CN108868106A - Prefabrication construction external scaffolding connects wall mechanism and construction method - Google Patents

Prefabrication construction external scaffolding connects wall mechanism and construction method Download PDF

Info

Publication number
CN108868106A
CN108868106A CN201810727692.8A CN201810727692A CN108868106A CN 108868106 A CN108868106 A CN 108868106A CN 201810727692 A CN201810727692 A CN 201810727692A CN 108868106 A CN108868106 A CN 108868106A
Authority
CN
China
Prior art keywords
wall
scaffold
connection sleeve
connector
buried connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810727692.8A
Other languages
Chinese (zh)
Inventor
李大飞
金翔鹰
李功超
胡海伟
陈洪帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201810727692.8A priority Critical patent/CN108868106A/en
Publication of CN108868106A publication Critical patent/CN108868106A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of prefabrication construction external scaffoldings to connect wall mechanism and construction method, if this connect wall mechanism include several pre-buried connection sleeves in the prefabricated outer wall panel, on scaffold and involvement wall steel pipe corresponding with pre-buried connection sleeve, set on each company's connector of the wall steel pipe far from scaffold one end, the connector is threadedly coupled with the pre-buried connection sleeve.By the way that pre-buried connection sleeve is arranged in prefabricated outer wall panel, and connector is set far from scaffold one end in even wall steel pipe, during scaffold building, even wall steel pipe is passed through into the pre-buried connection sleeve connection in connector and prefabricated outer wall panel, the effective connection for realizing scaffold body and wall body structure, meets the whole stress and stability requirement of scaffold.

Description

Prefabrication construction external scaffolding connects wall mechanism and construction method
Technical field
The present invention relates to architectural engineering construction technique field, in particular to a kind of prefabrication construction external scaffolding Even wall mechanism and construction method.
Background technique
In Building Construction, it usually needs set up peripheral operation scaffold to meet concrete exterior wall structure Each processes such as template installation, reinforcing bar binding.Under normal circumstances, peripheral operation scaffold can choose steel tube fastener formula, socket joint The scaffold of the different types such as disk button.It is required according to industry standard, setting up for scaffold needs to be arranged a certain number of even walls Frame body and main structure are carried out drawknot by part, meet whole stress and stability requirement.
Existing wall-connecting piece generallys use steel pipe and the modes such as connect with pre-embedded steel slab in the structure or embedded steel tube.However, In prefabrication work progress, usual exterior wall uses prefabricated panel, and floor uses precast floor slab, therefore traditional foot Hand cradle wall-connecting piece cannot smoothly be implemented, and pre-embedded steel slab and embedded steel tube are difficult to carry out in prefabricated components.Therefore, in prefabrication and assembly construction In formula construction, a kind of easy applicable wall-connecting piece is needed, sets up requirement with meet external scaffolding.
Summary of the invention
The present invention for the technical problems in the prior art, it is simple and meet scaffold entirety to provide a kind of arrangement Stress and the prefabrication of stability requirement construction external scaffolding connect wall mechanism and construction method.
In order to solve the above-mentioned technical problem, the technical scheme is that:A kind of prefabrication construction out-mould scaffold Frame connects wall mechanism, including be set in prefabricated outer wall panel several pre-buried connection sleeves, on the scaffold and with pre-buried connector sleeve If the corresponding involvement wall steel pipe of cylinder, set on each even connector of the wall steel pipe far from scaffold one end, the connector with The pre-buried connection sleeve is threadedly coupled.
Further, the connector is screw rod, is equipped with and the external screw thread on the screw rod in the pre-buried connection sleeve The internal screw thread of adaptation, the screw rod are sheathed in the pre-buried connection sleeve.
Further, it is described it is pre-buried connection sleeve outer end be located in the prefabricated outer wall panel, the prefabricated outer wall panel and Pit is equipped between the top of the pre-buried connection sleeve, the pit is exposed in the outer end of the pre-buried connection sleeve.
Further, the pre-buried connection sleeve is equipped with embedded bar far from one end of connector.
Further, the even wall steel pipe is equipped with steel plate far from scaffold one end, and the connector is fixed on the steel plate On.
Further, the surface of the vertical scaffold of even wall steel pipe and the connector, the steel plate foot in parallel The surface of hand cradle.
Further, pre-buried connection sleeve gap setting in the horizontal direction, the connector and the pre-buried connection Sleeve corresponds.
The present invention also provides the construction parties that a kind of prefabrication construction external scaffolding as described above connects wall mechanism Method includes the following steps:
S1:Prefabricated outer wall panel is made, several pre-buried connection sleeves are set in the prefabricated outer wall panel according to design requirement;
S2:Set up scaffold, and if in the scaffold corresponding with prefabricated outer wall panel side, involvement wall steel pipe is set, Connector is arranged far from one end of scaffold in the even wall steel pipe;
S3:The connector is threadedly coupled with the pre-buried connection sleeve, is connected as scaffold with prefabricated outer wall panel It is whole;
S4:After scaffold use, connector is screwed out from pre-buried connection sleeve, makes scaffold from precast facade It is removed on plate.
Further, in the step S1, when pre-buried connection sleeve is arranged on the prefabricated outer wall panel, make pre-buried connection The outer end of sleeve is located in prefabricated outer wall panel, and sets in prefabricated outer wall panel position corresponding with the pre-buried connection top of sleeve Pit is set, exposes the outer end of the pre-buried connection sleeve from the pit.
It further, further include being tamped using waterproof cement mortar described pre- after removing scaffold in the step S4 Bury connection sleeve and pit.
Prefabrication construction external scaffolding provided by the invention connects wall mechanism and construction method, this connects wall mechanism packet If including several pre-buried connection sleeves being set in prefabricated outer wall panel, on the scaffold and involvement corresponding with pre-buried connection sleeve Wall steel pipe, set on each even connector of the wall steel pipe far from scaffold one end, the connector and the pre-buried connector sleeve Cylinder is threadedly coupled.It is arranged by the way that pre-buried connection sleeve is arranged in prefabricated outer wall panel, and in even wall steel pipe far from scaffold one end Connector is connected even wall steel pipe by the pre-buried connection sleeve in connector and prefabricated outer wall panel during scaffold building It connects, realizes effective connection of scaffold body and wall body structure, meet the whole stress and stability requirement of scaffold.
Detailed description of the invention
Fig. 1 is that prefabrication construction external scaffolding of the present invention connects the structural representation that wall mechanism is located at wall side Figure;
Fig. 2 is that prefabrication construction external scaffolding of the present invention connects the structural representation that wall mechanism is located at scaffold side Figure.
As shown in the figure:10, prefabricated outer wall panel;110, pit;20, pre-buried connection sleeve;30, connect wall steel pipe;40, it connects Part;50, steel plate;60, embedded bar;70, wallboard is poured after.
Specific embodiment
The present invention is described in detail with reference to the accompanying drawing:
As shown in Figs. 1-2, the present invention provides a kind of prefabrication construction external scaffoldings to connect wall mechanism, including sets Several pre-buried connection sleeves 20 in prefabricated outer wall panel 10, be set to it is on scaffold and corresponding several with pre-buried connection sleeve 20 Even wall steel pipe 30, set on it is each it is described even connector 40 of the wall steel pipe 30 far from scaffold one end, the connector 40 with it is described Pre-buried connection sleeve 30 is threadedly coupled.By the way that pre-buried connection sleeve 20 is arranged in prefabricated outer wall panel 10, and in even wall steel pipe 30 Far from scaffold one end be arranged connector 40, during scaffold building, will even wall steel pipe 30 by connector 40 with it is prefabricated Pre-buried connection sleeve 20 connection in Side fascia 10, realizes effective connection of scaffold body and wall body structure, guarantees scaffold Whole stress and stability requirement.
Preferably, the connector 40 is screw rod, is equipped with and the outer spiral shell on the screw rod in the pre-buried connection sleeve 20 The internal screw thread of line adaptation, the screw rod are sheathed in the pre-buried connection sleeve 20, and the two is threadedly coupled.Preferably, the company Wall steel pipe 30 is equipped with steel plate 50 far from scaffold one end, and the connector 40 is fixed on the steel plate 50, the even wall steel pipe 30 and the vertical scaffold of connector 40 surface, the surface of the parallel scaffold of the steel plate 50.Specifically, steel plate 50 Set on the outer end of even wall steel pipe 30, and it is vertical with even wall steel pipe 30, screw rod is weldingly fixed on steel plate 50, and steel plate 50 opposite can connect Wall steel pipe 30 rotates, to by screw rod precession or screw out pre-buried connection sleeve 20, realizes the connection and disassembly of the two.
Preferably, the outer end of the pre-buried connection sleeve 20 is located in the prefabricated outer wall panel 10, the prefabricated outer wall panel 10 and it is described it is pre-buried connection sleeve 20 top between be equipped with pit 110, it is described it is pre-buried connection sleeve 20 outer end expose described in Pit 110.Specifically, screw rod is screwed out from pre-buried connection sleeve 20, scaffold is removed after scaffold use, It is using waterproof cement mortar that pre-buried connection sleeve 20 and the repairing of 110 position of pit is closely knit at this time, guarantee prefabricated outer wall panel 10 Waterproof performance.
Preferably, the pre-buried connection sleeve 20 is equipped with embedded bar 60 far from one end of connector 40.Specifically, pre-buried Reinforcing bar 60 is the bar dowel with the end vertical of pre-buried connection sleeve 20, and guarantee prefabricated outer wall panel 10 pours the reliable of wallboard 70 with after Connection.
Preferably, the pre-buried connection sleeve 20 gap setting in the horizontal direction, the connector 40 and the pre-buried company Female connector cylinder 20 corresponds, it should be noted that when processing prefabricated outer wall panel 10, determines pre-buried connection sleeve according to design drawing 20 position and quantity, when setting up scaffold, even the position of wall steel pipe 30 is then according to the position sum number of pre-buried connection sleeve 20 Amount setting is arranged connector 40 close to one end of prefabricated outer wall panel 10 in even wall steel pipe 30, makes connector 40 and pre-buried connector sleeve Cylinder 20 is corresponding, to guarantee being reliably connected for the two.
The present invention also provides the construction parties that a kind of prefabrication construction external scaffolding as described above connects wall mechanism Method includes the following steps:
S1:Prefabricated outer wall panel 10 is made, several pre-buried connections are arranged in the prefabricated outer wall panel 10 according to design requirement Sleeve 20;Specifically, the quantity of pre-buried connection sleeve 20 and position are determined according to design drawing, and in pre-buried connection sleeve 20 Embedded bar 60 is arranged in inner end (i.e. different from the one end connecting with connector 40), in the present embodiment, embedded bar 60 using with it is pre- The bar dowel for burying the end vertical of connection sleeve 20 guarantees that prefabricated outer wall panel 10 pours being reliably connected for wallboard 70 with after, meanwhile, When pre-buried connection sleeve 20 is set on the prefabricated outer wall panel 10, the outer end of pre-buried connection sleeve 20 is made to be located at prefabricated outer wall panel 10 It is interior, 3~5cm of surface apart from prefabricated outer wall panel 20, and it is right in prefabricated outer wall panel 10 and the top of the pre-buried connection sleeve 20 The position setting pit 110 answered exposes the outer end of the pre-buried connection sleeve 20 from the pit 110.
S2:Scaffold is set up, and if involvement wall steel pipe is arranged in scaffold side corresponding with prefabricated outer wall panel 10 30, connector 40 is set far from one end of scaffold in the even wall steel pipe 30;Even the position of wall steel pipe 30 is according to pre-buried connection The position of sleeve 20 and quantity setting, in the present embodiment, even wall steel pipe 30 in two steps two across mode installed, and even wall Steel pipe 30 is equipped with steel plate 50 far from scaffold one end, and connector 40 is fixed on steel plate 50, in the present embodiment, connects 30 He of wall steel pipe The surface of the vertical scaffold of connector 40, the surface of the parallel scaffold of steel plate 50, connector 40 are screw rod, and screw rod is weldingly fixed on On steel plate 50, steel plate 50 can be rotated relative to wall steel pipe 30 is connected, to by screw rod precession or screw out pre-buried connection sleeve 20, realize two The connection and disassembly of person.
S3:The connector 40 is threadedly coupled with the pre-buried connection sleeve 20, makes scaffold and prefabricated outer wall panel 10 It is connected as entirety, i.e., is equipped with internal screw thread compatible with the external screw thread of screw rod in pre-buried connection sleeve 20, steel plate 50 is rotated, by spiral shell In the pre-buried connection sleeve 20 of bar precession, the steady connection of the two is realized.
S4:After scaffold use, connector 40 is screwed out from pre-buried connection sleeve 20, makes scaffold from prefabricated It is removed on Side fascia 10.After removing scaffold, the pre-buried connection sleeve 20 and pit are tamped using waterproof cement mortar 110, guarantee the waterproof performance of prefabricated outer wall panel 10.
In conclusion prefabrication construction external scaffolding provided by the invention connects wall mechanism and construction method, it should Even wall mechanism include several pre-buried connection sleeves 20 in the prefabricated outer wall panel 10, on scaffold and with pre-buried connector sleeve If cylinder 20 corresponding involvement wall steel pipes 30, set on it is each it is described even connector 40 of the wall steel pipe 30 far from scaffold one end, it is described Connector 40 is threadedly coupled with the pre-buried connection sleeve 30.By the way that pre-buried connection sleeve 20 is arranged in prefabricated outer wall panel 10, And connector 40 is set far from scaffold one end in even wall steel pipe 30, during scaffold building, even wall steel pipe 30 is passed through Connector 40 is connect with the pre-buried connection sleeve 20 in prefabricated outer wall panel 10, realizes that scaffold body and the effective of wall body structure connect It connects, meets the whole stress and stability requirement of scaffold.
Although embodiments of the present invention are illustrated in specification, these embodiments are intended only as prompting, It should not limit protection scope of the present invention.It is equal that various omission, substitution, and alteration are carried out without departing from the spirit and scope of the present invention It should be included within the scope of the present invention.

Claims (10)

1. a kind of prefabrication construction external scaffolding connects wall mechanism, which is characterized in that including being set in prefabricated outer wall panel If several pre-buried connection sleeves, be set on scaffold and involvement wall steel pipe corresponding with pre-buried connection sleeve, set on each institute Connector of the company's of stating wall steel pipe far from scaffold one end, the connector are threadedly coupled with the pre-buried connection sleeve.
2. prefabrication construction external scaffolding according to claim 1 connects wall mechanism, which is characterized in that the company Fitting is screw rod, is equipped with the internal screw thread being adapted to the external screw thread on the screw rod, the screw rod set in the pre-buried connection sleeve In the pre-buried connection sleeve.
3. prefabrication construction external scaffolding according to claim 1 connects wall mechanism, which is characterized in that described pre- Bury connection sleeve outer end be located in the prefabricated outer wall panel, the prefabricated outer wall panel and it is described it is pre-buried connect sleeve top it Between be equipped with pit, the pit is exposed in the outer end of the pre-buried connection sleeve.
4. prefabrication construction external scaffolding according to claim 1 connects wall mechanism, which is characterized in that described pre- It buries connection sleeve and is equipped with embedded bar far from one end of connector.
5. prefabrication construction external scaffolding according to claim 1 connects wall mechanism, which is characterized in that the company Wall steel pipe is equipped with steel plate far from scaffold one end, and the connector is fixed on the steel plate.
6. prefabrication construction external scaffolding according to claim 5 connects wall mechanism, which is characterized in that the company The surface of the vertical scaffold of wall steel pipe and connector, the surface of the steel plate scaffold in parallel.
7. prefabrication construction external scaffolding according to claim 1 connects wall mechanism, which is characterized in that described pre- Connection sleeve gap setting in the horizontal direction is buried, the connector and the pre-buried connection sleeve correspond.
8. described in any item prefabrication construction external scaffoldings connect the construction party of wall mechanism according to claim 1~7 Method, which is characterized in that include the following steps:
S1:Prefabricated outer wall panel is made, several pre-buried connection sleeves are set in the prefabricated outer wall panel according to design requirement;
S2:Set up scaffold, and if in the scaffold corresponding with prefabricated outer wall panel side, involvement wall steel pipe is set, described Even connector is arranged far from one end of scaffold in wall steel pipe;
S3:The connector is threadedly coupled with the pre-buried connection sleeve, scaffold and prefabricated outer wall panel is made to be connected as entirety;
S4:After scaffold use, connector is screwed out from pre-buried connection sleeve, makes scaffold from prefabricated outer wall panel It removes.
9. prefabrication construction external scaffolding according to claim 8 connects the construction method of wall mechanism, feature It is, in the step S1, when pre-buried connection sleeve is arranged on the prefabricated outer wall panel, makes the outer end position of pre-buried connection sleeve Pit is set in prefabricated outer wall panel, and in prefabricated outer wall panel position corresponding with the pre-buried connection top of sleeve, makes institute Expose from the pit outer end for stating pre-buried connection sleeve.
10. prefabrication construction external scaffolding according to claim 9 connects the construction method of wall mechanism, feature Be, in the step S4, further include after removing scaffold, using waterproof cement mortar tamp the pre-buried connection sleeve and Pit.
CN201810727692.8A 2018-07-05 2018-07-05 Prefabrication construction external scaffolding connects wall mechanism and construction method Pending CN108868106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810727692.8A CN108868106A (en) 2018-07-05 2018-07-05 Prefabrication construction external scaffolding connects wall mechanism and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810727692.8A CN108868106A (en) 2018-07-05 2018-07-05 Prefabrication construction external scaffolding connects wall mechanism and construction method

Publications (1)

Publication Number Publication Date
CN108868106A true CN108868106A (en) 2018-11-23

Family

ID=64299294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810727692.8A Pending CN108868106A (en) 2018-07-05 2018-07-05 Prefabrication construction external scaffolding connects wall mechanism and construction method

Country Status (1)

Country Link
CN (1) CN108868106A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359693A (en) * 2019-06-24 2019-10-22 中国五冶集团有限公司 A kind of boat scaffold structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100681882B1 (en) * 2006-01-27 2007-02-12 주식회사 퍼스폼 The precast kicker block and the method of construction using the same
CN101892738A (en) * 2010-08-20 2010-11-24 中太建设集团股份有限公司 Embedded scaffold connecting tube and construction method thereof
CN205713189U (en) * 2016-06-15 2016-11-23 中民筑友科技投资有限公司 External hanging type preventer
CN107447975A (en) * 2016-05-31 2017-12-08 桂林建筑安装工程有限公司 Exterior wall scaffold tapered cup nut wall-connecting piece
CN208734052U (en) * 2018-07-05 2019-04-12 上海建工七建集团有限公司 Prefabrication construction external scaffolding connects wall member

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100681882B1 (en) * 2006-01-27 2007-02-12 주식회사 퍼스폼 The precast kicker block and the method of construction using the same
CN101892738A (en) * 2010-08-20 2010-11-24 中太建设集团股份有限公司 Embedded scaffold connecting tube and construction method thereof
CN107447975A (en) * 2016-05-31 2017-12-08 桂林建筑安装工程有限公司 Exterior wall scaffold tapered cup nut wall-connecting piece
CN205713189U (en) * 2016-06-15 2016-11-23 中民筑友科技投资有限公司 External hanging type preventer
CN208734052U (en) * 2018-07-05 2019-04-12 上海建工七建集团有限公司 Prefabrication construction external scaffolding connects wall member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359693A (en) * 2019-06-24 2019-10-22 中国五冶集团有限公司 A kind of boat scaffold structure
CN110359693B (en) * 2019-06-24 2024-04-09 中国五冶集团有限公司 Suspension type scaffold structure

Similar Documents

Publication Publication Date Title
CN202391019U (en) End part thickened grouting connector of steel bar
CN105839677A (en) Advanced water prevention construction process for post-cast strip of side wall of basement
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
KR200417925Y1 (en) piping inspect of a wall reclamation style
CN208734052U (en) Prefabrication construction external scaffolding connects wall member
CN108868106A (en) Prefabrication construction external scaffolding connects wall mechanism and construction method
CN108411941A (en) A kind of assembled monolithic concrete structure pipe gallery and its construction method
CN102865087B (en) Embedded grout pipe device in lining concrete of chamber and construction method
RU2008152058A (en) VERTICAL BUILDING SEAMS
CN218374567U (en) Can fix a position ALC wallboard reinforced structure that can exempt from to plaster
CN210950229U (en) Embedded device for gas inlet pipe sleeve in indoor shear wall
AU2013366093B2 (en) Reinforced blockwork construction method
KR20220049720A (en) Rapid Construction Structure of Core Part Using Multi-Story Precast Wall
CN103835421B (en) Leakage-proof floor and anti-seepage construction method
CN208777720U (en) Detachable straight thread steel bar base of wall hanging mould inclined strut
CN217631737U (en) Embedded enclosure structure of adjustable prefabricated assembly that suitability is strong
CN114197526B (en) Formwork system with vertical structure by reverse construction method and construction method
KR101072258B1 (en) Column connectiom parts construction method
CN108951887B (en) Construction method of assembled type autoclaved lightweight concrete parapet joint
CN207743669U (en) Cable duct structure for large equipment base side
CN110761399A (en) Vertical splicing structure of prefabricated wall board and assembling method thereof
KR20040046578A (en) The construction method of drain and bottom of building using mixed rubbernized asphalt with polyurethan resin and stainless drain
CN214833311U (en) Assembled drainage pipe
CN213087168U (en) Assembled T-shaped plate connecting node structure
CN209907654U (en) Special prefabricated component for mounting electrical box

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination