CN108798726A - A kind of tunnel fast lifting baffle - Google Patents

A kind of tunnel fast lifting baffle Download PDF

Info

Publication number
CN108798726A
CN108798726A CN201810844517.7A CN201810844517A CN108798726A CN 108798726 A CN108798726 A CN 108798726A CN 201810844517 A CN201810844517 A CN 201810844517A CN 108798726 A CN108798726 A CN 108798726A
Authority
CN
China
Prior art keywords
baffle
fast lifting
screw rod
top plate
box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810844517.7A
Other languages
Chinese (zh)
Inventor
李富友
李辅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Haodesi New Material Technology Co Ltd
Original Assignee
Sichuan Haodesi New Material Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Haodesi New Material Technology Co Ltd filed Critical Sichuan Haodesi New Material Technology Co Ltd
Priority to CN201810844517.7A priority Critical patent/CN108798726A/en
Publication of CN108798726A publication Critical patent/CN108798726A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to technical field of tunnel construction, disclose a kind of tunnel fast lifting baffle, including baffle, the upper surface of the baffle offers counterbore, fast lifting device is provided in counterbore, the fast lifting device includes lifting box, lifting box is fixedly connected with counterbore, it is arranged with screw rod in lifting box and is threadedly coupled, extend lifting box and be provided with jacking block in the upper end of the screw rod, the upper surface of jacking block is provided with top plate and contradicts connection, rotating handle is additionally provided on the screw rod and is fixedly connected, and the rotating handle is located between jacking block and lifting box.Present invention can be implemented in the faulting of slab ends during Tunnel Second Lining Construction quickly between back pressure type waterstop to block, and to avoid the purpose of spillage, and can avoid expending time long, of high cost, efficiency is low problem for the processing of the situation.

Description

A kind of tunnel fast lifting baffle
Technical field
The present invention relates to technical field of tunnel construction, in particular to a kind of tunnel fast lifting baffles.
Background technology
Maximum security risk is exactly arch cracking, chip off-falling and inverted arch protuberance in railway tunnel operation.Generate cracking chip off-falling The main reason for there is at construction joint trolley rigidly squeeze, the cutting of waterstop cantilever end, the cold seam of concrete construction, coagulation at construction joint Empty sound, voids and pits, sand, dusting etc. caused by native not full, concrete spillage, while difficulty of vibrating at construction joint, arch Can not vibrate at construction joint, thus caused by operation tunnel disease it is very strange, but from influence concrete performance from the perspective of, Most universal, most basic problem is still spillage.
Spillage can not be mainly completely superposed because back pressure type sealing is with seam when live inverted arch and lining cutting circumferential direction are constructed, and thus served as a contrast Platform building cart easily causes spillage to will form the faulting of slab ends that can not close up after mould between back pressure type waterstop in casting process, And irregular faulting of slab ends is formed, traditional handicraft is blocked using along lining trolley lower edge using wooden model, however wooden model exists It is had the following problems during use:1, construction speed is slow, and during practice of construction, preliminary bracing profiled may not be too round Suitable, end head formwork width differs when end being caused to be constructed, more so as to cause end wooden model block number, and blanking punch heavy workload is applied Work is more slow;2, labor intensity is big, and every piece of wooden model securely must just can guarantee and not run the quick-fried mould of mould in reinforcing process, reinforces Get up particularly cumbersome;3, closed matereial cycle rate is low, and wooden model is cut when blocking according to section configuration, construction next time after form removal Utilization rate is quite low, causes wood consumption very big, increases construction cost.
Invention content
Based on problem above, the present invention provides a kind of tunnel fast lifting baffles.It is secondary that present invention can be implemented in tunnels Faulting of slab ends during lining construction quickly between back pressure type waterstop blocks, to avoid the purpose of spillage, by keeping off Fast lifting device is installed in plate, and top plate is installed in the output end of fast lifting device, top plate can be in fast lifting device Top pressure inverted arch or back pressure type waterstop under effect of increasing, solving can make in existing tunnel construction because of the faulting of slab ends between waterstop At in casting process, there is a situation where spillages, and expend that the time is long, of high cost, efficiency is low asks for the processing of the situation Topic.
In order to solve the above technical problems, the technical solution adopted by the present invention is as follows:
The upper surface of a kind of tunnel fast lifting baffle, including baffle, the baffle offers counterbore, is provided in counterbore Fast lifting device, the fast lifting device include lifting box, and lifting box is fixedly connected with counterbore, lifts in box and be arranged with spiral shell Bar is simultaneously threadedly coupled, and the upper end of the screw rod extends lifting box and is provided with jacking block, and the upper surface of jacking block is provided with top plate simultaneously Contradict connection, be additionally provided with rotating handle on the screw rod and be fixedly connected, the rotating handle be located at jacking block and lift box it Between.
In the present invention, baffle is placed on middle buried water stop, make be mounted on baffle in fast lifting device and Back pressure type waterstop is corresponding, and the screw rod that fast lifting device is threadedly coupled by lifting box and with it forms, by turning fixation The rotating handle being set on screw rod makes screw rod rotate, to screwing length of the adjusting screw rod in lifting box, the upper end of screw rod It is fixedly installed jacking block, jacking block upper surface is equipped with top plate and contradicts connection again, i.e. the rotation by adjusting screw rod in lifting box Closing length can be such that top plate rises to contact with back pressure type waterstop, since back pressure type waterstop is made of compounded rubber, work as top Plate can make it generate elastic deformation when squeezing waterstop, achieve the purpose that blocking faulting of slab ends avoids spillage.
Present invention can be implemented in the quickly faulting of slab ends progress between back pressure type waterstop during Tunnel Second Lining Construction It blocks, to avoid the purpose of spillage, pacifies by installing fast lifting device in baffle, and in the output end of fast lifting device Fill top plate, top plate can under the effect of increasing of fast lifting device top pressure inverted arch or back pressure type waterstop, solve existing tunnel It can cause in casting process that there is a situation where spillages because of the faulting of slab ends between waterstop in construction, and for the processing of the situation Expend time long, of high cost, efficiency is low problem, my company to tunnel lining trolley faces end head plugging system by repetition test, It improves, using fast lifting baffle blocking technology, realizes closed, the rapid construction at end position, it is ensured that concrete quality With waterstop precision, substantially increase work efficiency.
As a preferred mode, baffle uses composite rubber material, and rigid strutting piece is provided in baffle, described Rigid strutting piece includes the multigroup horizontal ribs being laterally arranged in baffle, and overlap joint rib is symmetrically arranged at left and right sides of baffle, described Overlap joint rib can be used for baffle lap seal two-by-two.
As a preferred mode, the upper surface of top plate is set as the arc being bonded with inverted arch or back pressure type waterstop, The side vertical of top plate is provided with pressing plate, the side of the pressing plate and concrete surface fitting.
As a preferred mode, the lower surface of top plate is provided with "T"-shaped guide rail, and the jacking block is set as "T"-shaped, top Block and "T"-shaped guide rail are slidably matched.
As a preferred mode, top plate uses composite rubber material.
As a preferred mode, fast lifting device is at least two and is being kept off along the center line symmetrical setting of baffle The both ends of plate.
As a preferred mode, lifting box includes box body, and spiral shell block, the screw rod and spiral shell block are fixedly installed in box body It is threadedly coupled, the upper end of box body is provided with capping, and the upper end of screw rod is through capping.
Compared with prior art, the beneficial effects of the invention are as follows:
(1) present invention can be implemented in during Tunnel Second Lining Construction quickly the faulting of slab ends between back pressure type waterstop into Row blocks, to avoid the purpose of spillage, by installing fast lifting device in baffle, and in the output end of fast lifting device Install top plate, top plate can under the effect of increasing of fast lifting device top pressure inverted arch or back pressure type waterstop, solve existing tunnel Spillage processing is difficult in road construction, expends the problem of time length.
(2) baffle uses composite rubber material in the present invention, and multigroup horizontal ribs are horizontally arranged in baffle, a left side for baffle Right both sides are symmetrically arranged with overlap joint rib, and the overlap joint rib can be used for baffle lap seal two-by-two, had using compounded rubber made of Baffle has material light, elastic good and good comprehensive performance, and the application of composite rubber material revolutionizes traditional block up Rigid contact between head plate and reinforcing bar is flexible contact, reinforces the structural strength of baffle by the way that multigroup horizontal ribs are arranged in baffle So that its pressure-bearing property is improved, can constitute one with tunnel-shaped fitting by overlapping rib lap hermetically together between baffle two-by-two Adjustable end stop system is covered, the using flexible of the invention is improved.
(3) upper surface of top plate is set as the arc being bonded with inverted arch or back pressure type waterstop, the side of top plate in the present invention Face is vertically arranged with pressing plate, the side of pressing plate and concrete surface fitting, by setting and back pressure type the upper surface of top plate to The arc of waterstop fitting, improves the laminating degree of top plate and waterstop, the faulting of slab ends maximum journey that can will be formed between waterstop Degree block, and improves leakproofness, and the pressing plate of top plate side setting can limit that concrete is brought in process of setting Power keeps the flatness of entire concrete cut ends.
(4) lower surface of top plate is provided with "T"-shaped guide rail in the present invention, and the jacking block is set as "T"-shaped, jacking block and " T " Shape guide rail is slidably matched, and since jacking block and "T"-shaped guide rail are slidably matched, baffle and top plate can be made to take off by the way that jacking block horizontally slips From, the baffle of replaceable different height to adapt to different constructing tunnel situations, improves the interchangeability of the invention and use Flexibility.
(5) top plate uses composite rubber material in the present invention, and having manufactured top plate using compounded rubber has material light, bullet Property good and good comprehensive performance, and the application of composite rubber material revolutionizes the rigidity between traditional bulkhead and reinforcing bar Contact is flexible contact, since top plate plasticity made of composite rubber material is good, then is applied to jacking block by screw rod rotation and is pressed When power, top plate can be made to generate certain elastic deformation, improve the leakproofness between top plate and back pressure type waterstop, reduce leakage The possibility of slurry.
(6) it is two and along the center line symmetrical setting of baffle the two of baffle that fast lifting device is minimum in the present invention End avoids top plate by discontinuity caused by lateral force by the way that fast lifting device to be symmetricly set on to the both ends of baffle, The problem for keeping leak stopping sealing effect bad, two fast lifting devices can reach best effective in manufacturing cost and service condition Fruit.
(7) lifting box includes box body in the present invention, and spiral shell block is fixedly installed in box body, and the screw rod connects with spiral shell block screw thread It connects, the upper end of box body is provided with capping, and the upper end of screw rod is covered by being arranged on box body through capping, improves lifting box Leakproofness impurity can avoid by capping and enter and block screw rod in box body since impurity is more in the air in constructing tunnel, Influence screwing for screw rod and spiral shell block.
Description of the drawings
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is the structural schematic diagram of Fig. 1 side views.
Fig. 3 is the structural schematic diagram of fast lifting device in Fig. 1.
Fig. 4 is the structural schematic diagram of rotating handle.
Fig. 5 is the structural schematic diagram of baffle.
Wherein, 1- rotating handles, 2- top plates, 3- jacking blocks, the "T"-shaped guide rails of 4-, 5- screw rods, 6- liftings box, 7- box bodys, 8- pressures Plate, 9- cappings, 10- spiral shells block, 11- baffles, 12- overlap joint rib, 13- horizontal ribs.
Specific implementation mode
The present invention will be further described below with reference to the drawings.Embodiments of the present invention include but not limited to following reality Apply example.
Embodiment 1:
Referring to Fig. 1~5, a kind of tunnel fast lifting baffle, including baffle 11, it is heavy that the upper surface of the baffle 11 offers Hole is provided with fast lifting device in counterbore, and the fast lifting device includes lifting box 6, lifts box 6 and counterbore is fixed and connected It connecing, lifts and be arranged with screw rod 5 in box 6 and be threadedly coupled, the upper end of the screw rod 5 extends lifting box 6 and is provided with jacking block 3, The upper surface of jacking block 3 is provided with top plate 2 and contradicts connection, rotating handle 1 is additionally provided on the screw rod 5 and is fixedly connected, institute Rotating handle 1 is stated to be located between jacking block 3 and lifting box 6.
In the present invention, baffle is placed on middle buried water stop, make be mounted on baffle in fast lifting device and Back pressure type waterstop is corresponding, and the screw rod that fast lifting device is threadedly coupled by lifting box and with it forms, by turning fixation The rotating handle being set on screw rod makes screw rod rotate, to screwing length of the adjusting screw rod in lifting box, the upper end of screw rod It is fixedly installed jacking block, jacking block upper surface is equipped with top plate and contradicts connection again, i.e. the rotation by adjusting screw rod in lifting box Closing length can be such that top plate rises to contact with back pressure type waterstop, since back pressure type waterstop is made of compounded rubber, work as top Plate can make it generate elastic deformation when squeezing waterstop, achieve the purpose that blocking faulting of slab ends avoids spillage.
Present invention can be implemented in the quickly faulting of slab ends progress between back pressure type waterstop during Tunnel Second Lining Construction It blocks, to avoid the purpose of spillage, pacifies by installing fast lifting device in baffle, and in the output end of fast lifting device Fill top plate, top plate can under the effect of increasing of fast lifting device top pressure inverted arch or back pressure type waterstop, solve existing tunnel It can cause in casting process that there is a situation where spillages because of the faulting of slab ends between waterstop in construction, and for the processing of the situation Expend time long, of high cost, efficiency is low problem.
Embodiment 2:
Referring to Fig. 1~5, a kind of tunnel fast lifting baffle, including baffle 11, it is heavy that the upper surface of the baffle 11 offers Hole is provided with fast lifting device in counterbore, and the fast lifting device includes lifting box 6, lifts box 6 and counterbore is fixed and connected It connecing, lifts and be arranged with screw rod 5 in box 6 and be threadedly coupled, the upper end of the screw rod 5 extends lifting box 6 and is provided with jacking block 3, The upper surface of jacking block 3 is provided with top plate 2 and contradicts connection, rotating handle 1 is additionally provided on the screw rod 5 and is fixedly connected, institute Rotating handle 1 is stated to be located between jacking block 3 and lifting box 6.
Baffle 11 uses composite rubber material, and rigid strutting piece is provided in baffle 11, and the rigid strutting piece includes The left and right sides of the multigroup horizontal ribs 13 being laterally arranged in baffle 11, baffle 11 is symmetrically arranged with overlap joint rib 12, the overlap joint rib 12 can be used for 11 lap seal of baffle two-by-two.
In the present embodiment, having manufactured baffle using compounded rubber has material light, elastic good and good comprehensive performance, And the application of composite rubber material revolutionize the rigid contact between traditional bulkhead and reinforcing bar be flexible contact, by The structural strength that the interior rigid strutting piece that multigroup horizontal ribs are arranged and are formed of baffle reinforces baffle makes its pressure-bearing property improve, and keeps off two-by-two It can be constituted a set of adjustable end stop system with tunnel-shaped fitting by overlapping rib lap hermetically together, improve between plate The using flexible of the invention.
The other parts of the present embodiment are same as Example 1, just repeat no more here.
Embodiment 3:
Referring to Fig. 1~5, a kind of tunnel fast lifting baffle, including baffle 11, it is heavy that the upper surface of the baffle 11 offers Hole is provided with fast lifting device in counterbore, and the fast lifting device includes lifting box 6, lifts box 6 and counterbore is fixed and connected It connecing, lifts and be arranged with screw rod 5 in box 6 and be threadedly coupled, the upper end of the screw rod 5 extends lifting box 6 and is provided with jacking block 3, The upper surface of jacking block 3 is provided with top plate 2 and contradicts connection, rotating handle 1 is additionally provided on the screw rod 5 and is fixedly connected, institute Rotating handle 1 is stated to be located between jacking block 3 and lifting box 6.
The upper surface of top plate 2 is set as the arc being bonded with inverted arch or back pressure type waterstop, the side vertical setting of top plate 2 There are pressing plate 8, the side of the pressing plate 8 and concrete surface fitting, pressing plate 8 that can be integrally formed with top plate 2.
In the present embodiment, by the arc for being set as being bonded with back pressure type waterstop by the upper surface of top plate, top is improved The faulting of slab ends formed between waterstop can to the greatest extent be blocked, improve leakproofness by the laminating degree of plate and waterstop, The pressing plate of top plate side setting can limit the tension that concrete is brought in process of setting, keep the flat of entire concrete cut ends Whole degree.
As a preferred mode, the lower surface of top plate 2 is provided with "T"-shaped guide rail 4, and the jacking block 3 is set as " T " Shape, jacking block 3 and "T"-shaped guide rail 4 are slidably matched.In which, baffle and top plate can be made to be detached from by the way that jacking block horizontally slips, it can The baffle of different height is replaced to adapt to different constructing tunnel situations, locally surpassed with meeting tunnel top, owe the closure requirement dug, The flexibility for improving the interchangeability of the invention and using.
As a preferred mode, top plate 2 uses composite rubber material.In which, it is made of compounded rubber tool Top plate have material light, elasticity is good and good comprehensive performance, and the application of composite rubber material revolutionize it is traditional Rigid contact between bulkhead and reinforcing bar is flexible contact, since top plate plasticity made of composite rubber material is good, then is passed through When screw rod rotation applies pressure to jacking block, top plate can be made to generate certain elastic deformation, improve top plate and back pressure type waterstop Between leakproofness, reduce the possibility of spillage.
The other parts of the present embodiment are same as Example 1, just repeat no more here.
Embodiment 4:
Referring to Fig. 1~5, a kind of tunnel fast lifting baffle, including baffle 11, it is heavy that the upper surface of the baffle 11 offers Hole is provided with fast lifting device in counterbore, and the fast lifting device includes lifting box 6, lifts box 6 and counterbore is fixed and connected It connecing, lifts and be arranged with screw rod 5 in box 6 and be threadedly coupled, the upper end of the screw rod 5 extends lifting box 6 and is provided with jacking block 3, The upper surface of jacking block 3 is provided with top plate 2 and contradicts connection, rotating handle 1 is additionally provided on the screw rod 5 and is fixedly connected, institute Rotating handle 1 is stated to be located between jacking block 3 and lifting box 6.
Fast lifting device is at least for two and along the center line symmetrical setting of baffle 11 at the both ends of baffle 11.
In the present embodiment, by the way that fast lifting device to be symmetricly set on to the both ends of baffle, avoid top plate by lateral force Caused discontinuity, the problem for keeping leak stopping sealing effect bad, two fast lifting devices are in manufacturing cost and use feelings Optimum efficiency can be reached in condition.
As a preferred mode, lifting box 6 includes box body 7, and spiral shell block 10, the screw rod 5 are fixedly installed in box body 7 It is threadedly coupled with spiral shell block 10, the upper end of box body 7 is provided with capping 9, and the upper end of screw rod 5 is through capping 9.In the present embodiment, pass through Capping is set on box body, and the leakproofness for improving lifting box passes through capping since impurity is more in the air in constructing tunnel Avoidable impurity, which enters, blocks screw rod in box body, influences screwing for screw rod and spiral shell block.
The other parts of the present embodiment are same as Example 1, just repeat no more here.
As above it is the embodiment of the present invention.Design parameter in above-described embodiment and embodiment is merely to understand table The verification process of the present invention is stated, not to limit the scope of patent protection of the present invention, scope of patent protection of the invention is still It is subject to its claims, equivalent structure variation made by every specification and accompanying drawing content with the present invention, similarly It should be included within the scope of the present invention.

Claims (7)

1. a kind of tunnel fast lifting baffle, including baffle (11), it is characterised in that:The upper surface of the baffle (11) offers Counterbore is provided with fast lifting device in counterbore, and the fast lifting device includes lifting box (6), and lifting box (6) and counterbore are consolidated Fixed connection, lifting box (6) is interior to be arranged with screw rod (5) and is threadedly coupled, and lifting box (6) is extended simultaneously in the upper end of the screw rod (5) It is provided with jacking block (3), the upper surface of jacking block (3) is provided with top plate (2) and contradicts connection, and rotation is additionally provided on the screw rod (5) It changes hands handle (1) and is fixedly connected, the rotating handle (1) is located between jacking block (3) and lifting box (6).
2. tunnel fast lifting baffle according to claim 1, it is characterised in that:The baffle (11) uses compounded rubber Material, and rigid strutting piece is provided in baffle (11), the rigid strutting piece include laterally be arranged in baffle (11) it is multigroup Horizontal ribs (13), overlap joint rib (12) is symmetrically arranged at left and right sides of baffle (11), and the overlap joint rib (12) can be used for keeping off two-by-two Plate (11) lap seal.
3. tunnel fast lifting baffle according to claim 1, it is characterised in that:The upper surface of the top plate (2) is arranged Side vertical for the arc being bonded with inverted arch or back pressure type waterstop, top plate (2) is provided with pressing plate (8), the pressing plate (8) Side and concrete surface fitting.
4. tunnel fast lifting baffle according to claim 3, it is characterised in that:The lower surface of the top plate (2) is arranged There are "T"-shaped guide rail (4), the jacking block (3) to be set as "T"-shaped, jacking block (3) and "T"-shaped guide rail (4) are slidably matched.
5. tunnel fast lifting baffle according to claim 4, it is characterised in that:The top plate (2) uses compounded rubber Material.
6. tunnel fast lifting baffle according to claim 1, it is characterised in that:The fast lifting device is at least two It is a and along the center line symmetrical setting of baffle (11) baffle (11) both ends.
7. tunnel fast lifting baffle according to claim 6, it is characterised in that:The lifting box (6) includes box body (7), it is fixedly installed spiral shell block (10) in box body (7), the screw rod (5) is threadedly coupled with spiral shell block (10), and the upper end of box body (7) is set It is equipped with capping (9), the upper end of screw rod (5) is through capping (9).
CN201810844517.7A 2018-07-27 2018-07-27 A kind of tunnel fast lifting baffle Pending CN108798726A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810844517.7A CN108798726A (en) 2018-07-27 2018-07-27 A kind of tunnel fast lifting baffle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810844517.7A CN108798726A (en) 2018-07-27 2018-07-27 A kind of tunnel fast lifting baffle

Publications (1)

Publication Number Publication Date
CN108798726A true CN108798726A (en) 2018-11-13

Family

ID=64077125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810844517.7A Pending CN108798726A (en) 2018-07-27 2018-07-27 A kind of tunnel fast lifting baffle

Country Status (1)

Country Link
CN (1) CN108798726A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4867835A (en) * 1987-01-15 1989-09-19 Poole William J Waterstop splicing method and apparatus
CN102367735A (en) * 2011-12-03 2012-03-07 长安大学 Back-to-back waterstop installation equipment for tunnel construction joint
CN103670452A (en) * 2013-12-23 2014-03-26 中铁五局(集团)有限公司 Installation structure and method for accurately positioning tunnel arch wall lining buried type water-stop belt
CN107035388A (en) * 2017-05-19 2017-08-11 四川皓德斯新材料科技有限公司 A kind of tunnel double-lining compounded rubber lifting locking plug template and its application method
CN107620599A (en) * 2017-09-13 2018-01-23 四川皓德斯新材料科技有限公司 A kind of tunnel double-lining locking plug template with jacking apparatus
CN208502801U (en) * 2018-07-27 2019-02-15 四川皓德斯新材料科技有限公司 A kind of tunnel fast lifting baffle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4867835A (en) * 1987-01-15 1989-09-19 Poole William J Waterstop splicing method and apparatus
CN102367735A (en) * 2011-12-03 2012-03-07 长安大学 Back-to-back waterstop installation equipment for tunnel construction joint
CN103670452A (en) * 2013-12-23 2014-03-26 中铁五局(集团)有限公司 Installation structure and method for accurately positioning tunnel arch wall lining buried type water-stop belt
CN107035388A (en) * 2017-05-19 2017-08-11 四川皓德斯新材料科技有限公司 A kind of tunnel double-lining compounded rubber lifting locking plug template and its application method
CN107620599A (en) * 2017-09-13 2018-01-23 四川皓德斯新材料科技有限公司 A kind of tunnel double-lining locking plug template with jacking apparatus
CN208502801U (en) * 2018-07-27 2019-02-15 四川皓德斯新材料科技有限公司 A kind of tunnel fast lifting baffle

Similar Documents

Publication Publication Date Title
CN103510965A (en) Highway tunnel lining surface sticky steel strip strengthening method and device
CN208502801U (en) A kind of tunnel fast lifting baffle
CN107764563A (en) A kind of rail traffic vehicles pilot test of static strength method and device
CN108798726A (en) A kind of tunnel fast lifting baffle
CN207538502U (en) A kind of novel reinforced concrete frame beam column reinforcing joint
CN203835403U (en) Clearance strengthening system for serious cracking of existing tunnel lining arch
CN211947981U (en) Slurry leakage prevention device for construction of pier creeping formwork segment
CN107100197A (en) A kind of detachable water-stop opposite-pulling screw rod erecting device of large steel moulding plate
CN204401377U (en) Adjustable ballastless track self-compacting concrete perfusion gang form
CN104453235B (en) Current conversion station fire wall construction technology
CN206902549U (en) A kind of bridge coxopodite pier shaft pours leakproof sizing device
CN207500710U (en) Fast cassette blocks threeway
CN109667602A (en) For preventing the construction method of concrete capping at two lining circular construction joints
CN107059627A (en) A kind of bridge coxopodite pier shaft pours leakproof sizing device and bridge pier shaft casting method
CN208545965U (en) A kind of template component for secondary structure pouring construction
CN209959259U (en) Water stop belt positioning and fastening plug board device for tunnel trolley lining construction
CN108978595B (en) Structure for repairing water stop at bottom of peripheral seam of concrete faced rockfill dam and construction method
CN208379644U (en) A kind of post-cast strip built for basement
CN107444568A (en) The method that vessel support frock and the vessel support frock remove block
CN110295924B (en) Shield tunnel reinforcing structure based on H-shaped steel plate and construction method
CN209228386U (en) A kind of lining of tunneling Subway Tunnel big cross section stop line two new type formwork trolley
CN107842199A (en) A kind of preforming combination tool of mattess partitioning slot and its built-in process
CN208517965U (en) A kind of readily removable reserved bolt deep holes template removed, can be used in turn
CN206328692U (en) A kind of road and bridge crack ruggedized construction
CN103276668A (en) Waterproof structure of railway bridge expansion joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination