CN108842723A - A kind of thin plate construction of concrete lining method - Google Patents

A kind of thin plate construction of concrete lining method Download PDF

Info

Publication number
CN108842723A
CN108842723A CN201810806139.3A CN201810806139A CN108842723A CN 108842723 A CN108842723 A CN 108842723A CN 201810806139 A CN201810806139 A CN 201810806139A CN 108842723 A CN108842723 A CN 108842723A
Authority
CN
China
Prior art keywords
concrete
thin plate
parts
coarse aggregate
plate construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810806139.3A
Other languages
Chinese (zh)
Other versions
CN108842723B (en
Inventor
吴小玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Jincheng Zhixin Construction Engineering Co Ltd
Original Assignee
Sichuan Jincheng Zhixin Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Jincheng Zhixin Construction Engineering Co Ltd filed Critical Sichuan Jincheng Zhixin Construction Engineering Co Ltd
Priority to CN201810806139.3A priority Critical patent/CN108842723B/en
Publication of CN108842723A publication Critical patent/CN108842723A/en
Application granted granted Critical
Publication of CN108842723B publication Critical patent/CN108842723B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/02Making or lining canals
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/08Slag cements
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2201/00Mortars, concrete or artificial stone characterised by specific physical values
    • C04B2201/50Mortars, concrete or artificial stone characterised by specific physical values for the mechanical strength
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/22Improving land use; Improving water use or availability; Controlling erosion

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Structural Engineering (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Organic Chemistry (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

The present invention relates to a kind of thin plate construction of concrete lining methods, belong to technical field of building construction, cleaning including slope surface and compacting leveling, slope surface be laid with sandy gravel loaded filter, be laid with lower composite geo-membrane, be laid with geotextiles, the upper composite geo-membrane of layings, the preparation of concrete, the pouring of lower-layer concrete panel, the pouring of upper layer concrete slab, finisher is plastered and manually press polish, the maintenance of concrete.Thin plate construction of concrete lining method of the invention, it is rolled and is tamped in slope surface, pouring for concrete slab is divided into pouring for lower-layer concrete panel and pouring for upper layer concrete slab simultaneously, improve the compression strength and tensile splitting strength of concrete, in combination with lower composite geo-membrane, the mutual cooperation of geotextiles, upper composite geo-membrane, the concrete-lined antiseepage effect of thin plate is improved, the concrete-lined service life of thin plate is extended.

Description

A kind of thin plate construction of concrete lining method
Technical field
The present invention relates to technical field of building construction, more specifically, it is related to a kind of thin plate construction of concrete lining side Method.
Background technique
Traditional large channel lining project construction technology is generally mainly grouted using slip form concreting or use mixed Solidifying soil prefabricated board lining cutting.When using slipform lining, the uniformity and flat appearance degree of concrete are poor, and speed of application is slower;It adopts When with grouting concrete prefabricated board lining cutting, puzzle joint area accounts for about the 10% of the lining cutting gross area, and there are long in puzzle joint mortar cracking, seam Grass, lining cutting body unstable failure phenomenon, concrete lining course antiseepage effect are lower.
Summary of the invention
The purpose of the present invention is to provide a kind of thin plate construction of concrete lining methods, not only increase the anti-of concrete Compressive Strength and tensile splitting strength are improved in combination with lower composite geo-membrane, the mutual cooperation of geotextiles, upper composite geo-membrane The concrete-lined antiseepage effect of thin plate, extends thin plate concrete-lined service life.Simultaneously because being added in coarse aggregate The fried mixing of discarded concrete, reduces construction cost.
Above-mentioned technical purpose of the invention technical scheme is that:
A kind of thin plate construction of concrete lining method, includes the following steps:
(1)Slope surface is cleared up, thin plate concrete lining side is laid in canal dike and fills the canal dike soil body, and extra-fill 30-40cm, later It is rolled with self-propelled vibrating roller along channel direction walking, is carried out cutting slope from top to bottom with backacter, and eliminate extra-fill part, Then compacting leveling is carried out to slope surface with dynamic compaction machinery, makes head fall 1-5%, cross fall 1:1-3;
(2)It is successively laid with sandy gravel loaded filter, lower composite geo-membrane, geotextiles, upper composite geo-membrane from bottom to top in slope surface;
(3)Water, cement, coarse aggregate, sand, flyash, high efficiency water reducing agent, air entraining agent, retarder are stirred, coagulation is formed Soil, the slump of concrete are 90-130mm;
(4)In upper composite geo-membrane far from slope surface side vibration sliding-mode lining machine continuous concrete, the thickness of concrete For 10-12cm, lower-layer concrete panel is formed;
(5)After slope surface displacement is stablized, it is laid with and is connected with vibration sliding-mode lining machine far from slope surface side in lower-layer concrete panel layer Continuous casting concrete, concrete with a thickness of 5-8cm, form upper layer concrete slab;
(6)After the completion of concreting, static 1-2h is plastered with finisher, artificial press polish;
(7)On upper layer, concrete surface plate surface sprays curing agent, and is laid with two layers of plastic film in upper layer concrete surface plate surface, together When cover two layers of woven straw, conserve 7-10 days, remove woven straw, plastic foil later, and in the progress of upper layer concrete surface plate surface Watering moisturizing, conserves 21-25 days, completes thin plate construction of concrete lining.
By using above-mentioned technical proposal, leveling is rolled and tamped in slope surface, while concrete slab pours point For pouring for lower-layer concrete panel and pouring for upper layer concrete slab, the compression strength and Split-tension of Rolled of concrete are improved Intensity improves thin plate concrete lining in combination with lower composite geo-membrane, the mutual cooperation of geotextiles, upper composite geo-membrane Antiseepage effect, extend the concrete-lined service life of thin plate.
Preferably, the concrete, prepares with the following method:Water, cement, sand, flyash are put into stirring In kettle, 30-40min is stirred, puts into high efficiency water reducing agent later, continues to stir 5-8min, investment air entraining agent, retarder stirring are mixed It closes, continues to stir 20-30min, then put into coarse aggregate, continue to stir 10-15min, obtain concrete.
By using above-mentioned technical proposal, mixing each raw material of concrete in batches not only increases concrete Uniformity, while improving the compression strength and tensile splitting strength of concrete.
Preferably, the concrete, according to parts by weight, raw material include 98-120 parts of water, 171-195 parts of cement, 1250-1420 parts of coarse aggregate, 652-723 parts of sand, 65-73 parts of flyash, 4.1-4.6 parts of high efficiency water reducing agent, air entraining agent 2.2- 2.7 parts, 1.1-1.23 parts of retarder.
Preferably, the concrete, according to parts by weight, raw material include 110 parts of water, 183 parts of cement, coarse aggregate 1362 parts, 684 parts of sand, 69 parts of flyash, 4.22 parts of high efficiency water reducing agent, 2.46 parts of air entraining agent, 1.15 parts of retarder.
By using above-mentioned technical proposal, each raw material proportioning of concrete is optimized, concrete is further increased Compression strength and tensile splitting strength.
Preferably, the coarse aggregate include the middle stone of 10-20mm, the handstone of 5-10mm, 5-25mm it is discarded mixed Solidifying soil slag, the weight of the middle stone account for the 48-55wt% of coarse aggregate total weight, and the weight of the handstone accounts for coarse aggregate gross weight The weight of the 31-39wt% of amount, the discarded concrete slag account for the 6-21wt% of coarse aggregate total weight.
By using above-mentioned technical proposal, the mutual cooperation of middle stone and handstone further improves the anti-of concrete Compressive Strength and tensile splitting strength, while discarded concrete slag being added in coarse aggregate, in the case where guaranteeing concrete quality, Reduce construction cost.
Preferably, the weight of the middle stone accounts for the 52wt% of coarse aggregate total weight, and the weight of the handstone accounts for rough set Expect the 35wt% of total weight, the weight of the discarded concrete slag accounts for the 13wt% of coarse aggregate total weight.
By using above-mentioned technical proposal, centering stone, handstone, discarded concrete slag proportion optimize, improve The compression strength and tensile splitting strength of concrete.
Preferably, the cement is selected from ordinary portland cement, portland cement, KS- slag cements.
Preferably, the high efficiency water reducing agent is polycarboxylate water-reducer, naphthalene water reducer, lignin sulfonic acid sodium salt water-reducing agent One of or it is a variety of.
Preferably, the air entraining agent is fatty alcohol sulfonate class air entraining agent, rosin tree lipid air entraining agent, alkyl benzene sulphonate One of salt air entraining agent is a variety of.
Preferably, the retarder is cellulose family retarder, in phosphoric acid class retarder, hydroxycarboxylic acid retarder It is one or more.
By using above-mentioned technical proposal, cement, high efficiency water reducing agent, air entraining agent, retarder are optimized respectively, it can be with It is selected according to the actual situation, in the case where guaranteeing that concrete performance is met the requirements, reduces production cost.
In conclusion the invention has the advantages that:
The first, thin plate construction of concrete lining method of the invention, compression strength and the splitting for not only increasing concrete are anti- Tensile strength improves thin plate concrete lining in combination with lower composite geo-membrane, the mutual cooperation of geotextiles, upper composite geo-membrane The antiseepage of block acts on, and extends the concrete-lined service life of thin plate.
The second, by the way that leveling is rolled and tamped to slope surface, and concrete slab is poured in two times, that is, under completing After layer concrete panel pours, after slope surface displacement steadily, pouring for upper layer concrete slab is being carried out, is being further increased The compression strength and tensile splitting strength of concrete.
Third, the optimization by matching to concrete material, compression strength and the splitting for further improving concrete are anti- Tensile strength.
4th, by the mutual cooperation of both middle stone and handstone, the compression strength of concrete is further improved And tensile splitting strength, while addition discarded concrete slag is reduced in the case where guaranteeing concrete quality in coarse aggregate Construction cost.
Specific embodiment
Invention is further described in detail with reference to embodiments.It should be understood that described in the embodiment of the present invention Preparation method is only used for illustrating the present invention, rather than limiting the invention, to this hair under concept thereof of the invention The simple modifications of bright preparation method belong to the scope of protection of present invention.
The raw material weight percentage of coarse aggregate in 1 embodiment of table(Unit:wt%)
Each material content of concrete in 2 embodiment of table(Unit:Kg)
Embodiment 1
(1)Slope surface is cleared up, thin plate concrete lining side is laid in canal dike and fills the canal dike soil body, and extra-fill 30cm, Zhi Houyong Self-propelled vibrating roller is rolled along channel direction walking, is carried out cutting slope from top to bottom with backacter, and eliminate extra-fill part, so Compacting leveling is carried out to slope surface with dynamic compaction machinery afterwards, makes head fall 1%, cross fall 1:1;
(2)It is successively laid with sandy gravel loaded filter, lower composite geo-membrane, geotextiles, upper composite geo-membrane from bottom to top in slope surface;
(3)By water, portland cement, coarse aggregate, sand, flyash, lignin sulfonic acid sodium salt water-reducing agent, rosin tree lipid bleed Agent, cellulose family retarder are stirred, and form concrete, and the slump of concrete is 130mm;
(4)In upper composite geo-membrane far from slope surface side vibration sliding-mode lining machine continuous concrete, the thickness of concrete For 10cm, lower-layer concrete panel is formed;
(5)After slope surface displacement is stablized, it is laid with and is connected with vibration sliding-mode lining machine far from slope surface side in lower-layer concrete panel layer Continuous casting concrete, concrete with a thickness of 8cm, form upper layer concrete slab;
(6)After the completion of concreting, static 1h is plastered with finisher, artificial press polish;
(7)On upper layer, concrete surface plate surface sprays curing agent, and is laid with two layers of plastic film in upper layer concrete surface plate surface, together When cover two layers of woven straw, conserve 10 days, remove woven straw, plastic foil later, and spilt in upper layer concrete surface plate surface Water moisturizing conserves 21 days, completes thin plate construction of concrete lining.
Wherein, concrete is prepared with the following method:Water, portland cement, sand, flyash are put into stirred tank In, stir 30min, later put into lignin sulfonic acid sodium salt water-reducing agent, continue stir 8min, investment rosin tree lipid air entraining agent, Cellulose family retarder is stirred, and is continued to stir 20min, is then put into coarse aggregate, is continued to stir 15min, is obtained concrete.
Embodiment 2-3
It is in place of the difference of embodiment 2-3 and embodiment 1, the raw material proportioning for preparing concrete is different, as shown in Table 1 and Table 2.
Embodiment 4
(1)Slope surface is cleared up, thin plate concrete lining side is laid in canal dike and fills the canal dike soil body, and extra-fill 35cm, Zhi Houyong Self-propelled vibrating roller is rolled along channel direction walking, is carried out cutting slope from top to bottom with backacter, and eliminate extra-fill part, so Compacting leveling is carried out to slope surface with dynamic compaction machinery afterwards, makes head fall 3%, cross fall 1:2;
(2)It is successively laid with sandy gravel loaded filter, lower composite geo-membrane, geotextiles, upper composite geo-membrane from bottom to top in slope surface;
(3)By water, KS- slag cements, coarse aggregate, sand, flyash, polycarboxylate water-reducer, fatty alcohol sulfonate class air entraining agent, Hydroxycarboxylic acid retarder is stirred, and forms concrete, and the slump of concrete is 110mm;
(4)In upper composite geo-membrane far from slope surface side vibration sliding-mode lining machine continuous concrete, the thickness of concrete For 11cm, lower-layer concrete panel is formed;
(5)After slope surface displacement is stablized, it is laid with and is connected with vibration sliding-mode lining machine far from slope surface side in lower-layer concrete panel layer Continuous casting concrete, concrete with a thickness of 7cm, form upper layer concrete slab;
(6)After the completion of concreting, static 1.5h is plastered with finisher, artificial press polish;
(7)On upper layer, concrete surface plate surface sprays curing agent, and is laid with two layers of plastic film in upper layer concrete surface plate surface, together When cover two layers of woven straw, conserve 9 days, remove woven straw, plastic foil later, and sprinkle water in upper layer concrete surface plate surface Moisturizing conserves 23 days, completes thin plate construction of concrete lining.
Wherein, concrete is prepared with the following method:Water, KS- slag cements, sand, flyash are put into stirred tank In, 35min is stirred, puts into polycarboxylate water-reducer later, continues to stir 7min, puts into fatty alcohol sulfonate class air entraining agent, hydroxyl Carboxylic acids retarder is stirred, and is continued to stir 25min, is then put into coarse aggregate, is continued to stir 12min, is obtained concrete.
Embodiment 5
(1)Slope surface is cleared up, thin plate concrete lining side is laid in canal dike and fills the canal dike soil body, and extra-fill 40cm, Zhi Houyong Self-propelled vibrating roller is rolled along channel direction walking, is carried out cutting slope from top to bottom with backacter, and eliminate extra-fill part, so Compacting leveling is carried out to slope surface with dynamic compaction machinery afterwards, makes head fall 5%, cross fall 1:3;
(2)It is successively laid with sandy gravel loaded filter, lower composite geo-membrane, geotextiles, upper composite geo-membrane from bottom to top in slope surface;
(3)By water, ordinary portland cement, coarse aggregate, sand, flyash, naphthalene water reducer, alkyl benzene sulfonate air entraining agent, phosphoric acid Class retarder is stirred, and forms concrete, and the slump of concrete is 90mm;
(4)In upper composite geo-membrane far from slope surface side vibration sliding-mode lining machine continuous concrete, the thickness of concrete For 12cm, lower-layer concrete panel is formed;
(5)After slope surface displacement is stablized, it is laid with and is connected with vibration sliding-mode lining machine far from slope surface side in lower-layer concrete panel layer Continuous casting concrete, concrete with a thickness of 5cm, form upper layer concrete slab;
(6)After the completion of concreting, static 2h is plastered with finisher, artificial press polish;
(7)On upper layer, concrete surface plate surface sprays curing agent, and is laid with two layers of plastic film in upper layer concrete surface plate surface, together When cover two layers of woven straw, conserve 7 days, remove woven straw, plastic foil later, and sprinkle water in upper layer concrete surface plate surface Moisturizing conserves 25 days, completes thin plate construction of concrete lining.
Wherein, concrete is prepared with the following method:Water, ordinary portland cement, sand, flyash are put into stirred tank, 40min is stirred, puts into naphthalene water reducer later, continues to stir 5min, puts into alkyl benzene sulfonate air entraining agent, phosphoric acid class slow setting Agent is stirred, and is continued to stir 30min, is then put into coarse aggregate, is continued to stir 10min, is obtained concrete.
Comparative example 1
The difference of comparative example 1 and embodiment 4 is, thin plate construction of concrete lining method and step(1)In not to slope surface carry out Roll and tamp leveling.
Comparative example 2
The difference of comparative example 2 and embodiment 4 is, thin plate construction of concrete lining method is by step(5)Lower-layer concrete panel Pour and step(6)A step is merged into pouring for upper layer concrete slab, i.e. concrete slab continuously poured in one forms.
Comparative example 3
The difference of comparative example 3 and embodiment 4 is, prepares in concrete without addition coarse aggregate.
Comparative example 4
The difference of comparative example 4 and embodiment 4 is, without stone in addition in the coarse aggregate in concrete.
Comparative example 5
The difference of comparative example 5 and embodiment 4 is, without addition handstone in the coarse aggregate in concrete.
Comparative example 6
The difference of comparative example 6 and embodiment 4 is, without addition discarded concrete slag in the coarse aggregate in concrete.
Test case
After maintenance 28 days, under conditions of -40 DEG C, to embodiment 1-5 and comparative example 1-6, compression strength and Split-tension of Rolled are carried out The detection of intensity, testing result are as shown in table 3.
3 testing result of table
Detection project Compression strength/MPa Tensile splitting strength/MPa
Embodiment 1 51 5.21
Embodiment 2 55 5.34
Embodiment 3 50 5.29
Embodiment 4 62 5.38
Embodiment 5 59 5.32
Comparative example 1 23 1.74
Comparative example 2 42 3.94
Comparative example 3 18 1.46
Comparative example 4 22 1.87
Comparative example 5 31 3.01
Comparative example 6 61 5.24
From table 3 it is observed that thin plate construction of concrete lining method of the invention, not only maintains normally applying for concrete Work improves construction efficiency, while improving the compression strength and tensile splitting strength of concrete.Due to stone in coarse aggregate use Son and handstone mixing, by the interaction of the two, further improve the compression strength and tensile splitting strength of concrete, In combination with lower composite geo-membrane, the mutual cooperation of geotextiles, upper composite geo-membrane, the concrete-lined antiseepage of thin plate is improved Effect extends the concrete-lined service life of thin plate.Since discarded concrete slag being added in coarse aggregate, guaranteeing concrete In the case where quality, construction cost is reduced.
It is do not have by the difference place that comparative example 4 and comparative example 1-2 can be seen that comparative example 1 and embodiment 4 Leveling is rolled and tamped to slope surface;It is once to connect in concrete slab in place of the difference of comparative example 2 and embodiment 4 and pours It builds, it can be seen that, after being rolled to slope surface and tamping leveling, hence it is evident that improve the compression strength and splitting of concrete Tensile strength, while concrete slab being poured in two times, extend concrete surface and the time peeled off occur, prevents concrete from going out Existing depression, improves and extends the concrete-lined service life of thin plate.
It is coagulation by the difference place that comparative example 4 and comparative example 3-5 can be seen that comparative example 3 and embodiment 4 Without addition coarse aggregate in soil;It is in coarse aggregate in place of the difference of comparative example 4 and embodiment 4 without stone in addition;Comparison It is in coarse aggregate in place of the difference of example 5 and embodiment 4 without addition handstone;It can be seen that passing through middle stone and handstone Mutual cooperation, hence it is evident that improve the compression strength and tensile splitting strength of concrete.Pass through comparative example 4 and comparative example again 6 in place of the difference of comparative example 6 and embodiment 4 as can be seen that be in coarse aggregate thus may be used without addition discarded concrete slag See, adds a certain amount of discarded concrete slag, do not influence the performance of concrete, but be reduction of construction cost.

Claims (10)

1. a kind of thin plate construction of concrete lining method, it is characterised in that:Include the following steps:
(1)Slope surface is cleared up, thin plate concrete lining side is laid in canal dike and fills the canal dike soil body, and extra-fill 30-40cm, later It is rolled with self-propelled vibrating roller along channel direction walking, is carried out cutting slope from top to bottom with backacter, and eliminate extra-fill part, Then compacting leveling is carried out to slope surface with dynamic compaction machinery, makes head fall 1-5%, cross fall 1:1-3;
(2)It is successively laid with sandy gravel loaded filter, lower composite geo-membrane, geotextiles, upper composite geo-membrane from bottom to top in slope surface;
(3)Water, cement, coarse aggregate, sand, flyash, high efficiency water reducing agent, air entraining agent, retarder are stirred, coagulation is formed Soil, the slump of concrete are 90-130mm;
(4)In upper composite geo-membrane far from slope surface side vibration sliding-mode lining machine continuous concrete, the thickness of concrete For 10-12cm, lower-layer concrete panel is formed;
(5)After slope surface displacement is stablized, it is laid with and is connected with vibration sliding-mode lining machine far from slope surface side in lower-layer concrete panel layer Continuous casting concrete, concrete with a thickness of 5-8cm, form upper layer concrete slab;
(6)After the completion of concreting, static 1-2h is plastered with finisher, artificial press polish;
(7)On upper layer, concrete surface plate surface sprays curing agent, and is laid with two layers of plastic film in upper layer concrete surface plate surface, together When cover two layers of woven straw, conserve 7-10 days, remove woven straw, plastic foil later, and in the progress of upper layer concrete surface plate surface Watering moisturizing, conserves 21-25 days, completes thin plate construction of concrete lining.
2. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The concrete, is adopted It prepares with the following method:Water, cement, sand, flyash are put into stirred tank, 30-40min is stirred, investment is efficient later Water-reducing agent continues to stir 5-8min, and investment air entraining agent, retarder are stirred, and are continued to stir 20-30min, are then put into rough set Material continues to stir 10-15min, obtains concrete.
3. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The concrete, is pressed Parts by weight meter, raw material include 98-120 parts of water, 171-195 parts of cement, 1250-1420 parts of coarse aggregate, sand 652-723 Part, 65-73 parts of flyash, 4.1-4.6 parts of high efficiency water reducing agent, 2.2-2.7 parts of air entraining agent, 1.1-1.23 parts of retarder.
4. a kind of thin plate construction of concrete lining method according to claim 3, it is characterised in that:The concrete, is pressed Parts by weight meter, raw material include 110 parts of water, 183 parts of cement, 1362 parts of coarse aggregate, 684 parts of sand, 69 parts of flyash, efficiently 4.22 parts of water-reducing agent, 2.46 parts of air entraining agent, 1.15 parts of retarder.
5. a kind of thin plate construction of concrete lining method according to claim 3, it is characterised in that:The coarse aggregate includes The middle stone of 10-20mm, the handstone of 5-10mm, 5-25mm discarded concrete slag, the weight of the middle stone accounts for coarse aggregate The 48-55wt% of total weight, the weight of the handstone account for the 31-39wt% of coarse aggregate total weight, the discarded concrete slag Weight accounts for the 6-21wt% of coarse aggregate total weight.
6. a kind of thin plate construction of concrete lining method according to claim 5, it is characterised in that:The weight of the middle stone Amount accounts for the 52wt% of coarse aggregate total weight, and the weight of the handstone accounts for the 35wt% of coarse aggregate total weight, the discarded concrete The weight of slag accounts for the 13wt% of coarse aggregate total weight.
7. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The cement is selected from general Silicon cement, portland cement, KS- slag cements.
8. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The high efficiency water reducing agent For one of polycarboxylate water-reducer, naphthalene water reducer, lignin sulfonic acid sodium salt water-reducing agent or a variety of.
9. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The air entraining agent is rouge One of fat alcohol Sulfonates air entraining agent, rosin tree lipid air entraining agent, alkyl benzene sulfonate air entraining agent are a variety of.
10. a kind of thin plate construction of concrete lining method according to claim 1, it is characterised in that:The retarder is One of cellulose family retarder, phosphoric acid class retarder, hydroxycarboxylic acid retarder are a variety of.
CN201810806139.3A 2018-07-20 2018-07-20 Sheet concrete lining construction method Active CN108842723B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810806139.3A CN108842723B (en) 2018-07-20 2018-07-20 Sheet concrete lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810806139.3A CN108842723B (en) 2018-07-20 2018-07-20 Sheet concrete lining construction method

Publications (2)

Publication Number Publication Date
CN108842723A true CN108842723A (en) 2018-11-20
CN108842723B CN108842723B (en) 2020-08-21

Family

ID=64196537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810806139.3A Active CN108842723B (en) 2018-07-20 2018-07-20 Sheet concrete lining construction method

Country Status (1)

Country Link
CN (1) CN108842723B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485377A (en) * 2019-07-16 2019-11-22 中电建十一局工程有限公司 A kind of light section canal lining construction method
CN111074851A (en) * 2019-12-20 2020-04-28 湖北锦天禹建设工程有限公司 Construction method for concrete lining at bottom of channel
CN111074852A (en) * 2019-12-20 2020-04-28 湖北锦天禹建设工程有限公司 Channel lining concrete cast-in-place method and nonlinear channel lining construction method
CN111302734A (en) * 2020-03-17 2020-06-19 安徽农业大学 Protective building material for farmland ditches and preparation method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102010160A (en) * 2010-10-29 2011-04-13 广西壮族自治区水利科学研究院 Crack-resistant abrasion-resistant hydraulic concrete and preparation method thereof
CN102864759A (en) * 2012-10-22 2013-01-09 安蓉建设总公司 Method for constructing sheet concrete lining
CN106759126A (en) * 2017-02-24 2017-05-31 化学工业岩土工程有限公司 Construction method of side slope support drainage channel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102010160A (en) * 2010-10-29 2011-04-13 广西壮族自治区水利科学研究院 Crack-resistant abrasion-resistant hydraulic concrete and preparation method thereof
CN102864759A (en) * 2012-10-22 2013-01-09 安蓉建设总公司 Method for constructing sheet concrete lining
CN106759126A (en) * 2017-02-24 2017-05-31 化学工业岩土工程有限公司 Construction method of side slope support drainage channel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
水利水电工程施工实用手册: "《建筑材料与检测》", 31 December 2017, 中国环境出版社 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485377A (en) * 2019-07-16 2019-11-22 中电建十一局工程有限公司 A kind of light section canal lining construction method
CN111074851A (en) * 2019-12-20 2020-04-28 湖北锦天禹建设工程有限公司 Construction method for concrete lining at bottom of channel
CN111074852A (en) * 2019-12-20 2020-04-28 湖北锦天禹建设工程有限公司 Channel lining concrete cast-in-place method and nonlinear channel lining construction method
CN111074851B (en) * 2019-12-20 2021-09-10 湖北锦天禹建设工程有限公司 Construction method for concrete lining at bottom of channel
CN111074852B (en) * 2019-12-20 2021-10-12 湖北锦天禹建设工程有限公司 Channel lining concrete cast-in-place method and nonlinear channel lining construction method
CN111302734A (en) * 2020-03-17 2020-06-19 安徽农业大学 Protective building material for farmland ditches and preparation method thereof

Also Published As

Publication number Publication date
CN108842723B (en) 2020-08-21

Similar Documents

Publication Publication Date Title
CN108842723A (en) A kind of thin plate construction of concrete lining method
CN106401144A (en) Construction technology for addition type wear resisting concrete ground
CN105298133A (en) Construction method to strengthen crack resistance of large-volume concrete baseplate
CN101619558A (en) Air entraining vacuum concrete roadway and constructing method thereof
CN104929365B (en) Refuse of refuse burning generating plant discharging platform combined type surface construction technology
CN101806127A (en) Polyphenyl composite decorative board and manufacture process thereof
CN109384442A (en) A kind of cement combination permeable pavement brick and preparation method thereof
CN114477869A (en) Thick-layer leveling material and construction method thereof
CN101531026A (en) Method for preparing plaster evacuated mould
CN108585696A (en) A kind of pervious concrete preparation method of anti-moisture evaporation
CN110028292A (en) A kind of preparation method inhibiting the high-strength concrete heat of hydration
JP3319734B2 (en) Architectural materials and their production and construction methods
CN111377682A (en) Anti-cracking concrete and preparation method thereof, and anti-cracking fabricated prefabricated part composite floor slab and preparation method thereof
CN111042310A (en) Basement bottom plate structure and construction method thereof
JPH08157249A (en) Concrete for sprayed concrete structure
CN104712088A (en) Construction method for post-poured concrete of prefabricated composite floor slabs
CN215368500U (en) Flame-retardant anti-cracking extruded polystyrene foam heat-insulation terrace
US20150191398A1 (en) Method for creating patterns on a concrete surface
CN109180099A (en) It is a kind of for pouring the concrete material, additive and application method of pier stud
RU2245784C2 (en) Method of production of decorative facade made out of architectural concrete and a form for its realization
CN201649501U (en) Polyphenyl composite decorative board
CN101343154A (en) Anticlastic supplementary material for pump concrete and method of preparing the same
CN110304868A (en) A kind of high additive Machine-made Sand border stone slip-form concrete and its construction technology
CN110206139A (en) A kind of mass concrete construction method
RU2330000C1 (en) Method of producing of decorative concrete products

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant