CN108797372A - A kind of construction method for deep water shallow overburden steel trestle - Google Patents

A kind of construction method for deep water shallow overburden steel trestle Download PDF

Info

Publication number
CN108797372A
CN108797372A CN201811003834.2A CN201811003834A CN108797372A CN 108797372 A CN108797372 A CN 108797372A CN 201811003834 A CN201811003834 A CN 201811003834A CN 108797372 A CN108797372 A CN 108797372A
Authority
CN
China
Prior art keywords
steel
pipe pile
trestle
pipe
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811003834.2A
Other languages
Chinese (zh)
Inventor
程柯达
姜志强
程伟峰
刘光军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB Fourth Engineering Co Ltd
Original Assignee
CCCC SHB Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB Fourth Engineering Co Ltd filed Critical CCCC SHB Fourth Engineering Co Ltd
Priority to CN201811003834.2A priority Critical patent/CN108797372A/en
Publication of CN108797372A publication Critical patent/CN108797372A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/18Placing by vibrating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Architecture (AREA)
  • Revetment (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention belongs to steel trestle construction method technical fields, propose a kind of construction method for deep water shallow overburden steel trestle.It is proposed a kind of construction method for deep water shallow overburden steel trestle, for riverbed bottom be rocky bed part steel-pipe pile, need to be squeezed into rocky bed to beat it is motionless until;Then steel-pipe pile is fixed on leading truck with channel steel, it is ensured that steel-pipe pile stability;It is the surrounding throwing sand pocket of all steel-pipe piles of rocky bed in bottom, forms sand pocket cofferdam;Pouring underwater concrete ensures that bottom is the steel-pipe pile of rocky bed and has enough building-in depths, meets resistance to capsizing requirement as artificial concrete coating in sand pocket cofferdam;While the present invention ensures steel trestle overall stability, project cost is reduced;The characteristics of this method is adaptable, convenient for construction, saving duration simultaneously.

Description

A kind of construction method for deep water shallow overburden steel trestle
Technical field
The invention belongs to steel trestle construction method technical field, especially a kind of applying for deep water shallow overburden steel trestle Work method.
Background technology
In-water foundation construction generally uses steel trestle as temporary traffic facility, is used for transport of materials, personnel, mechanical equipment Temporary traffic waterborne etc.;Since holding force component is steel-pipe pile, therefore the stability of steel-pipe pile generates weight to the safe handling of steel trestle It is big to influence.Mud, sand pebble layer can be encountered when usual steel trestle construction, provides execution conditions for rapping steel-pipe pile, but flowing It is fast big, be under water solid rock, shallow overburden or intectate, the depth of water relatively depth or flood level are higher it is equal in the case of, steel-pipe pile is slotting It is particularly difficult to play construction, it is difficult to the enough depth of underwater stratum be squeezed into, it is difficult to ensure that steel-pipe pile stability.
Existing patent of invention《The method that deep water steel trestle and platform are set up on the exposed bedrock of shallow sea》(The patent No.: 201210164272.6), comprise the following steps:(1)Model is established, determines parameter;(2)Inserting piling trestle steel pipe pile;(3)Inserting piling side It is supported to chamfer triangle taper pile;(4)Integral frame structure is molded;(5)Perform the knots such as trestle Bailey beam, floorings Structure forms trestle.Patent to the effect that adds row's chamfer triangle taper pile in steel trestle steel-pipe pile both sides, by taper pile with Trestle steel pipe pile is rigidly connected, to ensure steel-pipe pile stability;But in its work progress, the construction duration is long, quantities Greatly, the amount of labour of construction personnel is big.
Invention content
The purpose of the present invention is according to the existing deficiency of above-mentioned engineering technology, propose a kind of for deep water shallow overburden steel stack The construction method of bridge is suitable for the construction method of deep water shallow overburden steel trestle steel-pipe pile, especially suitable for being hard rock under water Stone, shallow overburden or intectate, the steel trestle steel pipe pile driving construction in the case of the depth of water relatively depth or flood level are higher etc..
The present invention is to complete above-mentioned purpose to adopt the following technical scheme that:
A kind of construction method for deep water shallow overburden steel trestle, the construction method are as follows:
1)Model is established, steel trestle modelling is carried out, determines steel trestle steel-pipe pile model and meet under antidumping requirement condition Artificial concrete coating parameters;
2)Steel-pipe pile is transferred into riverbed bottom in designated position using crane lifting vibration hammer;The steel-pipe pile is along steel trestle Length direction setting two row, be often classified as it is multigroup, every group be two;For the steel-pipe pile that riverbed bottom is rocky bed part, need Squeezed into rocky bed to beat it is motionless until;Then steel-pipe pile is fixed on leading truck with channel steel, it is ensured that steel-pipe pile is stablized Property;
3)It is the surrounding throwing sand pocket of all steel-pipe piles of rocky bed in bottom, forms sand pocket cofferdam;
4)According to step 1)Calculate parameters obtained, in sand pocket cofferdam pouring underwater concrete as artificial concrete coating, Ensure that bottom is the steel-pipe pile of rocky bed and there are enough building-in depths, meets resistance to capsizing requirement;
5)It is connected as with channel steel welding bridging, stull between every group of two steel-pipe piles, between the two corresponding steel-pipe piles of row One, is allowed to constitute a frame structure, enhances the stability of steel-pipe pile;
(6)According to each steel pipe stake top of design altitude leveling after surveying and locating, 2/3 long gravel or coagulation are poured into steel-pipe pile Soil enhances resistance to capsizing to reduce the center of gravity of steel-pipe pile;
7)Each steel pipe stake top after leveling is fixed with more Bailey beams being arranged along steel trestle length direction;The more shellfish thunders Steel trestle floorings are fixed on the top of beam, and connect firmly steel trestle railing at the both ends of steel trestle floorings.
It is proposed by the present invention a kind of for deep water shallow overburden steel trestle construction method, by being rocky bed in bottom Sand pocket cofferdam is cast around steel-pipe pile, and concrete perfusion establishes artificial concrete coating in sand pocket cofferdam, ensureing steel While trestle overall stability, project cost is reduced;Simultaneously this method it is adaptable, convenient for constructing, save the spy of duration Point.
Description of the drawings
Fig. 1 is artificial cofferdam and steel-pipe pile position plane figure;
Fig. 2 is artificial underwater concrete coating schematic diagram;
Fig. 3 is steel trestle cross-sectional view;
Fig. 4 is steel trestle front view;
In figure:1, steel-pipe pile;2, sand pocket cofferdam;3, artificial concrete coating;4, gravel;5, rocky bed;6, channel steel welds Bridging;7, channel steel welds stull;8, Bailey beam;9, steel trestle floorings;10, steel trestle railing.
Specific implementation mode
The present invention is illustrated with reference to the drawings and specific embodiments:
A kind of construction method for deep water shallow overburden steel trestle, the construction method are as follows:
1)Model is established, steel trestle modelling is carried out, determines steel trestle steel-pipe pile model and meet under antidumping requirement condition Artificial concrete coating parameters;
2)Steel-pipe pile is transferred into riverbed bottom in designated position using crane lifting vibration hammer;The steel-pipe pile is along steel trestle Length direction setting two row, be often classified as it is multigroup, every group be two;For the steel-pipe pile that riverbed bottom is rocky bed part, need Squeezed into rocky bed to beat it is motionless until;Then steel-pipe pile is fixed on leading truck with channel steel, it is ensured that steel-pipe pile is stablized Property;
3)It is the surrounding throwing sand pocket of all steel-pipe piles of rocky bed in bottom, forms sand pocket cofferdam 2;As shown in Figure 1;
4)According to step 1)Calculate parameters obtained, in sand pocket cofferdam pouring underwater concrete as artificial concrete coating 3, Ensure that bottom is the steel-pipe pile of rocky bed and there are enough building-in depths, meets resistance to capsizing requirement;Artificial concrete covering The structural schematic diagram of layer 3 is as shown in Figure 2;
5)In conjunction with Fig. 3, Fig. 4, scissors is welded with channel steel between every group of two steel-pipe piles, between the two corresponding steel-pipe piles of row Support, stull are connected as one, and are allowed to constitute a frame structure, are enhanced the stability of steel-pipe pile;
(6)According to each steel pipe stake top of design altitude leveling after surveying and locating, 2/3 long gravel or coagulation are poured into steel-pipe pile Soil enhances resistance to capsizing to reduce the center of gravity of steel-pipe pile;
7)Each steel pipe stake top after leveling is fixed with more Bailey beams being arranged along steel trestle length direction;The more shellfish thunders Steel trestle floorings are fixed on the top of beam, and connect firmly steel trestle railing at the both ends of steel trestle floorings.
Preferred embodiment above is merely illustrative of the technical solution of the present invention and unrestricted, although passing through above-mentioned preferred implementation Example is described in detail the present invention, however, those skilled in the art should understand that, can be in the form and details Various changes, such as the selection of bank material are made to it, without departing from model defined by claims of the present invention It encloses.

Claims (1)

1. a kind of construction method for deep water shallow overburden steel trestle, it is characterised in that:The specific steps of the construction method It is as follows:
1)Model is established, steel trestle modelling is carried out, determines steel trestle steel-pipe pile model and meet under antidumping requirement condition Artificial concrete coating parameters;
2)Steel-pipe pile is transferred into riverbed bottom in designated position using crane lifting vibration hammer;The steel-pipe pile is along steel trestle Length direction setting two row, be often classified as it is multigroup, every group be two;For the steel-pipe pile that riverbed bottom is rocky bed part, need Squeezed into rocky bed to beat it is motionless until;Then steel-pipe pile is fixed on leading truck with channel steel, it is ensured that steel-pipe pile is stablized Property;
3)It is the surrounding throwing sand pocket of all steel-pipe piles of rocky bed in bottom, forms sand pocket cofferdam;
4)According to step 1)Calculate parameters obtained, in sand pocket cofferdam pouring underwater concrete as artificial concrete coating, Ensure that bottom is the steel-pipe pile of rocky bed and there are enough building-in depths, meets resistance to capsizing requirement;
5)It is connected as with channel steel welding bridging, stull between every group of two steel-pipe piles, between the two corresponding steel-pipe piles of row One, is allowed to constitute a frame structure, enhances the stability of steel-pipe pile;
6)According to each steel pipe stake top of design altitude leveling after surveying and locating, 2/3 long gravel or coagulation are poured into steel-pipe pile Soil enhances resistance to capsizing to reduce the center of gravity of steel-pipe pile;
7)Each steel pipe stake top after leveling is fixed with more Bailey beams being arranged along steel trestle length direction;The more shellfish thunders Steel trestle floorings are fixed on the top of beam, and connect firmly steel trestle railing at the both ends of steel trestle floorings.
CN201811003834.2A 2018-08-30 2018-08-30 A kind of construction method for deep water shallow overburden steel trestle Pending CN108797372A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811003834.2A CN108797372A (en) 2018-08-30 2018-08-30 A kind of construction method for deep water shallow overburden steel trestle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811003834.2A CN108797372A (en) 2018-08-30 2018-08-30 A kind of construction method for deep water shallow overburden steel trestle

Publications (1)

Publication Number Publication Date
CN108797372A true CN108797372A (en) 2018-11-13

Family

ID=64081326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811003834.2A Pending CN108797372A (en) 2018-08-30 2018-08-30 A kind of construction method for deep water shallow overburden steel trestle

Country Status (1)

Country Link
CN (1) CN108797372A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653076A (en) * 2018-12-24 2019-04-19 四川港航建设工程有限公司 Combined type flood control is passed the flood period lock head shellfish Lei Gangqiao and construction method
CN110409281A (en) * 2019-08-12 2019-11-05 中交隧道工程局有限公司 A kind of deep water drift net steel trestle
CN110847169A (en) * 2019-11-26 2020-02-28 湖北省路桥集团有限公司 Construction method of steel pipe pile steel trestle
CN112627035A (en) * 2020-12-10 2021-04-09 上海宝冶集团有限公司 Design and construction method of large-span Bailey steel trestle
CN113818352A (en) * 2021-09-29 2021-12-21 湖南交通国际经济工程合作有限公司 Soft foundation high pier curve cast-in-situ box girder bridge and construction method thereof
CN114960651A (en) * 2022-04-29 2022-08-30 中国铁建港航局集团有限公司 Bored concrete pile drilling platform and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101347558B1 (en) * 2013-03-05 2014-01-06 권오근 Construction method for corrugated steel plate web-psc composite beam
CN106351242A (en) * 2016-08-31 2017-01-25 中交第二航务工程局有限公司 Deepwater high-flow-rate exposed high-strength steep rock sea area steel trestle and construction method thereof
CN106801424A (en) * 2017-01-18 2017-06-06 杭州天顺市政园林工程有限公司 A kind of cofferdam construction method
CN107119569A (en) * 2017-05-19 2017-09-01 中铁十六局集团第五工程有限公司 A kind of construction method of the oblique rock geology construction make-shift bridge of deep water shallow overburden

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101347558B1 (en) * 2013-03-05 2014-01-06 권오근 Construction method for corrugated steel plate web-psc composite beam
CN106351242A (en) * 2016-08-31 2017-01-25 中交第二航务工程局有限公司 Deepwater high-flow-rate exposed high-strength steep rock sea area steel trestle and construction method thereof
CN106801424A (en) * 2017-01-18 2017-06-06 杭州天顺市政园林工程有限公司 A kind of cofferdam construction method
CN107119569A (en) * 2017-05-19 2017-09-01 中铁十六局集团第五工程有限公司 A kind of construction method of the oblique rock geology construction make-shift bridge of deep water shallow overburden

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653076A (en) * 2018-12-24 2019-04-19 四川港航建设工程有限公司 Combined type flood control is passed the flood period lock head shellfish Lei Gangqiao and construction method
CN110409281A (en) * 2019-08-12 2019-11-05 中交隧道工程局有限公司 A kind of deep water drift net steel trestle
CN110409281B (en) * 2019-08-12 2024-03-15 中交隧道工程局有限公司 Deepwater bare rock steel trestle
CN110847169A (en) * 2019-11-26 2020-02-28 湖北省路桥集团有限公司 Construction method of steel pipe pile steel trestle
CN110847169B (en) * 2019-11-26 2021-09-28 湖北省路桥集团有限公司 Construction method of steel pipe pile steel trestle
CN112627035A (en) * 2020-12-10 2021-04-09 上海宝冶集团有限公司 Design and construction method of large-span Bailey steel trestle
CN113818352A (en) * 2021-09-29 2021-12-21 湖南交通国际经济工程合作有限公司 Soft foundation high pier curve cast-in-situ box girder bridge and construction method thereof
CN114960651A (en) * 2022-04-29 2022-08-30 中国铁建港航局集团有限公司 Bored concrete pile drilling platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN108797372A (en) A kind of construction method for deep water shallow overburden steel trestle
CN106351242B (en) A kind of exposed high intensity sea area the Dou Yan steel trestle of the big flow velocity of deep water and its construction method
CN102677592B (en) Method for erecting deepwater steel trestle and platform on exposed bedrock in shallow sea
CN107059774A (en) A kind of assembled high-rise pile cap revetment structure and construction method
CN101696578A (en) Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102653945A (en) Foundation reinforcing and replacing structure and construction method thereof
CN107034884A (en) The steel pile casting constructing device and method of the big oblique rock surface of shallow overburden profundal zone flow velocity
CN110984213A (en) Offshore wind power single pile-friction cone composite foundation and construction method thereof
JP2017508087A (en) Water bottom fixing hollow roll used for water platform and its construction method
CN108179735A (en) A kind of boulder bed large-sized deep water foundation construction platform and method
CN107724383A (en) Rotary digging cast-in-place pile construction method
CN109797749A (en) Underwater foundation pit construction device and construction method
CN110359476A (en) A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN107489106B (en) A kind of rocky bed subaqueous bearing platform construction method
CN107859034B (en) Large diameter pile foundation spillage immediate processing method
CN101392521A (en) Rock-socketed steel dock structure and construction method thereof
CN207878458U (en) Interim steel trestle with resistance to plucking auxiliary pile
CN112149259B (en) Water storage stability calculation method and device for dumping ulcer Qu Bianpo and storage medium
CN202969333U (en) Steel truss rock-socketed wharf structure
CN104863152A (en) High-strength bare rock pipe pile inserting-driving method
CN105735348B (en) A kind of construction method of river channel hydroelectric resource development station factory building water inlet sediment trapping bank
JP6105044B2 (en) Partially floating offshore platform for offshore wind power, bridges and offshore structures, and construction method
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181113

WD01 Invention patent application deemed withdrawn after publication