CN108868122A CN201710343592.0A CN201710343592A CN108868122A CN 108868122 A CN108868122 A CN 108868122A CN 201710343592 A CN201710343592 A CN 201710343592A CN 108868122 A CN108868122 A CN 108868122A
Authority
CN
China
Prior art keywords
early
module
open
support
support frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710343592.0A
Other languages
Chinese (zh)
Inventor
孙莎莎
孙文祥
白冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Xiang Xiang Template Technology Co Ltd
Original Assignee
Shandong Xiang Xiang Template Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Xiang Xiang Template Technology Co Ltd filed Critical Shandong Xiang Xiang Template Technology Co Ltd
Priority to CN201710343592.0A priority Critical patent/CN108868122A/en
Publication of CN108868122A publication Critical patent/CN108868122A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Roof plate-girder early tears system open, belongs to technical field of building construction.Support frame is torn open including early(2)Support frame is early torn open with being fixed on(2)On multiple early demoulding blocks(9), it is characterised in that:Further include at least one set of holding supporting mechanism for keeping module and being used to support holding module, keeps module setting in two early demoulding blocks(9)Between, early tear support frame open(2)With early demoulding block(9)By keeping supporting mechanism support to keep module after dismounting.Logical form removal eraly block and holding block combiner support shuttering, template is independently arranged on keeping module, after the completion of pouring, after floor reaches some strength, so that it may remove early demoulding block and early tear support frame open, module is kept using keeping supporting mechanism to support, until floor reaches enough intensity, the early demoulding block of premature removal can transport other floors to be poured and use, and can effectively improve speed of application in this way, and early demoulding block and the early dosage for tearing support frame open are saved, construction cost is reduced.

Description

Roof plate-girder early tears system open
Technical field
Roof plate-girder early tears system open, belongs to technical field of building construction.
Background technique
When pouring build floor, needs to install roof plate-girder in advance, then template is laid on to the upside of roof plate-girder, in mould It pours to obtain floor on plate, at present after the completion of concrete floor slab placement, the entire floor such as needs integrally to tear open after reaching very high intensity Except roof plate-girder, therefore the construction period is extended, and needs a large amount of roof plate-girder, and construction cost is high.
Summary of the invention
The technical problem to be solved by the present invention is to:It is fast to overcome the deficiencies of the prior art and provide a kind of speed of application, it is at low cost Roof plate-girder early tear system open.
The technical solution adopted by the present invention to solve the technical problems is:The roof plate-girder early tears system open, including early tears branch open Support and it is fixed on the early multiple early demoulding blocks torn open on support frame, it is characterised in that:It further include at least one set of holding module and use The holding supporting mechanism of module is kept in support, keeps module setting between two early demoulding blocks, support frame is early torn open and is torn open with early Module is supported by holding supporting mechanism after removing and keeps module.
Preferably, the holding module includes multiple supporting beams, and the both ends of supporting beam, which are supported on, early tears open on support frame, is supported Beam lower part offers support location hole, after early tearing support frame and early demoulding block dismounting open, keeps supporting mechanism and support location hole phase The lower part for being supported on supporting beam of cooperation.
Preferably, the cross section of the supporting beam is rectangular, and the upside of supporting beam is concordant on the upside of early demoulding block.
Preferably, the holding supporting mechanism is to keep supported rod erecting, and the upper end of supported rod erecting is kept to reduce equipped with diameter Support positioning pin, support positioning pin is inserted into the support positioning hole.
Preferably, the holding module includes keeping crossbeam and keeping stringer, and two holding girder spaces are arranged, and at least two It is a that stringer is kept to be fixed on the upside for keeping crossbeam, it keeps supporting mechanism to be independently arranged at two morning and tears open between support frame, keep Crossbeam is fixed on the upside for keeping supporting mechanism.
Preferably, the holding supporting mechanism includes support rod and the support for being fixed on post upper, and support includes branch Bottom plate is supportted, keeps the lower part of crossbeam to be equipped with crossbeam bottom plate, the fixing for being connected to crossbeam bottom plate two sides is equipped on the upside of support baseboard Mechanism.
Preferably, the clamping mechanism includes the separating part being arranged in the middle part of support baseboard and is arranged in separating part two The positioning plate of side, positioning plate are equipped with the limiting slot for fixing crossbeam bottom plate in the side lower part close to separating part.
Preferably, the early demoulding block include it is early tear open crossbeam and it is early tear stringer open, multiple morning, which tear stringer open and are fixed on, early tears crossbeam open Upside, early tear open crossbeam be fixed on it is early tear open on support frame, be provided along its length recessing groove in the upper middle side part for early tearing stringer open.
Preferably, the early demoulding block includes standard module, lateral adjustments module and vertical adjustment module, vertical adjustment mould The adjustable connection standard module of block lengthwise position, the adjustable connection standard module in lateral adjustments module lateral position.
Preferably, the lateral outer side of standard module is arranged in the lateral adjustments module, and the setting of vertical adjustment module is being marked The longitudinally outboard of quasi-mode block;The morning demoulding block further includes cantilevered corner beam, for being fixed on vertical adjustment module and lateral adjustments module The corner of connection, the width of cantilevered corner beam are less than the half of lateral adjustments module width, and one end of cantilevered corner beam, which is fixed on, early tears support open On frame, the other end is connect with lateral adjustments module.
Compared with prior art, beneficial effect possessed by the present invention is:
1, the logical form removal eraly block of the present invention and holding block combiner support shuttering, are independently arranged template on keeping module, pour After the completion, after floor reaches some strength, so that it may remove early demoulding block and early tear support frame open, be supported using holding supporting mechanism Module is kept, until floor reaches enough intensity, the early demoulding block of premature removal can transport other floors to be poured It uses, can effectively improve speed of application in this way, and save early demoulding block and the early dosage for tearing support frame open, reduce construction Cost.
2, the present invention meets the concrete floor slab placement of various sizes by setting lateral adjustments module and vertical adjustment module, benefit Installing for basic beam is carried out with standard module, the lateral clearance at an inadequate standard module is installed by lateral adjustments module, Vertical adjustment module installs the axial clearance of an inadequate standard module, easy for construction, high-efficient.
3, system integrally uses high quality aluminum profiles production upper beam and underbeam, alleviates the weight of support frame.In early demoulding block Recessing groove is devised on the stringer of holding module, scene installs flitch fixed form additional when using here, will not destroy profile Skeleton, repeatable to be used in turn, practicability is stronger.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the embodiment of the present invention 1.
Fig. 2 is the partial enlarged view in Fig. 1 at A.
Fig. 3 is to remove early demoulding block to tear the structural schematic diagram after support frame open with early.
Fig. 4 is the structural schematic diagram of the embodiment of the present invention 2.
Fig. 5 is the structural schematic diagram for keeping module to be fixed between two early demoulding blocks in embodiment 2.
Fig. 6 is that standard module, lateral adjustments module, vertical adjustment module and cantilevered corner beam are fixed on the structure on Quick support frame Schematic diagram.
Fig. 7 is the structural schematic diagram that standard module is fixed on support rod and support.
Fig. 8 is the structural schematic diagram after lateral adjustments module is connect with standard module.
Fig. 9 is the structural schematic diagram of lateral adjustments module.
Figure 10 is operation chart when lateral adjustments module is connect with standard module.
Figure 11 is the structural schematic diagram of vertical adjustment module.
Figure 12 is the structural schematic diagram after vertical adjustment module is connect with standard module.
Figure 13 is the structural schematic diagram after vertical adjustment module is connect with standard module.
Figure 14 is the structural schematic diagram of cantilevered corner beam.
Figure 15 is the structural schematic diagram of support.
Figure 16 is the early main view for tearing stringer open.
Wherein:1, standard module 2, it is early tear open support frame 3, lateral adjustments module 4, vertical adjustment module 5, cantilevered corner beam 6, Longitudinal buckle 7, early stripping formwork system 9, early demoulding block 10, keeps template 11, supporting beam 12, keeps supported rod erecting floor 8 13, it keeps crossbeam 14, keep stringer 15, recessing groove;
101, standard horizontal beams 102, standard stringer 201, support rod 202, support 301, the first lateral adjustments stringer 302, Two lateral adjustments stringers 303, lateral adjustments crossbeam 401, first longitudinal direction adjust crossbeam 402, vertical adjustment stringer 403, indulge 503, second jiaos of 501, first jiaos of crossbeams 502 of crossbeam, angle stringer crossbeams are adjusted to adjusting support beam 404, second longitudinal direction;
2021, support baseboard 2022, separating part 2023, positioning plate 2024, retention bead 2025, limiting section 2026, installation Slot.
Specific embodiment
1 ~ 16 the present invention will be further described with reference to the accompanying drawing.
Embodiment 1
Referring to Fig.1, which early tears system open, including it is early tear support frame 2 open and be fixed on early tear multiple morning on support frame open and tear open Module 9 further includes at least one set of holding supporting mechanism for keeping module and being used to support holding module, module is kept to be arranged two Between a morning demoulding block 9, early tears open and keep module by keeping supporting mechanism to support after support frame 2 is removed with early demoulding block 9.Pass through Early demoulding block 9 and holding block combiner support early stripping formwork system 8, are independently arranged on keeping module and keep template 10, are keeping mould Build floor 7 is poured in the upside of plate 10 and early stripping formwork system 8, after floor 7 reaches some strength, so that it may remove early stripping formwork system 8, early demoulding Block 9 tears support frame 2 open with early, utilizes and supporting mechanism support is kept to keep module and keep template 10, the early demoulding block 9 of premature removal Other floors to be poured can be transported to use, can effectively improve speed of application in this way, and save early demoulding block 9 with The dosage for early tearing support frame 2 open, reduces construction cost.
Referring to Fig. 2, keeping module includes multiple supporting beams 11, and multiple supporting beams 11 connect from beginning to end, the both ends of supporting beam 11 It being supported on and early tears open on support frame 2,11 lower part of supporting beam offers support location hole, after early tearing support frame and early demoulding block dismounting open, The lower part for being supported on supporting beam 11 for keeping supporting mechanism and location hole being supported to match.The cross section of supporting beam 11 be it is rectangular, The upside of supporting beam 11 is concordant with early 9 upside of demoulding block.
Early tearing support frame 2 open includes multiple support rods 201 and support 202, and support 202 is fixed on the upper end of support rod 201, is held in the palm Support 202 is equipped with the hanging mechanisms for connecting early 9 end of demoulding block, and one end of early demoulding block 9 is connected to one by hanging structure In support 202, the other end is rotated up to level and fixed by another support rod 201 and support 202.
Referring to Fig. 3, keeping supporting mechanism is to keep supported rod erecting 12, and the upper end of supported rod erecting 12 is kept to reduce equipped with diameter Support positioning pin, support positioning pin insertion supporting beam 11 support positioning hole.Utilize the holding support support of supported rod erecting 12 Then beam 11 removes early stripping formwork system 8, early demoulding block 9 and early tears support frame 2 open, after floor reaches enough intensity, then removes holding Supported rod erecting 12, supporting beam 11 and holding template 10.
Embodiment 2
Referring to Fig. 4 ~ 5, keep module including keeping crossbeam 13 and keeping stringer 14, two holding crossbeam 13 intervals are arranged, at least Two keep stringers 14 to be fixed on the upsides for keeping crossbeam, keep supporting mechanism to be independently arranged at two morning and tear open between support frame 2, Crossbeam 13 is kept to be fixed on the upside for keeping supporting mechanism.Supporting mechanism is kept to tear 2 structure phase of support frame open with the morning in embodiment 1 Together, including support rod 201 and the support 202 for being fixed on post upper.
Be above in the present invention about keep module two embodiments, below to early demoulding block 9 and support 202 do into The explanation of one step.
Referring to Fig. 6, early demoulding block 9 includes standard module 1, lateral adjustments module 3 and vertical adjustment module 4, vertical adjustment The adjustable connection standard module 1 of 4 lengthwise position of module, the adjustable connection standard module 1 in 3 lateral position of lateral adjustments module.It is horizontal The lateral outer side of standard module 1 is set to adjustment module 3, and the longitudinally outboard of standard module 1 is arranged in vertical adjustment module 4; Early demoulding block 9 further includes cantilevered corner beam 5, the corner connecting for being fixed on vertical adjustment module 4 with lateral adjustments module 3, cantilevered corner beam 5 Width is less than the half of 3 width of lateral adjustments module, and one end of cantilevered corner beam 5, which is fixed on, early tears open on support frame 2, the other end and cross It is connected to adjustment module 3.
Referring to Fig. 7, standard module 1 includes standard horizontal beams 101 and standard stringer 102, and two intervals of standard horizontal beams 101 are set It sets, is arranged with multiple standard stringers 102 in the upside of standard horizontal beams 101, standard horizontal beams 101 are fixed in support 102.
Referring to Fig. 8 ~ 10, lateral adjustments module 3 includes a first lateral adjustments stringer 301, multiple second lateral adjustments The length of stringer 302 and two spaced lateral adjustments crossbeams 303, the first lateral adjustments stringer 301 is greater than standard module 1 Two standard horizontal beams 101 spacing, the length of the second lateral adjustments stringer 302 less than two standard horizontal beams 101 spacing, it is horizontal The downside of the first lateral adjustments stringer 301 and the second lateral adjustments stringer 302 is fixed on to adjusting crossbeam 303, and first is lateral Two lateral adjustments crossbeams 303, one end of lateral adjustments crossbeam 303 and the first lateral adjustments are stretched out in the both ends for adjusting stringer 301 Stringer 301 is fixedly connected, the other end be supported on it is early tears open on support frame 2, when connection, by the both ends of the first lateral adjustments stringer 301 It is overlapped on two standard horizontal beams 101 of standard module 1 respectively, rotates lateral adjustments crossbeam 303 then up far from the first cross To the other end for adjusting stringer 301, and it is fixed by support rod 201 and support 202.According to the width for pouring build floor, selection will First lateral adjustments stringer 301 is overlapped on the standard horizontal beams 101 between various criterion stringer 102, to adjust lateral adjustments Module 3 crosses out the width of standard module 1, easy to operate.
Referring to Fig.1 1~12, vertical adjustment module 4 includes that vertical adjustment stringer 402 and first longitudinal direction adjust crossbeam 401, is indulged It adjusts crossbeam 401 with first longitudinal direction to the one end for adjusting stringer 402 to be fixedly connected, the other end is overlapped on standard horizontal beams 101, root According to longitudinal sliding motion vertical adjustment stringer 402 is needed, so that the longitudinal length of whole system is adjusted, to adapt to the building of various sizes Plate.The downside of vertical adjustment stringer 402 is further fixed on a vertical adjustment support beam 403, and vertical adjustment support beam 403 In the side for adjusting crossbeam 401 close to first longitudinal direction, to guarantee the intensity of vertical adjustment module 4.
Referring to Fig.1 3, vertical adjustment module 4 further includes that second longitudinal direction adjusts crossbeam 404, and it is logical that second longitudinal direction adjusts crossbeam 404 It crosses longitudinal buckle 6 to connect with the standard stringer 102 of standard module 1, vertical adjustment stringer 402 is fixed on second longitudinal direction and adjusts crossbeam On 404, vertical adjustment stringer 402 can effectively be supported in this way, prevent vertical adjustment stringer 402 from deflecting, be guaranteed Construction safety is reliable.
Referring to Fig.1 4, the width of cantilevered corner beam 5 is less than the half of 3 width of lateral adjustments module, and one end of cantilevered corner beam 5 is fixed on It early tears open on support frame 2, the other end is connect with lateral adjustments module 3.Divide using vertical adjustment module 4 and lateral adjustments module 3 Not Tiao Jie longitudinal length and when transverse width dimension, the corner between vertical adjustment module 4 and lateral adjustments module 3 utilizes cantilevered corner beam 5 fillings.Specifically, cantilevered corner beam 5 includes first jiao of crossbeam, 501, second jiaos of crossbeams 503 and angle stringer 502, stringer 502 one end in angle is solid It is scheduled on the upside of first jiao of crossbeam 501, the other end is slidably connected the lateral adjustments crossbeam 303 of lateral adjustments module 3, and second jiao horizontal Beam 503 is fixed on middle side part under angle stringer 502, and diagonal beam 5 provides support.
Referring to Fig.1 5, support 202 includes a horizontal support baseboard 2021, standard module 1,3 and of lateral adjustments module Vertical adjustment module 4 is both supported upon 2021 upside of support baseboard, and the downside of support baseboard 2021 is equipped with mounting groove 2026, accordingly , the upper end of support rod 201 is fixed with a horizontal top plate, and support baseboard 2021 is slidably mounted on top by mounting groove 2026 On plate.The side of support baseboard 2021 is equipped with limiting section 2025, prevents support baseboard 2021 from undesirable phase occurs with top plate To sliding.It keeps crossbeam 13 to be equipped with crossbeam bottom plate with the lattice crossbeam lower part of demoulding block 9 early, is set on the upside of support baseboard 2021 There is the clamping mechanism for being connected to crossbeam bottom plate two sides.Clamping mechanism includes the separating part 2022 that 2021 middle part of support baseboard is arranged in And the positioning plate 2023 of 2022 two sides of separating part is set, positioning plate 2023 is equipped in the side lower part close to separating part 2022 For fixing the limiting slot of crossbeam bottom plate.Separating part 2022 two sides difference fixed standard module 1, lateral adjustments module 3 or Vertical adjustment module 4, and can guarantee its spacing, while reducing the dosage of support rod 201 and support 202.Positioning plate One upper lateral part of 2023 close separating part 2022 is equipped with retention bead 2024, and positioning plate 2023 and retention bead 2024, which are formed, hangs The hanging mechanisms for connecing standard module 1, lateral adjustments module 3 and vertical adjustment module 4, on the downside of retention bead 2024 is formed The limiting slot stated, the downside of standard module 1, lateral adjustments module 3 and vertical adjustment module 4 are equipped with crossbeam bottom plate, crossbeam bottom Plate is articulated on support baseboard 2021 by limiting slot, and can be rotated, and problem will not be fallen off, thus can be to avoid Vertical-lift causes the problem of large labor intensity, and only needs one to two workers that can smoothly complete.In crossbeam bottom plate On be also provided with limiting slot, limiting slot is corresponding with positioning plate 2023, and crossbeam bottom plate is connected at positioning plate 2023 by limiting slot, It is prevented that transverse shifting occurs for standard module 1, lateral adjustments module 3 and vertical adjustment module 4.
Early demoulding block 9 includes early tearing crossbeam open and early tearing stringer open, and multiple morning tear stringer open and are fixed on the early upside for tearing crossbeam open, early tear open Crossbeam, which is fixed on, early to be torn open on support frame, specific to the present embodiment, standard horizontal beams 101, lateral adjustments crossbeam 303, first longitudinal direction tune Section crossbeam 401 and second longitudinal direction adjust crossbeam 404 and belong to early tear crossbeam, standard stringer 102, the second lateral adjustments stringer 302 open It belongs to early tear stringer open with vertical adjustment stringer 402.It is provided along its length recessing groove 15 in the upper middle side part for early tearing stringer open, Flitch fixed form is installed additional in recessing groove 15 when scene uses, will not destroy sectional materials cage, and repeatable to be used in turn, practicability is more By force.
Lateral adjustments module 3 can also be between two adjacent standard modules 1 of fixed lateral.Vertical adjustment module 4 can also To be fixed between two longitudinally adjacent standard modules 1.
The above described is only a preferred embodiment of the present invention, being not that the invention has other forms of limitations, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. Imitate embodiment.But without departing from the technical solutions of the present invention, according to the technical essence of the invention to above embodiments institute Any simple modification, equivalent variations and the remodeling made, still fall within the protection scope of technical solution of the present invention.

Claims (10)

1. a kind of roof plate-girder early tears system open, including early tears support frame open(2)Support frame is early torn open with being fixed on(2)On multiple morning tear open Module(9), it is characterised in that:Further include at least one set of holding supporting mechanism for keeping module and being used to support holding module, protects Module setting is held in two early demoulding blocks(9)Between, early tear support frame open(2)With early demoulding block(9)By keeping support after dismounting Mechanism supports keep module.
2. roof plate-girder according to claim 1 early tears system open, it is characterised in that:The holding module includes multiple supports Beam(11), supporting beam(11)Both ends be supported on early support frame of tearing open(2)On, supporting beam(11)Lower part offers support location hole, Early tear support frame open(2)With early demoulding block(9)After dismounting, supporting mechanism is kept to be supported on supporting beam with what support location hole matched (11)Lower part.
3. roof plate-girder according to claim 2 early tears system open, it is characterised in that:The supporting beam(11)Cross section be It is rectangular, supporting beam(11)Upside and early demoulding block(9)Upside is concordant.
4. roof plate-girder according to claim 1 early tears system open, it is characterised in that:The holding supporting mechanism is to keep branch Support upright bar(12), keep supported rod erecting(12)Upper end be equipped with diameter reduce support positioning pin, support positioning pin insertion described in Support positioning hole.
5. roof plate-girder according to claim 1 early tears system open, it is characterised in that:The holding module includes keeping crossbeam (13)With holding stringer(14), two holding crossbeams(13)Interval setting, at least two keep stringer(14)It is horizontal to be fixed on holding Beam(13)Upside, keep supporting mechanism to be independently arranged at two morning and tear support frame open(2)Between, keep crossbeam(13)It is fixed on guarantor Hold the upside of supporting mechanism.
6. roof plate-girder according to claim 5 early tears system open, it is characterised in that:The holding supporting mechanism includes support Bar(201)With the support for being fixed on post upper(202), support(202)Including support baseboard(2021), keep crossbeam(13) Lower part be equipped with crossbeam bottom plate, in support baseboard(2021)Upside is equipped with the clamping mechanism for being connected to crossbeam bottom plate two sides.
7. roof plate-girder according to claim 6 early tears system open, it is characterised in that:The clamping mechanism includes that setting exists Separating part in the middle part of support baseboard(2022)And it is arranged in separating part(2022)The positioning plate of two sides(2023), positioning plate (2023)Close to separating part(2022)A side lower part be equipped with limiting slot for fixing crossbeam bottom plate.
8. roof plate-girder according to claim 1 early tears system open, it is characterised in that:The morning demoulding block(9)It is torn open including early Crossbeam and it is early tear stringer open, multiple morning tear stringer open and are fixed on the early upside for tearing crossbeam open, early tear crossbeam open and are fixed on and early tear support frame open(2) On, recessing groove is provided along its length in the upper middle side part for early tearing stringer open(15).
9. roof plate-girder according to claim 1 early tears system open, it is characterised in that:The morning demoulding block(9)Including standard Module(1), lateral adjustments module(3)With vertical adjustment module(4), vertical adjustment module(4)The adjustable connection mark of lengthwise position Quasi-mode block(1), lateral adjustments module(3)The adjustable connection standard module in lateral position(1).
10. roof plate-girder according to claim 9 early tears system open, it is characterised in that:The lateral adjustments module(3)Setting In standard module(1)Lateral outer side, vertical adjustment module(4)It is arranged in standard module(1)Longitudinally outboard;The morning demoulding Block(9)It further include cantilevered corner beam(5), for being fixed on vertical adjustment module(4)With lateral adjustments module(3)The corner of connection, cantilevered corner beam (5)Width be less than lateral adjustments module(3)The half of width, cantilevered corner beam(5)One end be fixed on early support frame of tearing open(2) On, the other end and lateral adjustments module(3)Connection.
CN201710343592.0A 2017-05-16 2017-05-16 Roof plate-girder early tears system open Pending CN108868122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710343592.0A CN108868122A (en) 2017-05-16 2017-05-16 Roof plate-girder early tears system open

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710343592.0A CN108868122A (en) 2017-05-16 2017-05-16 Roof plate-girder early tears system open

Publications (1)

Publication Number Publication Date
CN108868122A true CN108868122A (en) 2018-11-23

Family

ID=64320574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710343592.0A Pending CN108868122A (en) 2017-05-16 2017-05-16 Roof plate-girder early tears system open

Country Status (1)

Country Link
CN (1) CN108868122A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109812012A (en) * 2019-03-25 2019-05-28 何其佳 A kind of template and its architecture system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109812012A (en) * 2019-03-25 2019-05-28 何其佳 A kind of template and its architecture system
CN109812012B (en) * 2019-03-25 2023-11-14 何其佳 Template and architecture system thereof

Similar Documents

Publication Publication Date Title
JP6059719B2 (en) Improved formwork support
EP3114292B1 (en) A formwork support structure
CN106812312A (en) Large span form bracing system and its construction method
SE1350956A1 (en) Device and method for wall molding or the like
CN106499411B (en) A kind of single-track tunnel macroportion inverted arch self-propelled suspension template and construction method
CN103452313A (en) Early-removing independent support strip
EP3121349B1 (en) Formwork structure for the execution of horizontal castings for the provision of floor slabs
JP2016125287A (en) Support metal fitting for beam bottom mold, joint part structure for pca beam, and construction method therefor
CN103603491B (en) Method for erecting beam plate post-cast strip template support frame
CN105421781A (en) Synchronous pouring construction method and formwork system for concrete ridge platform and structural floor slab
CN108868122A (en) Roof plate-girder early tears system open
CN106948597A (en) Roof plate-girder Quick Release fast-assembling system and its erection method
CN206801009U (en) Roof plate-girder Quick Release fast-assembling system
CN108589772A (en) Method is torn open for the platform modular system of piping lane top plate and the morning of early stripping formwork system
KR200443605Y1 (en) Frame panel supporting apparatus for concrete casting a bridge structure
CN206801005U (en) Roof plate-girder early tears system open
CN110700490A (en) Transfer floor large-span steel reinforced concrete beam and construction method
CN108868123A (en) Roof plate-girder early tears method open
CN105715046A (en) Steel and wood template component and construction method thereof
CN207686280U (en) A kind of aluminum alloy mould plate early dismantling head device that assortable full hall scaffold uses
CN206801007U (en) A kind of roof plate-girder is with beam and installs module
CN206015539U (en) A kind of beret truss assembled culvert support for shuttering
CN108867408B (en) Cantilever pouring method for single-box single-chamber arch bridge arch ring
CN110242039B (en) Using method for building template construction
CN114046040A (en) Self-supporting concrete prefabricated formwork for building roof pouring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181123