CN109057337A - The area prefabricated concrete structure Hou Jiao construction method - Google Patents

The area prefabricated concrete structure Hou Jiao construction method Download PDF

Info

Publication number
CN109057337A
CN109057337A CN201810940089.8A CN201810940089A CN109057337A CN 109057337 A CN109057337 A CN 109057337A CN 201810940089 A CN201810940089 A CN 201810940089A CN 109057337 A CN109057337 A CN 109057337A
Authority
CN
China
Prior art keywords
area
hou jiao
prefabricated
prefabricated components
backplate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810940089.8A
Other languages
Chinese (zh)
Inventor
武涛
刘威
吴锋
张贵文
徐春丽
彭秀武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201810940089.8A priority Critical patent/CN109057337A/en
Publication of CN109057337A publication Critical patent/CN109057337A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of area prefabricated concrete structure Hou Jiao construction methods, comprising steps of A1: by the first prefabricated components and the positioning lifting of the second prefabricated components;The assembling reinforcement of the area A2: Hou Jiao;A3: Hou Jiao area's backplate, which is detachably fixed, to be connected on first prefabricated components and second prefabricated components, casting concrete;A4: after concrete reaches preset strength, the area Hou Jiao backplate is removed.In the area prefabricated concrete structure Hou Jiao provided by the present application construction method, realize that casting concrete position is blocked by the area Hou Jiao backplate, the area Qie Houjiao backplate is directly removably mounted on the first prefabricated components and the second prefabricated components, installation is simple, it can be reused after the disassembly of the area Qie Houjiao backplate, significantly reduce the construction cost in the area assembly concrete Hou Jiao.Meanwhile time when shortening construction, improve construction efficiency.

Description

The area prefabricated concrete structure Hou Jiao construction method
Technical field
The present invention relates to technical field of building construction, the in particular to a kind of area prefabricated concrete structure Hou Jiao construction party Method.
Background technique
Assembled architecture is built made of assemble in site as prefabricated component component, and the maximum advantage of assembled architecture is to subtract The workload for having lacked situ wet operation, is greatly saved man power and material, greatly improves site operation efficiency, wherein after Important connection type one of of the pouring concrete as prefabricated component.
The area prefabricated concrete structure Hou Jiao construction method are as follows: rear pouring concrete area, i.e. the first prefabricated components and second are in advance Supporting module between component processed due to template support heavy workload, sets up complicated, large labor intensity, and concrete curing is completed Demoulding afterwards, demoulding is cumbersome, and the component after disassembly is as construction waste processing, so that the construction cost in the area assembly concrete Hou Jiao It is higher.
Therefore, the construction cost for how reducing the area assembly concrete Hou Jiao is that those skilled in the art are urgently to be resolved Technical problem.
Summary of the invention
The object of the present invention is to provide a kind of area prefabricated concrete structure Hou Jiao construction methods, to reduce assembled coagulation The construction cost in the area Tu Houjiao.
To achieve the above object, the present invention provides a kind of area prefabricated concrete structure Hou Jiao construction method, comprising steps of
A1: by the first prefabricated components and the positioning lifting of the second prefabricated components;
The assembling reinforcement of the area A2: Hou Jiao;
A3: Hou Jiao area's backplate, which is detachably fixed, to be connected on first prefabricated components and second prefabricated components, is poured Build concrete;
A4: after concrete reaches preset strength, the area Hou Jiao backplate is removed.
Preferably, the step A3 includes:
A31: the pre-buried screw shell on first prefabricated components and second prefabricated components;
A32: the both ends of the area Hou Jiao backplate are fitted in respectively on first prefabricated components and second prefabricated components;
A33: the area Hou Jiao backplate and first prefabricated components and described second prefabricated are passed through by threaded fastener Screw shell on component is threadedly coupled.
Preferably, being fixedly connected on the screw shell can be with the first prefabricated components inner surface and described second The dowel that prefabricated components inner surface abuts.
Preferably, the dowel is arranged along perpendicular to the screw shell axis direction, and the screw thread is stretched out at both ends Sleeve.
Preferably, the dowel is plugged on the screw shell.
Preferably, further include step A5: being smoothed out in the pre-buried screw shell by cement mortar.
Preferably, the screw shell on first prefabricated components and the screw shell on second prefabricated components are symmetrical It is distributed in the opposite sides of the area Hou Jiao backplate.
Preferably, first prefabricated components and second prefabricated components are prefabricated post, composite beam or shear wall.
Preferably, the step A3 includes: and the casting concrete vibrates to catch up with flat and curing concrete.
Preferably, the area Hou Jiao backplate is plank, aluminium sheet or steel plate.
In the above-mentioned technical solutions, the area prefabricated concrete structure Hou Jiao provided by the invention construction method, comprising steps of A1: by the first prefabricated components and the positioning lifting of the second prefabricated components;The assembling reinforcement of the area A2: Hou Jiao;A3: Hou Jiao area's backplate (1) can Disassembly is fixedly connected on first prefabricated components and second prefabricated components, casting concrete;A4: concrete reaches pre- If after intensity, removing the area Hou Jiao backplate.
As can be seen from the above description, in the area prefabricated concrete structure Hou Jiao provided by the present application construction method, pass through The area Hou Jiao backplate realizes that casting concrete position is blocked, and the area Qie Houjiao backplate is directly removably mounted at the first prefabricated components and the On two prefabricated components, installation is simple, can reuse after the disassembly of the area Qie Houjiao backplate, significantly reduce assembly concrete The construction cost in the area Hou Jiao.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is the construction of the area Hou Jiao provided by embodiment of the present invention parts explosion;
Fig. 2 is the structural schematic diagram of prefabricated post and the area prefabricated post Hou Jiao provided by the embodiment of the present invention;
Fig. 3 is the structural schematic diagram of composite beam and the area composite beam Hou Jiao provided by the embodiment of the present invention;
Fig. 4 is the structural schematic diagram of shear wall and the vertical area Hou Jiao of shear wall provided by the embodiment of the present invention;
Fig. 5 is the area prefabricated concrete structure Hou Jiao construction method flow chart provided by the embodiment of the present invention.
Wherein in Fig. 1-4: the area 1- Hou Jiao backplate, 2- screw shell, 3- threaded fastener, 4- composite beam, 5- shear wall, 6- Prefabricated post, 7- mounting hole.
Specific embodiment
Core of the invention is to provide a kind of area prefabricated concrete structure Hou Jiao construction method, to reduce assembled coagulation The construction cost in the area Tu Houjiao.
In order to make those skilled in the art more fully understand technical solution of the present invention, with reference to the accompanying drawing and embodiment party The present invention is described in further detail for formula.
Fig. 1 to Fig. 5 is please referred to, in a specific embodiment, the assembled coagulation that the specific embodiment of the invention provides The area soil structure Hou Jiao construction method, comprising steps of
A1: by the first prefabricated components and the positioning lifting of the second prefabricated components.Wherein, the first prefabricated components and the second prefabricated structure Part can be prefabricated post 6, composite beam 4 or shear wall 5 etc., carry out the construction of the area corresponding concrete Hou Jiao according to practice of construction position. Specifically, in construction, then live unwrapping wire positioning is arrived using the first prefabricated components and the second area Hou Jiao as prefabricated part hanging Behind position.
A2: in the assembling reinforcement of the area Hou Jiao.Wherein, depending on the specification and quantity of rear assembling reinforcement are designed according to structure, this Shen It please be not specifically limited.
A3: the area Hou Jiao backplate 1 is detachably fixed and is connected on the first prefabricated components and the second prefabricated components, coagulation is poured Soil.In order to improve construction quality, it is preferable that the step further includes that casting concrete vibrates to catch up with flat and curing concrete.
Specifically, determining 1 size of the area Hou Jiao backplate and thickness according to drawing and site specific, the area Hou Jiao backplate 1 can Think steel plate, plank or aluminium sheet etc..Wherein, the area Hou Jiao backplate 1 seals the first prefabricated components and the second prefabricated components connecting portion Stifled, the number used and the shape surrounded are decided according to the actual requirements when the area Hou Jiao backplate 1 is constructed, and the application does not do specific limit It is fixed.
Specifically, the area Hou Jiao backplate 1 can be connected by a snap on the first prefabricated components and the second prefabricated components.
In a kind of 1 fixed form of the specific area Shi Houjiao backplate, step A3 includes:
A31: the pre-buried screw shell 2 on the first prefabricated components and the second prefabricated components.
A32: the both ends of the area Hou Jiao backplate 1 are fitted in respectively on the first prefabricated components and the second prefabricated components.
A33: the spiral shell on the area Hou Jiao backplate 1 and the first prefabricated components and the second prefabricated components is passed through by threaded fastener 3 Line sleeve 2 is threadedly coupled, specifically, the first prefabricated components and the second prefabricated components are equipped with the peace passed through for threaded fastener 3 Fill hole 7.
In order to reduce construction cost, it is preferable that threaded fastener 3 is bolt, and before construction, field personnel utilizes spanner etc. The area Hou Jiao backplate 1 is mounted on the first prefabricated components and the second prefabricated components by tool by bolt and pre-buried screw shell 2, is had Body, depending on the positions of the first prefabricated components and the second prefabricated components is required according to construction, the application is not specifically limited. Wherein according to structural design drawing paper, the amount of pouring concrete and the stress form of bolt after determining, according to bolt institute bearing capacity Size selects the bolt of suitable quantity and specification.
When construction, the quantity of threaded fastener 3 and screw shell 2 is corresponded, and is determined according to the position in the area Hou Jiao Position of the embedded sleeve barrel in prefabricated components.To pre-buried screw thread in the first prefabricated components and the second prefabricated components design drawing Accurate positioning is applied, when prefabricated member factory produces prefabricated components, pre-buried screw shell 2 is positioned according to design drawing and is arranged, The prefabricated components with pre-buried screw shell 2 are finally produced, which can be used as the fixed use of the area Hou Jiao shield, moreover it is possible to make It is used for the fixed point of temporary support.Then, pre-buried 2 position of screw shell and selected Bolt sizes are based on, in the area Hou Jiao Aperture on backplate 1, so that bolt passes through.
Using bolt as the equal spare and accessory parts buying of 3 area Ji Houjiao backplate 1 of threaded fastener or easy to make quick, specification Unanimously, pattern is unified, and installation and demolishing process are simple and quick;Simplify the area assembled Hou Jiao construction technology simultaneously, reduces manpower Cost has saved the time, improves construction efficiency.
A4: after concrete reaches preset strength, the area Hou Jiao backplate 1 is removed.
As can be seen from the above description, in the area prefabricated concrete structure Hou Jiao provided by the present application construction method, pass through The area Hou Jiao backplate 1 realize casting concrete position block, the area Qie Houjiao backplate 1 be directly removably mounted at the first prefabricated components with On second prefabricated components, installation is simple, and the area Qie Houjiao backplate 1 can reuse after dismantling, and it is mixed to significantly reduce assembled The construction cost in the area Ning Tuhoujiao.
The construction method provided by the present application for exempting from formwork, it is convenient to operate, and construction efficiency is high, reduces the labour of staff Intensity.
Further, which further includes step A5: being smoothed out in pre-buried screw shell 2 by cement mortar.It is poured after Concrete strength reaches requirement, removes the area node Hou Jiao backplate 1, and pre-buried 2 hole of screw shell is smoothed out with cement mortar, improves building Surface smoothness, shape are more beautiful.
Being fixedly connected on screw shell 2 can abut with the first prefabricated components inner surface and the second prefabricated components inner surface Dowel.Specifically, limit is abutted with the first prefabricated components inner surface and the second prefabricated components inner surface by dowel, after avoiding After pouring the fastening of area's backplate 1, the case where loosening in casting concrete, connective stability is improved.
In order to further increase connective stability, it is preferable that dowel is arranged along perpendicular to 2 axis direction of screw shell, and two Screw shell 2 is stretched out at end.For the ease of assembling dowel and screw shell 2, it is preferable that dowel is directly plugged on screw shell 2.
In order to provide stability maintenance, it is preferable that the spiral shell on screw shell 2 and the second prefabricated components on the first prefabricated components Line sleeve 2 is symmetrically distributed in the opposite sides of the area Hou Jiao backplate 1.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (10)

1. a kind of area prefabricated concrete structure Hou Jiao construction method, which is characterized in that comprising steps of
A1: by the first prefabricated components and the positioning lifting of the second prefabricated components;
The assembling reinforcement of the area A2: Hou Jiao;
A3: Hou Jiao area's backplate (1), which is detachably fixed, to be connected on first prefabricated components and second prefabricated components, is poured Concrete;
A4: after concrete reaches preset strength, the area Hou Jiao backplate (1) is removed.
2. the area prefabricated concrete structure Hou Jiao according to claim 1 construction method, which is characterized in that the step A3 Include:
A31: the pre-buried screw shell (2) on first prefabricated components and second prefabricated components;
A32: the both ends of the area Hou Jiao backplate (1) are fitted in respectively on first prefabricated components and second prefabricated components;
A33: the area Hou Jiao backplate (1) and first prefabricated components and described second are passed through in advance by threaded fastener (3) The screw shell (2) on component processed is threadedly coupled.
3. the area prefabricated concrete structure Hou Jiao according to claim 2 construction method, which is characterized in that the thread bush The anchor that can be abutted with the first prefabricated components inner surface and the second prefabricated components inner surface is fixedly connected on cylinder (2) Muscle.
4. the area prefabricated concrete structure Hou Jiao according to claim 3 construction method, which is characterized in that the dowel edge It is arranged perpendicular to the screw shell (2) axis direction, and the screw shell (2) are stretched out at both ends.
5. the area prefabricated concrete structure Hou Jiao according to claim 4 construction method, which is characterized in that the dowel is inserted It is located on the screw shell (2).
6. the area prefabricated concrete structure Hou Jiao according to claim 2 construction method, which is characterized in that further include step A5: it is smoothed out in the pre-buried screw shell (2) by cement mortar.
7. the area prefabricated concrete structure Hou Jiao according to claim 2 construction method, which is characterized in that described first is pre- The screw shell (2) on screw shell (2) and second prefabricated components on component processed is symmetrically distributed in the area Hou Jiao and protects The opposite sides of plate (1).
8. the area prefabricated concrete structure Hou Jiao according to claim 1 construction method, which is characterized in that described first is pre- Component processed and second prefabricated components are prefabricated post (6), composite beam (4) or shear wall (5).
9. the area prefabricated concrete structure Hou Jiao according to claim 1 construction method, which is characterized in that the step A3 It include: that the casting concrete vibrates to catch up with flat and curing concrete.
10. the area prefabricated concrete structure Hou Jiao according to claim 1 to 9 construction method, feature exist In the area Hou Jiao backplate (1) is plank, aluminium sheet or steel plate.
CN201810940089.8A 2018-08-17 2018-08-17 The area prefabricated concrete structure Hou Jiao construction method Pending CN109057337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810940089.8A CN109057337A (en) 2018-08-17 2018-08-17 The area prefabricated concrete structure Hou Jiao construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810940089.8A CN109057337A (en) 2018-08-17 2018-08-17 The area prefabricated concrete structure Hou Jiao construction method

Publications (1)

Publication Number Publication Date
CN109057337A true CN109057337A (en) 2018-12-21

Family

ID=64686314

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810940089.8A Pending CN109057337A (en) 2018-08-17 2018-08-17 The area prefabricated concrete structure Hou Jiao construction method

Country Status (1)

Country Link
CN (1) CN109057337A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110210166A (en) * 2019-06-14 2019-09-06 上海宝冶集团有限公司 A kind of prefabricated superimposed sheet method for splitting

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204163115U (en) * 2014-10-17 2015-02-18 江西中联建设集团有限公司 Template construction device is hung in a kind of ater-casting

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204163115U (en) * 2014-10-17 2015-02-18 江西中联建设集团有限公司 Template construction device is hung in a kind of ater-casting

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110210166A (en) * 2019-06-14 2019-09-06 上海宝冶集团有限公司 A kind of prefabricated superimposed sheet method for splitting
CN110210166B (en) * 2019-06-14 2023-04-18 上海宝冶集团有限公司 Splitting method for prefabricated laminated slab

Similar Documents

Publication Publication Date Title
WO2022160388A1 (en) Fabricated concrete beam-column joint and construction method therefor
CN102296810A (en) Deformation joint template support structure and construction method thereof
CN209369051U (en) A kind of pre-embedded device in concrete
CN210658721U (en) Concrete embedded part
CN107060323B (en) A kind of pulling-on piece structure aluminum alloy mould plate early tears system and construction method open
CN109057337A (en) The area prefabricated concrete structure Hou Jiao construction method
CN203795825U (en) Scaffold and wall connector and scaffold and wall connecting structure
CN204676885U (en) A kind of steel concrete column template fast pacifies the system of tearing open
CN209799022U (en) semicircular bolt clamping ring component
CN208777720U (en) Wall hangs the detachable straight thread reinforced bar pedestal of mould diagonal brace
CN217079684U (en) Split type form removal-free concrete hollow structure
CN215671022U (en) Pre-embedded type mounting device for aluminum alloy template
CN215443119U (en) ALC wallboard entrance to a cave pouring structure
CN212002217U (en) A template subassembly for secondary structure pouring construction
CN210002866U (en) Quick mounting and dismounting shaping template for pouring settlement joint shear wall
CN210134642U (en) Column corner template suitable for assembly type building
CN211622573U (en) Aluminum alloy template reinforcing system for standard floor full cast-in-place stair pouring
CN103216087B (en) A kind of two-way self-bearing type construction formwork system
CN210288775U (en) Monolithic wall prefabricated part with template
KR19990035156U (en) for construction mold fixing equipment
CN215926756U (en) Assembled aluminum film screw plug device
CN218375271U (en) Formwork support frame
CN203808544U (en) Concrete defect repairing formwork
CN214575760U (en) General base of floor formwork
CN210713787U (en) A building steel form for strutting wall body and pour

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221

RJ01 Rejection of invention patent application after publication