CN109020151A - Intelligent watercourse sewage disposal system and method - Google Patents

Intelligent watercourse sewage disposal system and method Download PDF

Info

Publication number
CN109020151A
CN109020151A CN201811123187.9A CN201811123187A CN109020151A CN 109020151 A CN109020151 A CN 109020151A CN 201811123187 A CN201811123187 A CN 201811123187A CN 109020151 A CN109020151 A CN 109020151A
Authority
CN
China
Prior art keywords
sludge
band
recycling
locellus
collecting tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811123187.9A
Other languages
Chinese (zh)
Other versions
CN109020151B (en
Inventor
蔡小春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Huazhen Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811123187.9A priority Critical patent/CN109020151B/en
Publication of CN109020151A publication Critical patent/CN109020151A/en
Application granted granted Critical
Publication of CN109020151B publication Critical patent/CN109020151B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F11/00Treatment of sludge; Devices therefor
    • C02F11/12Treatment of sludge; Devices therefor by de-watering, drying or thickening
    • C02F11/121Treatment of sludge; Devices therefor by de-watering, drying or thickening by mechanical de-watering
    • C02F11/123Treatment of sludge; Devices therefor by de-watering, drying or thickening by mechanical de-watering using belt or band filters
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F11/00Treatment of sludge; Devices therefor
    • C02F11/008Sludge treatment by fixation or solidification

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Treatment Of Sludge (AREA)

Abstract

The invention discloses a kind of Intelligent watercourse sewage disposal system and method, system therein includes two frames being set side by side, and one end is set as aqueduct between two frames, and other end is set as Efferent tube;One end of aqueduct is connected to sedimentation basin and is output to purification pot by pipeline for being connected to river, one end of Efferent tube;Several spoil disposal assemblies are set gradually on above-mentioned frame and between aqueduct and Efferent tube, wherein spoil disposal assembly includes the sludge band for driving sludge, sludge bar for stopping to sludge and being oriented to, for collecting and handling the sludge curing device of sludge, wherein each sludge band sludge bar is that horizontally disposed and horizontal plane is identical as horizontal plane where aqueduct or Efferent tube, one end of sludge band is located at two sludge curing devices of setting on frame, sludge bar is arranged in two the intermediate of sludge curing device, the invention also discloses the river sewage processing methods using above system, it may be implemented to recycle in sludge tiling to sludge band.

Description

Intelligent watercourse sewage disposal system and method
Technical field
The present invention relates to river sewage preprocessing technical field, especially a kind of Intelligent watercourse sewage disposal system vdiverse in function And method.
Background technique
Sewage in Intelligent watercourse sewage, that is, river, there are many factories for most of river two sides, there is a large amount of waste water daily It is discharged into canal, solid suspension in water body, organic matter, heavy metal and phenol, cyanide equal size is made to substantially exceed ground water quality standard, In addition to this, river sewage requires the processing for carrying out sludge per se with many sludge before handling river sewage, Traditional technology majority the methods of is excavated using bottom and is cleared up sludge, however very extensive treated the river of this mode The content of road sewage sludge is still very much, it would be highly desirable to which one kind is for fining and efficient sewage treatment in river sewage Treatment of Sludge Technique.
Summary of the invention
The technical solution adopted by the present invention to solve the technical problems is: system of the invention includes two and is set side by side Frame, one end is set as aqueduct between two frames, and other end is set as Efferent tube;One end of aqueduct is for being connected to river Road, one end of Efferent tube are connected to sedimentation basin and are output to purification pot by pipeline;On above-mentioned frame and be located at aqueduct with Several spoil disposal assemblies are set gradually between Efferent tube, wherein spoil disposal assembly includes for driving the sludge band of sludge, for dirt Mud stops and the sludge bar of guiding, the sludge curing device for collecting and handling sludge, wherein each sludge band sludge bar It is that horizontally disposed and horizontal plane is identical as horizontal plane where aqueduct or Efferent tube, one end of sludge band, which is located on frame, is arranged two Sludge bar is arranged in a sludge curing device, two the intermediate of sludge curing device.
Further, it further includes being used to provide power that sludge bar, which includes the rubber item for being stopped to sludge and being oriented to, Push rod between self-powered wheel and connection self-powered wheel wheel shaft, rubber item.
Further, sludge curing device includes the interim collecting tank that sludge is arranged in and is used to collect sludge with side, temporarily Slot movable plate is arranged in the collection port two sides of collecting tank, and the fixed adsorption pump of interim collecting tank inner wall, adsorption pump is connected to solid by pipeline Cured plate is arranged in the outlet for changing mould and curing mold.
Further, sludge band includes two flexible endless belt fixed strips, two for driving the drive with fixed strip Driving wheel, setting band basal plane between two band fixed strips;Driving wheel is used to drive the periphery with fixed strip and with basal plane that convex-concave is arranged Correspondingly concave-convex ditch is arranged with the side that basal plane is contacted with convex-concave ditch in ditch.
Further, sludge recycling band is arranged in parallel in the side of frame and frame, and the output end that sludge recycles band is connected to sludge Recovery room, sludge recycling band is divided into the first recycling point band side by side, the second recycling point band, third recycling point band, the 4th recycling divide band, Interim collecting tank is connected to by ladder conveyer belt and is output to sludge recycling band top.
Further, several spoil disposal assemblies are categorized into four kinds of gradients according to the distance in distance input road, wherein first gradient The interim collecting tank of spoil disposal assembly be connected to by ladder conveyer belt and be output to the first recycling point band top, the row of the second gradient The interim collecting tank of mud assembly is connected to by ladder conveyer belt and is output to the second recycling point band top, and the spoil disposal of 3rd gradient is total At interim collecting tank be connected to by ladder conveyer belt and be output to third recycling point band a top, the spoil disposal assembly of 4th gradient Interim collecting tank is connected to by ladder conveyer belt and is output to the 4th recycling point band top;Sludge recovery room sludge recovery room includes First recycling locellus, the second recycling locellus, third recycling locellus, the 4th recycling four regions of locellus, the first recycling point band, second Recycling point band, third recycling point band, the 4th recycling divide band to be respectively communicated with the first recycling locellus, the second recycling locellus, third recycling Locellus, the 4th recycling locellus.
The method comprise the steps that step S1, river sewage are discharged into after slowing down by aqueduct share split, and according to week If the phase is that the time sequencing share split of t flows through dewatered sludge band;Step S2, river sewage is discharged from sludge band and is drained into Efferent tube; Step S3, river sewage is drained into sedimentation basin by Efferent tube and completes deposition;Step S4, river sewage is drained into purification by sedimentation basin Tank carries out purification filtering;Step S5, drive wheel transports sludge to outer end and by the rubber item of self-powered wheel drive with basal plane Sludge is pushed into sludge curing device, completes solidification.
Further, in step S5, sludge is first pushed into interim collecting tank by rubber item, and then adsorption pump adsorbs sludge and is pumped into Solidification board placing is discharged to after completing solidification to curing mold.
In step s 5, sludge is first pushed into interim collecting tank by rubber item, is then divided sludge by several ladder conveyer belts Not transporting to the first recycling point band, the second recycling point band, third recycling divides band and the 4th to recycle and divide band, the first recycling point band, the Two recycling point bands, third recycling divide band and the 4th recycling that band is divided respectively to transport sludge to the first recycling locellus, the second recycling point Room, third recycling locellus and the 4th recycling locellus complete solidification.
The invention has the advantages that river sewage is discharged into after slowing down by aqueduct share split in the present invention, and press If the time sequencing share split according to the period flows through dewatered sludge band, may be implemented to recycle in sludge tiling to sludge band, and Sludge is also different to the distance on sludge band since density difference tiles, by the different densities that tile on different far and near sludge bands Sludge, the present invention, which can classify the sludge of different densities, to be recycled;The present invention can be cured in recycling sludge with sludge curing Sludge afterwards is readily transported the bottom material that can also do other products.
Detailed description of the invention
Fig. 1 is the example structure schematic diagram of present system.
Fig. 2 is the structural schematic diagram of spoil disposal assembly embodiment.
Fig. 3 is structural schematic diagram of the sludge with embodiment.
Fig. 4 is the present invention in structural schematic diagram of the sludge recycling with connection place embodiment.
Fig. 5 is the present invention in structural schematic diagram of the sludge recycling with connection place embodiment.
Fig. 6 is the present invention in sludge recycling band, the structural schematic diagram of sludge recovery room connection place embodiment.
In figure:
1 aqueduct;
2 frames;
3 Efferent tubes;
4 sedimentation basins;
5 purification pots;
6 spoil disposal assemblies;
7 ladder conveyer belts;
8 sludge recycle band;
9 sludge recovery rooms;
6a sludge band;
6b sludge bar;
6c sludge curing device;
6a1 band basal plane;
6a2 driving wheel;
6a3 bumps ditch;
6a4 convex-concave ditch;
6a5 band fixed strip;
6b1 self-powered wheel;
6b2 push rod;
6b3 rubber item;
The interim collecting tank of 6c1;
6c2 slot movable plate;
6c3 adsorption pump;
6c4 curing mold;
6c5 cured plate;
The recycling of 8a first divides band;
The recycling of 8b second divides band;
The recycling of 8c third divides band;
The recycling of 8d the 4th divides band;
9a first recycles locellus;
9b second recycles locellus;
9c third recycles locellus;
9d the 4th recycles locellus.
Specific embodiment
In embodiment, such as Fig. 1, system of the invention includes two frames being set side by side 2, one between two frames 2 End is set as aqueduct 1, and other end is set as Efferent tube 3;One end of aqueduct 1 is for being connected to river, one end of Efferent tube 3 It is connected to sedimentation basin 4 and purification pot 5 is output to by pipeline;On above-mentioned frame 2 and between aqueduct 1 and Efferent tube 3 Several spoil disposal assemblies 6 are set gradually, as shown in Fig. 2, wherein spoil disposal assembly 6 includes for driving the sludge band 6a of sludge, being used for Sludge bar 6b, the sludge curing device 6c for collecting and handling sludge that sludge is stopped and is oriented to, wherein each sludge band Sludge bar 6a is that horizontally disposed and horizontal plane is identical as aqueduct 1 or 3 place horizontal plane of Efferent tube, one end position of the sludge with 6a In two sludge curing device 6c are arranged on frame 2, sludge bar 6b is arranged in two the intermediate of sludge curing device 6c;Sludge bar 6b includes that the rubber 6b3 for being stopped to sludge and being oriented to further includes the self-powered wheel 6b1 being used to provide power and connection Push rod 6b2 between self-powered wheel 6b1 wheel shaft, rubber 6b3;Sludge curing device 6c includes that setting is used in the sludge band side 6a In the collection port two sides of the interim collecting tank 6c1 for collecting sludge, interim collecting tank 6c1, slot movable plate 6c2, interim collecting tank are set 6c1 inner wall fixes adsorption pump 6c3, and solidification is arranged by the outlet that pipeline is connected to curing mold 6c4 and curing mold 6c4 in adsorption pump 6c3 Plate 6c5.
Again as shown in figure 3, sludge band 6a is used to drive band including two flexible endless belt fixed strip 6a5, two Setting band basal plane 6a1 between the driving wheel 6a2, two band fixed strip 6a5 of fixed strip 6a5;Driving wheel 6a2 is for driving band fixed Convex-concave ditch 6a4 is arranged in 6a5 and periphery with basal plane 6a1, is correspondingly arranged with the side that basal plane 6a1 is contacted with convex-concave ditch 6a4 Concave-convex ditch 6a3.
Again as illustrated in figures 4-5, sludge recycling band 8 is arranged in parallel in the side of frame 2 and frame 2, and sludge recycles the output of band 8 End connection sludge recovery room 9, sludge recycling band 8 are divided into the first recycling point band 8a, the second recycling point band 8b, third side by side and recycle Divide to pass through the connection of ladder conveyer belt 7 with 8c, the 4th recycling point band a 8d, interim collecting tank 6c1 and be output to sludge and recycle on band 8 Portion;Several spoil disposal assemblies 6 are categorized into four kinds of gradients according to the distance in distance input road 1, wherein the spoil disposal assembly 6 of first gradient Interim collecting tank 6c1 be connected to by ladder conveyer belt 7 and be output to the first recycling point band top 8a, the spoil disposal of the second gradient is total It is connected at 6 interim collecting tank 6c1 by ladder conveyer belt 7 and is output to the second recycling point band top 8b, the row of 3rd gradient The interim collecting tank 6c1 of mud assembly 6 is connected to by ladder conveyer belt 7 and is output to the third recycling point band top 8c, 4th gradient Spoil disposal assembly 6 interim collecting tank 6c1 by ladder conveyer belt 7 be connected to and be output to the 4th recycling point band the top 8d.
Again as shown in fig. 6,9 sludge recovery room of sludge recovery room includes the first recycling locellus 9a, the second recycling locellus 9b, the Three recycling locellus 9c, the 4th recycling tetra- regions locellus 9d, the first recycling point band 8a, the second recycling point band 8b, third recycling point Band 8c, the 4th recycling point band 8d are respectively communicated with the first recycling locellus 9a, the second recycling locellus 9b, third recycling locellus 9c, the 4th Recycle locellus 9d.
As known by the technical knowledge, the present invention can pass through the embodiment party of other essence without departing from its spirit or essential feature Case is realized.Embodiment disclosed above, in all respects are merely illustrative, not the only.It is all this It is included in the invention in invention scope or in the change being equal in the scope of the present invention.
The method comprise the steps that step S1, river sewage are discharged into after slowing down by 1 share split of aqueduct, and according to If the time sequencing share split that the period is t flows through dewatered sludge band 6a;
Step S2, river sewage is discharged from sludge band 6a and is drained into Efferent tube 3;
Step S3, river sewage is drained into sedimentation basin 4 by Efferent tube 3 and completes deposition;
Step S4, river sewage is drained into purification pot 5 by sedimentation basin 4 and carries out purification filtering;
Step S5, driving wheel 6a2 driving transports sludge to outer end and by the rubber 6b3 of self-powered wheel 6b1 driving with basal plane 6a1 Sludge is pushed into sludge curing device 6c, completes solidification.
Specifically, in step S5, sludge is first pushed into interim collecting tank 6c1 by rubber 6b3, and then adsorption pump 6c3 is adsorbed Sludge is simultaneously pumped into after curing mold 6c4 completes solidification and is discharged to cured plate 6c5 and puts;In step s 5, rubber 6b3 first will be dirty Mud is pushed into interim collecting tank 6c1, is then transported sludge respectively by several ladder conveyer belts 7 to the first recycling point band 8a, second Recycling point band 8b, the third recycling point recycling point band of band 8c and the 4th 8d, the first recycling point band 8a, the second recycling point band 8b, third The recycling point recycling point band of band 8c and the 4th 8d respectively transports sludge to the first recycling locellus 9a, the second recycling locellus 9b, third It recycles the recycling of locellus 9c and the 4th locellus 9d and completes solidification.

Claims (9)

1. a kind of Intelligent watercourse sewage disposal system, which is characterized in that the frame being set side by side including two, between two frames One end is set as aqueduct, and other end is set as Efferent tube;One end of aqueduct connects for being connected to river, one end of Efferent tube Lead to sedimentation basin and purification pot is output to by pipeline;It is set gradually on above-mentioned frame and between aqueduct and Efferent tube Several spoil disposal assemblies, wherein spoil disposal assembly includes for driving the sludge band of sludge, for sludge sludge blocking and be oriented to Bar, the sludge curing device for collecting and handling sludge, wherein each sludge band sludge bar is horizontally disposed and horizontal plane Identical as horizontal plane where aqueduct or Efferent tube, one end of sludge band, which is located on frame, is arranged two sludge curing devices, and two Sludge bar is arranged in the intermediate of a sludge curing device.
2. a kind of Intelligent watercourse sewage disposal system according to claim 1, which is characterized in that sludge bar include for pair Sludge stopped and the rubber item that is oriented to further include the self-powered wheel being used to provide power and connection self-powered wheel wheel shaft, rubber item it Between push rod.
3. a kind of Intelligent watercourse sewage disposal system according to claim 1, which is characterized in that sludge curing device includes The interim collecting tank that sludge is used to collect sludge with side is set, slot movable plate is arranged in the collection port two sides of interim collecting tank, Cured plate is arranged by the outlet that pipeline is connected to curing mold and curing mold in the interim fixed adsorption pump of collecting tank inner wall, adsorption pump.
4. a kind of Intelligent watercourse sewage disposal system according to claim 1, which is characterized in that sludge band includes two tools Flexible endless belt fixed strip, two for drive the driving wheel with fixed strip, setting is with basal plane between two band fixed strips; Driving wheel is used to drive the periphery with fixed strip and with basal plane that convex-concave ditch, the side correspondingly contacted with basal plane with convex-concave ditch is arranged Concave-convex ditch is set.
5. a kind of Intelligent watercourse sewage disposal system according to claim 1, which is characterized in that the side of frame and frame Sludge recycling band is arranged in parallel, the output end that sludge recycles band is connected to sludge recovery room, and sludge recycling band is divided into first time side by side Contracture band, the second recycling point band, third recycling point band, the 4th recycling divide band, and interim collecting tank is connected to simultaneously by ladder conveyer belt It is output to sludge recycling band top.
6. a kind of Intelligent watercourse sewage disposal system according to claim 1, which is characterized in that press several spoil disposal assemblies Distance of the range from aqueduct is categorized into four kinds of gradients, and wherein the interim collecting tank of the spoil disposal assembly of first gradient is defeated by ladder It send band to be connected to and is output to the first recycling point band top, the interim collecting tank of the spoil disposal assembly of the second gradient passes through ladder conveyer belt It is connected to and is output to the second recycling point band top, the interim collecting tank of the spoil disposal assembly of 3rd gradient is connected to by ladder conveyer belt And it is output to a third recycling point band top, the interim collecting tank of the spoil disposal assembly of 4th gradient is connected to and defeated by ladder conveyer belt Out to the 4th recycling point band top;Sludge recovery room sludge recovery room includes the first recycling locellus, the second recycling locellus, third time Contracture room, the 4th recycling four regions of locellus, the first recycling point band, the second recycling point band, third recycling point band, the 4th recycling point Band is respectively communicated with the first recycling locellus, the second recycling locellus, third recycling locellus, the 4th recycling locellus.
7. a kind of Intelligent watercourse sewage water treatment method using any system of claim 1-6 characterized by comprising Step S1, river sewage is discharged into after slowing down by aqueduct share split, and if flowing through according to the time sequencing share split that the period is t Dewatered sludge band;Step S2, river sewage is discharged from sludge band and is drained into Efferent tube;Step S3, river sewage is arranged by Efferent tube Enter to sedimentation basin and completes to deposit;Step S4, river sewage is drained into purification pot by sedimentation basin and carries out purification filtering;Step S5, it drives Sludge is transported to outer end with basal plane and sludge is pushed into sludge curing device by the rubber item of self-powered wheel drive by driving wheel driving, complete At solidification.
8. a kind of Intelligent watercourse sewage water treatment method according to claim 7, which is characterized in that in step S5, rubber item Sludge is first pushed into interim collecting tank, then adsorption pump, which adsorbs sludge and is pumped into after curing mold completes solidification, is discharged to cured plate It puts.
9. a kind of Intelligent watercourse sewage water treatment method according to claim 7, which is characterized in that in step s 5, rubber Sludge is first pushed into interim collecting tank by item, is then transported sludge respectively by several ladder conveyer belts to the first recycling point band, the Two recycling point bands, third recycling divide band and the 4th recycling divides band, and the first recycling point band, the second recycling divide band, third recycling to divide band Band is divided respectively to transport sludge to the first recycling locellus, the second recycling locellus, third recycling locellus and the 4th time with the 4th recycling Complete solidification in contracture room.
CN201811123187.9A 2018-09-26 2018-09-26 Intelligent river sewage treatment system and method Active CN109020151B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811123187.9A CN109020151B (en) 2018-09-26 2018-09-26 Intelligent river sewage treatment system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811123187.9A CN109020151B (en) 2018-09-26 2018-09-26 Intelligent river sewage treatment system and method

Publications (2)

Publication Number Publication Date
CN109020151A true CN109020151A (en) 2018-12-18
CN109020151B CN109020151B (en) 2021-12-31

Family

ID=64618553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811123187.9A Active CN109020151B (en) 2018-09-26 2018-09-26 Intelligent river sewage treatment system and method

Country Status (1)

Country Link
CN (1) CN109020151B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1099713A (en) * 1996-09-27 1998-04-21 Takeo Mori Device for crushing dehydrated cake in waste water treatment system
CN202849228U (en) * 2012-10-17 2013-04-03 曹健 Excess activated sludge deep dehydration device
CN203890125U (en) * 2014-06-11 2014-10-22 江苏省沿海水利科学研究所 Crawler-type biological transfer chain sewage treatment device
CN104963371A (en) * 2015-06-10 2015-10-07 河南工业大学 Sludge removing device
CN106269790A (en) * 2016-08-16 2017-01-04 中电建水环境治理技术有限公司 Lake, river is gushed polluted bed mud and is processed remaining sand regenerative system
CN206828352U (en) * 2017-06-29 2018-01-02 重庆阳正环保科技股份有限公司 Wastewater sludge handles retracting device
CN207538098U (en) * 2017-10-17 2018-06-26 安吉晨源环保资源再生利用有限公司 A kind of sewage-treatment plant

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1099713A (en) * 1996-09-27 1998-04-21 Takeo Mori Device for crushing dehydrated cake in waste water treatment system
CN202849228U (en) * 2012-10-17 2013-04-03 曹健 Excess activated sludge deep dehydration device
CN203890125U (en) * 2014-06-11 2014-10-22 江苏省沿海水利科学研究所 Crawler-type biological transfer chain sewage treatment device
CN104963371A (en) * 2015-06-10 2015-10-07 河南工业大学 Sludge removing device
CN106269790A (en) * 2016-08-16 2017-01-04 中电建水环境治理技术有限公司 Lake, river is gushed polluted bed mud and is processed remaining sand regenerative system
CN206828352U (en) * 2017-06-29 2018-01-02 重庆阳正环保科技股份有限公司 Wastewater sludge handles retracting device
CN207538098U (en) * 2017-10-17 2018-06-26 安吉晨源环保资源再生利用有限公司 A kind of sewage-treatment plant

Also Published As

Publication number Publication date
CN109020151B (en) 2021-12-31

Similar Documents

Publication Publication Date Title
CN101402065B (en) Magnetic separation device
CN101381134B (en) Sewage disposal technique of stone processing and system
CN102225834B (en) Sludge treatment method and device for urban drainage pipe network
US9908067B2 (en) Floatables and scum removal apparatus for a waste water treatment system
CA2640019C (en) Magnetic separation apparatus
CN206463549U (en) It is a kind of can automatic desilting mud sedimentation basin
US4113616A (en) Fish manure removal method
CN203425567U (en) Sewage treatment device
KR101207999B1 (en) Cleaning system of conveyor belt with temperature sensor and recycle system of washing water
CN109020151A (en) Intelligent watercourse sewage disposal system and method
CN207822639U (en) A kind of water pollution control sedimentation basin
CN107285562B (en) Garden water self-purification circulating system
US20150182887A1 (en) Method and apparatus for using backwash to clean a bar rack in a waste water treatment system
CN213173642U (en) Sewage treatment integration equipment for environmental protection
CN105236577A (en) Detachable module-type wetland system, and sewage treatment method
CN202063817U (en) Municipal drainage pipe network sludge treatment device
CN209668924U (en) Substep recycling building sewage settling tank
CN204981350U (en) Detachable constructed wetland filler module
CN107089737A (en) Nanoscale groundwater extraction handles unitary module intelligence system
CN202643468U (en) Novel waste water cycle processor
CN207270880U (en) A kind of sewage classification cleaning environmental protecting device
CN105417660A (en) Method and device for treating production wastewater of water works
CN110156215A (en) Sewage disposal device and its method
CN206590941U (en) A kind of waste water solid separation equipment and system
CN214784212U (en) Municipal administration is with well lid that has filtering capability

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230719

Address after: 311800 East China International Jewelry City c1301-10, Shanxiahu Town, Zhuji City, Shaoxing City, Zhejiang Province

Patentee after: Zhejiang Huazhen Technology Co.,Ltd.

Address before: 311826 No. 7, Ganling village, Ruan Town, Zhuji City, Shaoxing City, Zhejiang Province

Patentee before: Cai Xiaochun

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Intelligent River Sewage Treatment System and Method

Effective date of registration: 20230721

Granted publication date: 20211231

Pledgee: Shaoxing Bank Co.,Ltd. Zhuji sub branch

Pledgor: Zhejiang Huazhen Technology Co.,Ltd.

Registration number: Y2023980049293