-carbon level of electric system
CN105470956A (en) * 2015-12-29 2016-04-06 中国电力科学研究院 Optimal dispatching method for inter-provincial interconnecting line for production analogue simulation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
A New Strategy of HVDC Operation for Maximizing Renewable Energy Accommodation;Haibo Zhang,Sen Zhang;《2017 IEEE Power & Energy Society General Meeting》;20180201;第1~6页 *
新能源消纳关键因素分析及解决措施研究;舒印彪等;《中国电机工程学报》;20170105;第37卷(第1期);第1~9页 *

Also Published As

Publication number Publication date
CN109066738A (en) 2018-12-21

Similar Documents

Publication Publication Date Title
US11757404B2 (en) Coordinated control of renewable electric generation resource and charge storage device
US9489701B2 (en) Adaptive energy management system
CN103368173B (en) Active power flow optimizing distribution method for alternating-direct current parallel system containing soft direct current power transmission
JP5756348B2 (en) Power generation system and power generation apparatus
Rodriguez-Diaz et al. Real-time Energy Management System for a hybrid AC/DC residential microgrid
CN102930351A (en) Comprehensive energy-conservation optimal operation daily plan generation method
WO2019128012A1 (en) Robust optimal coordinated dispatching method for alternating-current and direct-current hybrid micro-grid
CN108493998B (en) Robust power transmission network planning method considering demand response and N-1 expected faults
US20170363666A1 (en) Method and apparatus for energy flow visualization
CN111667136A (en) Clearing method and device for regional power market and storage medium
CN117077974A (en) Virtual power plant resource optimal scheduling method, device, equipment and storage medium
Mizuno et al. Optimum facility design in large hospital using renewable energy
CN109066738B (en) Dynamic load balance-based tie line absorption amount calculation method and system
JP6764769B2 (en) Power supply control device, power supply control program, power rate setting system
Ramos et al. Effect of price responsive demand on the operation of microgrids
Tziovani et al. Grid friendly operation of a PV-storage system with profit maximization and reliability enhancement
CN110739684A (en) Multi-time scale-based multi-AC/DC hybrid micro-grid optimal scheduling method
Sechilariu et al. A conceptual framework for full optimal operation of a grid-connected DC microgrid
You et al. Flexibility quantification and pricing of household heat pump and combined heat and power unit
JP2008043170A (en) Power supply system, consumer group facility, and monitoring control method therefor
JP2023500471A (en) Method and apparatus for microgrid tertiary control with integrated overcurrent protection
CN105811459A (en) Optimized division method for direct-current outgoing wind power base balance regional grid
Sharma et al. Coordinated voltage control through optimal dispatch of responsive building loads
CN113162124B (en) New energy concentrated grid-connected node output optimization method, device, equipment and medium
Feng et al. Optimal configuration of energy storage for distributed photovoltaic generation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant