CN109024113B - 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法 - Google Patents

一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法 Download PDF

Info

Publication number
CN109024113B
CN109024113B CN201811192711.8A CN201811192711A CN109024113B CN 109024113 B CN109024113 B CN 109024113B CN 201811192711 A CN201811192711 A CN 201811192711A CN 109024113 B CN109024113 B CN 109024113B
Authority
CN
China
Prior art keywords
steel
rail
track panel
assembling
short sleeper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811192711.8A
Other languages
English (en)
Other versions
CN109024113A (zh
Inventor
龚楠富
***
周琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN201811192711.8A priority Critical patent/CN109024113B/zh
Publication of CN109024113A publication Critical patent/CN109024113A/zh
Application granted granted Critical
Publication of CN109024113B publication Critical patent/CN109024113B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/16Transporting, laying, removing, or replacing rails; Moving rails placed on sleepers in the track
    • E01B29/17Lengths of rails assembled into strings, e.g. welded together

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

本发明公开了一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法,包括钢轨及扣配件组装台位和轨排框架短轨枕组装台位,钢轨及扣配件组装台位和轨排框架短轨枕组装台位均固定连接在硬化地面上且保持平行安装,钢轨及扣配件组装台位包括四根P60‑25m钢轨,四根P60‑25m钢轨两两并排成股安放,股间间距为1.5m,四根P60‑25m钢轨上表面设置有多排扣件安放油漆标识,轨排框架短轨枕组装台位包括四个钢支凳,四个钢支凳纵向间隔均匀布置,四个钢支凳纵向对应的地面上设置有间隔均匀的多个轨枕安放油漆标识。本发明方便了人工操作,提高了轨排拼装效率,单个25m轨排拼装时间可在2个小时内完成,重点解决了轨排拼装效率低的问题。

Description

一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法
技术领域
本发明属于地铁轨道工程铺轨施工领域,具体涉及一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法。
背景技术
轨排拼装作为地铁轨道施工的重要工序,其施工效率及拼装精度对后期工序影响巨大。以往的轨排拼装,是直接将轨枕按设计尺寸均匀摆放在平整的硬化地坪上,再安装钢轨及扣配件,每次需要用长钢尺拉尺,在钢轨上先标识出扣件安装位置,因轨枕间距位置调整工作量大,轨排几何尺寸精度不易控制,造成轨排拼装效率较低,一个25m短轨枕轨排成品拼装耗时约三个小时。
发明内容
本发明解决的技术问题是:提供一种地铁25m钢轨短轨枕轨排拼装台位***,方便人工操作,从而提高轨排拼装效率及提高轨排几何尺寸的精度。
本发明采取的技术方案为:一种地铁25m钢轨短轨枕轨排拼装台位***,包括钢轨及扣配件组装台位和轨排框架短轨枕组装台位,钢轨及扣配件组装台位和轨排框架短轨枕组装台位均固定连接在硬化地面上且保持平行安装,钢轨及扣配件组装台位包括四根P60-25m钢轨,四根P60-25m钢轨两两并排成股安放,股间间距为1.5m,四根P60-25m钢轨上表面设置有多排扣件安放油漆标识,轨排框架短轨枕组装台位包括四个钢支凳,四个钢支凳纵向间隔均匀布置,四个钢支凳纵向对应的地面上设置有间隔均匀的多个轨枕安放油漆标识。
优选的,上述钢支凳包括横梁和槽钢支腿,横梁两端安装有槽钢支腿。
优选的,上述四个钢支凳上表面纵向对应位置设置有钢轨限位槽,钢轨限位槽采用两钢筋条对称焊接在钢支凳上表面。
优选的,上述槽钢支腿采用两槽钢条对称焊接在横梁上,两槽钢条呈喇叭状结构。
优选的,上述两槽钢条上焊接有加强筋。
优选的,上述两两靠近放置的P60-25m钢轨采用地脚螺栓和扣板固定连接在地面上。
一种地铁25m钢轨短轨枕轨排拼装台位***的组装方法,该方法包括以下步骤:
1)先在钢轨及扣配件组装台位上的扣件安放油漆标识上摆放铁垫板和轨下橡胶垫,吊运两条25m钢轨至摆放好的铁垫板上,调节铁垫板位置并安装轨距块及弹条、轨距拉杆形成轨排框架;
2)将设定数量的短轨枕摆放在轨排框架短轨枕组装台位上的轨枕安放油漆标识,吊装轨排框架至轨排框架短轨枕组装台位的限位槽上,通过钢支凳支撑轨排框架,钢支凳顶面高度高于轨枕+扣件组合高度2至3cm,轨排框架扣件位置调整轨枕位置,安装轨枕连接锚固螺栓形成成品轨排。
本发明的有益效果:与现有技术相比,本发明的效果如下:
1)在钢轨、扣配件组装成轨排框架时,每个25m轨排扣配件安装位置按台位***上的标识位置精确摆放,省去了扣配件摆放间距的重复拉尺定位工序,简化了安装工序,方便了人工操作,能减少扣件及轨枕的后期调整工作量,提高组装轨枕后轨***度;
2)轨排框架放置于钢支凳上,且钢支凳顶面高度约高于轨枕+扣件组合高度,易于轨枕位置的挪动和调整,同时也易于短轨枕锚固螺栓的安装;
综上所述,采用本发明的地铁25m钢轨短轨枕轨排拼装台位***,方便了人工操作,提高了轨排拼装效率,单个25m轨排拼装时间可在2个小时内完成,重点解决了轨排拼装效率低的问题。
附图说明
图1是本发明的结构示意图;
图2是本发明的钢支腿结构示意图;
图3是图2的左视结构示意图;
图4是钢轨及扣配件组装台位截面结构示意图。
具体实施方式
下面结合附图及具体的实施例对本发明进行进一步介绍。
实施例1:如图1-图4所示,一种地铁25m钢轨短轨枕轨排拼装台位***,包括钢轨及扣配件组装台位1和轨排框架短轨枕组装台位2,钢轨及扣配件组装台位1和轨排框架短轨枕组装台位2均固定连接在硬化地面3上且保持平行安装,钢轨及扣配件组装台位1包括四根P60-25m钢轨101,四根P60-25m钢轨101两两并排成股安放,股间间距为1.5m,四根P60-25m钢轨101上表面设置有多排扣件安放油漆标识102,以便于扣配件快速准确摆放,轨排框架短轨枕组装台位2包括四个钢支凳201,四个钢支凳201纵向间隔均匀布置,四个钢支凳201纵向对应的地面上设置有间隔均匀的多个轨枕安放油漆标识202,以便于轨枕快速准确摆放,四个钢支凳201按5m间距布置。
优选的,上述钢支凳201包括横梁203和槽钢支腿204,横梁203两端安装有槽钢支腿204,横梁采用24kg/m钢轨,长2.5m,支腿采用12.6号槽钢,支腿与横梁焊接,横梁顶面高度高于轨枕+扣件组合高度2至3cm,易于轨枕位置的挪动和调整,同时也易于轨枕锚固螺栓的安装。
优选的,上述四个钢支凳201上表面纵向对应位置设置有钢轨限位槽205,钢轨限位槽205采用两钢筋条对称焊接在钢支凳201上表面。
优选的,上述槽钢支腿204采用两槽钢条对称焊接在横梁203上,两槽钢条呈喇叭状结构。
优选的,上述两槽钢条上焊接有加强筋206。
优选的,上述两两靠近放置的P60-25m钢轨101采用地脚螺栓103和扣板104固定连接在地面上,地脚螺栓布置间距5m,采用地脚螺栓和扣板能够对钢轨限位,防止钢轨滑移。
实施例2:一种地铁25m钢轨短轨枕轨排拼装台位***的组装方法,该方法包括以下步骤:
1)先在钢轨及扣配件组装台位上的扣件安放油漆标识上摆放铁垫板和轨下橡胶垫,吊运两条25m钢轨至摆放好的铁垫板上,调节铁垫板位置并安装轨距块及弹条、轨距拉杆形成轨排框架;
2)将设定数量的短轨枕摆放在轨排框架短轨枕组装台位上的轨枕安放油漆标识,吊装轨排框架至轨排框架短轨枕组装台位的限位槽上,通过钢支凳支撑轨排框架,钢支凳顶面高度高于轨枕+扣件组合高度2至3cm,轨排框架扣件位置调整轨枕位置,安装轨枕连接锚固螺栓形成成品轨排。
以上所述,仅为本发明的具体实施方式实例,本发明的保护范围并不局限于此。熟悉该技术领域的技术人员在本发明揭露的技术范围内,可轻易找到变化或替换方式,这些都应涵盖在本发明的保护范围之内。为此,本发明的保护范围应以所述权利要求的保护范围为准。

Claims (4)

1.一种地铁25m钢轨短轨枕轨排拼装台位***,其特征在于:包括钢轨及扣配件组装台位(1)和轨排框架短轨枕组装台位(2),钢轨及扣配件组装台位(1)和轨排框架短轨枕组装台位(2)均固定连接在硬化地面(3)上且保持平行安装,钢轨及扣配件组装台位(1)包括四根P60-25m钢轨(101),四根P60-25m钢轨(101)两两并排成股安放,股间间距为1.5m,四根P60-25m钢轨(101)上表面设置有多排扣件安放油漆标识(102),轨排框架短轨枕组装台位(2)包括四个钢支凳(201),四个钢支凳(201)纵向间隔均匀布置,四个钢支凳(201)纵向对应的地面上设置有间隔均匀的多个轨枕安放油漆标识(202);钢支凳(201)包括横梁(203)和槽钢支腿(204),横梁(203)两端安装有槽钢支腿(204);四个钢支凳(201)上表面纵向对应位置设置有钢轨限位槽(205),钢轨限位槽(205)采用两钢筋条对称焊接在钢支凳(201)上表面;一种地铁25m钢轨短轨枕轨排拼装台位***的组装方法包括以下步骤:
1)先在钢轨及扣配件组装台位上的扣件安放油漆标识上摆放铁垫板和轨下橡胶垫,吊运两条25m钢轨至摆放好的铁垫板上,调节铁垫板位置并安装轨距块及弹条、轨距拉杆形成轨排框架;
2)将设定数量的短轨枕摆放在轨排框架短轨枕组装台位上的轨枕安放油漆标识,吊装轨排框架至轨排框架短轨枕组装台位的限位槽上,通过钢支凳支撑轨排框架,钢支凳顶面高度高于轨枕+扣件组合高度2至3cm,轨排框架扣件位置调整轨枕位置,安装轨枕连接锚固螺栓形成成品轨排。
2.根据权利要求1所述的一种地铁25m钢轨短轨枕轨排拼装台位***,其特征在于:槽钢支腿(204)采用两槽钢条对称焊接在横梁(203)上,两槽钢条呈喇叭状结构。
3.根据权利要求2所述的一种地铁25m钢轨短轨枕轨排拼装台位***,其特征在于:两槽钢条上焊接有加强筋(206)。
4.根据权利要求1所述的一种地铁25m钢轨短轨枕轨排拼装台位***,其特征在于:两两靠近放置的P60-25m钢轨(101)采用地脚螺栓(103)和扣板(104)固定连接在地面上。
CN201811192711.8A 2018-10-13 2018-10-13 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法 Active CN109024113B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811192711.8A CN109024113B (zh) 2018-10-13 2018-10-13 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811192711.8A CN109024113B (zh) 2018-10-13 2018-10-13 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法

Publications (2)

Publication Number Publication Date
CN109024113A CN109024113A (zh) 2018-12-18
CN109024113B true CN109024113B (zh) 2024-01-23

Family

ID=64612880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811192711.8A Active CN109024113B (zh) 2018-10-13 2018-10-13 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法

Country Status (1)

Country Link
CN (1) CN109024113B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU204311U1 (ru) * 2021-02-05 2021-05-19 Акционерное Общество "Комплексное Сервисное Обслуживание Пути" Закладная деталь с радиометкой для записи идентификационных данных железобетонных шпал и брусьев стрелочных переводов

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH700828B1 (de) * 2010-06-16 2010-10-29 Arge Fahrbahn Transtec Gotthard Verfahren zum Erstellen eines Gleises für Schienenfahrzeuge auf oder in einem kanalförmigen Betontrassee.
CN202509351U (zh) * 2012-03-29 2012-10-31 中铁十一局集团有限公司 一种用于双块式轨排组装的轨枕定位装置
DE202013005289U1 (de) * 2013-06-12 2013-09-12 Easyrailtech Kg Anordnung zur Herstellung eines Oberbaus eines Schienenfahrbahnwegs
CN103696333A (zh) * 2013-12-25 2014-04-02 中铁五局(集团)有限公司 一种双块式无砟轨道道床施工使用的框架轨排及制造方法
CN205474636U (zh) * 2015-12-31 2016-08-17 上海市安装工程集团有限公司 一种f型轨排的线型定位装置
CN206298793U (zh) * 2016-11-30 2017-07-04 中铁十八局集团第五工程有限公司 一种隧道内弹性支承块式无砟轨道匀枕组装平台
CN107165005A (zh) * 2017-05-06 2017-09-15 中铁五局集团有限公司 一种确保轨道几何状态的双块式框架轨排组装装置及方法
CN206581089U (zh) * 2017-02-06 2017-10-24 中国水利水电第十三工程局有限公司 一种新型地铁施工轨排拼装平台
CN107313313A (zh) * 2017-05-25 2017-11-03 中国铁道科学研究院铁道建筑研究所 预制聚氨酯固化道床的排架施工方法
CN206858973U (zh) * 2017-05-06 2018-01-09 中铁五局集团有限公司 一种确保轨道几何状态的双块式框架轨排组装装置
CN208949660U (zh) * 2018-10-13 2019-06-07 中铁五局集团第六工程有限责任公司 一种地铁25m钢轨短轨枕轨排拼装台位***

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH700828B1 (de) * 2010-06-16 2010-10-29 Arge Fahrbahn Transtec Gotthard Verfahren zum Erstellen eines Gleises für Schienenfahrzeuge auf oder in einem kanalförmigen Betontrassee.
CN202509351U (zh) * 2012-03-29 2012-10-31 中铁十一局集团有限公司 一种用于双块式轨排组装的轨枕定位装置
DE202013005289U1 (de) * 2013-06-12 2013-09-12 Easyrailtech Kg Anordnung zur Herstellung eines Oberbaus eines Schienenfahrbahnwegs
CN103696333A (zh) * 2013-12-25 2014-04-02 中铁五局(集团)有限公司 一种双块式无砟轨道道床施工使用的框架轨排及制造方法
CN205474636U (zh) * 2015-12-31 2016-08-17 上海市安装工程集团有限公司 一种f型轨排的线型定位装置
CN206298793U (zh) * 2016-11-30 2017-07-04 中铁十八局集团第五工程有限公司 一种隧道内弹性支承块式无砟轨道匀枕组装平台
CN206581089U (zh) * 2017-02-06 2017-10-24 中国水利水电第十三工程局有限公司 一种新型地铁施工轨排拼装平台
CN107165005A (zh) * 2017-05-06 2017-09-15 中铁五局集团有限公司 一种确保轨道几何状态的双块式框架轨排组装装置及方法
CN206858973U (zh) * 2017-05-06 2018-01-09 中铁五局集团有限公司 一种确保轨道几何状态的双块式框架轨排组装装置
CN107313313A (zh) * 2017-05-25 2017-11-03 中国铁道科学研究院铁道建筑研究所 预制聚氨酯固化道床的排架施工方法
CN208949660U (zh) * 2018-10-13 2019-06-07 中铁五局集团第六工程有限责任公司 一种地铁25m钢轨短轨枕轨排拼装台位***

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卢朋、刘新社主编.《铁路工程铺架技术与管理》.中国铁道出版社,2007,第99页. *

Also Published As

Publication number Publication date
CN109024113A (zh) 2018-12-18

Similar Documents

Publication Publication Date Title
CN102785290B (zh) 一种先张法预应力u形梁用穿心牵引式台座及其施工方法
CN103255718A (zh) 一种先张法板梁轨道移动式钢横梁整体张拉装置与张拉工艺
CN203783165U (zh) 预埋件多方位精确调节装置
CN109024113B (zh) 一种地铁25m钢轨短轨枕轨排拼装台位***和组装方法
CN208949660U (zh) 一种地铁25m钢轨短轨枕轨排拼装台位***
CN203188130U (zh) 预应力反张拉预压牛腿式鹰架支撑装置
CN101837916A (zh) 电梯上曳引机机架水平度的调节装置
CN106738308A (zh) 预制t梁钢筋胎模架***
CN204160621U (zh) 用于预制装配式混凝土构件的不锈钢整板模台
CN203792305U (zh) 一种快速调平t型槽地轨装置
CN216505886U (zh) 一种可调节的预制t梁腹板钢筋胎架
CN103448883B (zh) 一种滑道井字梁安装导向与临时固定装置
CN207088114U (zh) 一种双向先张法预应力混凝土轨道板模型
CN202793750U (zh) 制动器液压升降试验平台
CN211142837U (zh) 一种波形钢腹板梁齿块钢筋绑扎胎具
CN107313444B (zh) 一种双滑轨梁式重物移位装置及移位方法
CN210082067U (zh) 一种多用型t梁台座结构
CN210587848U (zh) 一种预制混凝土构件生产线模台自动焊接设备
CN203792513U (zh) 一种批量生产预应力空心板梁的施工设施
CN207888895U (zh) 先张法预应力混凝土轨道板生产线放张***
CN109459224B (zh) 考虑盾构隧道横向性能的环间接头试验装置及安装方法
CN105034163A (zh) 一种t梁钢筋标准节生产绑扎装置
CN103556835B (zh) 一种楼板台车
CN107130981B (zh) 一种针梁式全圆钢模台车安装方法
CN217991364U (zh) 一种门架式曲面焊接***的调平装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant