CN108915086A - Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method - Google Patents

Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method Download PDF

Info

Publication number
CN108915086A
CN108915086A CN201810755202.5A CN201810755202A CN108915086A CN 108915086 A CN108915086 A CN 108915086A CN 201810755202 A CN201810755202 A CN 201810755202A CN 108915086 A CN108915086 A CN 108915086A
Authority
CN
China
Prior art keywords
column
steel
connecting plate
prefabricated
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810755202.5A
Other languages
Chinese (zh)
Inventor
张晓峰
迟毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201810755202.5A priority Critical patent/CN108915086A/en
Publication of CN108915086A publication Critical patent/CN108915086A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention provides a kind of assembling type steel structure concrete prefabricated column, and the pre- buried column of steel construction is connected in prefabricated column foundation, and the pre-buried column top of steel construction is equipped with column connecting pin, and column connecting pin two sides are equipped with column connecting plate;Column connecting plate is located among core steel column, its width is equal to the one third of core steel column width, a kind of concrete prefabricated beam of assembling type steel structure is also provided, core girder steel is set in beam body, two beam connecting plates are fixed in core girder steel end two sides, beam connection board width is the one third of core girder steel width, also provides the docking construction method of above-mentioned assembling type steel structure concrete prefabricated column and precast beam, prefabricated post is installed in place;Precast beam is lifted at the top of prefabricated post, docks beam connecting plate with column connecting plate, beam connecting plate, column connecting plate bolt is affixed;To connecting node and after pour section and tie up muscle and concreting, complete installation, the present invention forms mechanical connection, improves installation accuracy and overall stability, improves the safety in installation process.

Description

Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method
Technical field
The invention belongs to construction engineering technical fields, and in particular to assembling type steel structure concrete prefabricated column, precast beam The docking construction method of node structure and Liang Yuzhu.
Background technique
In assembly concrete frame structure, the installation needs of precast beam are docked with prefabricated post, traditional mounting means It is not able to satisfy installation accuracy, causes a little error, and during installation, precast beam needs are erected using support, and Its is unstable, easily becomes security risk.
Summary of the invention
The present invention is in order to solve the above technical problems, provide that a kind of error is small, installation accuracy is high, does not need support frame, construction The higher construction method of safety.
The present invention provides a kind of structure of assembling type steel structure concrete prefabricated column to achieve the above object of the invention, specifically For:
A kind of assembling type steel structure concrete prefabricated column, including the prefabricated column foundation being built by reinforcing bar, the prefabricated post The pre- buried column of steel construction is connected in basis, the pre- buried column of steel construction is combined by core steel column, cross connecting column, and cross connects Connect column be in prefabricated column foundation and one-piece casting in concrete structure;Core steel column is equipped with prominent cross connecting column with upper prop Connecting pin, column connecting pin two sides are equipped with column connecting plate;The column connection board width is equal to the one third of core steel column width, column Connecting plate is located among core steel column, and column connecting plate is equipped with bolt hole.
A kind of concrete prefabricated beam of assembling type steel structure is additionally provided, including the core steel being embedded in precast beam body Beam, core girder steel both ends are equipped with the beam connecting pin for protruding from precast beam body, and beam connecting pin is by two beam connecting board structures, Liang Lian Fishplate bar width is the one third of core girder steel width, and two beam connecting plates are fixed in core girder steel end two sides, and connecting plate is set There is bolt hole.
The docking construction method of above-mentioned assembling type steel structure concrete prefabricated column and precast beam:
1) assembling type steel structure concrete prefabricated column is lifted into installation site;
2) prefabricated column bottom is connected and fixed by sleeve and bottom joint bar;
3) precast beam is lifted at the top of prefabricated post, docks the beam connecting plate of precast beam with the connection of the column of prefabricated post, uses Bolt passes through beam connecting plate, the bolt hole of column connecting plate forms mechanical connection;
4) to connecting node and after pour section and tie up muscle and concreting, complete installation.
Beneficial effect is the present invention compared with prior art:1, prefabricated post and precast beam, which are formed, is mechanically connected, and improves installation Precision.
2, prefabricated post and precast beam, which are formed, is mechanically connected, and improves the safety in installation process.3, prefabricated post and precast beam Mechanical connection is formed, the overall stability of frame structure is improved.
Detailed description of the invention
Fig. 1 is prefabricated post structural schematic diagram;
Fig. 2 is prefabricated post side view;
Fig. 3 is line A-A cross-sectional view in Fig. 2;
Fig. 4 is precast beam structure figure;
Fig. 5 is precast beam angle of depression structure chart;
Fig. 6 is beam, column integral installation structure chart;
Fig. 7 is beam, column connected node figure.
In figure:Prefabricated column foundation 1, cross connecting column 2, core steel column 3, column connecting plate 4, precast beam body 5, core girder steel 6, beam connecting plate 7.
Specific embodiment
As shown in Figure 1, 2, 3, a kind of assembling type steel structure concrete prefabricated column, including the prefabricated base for post being built by reinforcing bar Plinth 1, the pre- buried column of steel construction is connected in the prefabricated column foundation 1, and the pre- buried column of steel construction is connected by core steel column 3, cross Column 2 is combined into, and cross connecting column 2 is in prefabricated column foundation 1 and one-piece casting is in concrete structure;Core steel column 3 is set There is the column connecting pin of prominent 2 or more cross connecting column, column connecting pin two sides are equipped with column connecting plate 4;Described 4 width of column connecting plate etc. In the one third of 3 width of core steel column, column connecting plate 4 is located among core steel column 3, and column connecting plate 4 is equipped with bolt hole.
This assembling type steel structure concrete prefabricated column manufacturing process:Prefabricated column foundation 1 is built-up by reinforcing bar, and reinforcing bar is the bottom of from Portion is welded upwards from level to level, and when horizontal reinforcement is constructed to certain altitude, pre-processed steel construction is embedded into prefabricated base for post In plinth 1, reinforced hole is set, reinforcing bar passes through reinforced hole, makes 1 shape of steel construction and prefabricated column foundation on the steel construction cross connecting column 2 At an entirety.The cross connecting column 2 is all cast in concrete structure when concreting, and core steel column 3 pushes up The column connecting pin in portion is exposed to outside concrete structure, and prefabricated column foundation 1 is integrally combined into assembling type steel structure concrete with steel construction Prefabricated post, prefabricated post complete the production.
The concrete prefabricated beam of assembling type steel structure used with the matching of above-mentioned prefabricated post, as shown in Figure 4,5, it includes pre-buried Core girder steel 6 in precast beam body 5,7 both ends of core girder steel are equipped with the beam connecting pin for protruding from precast beam body 5, Liang Lian End is connect by two 7 structures of beam connecting plate, 7 width of beam connecting plate is the one third of 6 width of core girder steel, two beam connecting plates 7 7 end two sides of core girder steel are fixed in, connecting plate is equipped with bolt hole.
The core girder steel 6 of this precast beam and the core steel column size of prefabricated post are identical, are separated by between two beam connecting plates 7 Width is equal to the width of column connecting plate 4, i.e. column connecting plate 4 can just be put into the interval of beam connecting plate 7.
In conjunction with shown in Fig. 6,7, the docking construction method of above-mentioned assembling type steel structure concrete prefabricated column and precast beam:
1) assembling type steel structure concrete prefabricated column is lifted into installation site;
2) prefabricated column bottom is connected and fixed by sleeve and bottom joint bar;
3) precast beam is lifted at the top of prefabricated post, docks the beam connecting plate of precast beam with the connection of the column of prefabricated post, uses Bolt passes through beam connecting plate, the bolt hole of column connecting plate forms mechanical connection;
4) to connecting node and after pour section and tie up muscle and concreting, complete installation.
The present invention is prefabricated post, precast beam devises connecting joint structure, facilitates the docking construction of beam, column, docking construction Speed is fast, this structure keeps installation accuracy at connecting node high, does not need support construction in installation process, highly-safe.

Claims (3)

1. a kind of assembling type steel structure concrete prefabricated column, including the prefabricated column foundation being built by reinforcing bar, it is characterized in that:It is described The pre- buried column of steel construction is connected in prefabricated column foundation, the pre- buried column of steel construction is combined by core steel column, cross connecting column, Cross connecting column is in prefabricated column foundation and one-piece casting is in concrete structure;Core steel column is equipped with prominent cross connecting column With upper prop connecting pin, column connecting pin two sides are equipped with column connecting plate;The column connection board width is equal to three points of core steel column width One of, column connecting plate is located among core steel column, and column connecting plate is equipped with bolt hole.
2. a kind of concrete prefabricated beam of assembling type steel structure, it is characterized in that:Including the core girder steel being embedded in precast beam body, Core girder steel both ends are equipped with the beam connecting pin for protruding from precast beam body, and beam connecting pin is by two beam connecting board structures, beam connection Board width is the one third of core girder steel width, and two beam connecting plates are fixed in core girder steel end two sides, and connecting plate is equipped with Bolt hole.
3. the docking construction method of assembling type steel structure concrete prefabricated column and precast beam as described in the claims, by following Step carries out:
1) assembling type steel structure concrete prefabricated column is lifted into installation site;
2) prefabricated column bottom is connected and fixed by sleeve and bottom joint bar;
3) precast beam is lifted at the top of prefabricated post, docks the beam connecting plate of precast beam with the connection of the column of prefabricated post, uses bolt Bolt hole across beam connecting plate, column connecting plate forms mechanical connection;
4) to connecting node and after pour section and tie up muscle and concreting, complete installation.
CN201810755202.5A 2018-07-11 2018-07-11 Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method Pending CN108915086A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810755202.5A CN108915086A (en) 2018-07-11 2018-07-11 Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810755202.5A CN108915086A (en) 2018-07-11 2018-07-11 Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method

Publications (1)

Publication Number Publication Date
CN108915086A true CN108915086A (en) 2018-11-30

Family

ID=64410688

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810755202.5A Pending CN108915086A (en) 2018-07-11 2018-07-11 Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method

Country Status (1)

Country Link
CN (1) CN108915086A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201695572U (en) * 2010-06-22 2011-01-05 中国建筑第二工程局有限公司 Stiff concrete column and reinforced concrete frame beam mixed structure
CN102493603A (en) * 2011-12-30 2012-06-13 王夏静 Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN204804057U (en) * 2015-06-05 2015-11-25 中国十七冶集团有限公司 Beam column connecting device of prefabricated frame
CN105155683A (en) * 2015-08-12 2015-12-16 四川省建筑设计研究院 Prefabricated beam-column connection in prefabricated concrete buildings and construction method thereof
CN205954836U (en) * 2016-08-23 2017-02-15 天津大学建筑设计研究院 Assembled frame construction
CN206844314U (en) * 2017-05-10 2018-01-05 福建璟榕工程建设发展有限公司 A kind of new prefabricated assembled bean column node
CN108018943A (en) * 2017-10-30 2018-05-11 上海市政工程设计研究总院(集团)有限公司 A kind of complete prefabricated beam column attachment device and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201695572U (en) * 2010-06-22 2011-01-05 中国建筑第二工程局有限公司 Stiff concrete column and reinforced concrete frame beam mixed structure
CN102493603A (en) * 2011-12-30 2012-06-13 王夏静 Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN204804057U (en) * 2015-06-05 2015-11-25 中国十七冶集团有限公司 Beam column connecting device of prefabricated frame
CN105155683A (en) * 2015-08-12 2015-12-16 四川省建筑设计研究院 Prefabricated beam-column connection in prefabricated concrete buildings and construction method thereof
CN205954836U (en) * 2016-08-23 2017-02-15 天津大学建筑设计研究院 Assembled frame construction
CN206844314U (en) * 2017-05-10 2018-01-05 福建璟榕工程建设发展有限公司 A kind of new prefabricated assembled bean column node
CN108018943A (en) * 2017-10-30 2018-05-11 上海市政工程设计研究总院(集团)有限公司 A kind of complete prefabricated beam column attachment device and its construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《简明钢与组合结构设计施工资料集成》编委会: "《简明钢与组合结构设计施工资料集成》", 30 April 2005, 中国电力出版社 *
倪建国: "《建设工程监理实施细则精选汇编》", 31 March 2013, 中国建筑工业出版社 *

Similar Documents

Publication Publication Date Title
CN108331158A (en) A kind of joint connection in site method of precast reinforced concrete beam column
CN110792165B (en) Prefabricated assembly type concrete beam column joint connecting device and method
KR20020011706A (en) Fabricated pier and Fabricated pier construction method
KR20190124615A (en) Foundation of girder for bridge cantilever bracket construction Magnetic type jig for bolt installation and method of making girder using the jig
CN106032706A (en) Integrated casting molding construction method of reinforced concrete shear wall
CN109339087A (en) A kind of foundation structure system of low-rise building
KR100923564B1 (en) Precast concrete panel, construction method and structure of precast concrete panel using steel plate
CN112211402A (en) Anti-bank of pre-buried formula pouring die
CN109610707B (en) Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method
CN108915086A (en) Assembling type steel structure concrete prefabricated column and precast beam and its docking construction method
CN207419695U (en) One kind assembles the prefabricated whole beam column construction of concrete frame structure for " dry type "
CN116290089A (en) Concrete pouring template system for underground space and construction method thereof
CN106032705A (en) Integrated casting molding construction method of reinforced concrete floor system
CN109707069A (en) One kind connecting detachable prefabricated modularization shear wall and its assembly method based on fashioned iron
CN214574621U (en) Node dry joining method assembly structure
KR102296982B1 (en) Transfer Structure Construction Method Using U-shaped Steel Girder
CN110722662B (en) Manufacturing method of bracket-containing type precast concrete frame column
CN107476432B (en) Prefabricated reinforced concrete upright post connection structure
CN111005497A (en) Assembled house ground reinforcing plate structure
CN217204819U (en) Rigid template steel bar truss floor bearing plate
CN216810448U (en) Assembled formwork support integrated shear wall device
CN109610736A (en) A kind of mold and its localization method of abutment sleeve reserved steel bar
KR100650444B1 (en) Cantilever part construction method of bridge
CN217268038U (en) Assembled beam column node structure
CN218090941U (en) Whip type precast concrete equipment foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181130