CN108756194A - A kind of telescopic scaffold and its method for installing elevator shaft frame - Google Patents

A kind of telescopic scaffold and its method for installing elevator shaft frame Download PDF

Info

Publication number
CN108756194A
CN108756194A CN201810879614.XA CN201810879614A CN108756194A CN 108756194 A CN108756194 A CN 108756194A CN 201810879614 A CN201810879614 A CN 201810879614A CN 108756194 A CN108756194 A CN 108756194A
Authority
CN
China
Prior art keywords
elevator shaft
shaft frame
panel
inner tube
operating platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810879614.XA
Other languages
Chinese (zh)
Other versions
CN108756194B (en
Inventor
李鹏
房秀斌
李想
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Beili Automobile Technology Co ltd
Original Assignee
Ningbo Sewell Elevator Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Sewell Elevator Equipment Co Ltd filed Critical Ningbo Sewell Elevator Equipment Co Ltd
Priority to CN201810879614.XA priority Critical patent/CN108756194B/en
Publication of CN108756194A publication Critical patent/CN108756194A/en
Application granted granted Critical
Publication of CN108756194B publication Critical patent/CN108756194B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/20Scaffolds comprising upright members and provision for supporting cross-members or platforms at different positions therealong
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F17/00Vertical ducts; Channels, e.g. for drainage
    • E04F17/005Lift shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of telescopic scaffolds and its method for installing elevator shaft frame, are related to elevator field of escalator installation.Telescopic scaffold for installing elevator includes:Panel and two transverse support bars;Panel is layed in two transverse support bars;Transverse support bar includes:Outer tube, inner tube, corner brace and bolt;Inner tube both ends are arranged respectively there are one outer tube, and inner tube can reciprocatingly slide in outer tube;Corner brace is fixed on one end of outer tube;Bolt-through is installed in corner brace, and the telescopic scaffold for being used to install elevator shaft frame of the invention and its operational method are simple in structure, and fast assembling-disassembling reduces the installation period and installation cost of elevator.

Description

A kind of telescopic scaffold and its method for installing elevator shaft frame
Technical field
The present invention relates to field of escalator installation more particularly to a kind of telescopic scaffolds for installing elevator shaft frame And its method.
Background technology
In elevator installation at present, it is time-consuming and laborious to build scaffold, and causes strong influence to installation progress.? The narrow region such as spiral stairs, building scaffold in hoistway frame, there are certain difficulties.Scaffold needs to wait until cage guide Installation is complete to remove, and runs through entire frame installation period, and cost is higher;
A kind of scaffold for elevator shaft as disclosed in Chinese invention patent 206859625U, including pedestal and frame body, it is described Pedestal includes supporting steel plate, two sleeves and four telescopic rods, which is respectively oppositely fixed at supporting steel The both sides of plate, and two telescopic rods are placed respectively in each sleeve, which can be respectively from two ports of sleeve It stretches out or retracts.
But the elevator scaffolding structure in technology disclosed above is complicated, and operating efficiency is low.
Invention content
One, technical problems to be solved
The purpose of the present invention is for the above problem present in the prior art, provide a kind of for installing elevator shaft The telescopic scaffold and its method of frame solve the problems, such as that complicated operating efficiency is low.
Two, technical solution
In order to solve the above technical problems, the present invention provide it is a kind of for install elevator shaft frame telescopic scaffold and Its method, including:Panel and two transverse support bars;
Panel is layed in two transverse support bars;
Transverse support bar includes:Outer tube, inner tube, corner brace and bolt;
Inner tube both ends are arranged respectively there are one outer tube, and inner tube can reciprocatingly slide in outer tube;
Corner brace is fixed on one end of outer tube;
Bolt-through is installed in corner brace.
Wherein, corner brace is set there are two bolt.
Wherein, outer tube and inner tube are pipe.
Wherein, panel is steel net plate.
Wherein, inner tube is equipped with warning mark.
Wherein, the method for installation elevator shaft frame includes the following steps:
Four columns are installed in elevator installation place, lateral crosspiece are installed between column, the stabilization for consolidating column Property;
First layer elevator shaft frame installs;
After crosspiece installs, corner brace and crosspiece are fixed with bolt on crosspiece;
Transverse support bar is secured transverse on crosspiece at this time, is used as scaffold;
Install after two transverse support bars the lay panel in transverse support bar;
Panel is laid on the outer tube at transverse support bar both ends;
First layer operating platform installs, and worker installs second layer elevator shaft frame in station through the above steps on panel Frame and second layer operating platform;
After second layer operating platform installs, the lay panel in the inner tube of first layer operating platform;
Then third layer elevator shaft frame and third layer operating platform are installed in worker station on second layer operating platform, and And and remove first layer operating platform, the lay panel in the inner tube of second layer operating platform;
Above-mentioned work step is repeated, until operation is completed in elevator.
Three, beneficial effects of the present invention
Compared with prior art, the telescopic scaffold and its method structure for installing elevator shaft frame of the invention Simply, fast assembling-disassembling reduces the installation period and installation cost of elevator.
Description of the drawings
Fig. 1 is the transverse support bar structural representation of the telescopic scaffold for installing elevator shaft frame of the present invention Figure;
Fig. 2 is the schematic diagram of the method for installing elevator shaft frame of the present invention;
Fig. 3 is the telescopic scaffold schematic diagram for installing elevator shaft frame of the present invention;In figure:1 is panel;2 For outer tube;3 be inner tube;4 be corner brace;5 be bolt.
Specific implementation mode
With reference to the accompanying drawings and examples, the specific implementation mode of the present invention is described in further detail.Implement below Example cannot be used for limiting the scope of the invention for illustrating the present invention.
The embodiment of the present invention for install elevator shaft frame telescopic scaffold and its method structure such as Fig. 1 and Include shown in 2:Panel 1 and two transverse support bars;
Panel 1 is layed in two transverse support bars;
Transverse support bar includes:Outer tube 2, inner tube 3, corner brace 4 and bolt 5;
3 both ends of inner tube are arranged respectively there are one outer tube 2, and inner tube 3 can reciprocatingly slide in outer tube 2, make lateral branch Strut can be mounted in different size of elevator shaft frame
Corner brace 4 consolidates the one end in outer tube 2 by the means of welding, by running through two bolts 5 in corner brace 4 by corner brace 4 are mounted on the strut rail of elevator shaft frame, so that transverse support bar is secured transverse in elevator shaft frame, then in cross Steel mesh panel is laid on supporting rod, worker, which may stand in, carries out operation on panel 1.
It is only laid on above the outer tube 2 at transverse support bar both ends when lay panel 1, inner tube is due to far from corner brace 4 Stress point, if personnel step down in, to be easy to cause transverse support bar stress above excessive and influence stability;
The method of installation elevator shaft frame includes the following steps:
Four columns are installed in elevator installation place, lateral crosspiece are installed between column, the stabilization for consolidating column Property;
First layer elevator shaft frame installs;
After crosspiece installs, corner brace 4 is fixed with crosspiece with bolt 5 on crosspiece;
Transverse support bar is secured transverse on crosspiece at this time, is used as scaffold;
Install after two transverse support bars lay panel 1 in transverse support bar;
Panel 1 is laid on the outer tube 2 at transverse support bar both ends;
First layer operating platform installs, and worker installs second layer elevator shaft in station through the above steps on panel 1 Frame and second layer operating platform;
After second layer operating platform installs, the lay panel in the inner tube 3 of first layer operating platform;
Then third layer elevator shaft frame and third layer operating platform are installed in worker station on second layer operating platform, and And and remove first layer operating platform, the lay panel in the inner tube 3 of second layer operating platform;
Above-mentioned work step is repeated, until operation is completed in elevator
After the completion of operation on first layer operating platform, second layer operating platform, second layer behaviour are built according to the method described above After the completion of making platform building, steel mesh panel is laid in the inner tube 3 of first layer operating platform, worker makees in second layer operating platform It when industry, falls once slipping, first layer operating platform can play cushioning effect.
It on second layer operating platform after the completion of operation, repeats the above steps and builds third layer operating platform, remove first layer Operating platform, the lay panel 1 in second layer operating platform inner tube 3;And so on, until the operation in elevator is all complete At.
Outer tube 2 and inner tube 3 usually pay the utmost attention to pipe from the point of view of facilitating production, must have been portrayed in inner tube 3 Apparent limit alert flag, display inner tube 3 can do the extreme position slided, the elongation of inner tube 3 to warning position in outer tube 2 When, it can not continue to stretch, prevent operation error from causing safety accident.
T-slot is arranged in crosspiece, can fixing bolt 5, when installation, bolt is formed directly into out of T-slot, you can fixed corner code 4, When installation is complete, the i.e. dismountable telescopic scaffold of corner brace 4 can be unclamped;
The elevator shaft frame installed by this method can substitute traditional mixed mud hoistway, not design elevator In building when installation elevator, cast mixed mud hoistway is no longer needed to, installation cost and the set-up time of elevator have been saved.
Steel net plate or plank can be selected in panel 1 in practice, waits other that can carry the plank of human body weight, this reality Apply the preferred steel net plate of example;
Inner tube 3 and outer tube 2 can use pipe or square tube to make, and the preferred pipe of the present embodiment is as inner tube 3 and outer tube 2.
It the above is only the preferred embodiment of the present invention, it is noted that those skilled in the art are come It says, without departing from the technical principles of the invention, several improvements and modifications can also be made, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (8)

1. a kind of telescopic scaffold for installing elevator shaft frame, which is characterized in that described for installing elevator shaft The telescopic scaffold of frame includes:Panel (1) and two transverse support bars;
The panel (1) is layed in two transverse support bars;
The transverse support bar includes:Outer tube (2), inner tube (3), corner brace (4) and bolt (5);
Said inner tube (3) both ends are arranged respectively there are one the outer tube (2), and said inner tube (3) can be in the outer tube (2) It reciprocatingly slides;
The corner brace (4) is fixed on one end of the outer tube (2);
The bolt (5), which is run through, to be installed in the corner brace (4).
2. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that the corner brace (4) bolt (5) there are two setting.
3. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that the outer tube (2) and said inner tube (3) is pipe.
4. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that the outer tube (2) and said inner tube (3) is square tube
5. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that the panel (1) it is steel net plate.
6. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that the panel (1) it is plank.
7. the telescopic scaffold as described in claim 1 for installing elevator shaft frame, which is characterized in that said inner tube (3) it is equipped with warning mark.
8. a kind of method of installation elevator shaft frame, which is characterized in that the method for the installation elevator shaft frame includes such as Lower step:
Four columns are installed in elevator installation place, lateral crosspiece are installed between column, the stability for consolidating column;
First layer elevator shaft frame installs;
After crosspiece installs, the corner brace (4) is fixed with the crosspiece with the bolt (5) on crosspiece;
The transverse support bar is secured transverse on the crosspiece at this time, is used as scaffold;
The panel (1) is laid in the transverse support bar after installing two transverse support bars;
The panel (1) is laid on the outer tube (2) at the transverse support bar both ends;
First layer operating platform installs, and worker installs second layer elevator in station through the above steps on the panel (1) Road frame and second layer operating platform;
After the second layer operating platform installs, the lay panel in the inner tube (3) of first layer operating platform;
Then third layer elevator shaft frame and third layer operating platform are installed in worker station on the second layer operating platform, and And and remove first layer operating platform, the lay panel in the inner tube (3) of the second layer operating platform;
Above-mentioned work step is repeated, until operation is completed in elevator.
CN201810879614.XA 2018-08-03 2018-08-03 Telescopic scaffold for installing elevator shaft frame and method thereof Active CN108756194B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810879614.XA CN108756194B (en) 2018-08-03 2018-08-03 Telescopic scaffold for installing elevator shaft frame and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810879614.XA CN108756194B (en) 2018-08-03 2018-08-03 Telescopic scaffold for installing elevator shaft frame and method thereof

Publications (2)

Publication Number Publication Date
CN108756194A true CN108756194A (en) 2018-11-06
CN108756194B CN108756194B (en) 2023-07-21

Family

ID=63968731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810879614.XA Active CN108756194B (en) 2018-08-03 2018-08-03 Telescopic scaffold for installing elevator shaft frame and method thereof

Country Status (1)

Country Link
CN (1) CN108756194B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115478677A (en) * 2022-11-01 2022-12-16 宁波建工建乐工程有限公司 Elevator shaft operation platform with adjustable promote certainly

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5230404A (en) * 1991-03-01 1993-07-27 Inventio Ag Erection scaffolding which is movable in an elevator shaft for the mounting of shaft equipment
CN102992133A (en) * 2012-12-03 2013-03-27 福建省连江县迅捷技术孵化有限公司 Falling prevention system of construction elevator
CN204510770U (en) * 2015-02-10 2015-07-29 中国建筑第四工程局有限公司 A kind of lift-type elevator hoistway construction platform being applicable to varying cross-section
CN205224567U (en) * 2015-11-19 2016-05-11 中国葛洲坝集团第六工程有限公司 Collapsible foldable elevartor shaft construction platform
CN206233546U (en) * 2016-11-11 2017-06-09 河南六建建筑集团有限公司 A kind of elevator hoistways workbench
CN206859625U (en) * 2017-06-16 2018-01-09 中国对外建设有限公司 Scaffold for elevator shaft
CN107697765A (en) * 2017-10-20 2018-02-16 宁波宏大电梯有限公司 A kind of elevator hoistways framework and installation method
CN208777664U (en) * 2018-08-03 2019-04-23 宁波赛威电梯设备有限公司 It is a kind of for installing the telescopic foot hand cradle of elevator shaft frame

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5230404A (en) * 1991-03-01 1993-07-27 Inventio Ag Erection scaffolding which is movable in an elevator shaft for the mounting of shaft equipment
CN102992133A (en) * 2012-12-03 2013-03-27 福建省连江县迅捷技术孵化有限公司 Falling prevention system of construction elevator
CN204510770U (en) * 2015-02-10 2015-07-29 中国建筑第四工程局有限公司 A kind of lift-type elevator hoistway construction platform being applicable to varying cross-section
CN205224567U (en) * 2015-11-19 2016-05-11 中国葛洲坝集团第六工程有限公司 Collapsible foldable elevartor shaft construction platform
CN206233546U (en) * 2016-11-11 2017-06-09 河南六建建筑集团有限公司 A kind of elevator hoistways workbench
CN206859625U (en) * 2017-06-16 2018-01-09 中国对外建设有限公司 Scaffold for elevator shaft
CN107697765A (en) * 2017-10-20 2018-02-16 宁波宏大电梯有限公司 A kind of elevator hoistways framework and installation method
CN208777664U (en) * 2018-08-03 2019-04-23 宁波赛威电梯设备有限公司 It is a kind of for installing the telescopic foot hand cradle of elevator shaft frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115478677A (en) * 2022-11-01 2022-12-16 宁波建工建乐工程有限公司 Elevator shaft operation platform with adjustable promote certainly
CN115478677B (en) * 2022-11-01 2023-09-22 宁波建工建乐工程有限公司 Self-lifting adjustable elevator shaft operation platform

Also Published As

Publication number Publication date
CN108756194B (en) 2023-07-21

Similar Documents

Publication Publication Date Title
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN105113388B (en) Formwork and bracket combining structure of vase pier of viaduct and application method
CN101748799B (en) Hydraulic lifting rollover construction method of chimney reinforced concrete shaft wall
CN205804190U (en) A kind of travelling bridge for the guardrail construction that builds a bridge
CN102677889A (en) System for alternatively supporting whole lifting steel platform formwork by steel column casing rack and construction method
CN208777664U (en) It is a kind of for installing the telescopic foot hand cradle of elevator shaft frame
CN208884362U (en) A kind of Construction of continuous beam bracket
CN108756194A (en) A kind of telescopic scaffold and its method for installing elevator shaft frame
CN202430994U (en) Template limiting clamp
JP2017048635A (en) Bridge disassembly method of using installation girder
CN109778713A (en) A kind of steel truss girder bridge scene suspension and slipping assembly device and method
CN103147569A (en) Operation platform system for cross-pulling slip form with both full-diameter silo and spoke-type center plate
CN211006341U (en) Assembled strength nature skeleton suitable for mound tower reinforcing bar location
JP4980257B2 (en) Construction method for column head construction, method for constructing mobile work vehicle using part thereof, and method for extending bridge
CN107720580B (en) Quick construction hoisting device and method for boiler construction water-cooled wall
CN213654364U (en) Many function combination formula removes protection canopy
CN204038917U (en) Dismountable external hanging service platform
CN104594631B (en) The construction technology of sliding form apparatus traction operation platform construction granulation tower spraying layer
CN209907435U (en) Pipe rack platform truck for comprehensive pipe rack building construction
CN209722761U (en) A kind of steel truss girder bridge scene suspension and slipping assembly device
CN110565518A (en) assembled stiff skeleton suitable for pier tower steel bar positioning and use method thereof
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
CN219430545U (en) Operation platform for utilizing stiffness framework for tower column head section
CN214737495U (en) Positioning trolley for arch culvert
CN114086461B (en) Rapid construction method for high pier combined assembly type steel bar inner support by matching with turnover formwork method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20230530

Address after: No. 9, Shangqiao Road, Xiwu Street, Fenghua District, Ningbo, Zhejiang 315000

Applicant after: NINGBO BEILI AUTOMOBILE TECHNOLOGY Co.,Ltd.

Address before: 315500 Xi Ruan, Kangling Village, Xikou Town, Fenghua District, Ningbo City, Zhejiang Province

Applicant before: NINGBO SAIWEI ELEVATOR EQUIPMENT Co.,Ltd.

GR01 Patent grant
GR01 Patent grant