CN108978717A - Precast assembling concrete manhole and prepackage method - Google Patents

Precast assembling concrete manhole and prepackage method Download PDF

Info

Publication number
CN108978717A
CN108978717A CN201710411555.9A CN201710411555A CN108978717A CN 108978717 A CN108978717 A CN 108978717A CN 201710411555 A CN201710411555 A CN 201710411555A CN 108978717 A CN108978717 A CN 108978717A
Authority
CN
China
Prior art keywords
well room
prefabricated
well
cover board
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710411555.9A
Other languages
Chinese (zh)
Inventor
王江涛
付嵘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Sheng Taiyuan Cement Products Co Ltd
Original Assignee
Shaanxi Sheng Taiyuan Cement Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Sheng Taiyuan Cement Products Co Ltd filed Critical Shaanxi Sheng Taiyuan Cement Products Co Ltd
Priority to CN201710411555.9A priority Critical patent/CN108978717A/en
Publication of CN108978717A publication Critical patent/CN108978717A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention belongs to a kind of underground structure more particularly to precast assembling concrete manholes and prepackage method.Comprising prefabricated lower well room (1) and prefabricated upper well room (2), include above prefabricated upper well room (2) well room cover board (3), include above well room cover board (3) pit shaft regulating block (4), be walling crib above pit shaft regulating block (4), includes well lid in walling crib;The above structure is linked to be entirety, and whole main body is that the well body that upper well room and lower well room are constituted is rectangle or circle.It using the present invention of technical solution as above, has the advantages that compared with the existing technology: the technical issues of industrialized production may be implemented, substitute clay brick masonry inspection shaft.Make its assembly flexibly, convenient for construction.To improve the safety and adaptability of various conduit runnings.

Description

Precast assembling concrete manhole and prepackage method
Technical field
The invention belongs to a kind of underground structure more particularly to precast assembling concrete manholes and prepackage method.
Background technique
Existing various underground piping inspection shafts are all made of the completion of clay brick masonry: 1, its intensity is low, and speed of application is slow, easily seeps Leakage, durability are poor, and service life is short, are unfavorable for the Northwest's use.2, clay brick inspection shaft is formed by brick masonry, is not exclusively seeped Leakage, in addition the Northwest plateau water shortage, effluent seepage polluted underground water resource, do not meet environmental protection policy.3, fired clay brick, greatly Amount causes clay resource to waste using clay brick.4, the field operation time is long, and wet construction heavy workload, curing time is long, longer Time cannot backfill, and the construction period is long, or even threaten the life security of surrounding environment and construction personnel.5, only it is with Xi'an Example, about newly-built more than 200 kilometer of pipeline, need to build various more than 10000 seats of pipe manhole every year, using 2,500,000 pieces of clay brick with On.Country, which also prohibites, at present uses clay brick as building material, carries out in this case prefabricated assembling type reinforced mixed Solidifying soil inspection shaft is imperative.
Currently, domestic application concrete inspection well substitutes brick masonry inspection shaft product, mainly there is prefabricated assembled concrete inspection Well and building-brick type concrete masonry units inspection shaft, there are also cast in situs armored concrete inspection shafts.Prefabricated assembled concrete inspection Well has the characteristics that high intensity, assembling rapid construction and seam are tight, can fundamentally solve lacking for clay brick inspection shaft Point, so as to make inspection shaft reach the advantages that bearing capacity is big, non-leakage, speed of application is fast.Building-brick type concrete masonry units inspection shaft, Only solve the problems, such as without using clay brick, building-brick type concrete masonry units inspection shaft and poured in place concrete inspection shaft, not from Fundamentally solve other problems.
Summary of the invention
The purpose of invention: in order to provide a kind of better precast assembling concrete manhole of effect and prepackage method, tool Body purpose is shown in multiple substantial technological effects of specific implementation part.
In order to reach purpose as above, the present invention is adopted the following technical scheme that:
Scheme one:
Precast assembling concrete manhole, which is characterized in that comprising prefabricated lower well room and prefabricated upper well room, prefabricated is upper Include well room cover board above well room, include pit shaft regulating block above well room cover board, is walling crib above pit shaft regulating block, is wrapped in walling crib Containing well lid;The above structure is linked to be entirety, and whole main body is that the well body that upper well room and lower well room are constituted is rectangle or circle.
The further technical solution of the present invention is, described to mark time as pre-buried reinforcing bar comprising marking time on the well body inner wall Item.
The further technical solution of the present invention is, includes preformed hole in the lower well room.
The further technical solution of the present invention is, the lower well room, upper well room, well room cover board, pit shaft regulating block, in walling crib Comprising reserved hole for hoist.
Scheme two:
The prepackage method of precast assembling concrete manhole as described above, which is characterized in that comprise the following steps:
Prefabricated pit shaft regulating block is connected below walling crib, anchor bolt is reserved in walling crib and well lid connection;
Well room is formed by connecting by prefabricated upper well room, prefabricated lower well room, wherein being reserved with well in prefabricated well room and walling crib Hole is provided with preformed hole in prefabricated lower well room, and prefabricated lower well room is prefabricated together bottom plate when producing, and prefabricated upper well room is raw It is when production that top plate is prefabricated together, it reduces by one of construction joint, increases inspection shaft globality, improve inspection shaft anti-floating ability.
The further technical solution of the present invention is that prefabricated lower well room, prefabricated upper well room, well room cover board connecting interface are Flexible tongue and groove, prefabricated well room, the well room cover board connecting interface of rectangle are rigid tongue and grooves, and prefabricated pit shaft, well room cover board connect Mouth is rigid tongue and groove.
The further technical solution of the present invention is, prefabricated upper well room, prefabricated lower well room, prefabricated well room cover board, pre- The pit shaft of system, prefabricated cover board have reserved lifting hole(eyelet).
The further technical solution of the present invention is that rigid tongue and groove is sealed with cement mortar, flexible tongue and groove wedge-shaped rubber glue Circle sealing.
The further technical solution of the present invention is, marking time for the inner wall of well room and pit shaft is that reserved mark time or pre-buried is stepped at hole location Walk component.
It using the present invention of technical solution as above, has the advantages that compared with the existing technology: may be implemented to industrialize The technical issues of production, substitution clay brick masonry inspection shaft.Make its assembly flexibly, convenient for construction.To improve various pipelines The safety and adaptability of operation.
Detailed description of the invention
In order to further illustrate the present invention, it is further illustrated with reference to the accompanying drawing:
Fig. 1 is the top view of circular inspection well of the present invention
Fig. 2 is the I-I of Fig. 1
Fig. 3 is the II-II of Fig. 1
Fig. 4 is the top view of rectangle inspection well of the present invention
Fig. 5 is the I-I of Fig. 4
Fig. 6 is the II-II of Fig. 4
Fig. 7 is cover board
Fig. 8 is the top view of Fig. 7
Fig. 9 is pit shaft
Figure 10 is the top view of Fig. 9
Figure 11 is well room interface form
Figure 12 is the Interface Shape of pit shaft (walling crib, cover board)
In figure: under 1- the upper well room of well room, 2-, 3- well room cover board, 4- pit shaft regulating block, 5- walling crib, 6- mark time, 7- preformed hole, 8- Bolt, 9- well lid, 10- sealing ring.
Specific embodiment
With reference to the accompanying drawings and detailed description, the present invention is furture elucidated, it should be understood that following specific embodiments are only For illustrating the present invention rather than limiting the scope of the invention.It should be noted that word " preceding " used in the following description, " rear ", "left", "right", "up" and "down" refer to that the direction in attached drawing, word "inner" and "outside" refer respectively to direction or remote Direction from geometric center of specific component.
The technical solution of precast inspection well of the present invention: by prefabricated lower well room, prefabricated upper well room, prefabricated pit shaft, from Lower and upper interface is linked to be entirety, has well room cover board between well room and pit shaft, well lid is equipped on pit shaft, it is characterised in that:
The shape of above-mentioned precast assembling concrete manhole has round, rectangle.
Above-mentioned circle pit shaft is that prefabricated adjusting block is connected below prefabricated walling crib, and prefabricated pit shaft, top plate connecting interface are rigidity Anchor bolt is reserved in tongue and groove, walling crib and well lid connection;
Above-mentioned (circle) prefabricated lower well room, prefabricated upper well room, connecting interface are flexible tongue and groove, (rectangle) prefabricated well room, prefabricated well Room cover plate connecting interface is rigid tongue and groove.It is flexible tongue and groove that (rectangle) prefabricated well room is connect with pipeline.
Above-mentioned prefabricated upper well room, lower well room, well room cover board, pit shaft, cover board have reserved lifting hole(eyelet).
Above-mentioned interface is sealed by rigid tongue and groove with cement mortar, flexible interface wedge-shaped rubber rubber sealing.
Above-mentioned prefabricated well room and marking time for shaft in wall are reserved mark time hole location or pre-buried components of marking time.
Above-mentioned prefabricated lower well room, upper well room, cover board, pit shaft, walling crib material be C30 concrete.
Above-mentioned prefabricated well room is the connection type that rigid interface and flexible interface combine, prefabricated well room with the connection of pipeline Connecting pipe is used to be connected no more than 1000mm tubing, therefore when differential settlement occurs for pipeline, can be effectively prevented from and be connect The phenomenon that mouth disengaging or pipeline break.It is that pipeline does not destroy, to improve conduit running safety.
Above-mentioned circle (rectangle) well room is formed by connecting by prefabricated upper well room, prefabricated lower well room, wherein on prefabricated well room cover plate It is reserved with wellhole, preformed hole connecting pipe is provided in prefabricated lower well room and uses, prefabricated lower well room is prefabricated together bottom plate when producing, It reduces by one of construction joint, increases inspection shaft globality, improve inspection shaft anti-floating ability.
Precast assembling concrete manhole of the present invention is produced with advanced Core Vibrated Casting Process, high production efficiency.
The utility model has the advantages that precast assembling concrete manhole is by the prefabricated completion of armored concrete, well room and pit shaft are by difference Modulus adjusting is assembled, it is mating with various pipelines, realizes the rapid construction of pipeline assembling.Prefabricated assembled concrete inspection Well does not use clay brick, is conducive to protect environment.It is fast compared with brick masonry inspection shaft speed of application, quality is high, compressive resistance is high, can be with It is subjected to the impact of heavy-duty machinery and rolls, advantageously account for road well room collapses problem.It is high, antiseep excellent with intensity Point, frost resistance, corrosion resistance all compared with clay brick height, to extend service life, can satisfy design standard and construction requirement. So that the construction of inspection shaft is become quick, simple, save lay bricks, jointing.Plastering, precipitation process greatly improve labour production Rate and working efficiency accelerate the period of infrastructure construction.It can be widely applied to the inspection of various coal gas and waters, electricity, heat supply pipeline Look into well.
As shown in figures 1 to 6, precast assembling concrete manhole, adjusting block are respectively by seven kinds of different size compositions 90mm, 140mm, 180mm, 360mm, 720mm, 1440mm.1800mm, internal diameter are 700mm and 800mm.Prefabricated assembled coagulation Native inspection shaft has all reserved hole for hoist in different component or has been furnished with special hanger, all C30 of prefabricated concrete used.
The shape of precast assembling concrete manhole has round, rectangle.The structure size and suitable conduit of inspection shaft.
Circular inspection well diameter range, D1000-D1500, suitable conduit diameter D200-D800.
Rectangle inspection well size L1100 × 1100, L1100 × 1400, L1100 × 1600, L1100 × 1800, L1100 × 2200, L1100 × 2600, L1600 × 1600, the suitable conduit diameter of L2200 × 2200 D800-D2000.
The 6- of inspection shaft marks time and equips on component in advance, and the step pitch that 6- marks time is 360mm, and the prefabricated well room first step is located at Well room cover board bottom 100mm, pit shaft to well room cover board first are located at the upward 100mm of cover board, and material of marking time is plastic-steel or ball milling cast steel.
In a creative way, above each effect is individually present, moreover it is possible to the combination of the above results is completed with a nested structure.
It is clear that the technical effect that the above structure is realized is realized, if the additional technical solution is not taken into account, this patent title is also It can be a kind of inspection shaft.Part details is not shown in the figure.
It should be noted that multiple schemes that this patent provides include the basic scheme of itself, independently of each other, not mutually It restricts, but it can also be combined with each other in the absence of conflict, reach multiple effects and realize jointly.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of this field Personnel should be recognized that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this hairs Bright principle, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these variations It is both fallen in claimed range with improving.

Claims (9)

1. precast assembling concrete manhole, which is characterized in that comprising prefabricated lower well room (1) and prefabricated upper well room (2), Including above prefabricated upper well room (2) well room cover board (3) includes pit shaft regulating block (4) that pit shaft is adjusted above well room cover board (3) It is walling crib above block (4), includes well lid in walling crib;The above structure is linked to be entirety, the i.e. upper well room of whole main body and lower well room structure At well body be rectangle or circle.
2. precast assembling concrete manhole as described in claim 1, which is characterized in that comprising stepping on the well body inner wall Step, it is described to mark time as pre-buried reinforcing rod.
3. precast assembling concrete manhole as described in claim 1, which is characterized in that include on the lower well room (1) Preformed hole (7).
4. precast assembling concrete manhole as described in claim 1, which is characterized in that the lower well room (1), upper well room (2), well room cover board (3), pit shaft regulating block (4), in walling crib comprising reserved hole for hoist.
5. the prepackage method of precast assembling concrete manhole, which is characterized in that comprise the following steps:
It is connected below walling crib prefabricated pit shaft regulating block (4), anchor bolt is reserved in walling crib and well lid connection;
Well room is formed by connecting by prefabricated upper well room, prefabricated lower well room, wherein being reserved with well in prefabricated well room and walling crib Hole is provided with preformed hole in prefabricated lower well room, and prefabricated lower well room is prefabricated together bottom plate when producing, and prefabricated upper well room is raw It is when production that top plate is prefabricated together, it reduces by one of construction joint, increases inspection shaft globality, improve inspection shaft anti-floating ability.
6. the prepackage method of precast assembling concrete manhole as claimed in claim 5, which is characterized in that prefabricated goes into the well Room, prefabricated upper well room, well room cover board connecting interface are flexible tongue and groove, prefabricated well room, the well room cover board connecting interface of rectangle It is rigid tongue and groove, prefabricated pit shaft, well room cover board connecting interface are rigid tongue and groove.
7. the prepackage method of precast assembling concrete manhole as claimed in claim 5, it is characterised in that: prefabricated upper well Room, prefabricated lower well room, prefabricated well room cover board, prefabricated pit shaft, prefabricated cover board have reserved lifting hole(eyelet).
8. the prepackage method of precast assembling concrete manhole as claimed in claim 5, it is characterised in that: rigid tongue and groove is used Cement mortar sealing, flexible tongue and groove wedge-shaped rubber rubber sealing.
9. the prepackage method of precast assembling concrete manhole as claimed in claim 5, it is characterised in that: well room and pit shaft Marking time for inner wall be reserved hole location or the pre-buried component of marking time of marking time.
CN201710411555.9A 2017-06-05 2017-06-05 Precast assembling concrete manhole and prepackage method Pending CN108978717A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710411555.9A CN108978717A (en) 2017-06-05 2017-06-05 Precast assembling concrete manhole and prepackage method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710411555.9A CN108978717A (en) 2017-06-05 2017-06-05 Precast assembling concrete manhole and prepackage method

Publications (1)

Publication Number Publication Date
CN108978717A true CN108978717A (en) 2018-12-11

Family

ID=64501351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710411555.9A Pending CN108978717A (en) 2017-06-05 2017-06-05 Precast assembling concrete manhole and prepackage method

Country Status (1)

Country Link
CN (1) CN108978717A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593599A (en) * 2019-09-12 2019-12-20 浙江大学城市学院 Temporary opening protection structure for top plate of operation high-voltage cable well and construction method
CN110924438A (en) * 2019-12-06 2020-03-27 安徽建川市政工程有限公司 Prefabricated member of assembled rectangular inspection well
CN113279470A (en) * 2021-06-30 2021-08-20 广东省第四建筑工程有限公司 Open-cut improved prefabricated horse riding well construction method
CN114737612A (en) * 2022-05-20 2022-07-12 济南黄河路桥建设集团有限公司 Municipal road inspection well installation process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2544763B1 (en) * 1983-04-22 1985-08-09 Bellorini Jacques PREFABRICATED REINFORCED CAPTURE OR MEETING CHAMBER
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
CN2597552Y (en) * 2002-12-20 2004-01-07 北京欣金宇砼制品有限公司 Prefabricated concrete round door arch type manhole
CN102587419A (en) * 2012-03-01 2012-07-18 安徽省方大水泥制品有限公司 Assembly type manhole
CN103374926A (en) * 2012-04-13 2013-10-30 哈尔滨市前进水泥管厂有限责任公司 Prefabricated assembly-type reinforced concrete inspection well

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2544763B1 (en) * 1983-04-22 1985-08-09 Bellorini Jacques PREFABRICATED REINFORCED CAPTURE OR MEETING CHAMBER
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
CN2597552Y (en) * 2002-12-20 2004-01-07 北京欣金宇砼制品有限公司 Prefabricated concrete round door arch type manhole
CN102587419A (en) * 2012-03-01 2012-07-18 安徽省方大水泥制品有限公司 Assembly type manhole
CN103374926A (en) * 2012-04-13 2013-10-30 哈尔滨市前进水泥管厂有限责任公司 Prefabricated assembly-type reinforced concrete inspection well

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
余洪方等: "《预制混凝土检查井》建材行业标准编制说明", 《混凝土世界》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593599A (en) * 2019-09-12 2019-12-20 浙江大学城市学院 Temporary opening protection structure for top plate of operation high-voltage cable well and construction method
CN110593599B (en) * 2019-09-12 2021-04-20 浙江大学城市学院 Temporary opening protection structure for top plate of operation high-voltage cable well and construction method
CN110924438A (en) * 2019-12-06 2020-03-27 安徽建川市政工程有限公司 Prefabricated member of assembled rectangular inspection well
CN113279470A (en) * 2021-06-30 2021-08-20 广东省第四建筑工程有限公司 Open-cut improved prefabricated horse riding well construction method
CN114737612A (en) * 2022-05-20 2022-07-12 济南黄河路桥建设集团有限公司 Municipal road inspection well installation process

Similar Documents

Publication Publication Date Title
CN108978717A (en) Precast assembling concrete manhole and prepackage method
CN201232197Y (en) Combined inspection well
CN103374926A (en) Prefabricated assembly-type reinforced concrete inspection well
CN205530344U (en) Utility tunnel is pour to split type no mould
CN208586722U (en) Precast concrete assembled piping shaft
CN202466631U (en) Prefabricated reinforced concrete inspection well and die thereof
CN202131613U (en) Lined prefabricated reinforced concrete inspection well
CN213508795U (en) Concrete module type inspection well shaft structure and concrete module brick
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN210069158U (en) Glass fiber reinforced plastic bell mouth concrete top pipe
CN208280179U (en) Precast assembling concrete manhole
CN205753309U (en) Prefabricated cable duct
CN203701145U (en) Underground pipe network inspection well concrete assembly
CN206600524U (en) A kind of modularization assembling steel backrest
CN104131613B (en) A kind of fiber glass reinforced plastics inspection well
CN2597552Y (en) Prefabricated concrete round door arch type manhole
CN2597553Y (en) Prefabricated concrete rectangular door arch type manhole
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN204529449U (en) A kind of septic tank
CN212000674U (en) Novel reverse construction method assembly type non-pressure culvert
CN107443548A (en) A kind of production method of water channel gool prefabricated component
CN202672331U (en) Prefabricated reinforced concrete circular grit well
CN203546754U (en) Prefabricated reinforced concrete manhole for communication pipeline
CN200952143Y (en) Integrated manhole ring
CN106592635A (en) Integrated inspection shaft and installation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181211