CN108755696A - A kind of rapid construction of pit earthwork at raining season method - Google Patents

A kind of rapid construction of pit earthwork at raining season method Download PDF

Info

Publication number
CN108755696A
CN108755696A CN201810626809.3A CN201810626809A CN108755696A CN 108755696 A CN108755696 A CN 108755696A CN 201810626809 A CN201810626809 A CN 201810626809A CN 108755696 A CN108755696 A CN 108755696A
Authority
CN
China
Prior art keywords
pit
construction
foundation pit
earthwork
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810626809.3A
Other languages
Chinese (zh)
Inventor
沈建军
夏正高
王李珍
周伟恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Dong Zhu View Limited-Liability Co
Original Assignee
Jiangsu Dong Zhu View Limited-Liability Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Dong Zhu View Limited-Liability Co filed Critical Jiangsu Dong Zhu View Limited-Liability Co
Priority to CN201810626809.3A priority Critical patent/CN108755696A/en
Publication of CN108755696A publication Critical patent/CN108755696A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • E03F3/046Open sewage channels
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention provides a kind of rapid construction of pit earthwork at raining season methods, before being included in pit earthwork excavation construction, after completing positioning, unwrapping wire, the work of datum mark pilot measurement, the construction of the pumping equipments such as the outer slope of foundation pit, traffic route progress place mat, the brick wall that intercepts water, drainage groove and catch pit is carried out;In pit earthwork excavation construction, carry out accordingly reinforcing and draining countermeasure;Rainy season earthwork construction scheme provided by the present invention, it is protected in advance by excavating early period in the simple Job readiness progress foundation pit Pluvial, has prevented the possibility that the outer rainwater of foundation pit flows into foundation pit, reduced drainage of foundation pit pressure, shorten the base pit dewatering period, realizes the rapid construction of pit earthwork at raining season;The drainage construction scheme that the offer Pluvial does not stop work reduces the construction safety hidden danger brought because Pluvial construction drainage is improper.

Description

A kind of rapid construction of pit earthwork at raining season method
Technical field
The invention belongs to technical field of building construction, and in particular, to a kind of rapid construction of pit earthwork at raining season method.
Background technology
Pit earthwork construction in, weather conditions be always one influence the duration an important factor for, in case of project site is located at Business district, most of units in charge of construction will face the situation that the duration is tight, dregs haul distance is remote, transit route vehicle flowrate is big, and be permitted More business district projects only allow the hour that carries on construction work at night, many units in charge of construction whether between rainy day venture construction and schedule delays it is difficult It chooses, and often therefore even there is construction accident in influence construction quality in order to compress the mistake resolution that the duration is made, even Bring huge economic losses and construction personnel's security risk.
Therefore, the above problem is urgently to be resolved hurrily.
Invention content
Goal of the invention:For overcome the deficiencies in the prior art, the object of the present invention is to provide one kind can be in rainy season situation Lower pit earthwork construction method that is conscientiously effective, reducing Pluvial construction safety hidden danger.
Technical solution:The present invention provides a kind of rapid construction of pit earthwork at raining season methods, which is characterized in that including following Construction procedure:
1)Before pit earthwork excavation construction, after completing positioning, unwrapping wire, the work of datum mark pilot measurement, fills and leads up foundation pit surrounding ground and stay Outer slope carries out place mat, in the foundation pit structure top ground with brick or sandstone to the outer slope and detail design traffic route Place builds the brick wall that intercepts water by laying bricks or stones, and the brick wall bilateral that intercepts water smears cement mortar, and the slope surface that intercepts water is made on ground on the outside of water stop, described The slope surface that intercepts water smears cement mortar surface, and the slope surface top of the slope periphery of intercepting water is arranged brick drainage groove, is set in four corners of foundation pit Catch pit is set, immersible pump is set in catch pit;
2)Pit earthwork excavation construction, stage excavation, excavation face should make stable side slope from top to bottom for the earthwork, to the foundation pit and Side slope, which synchronizes, carries out supporting;When earth excavation to foundation pit bottom, covered in time, and build the gutter interconnected in time And sump, sump is interior to be arranged immersible pump.
The rainy season earthwork construction scheme of the present invention, mainly by slope outside simple Job readiness early period such as foundation pit, intercept water it is outer The pumping equipments such as wall, drainage groove, gutter and sump, progress Pluvial protect in advance, have prevented the outer rainwater of foundation pit and have flowed into foundation pit Possibility, reduce drainage of foundation pit pressure, shorten the base pit dewatering period, and then realize pit earthwork at raining season rapid construction.
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that when rainfall, the side Slope plastic covering film.
Side slope plastic covering film prevents the rain wet slump of side slope.
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that foundation pit lower part soil body soil When the Pluvial is excavated by side, example adds 5~10% concrete accelerators and carries out whitewashing solidification in mass ratio in concrete grout, has whitewashed Whitewashing position is covered using plastic film at rear.
Whitewashing solidification can be carried out in Pluvial and non-Pluvial, mitigate the influence then stablized to foundation pit.
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that in the excavation slope Backwater drainpipe is set at a certain distance in soil.
Be arranged the backwater drainpipe make in order to prevent earth's surface water penetration to gunite concrete face layer generate pressure, simultaneously prevent Only rain penetration reduces the interfacial adhesion between soil strength and the soil body and soil nailing, causes foundation pit collapse, landslide, is realizing ground While face drains, the rainwater for penetrating into side slope is excluded using backwater drainpipe, ensures deep pit monitor
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that the collecting gutter is by width 600mm, deep 500~600mm settings, the gutter gradient 1%, apart from 0.2~0.3m of foundation pit leftover bits and pieces;The sump is along the base Cheat the setting of bottom edge angle, diameter 1.5m.
Above-mentioned is specific collecting gutter structure, and multiple construction experience proves that this structure collecting gutter has structural stability, no Easy turned-down edge.
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that the sump bottom is low In Foundation Pit bottom surface 1.5m, setting presses bottom, the ponding in sump to be arranged at any time by immersible pump without sand drain pipe, filtrate and rubble Go out.
Above-mentioned is specific catch pit structure, and above structure makes catch pit be not easy to form mud mortar, keeps draining smooth, is protected The bottom drying of card hole.
Further, a kind of above-mentioned rapid construction of pit earthwork at raining season method, which is characterized in that if foundation pit not on earth or When the collecting gutter and sump of substrate are not fixed, such as heavy showers, foundation pit is interior to be drained in the rain using slush pump.
Slush pump cooperation draining, prevents mud from destroying hole bottom and pumping equipment.
Above-mentioned technical proposal can be seen that the present invention and have the advantages that:
1)Rainy season earthwork construction scheme provided by the present invention, it is pre- by excavating early period in the simple Job readiness progress foundation pit Pluvial Protection has prevented the possibility that the outer rainwater of foundation pit flows into foundation pit, has reduced drainage of foundation pit pressure, shorten the base pit dewatering period, realize rain Season pit earthwork rapid construction;
2)This construction method provides the drainage construction scheme that do not stop work in the Pluvial, reduces because of the improper construction brought of Pluvial construction drainage Security risk.
Specific implementation mode
Embodiment
A kind of rapid construction of pit earthwork at raining season method, which is characterized in that including following construction procedure:
1)Before pit earthwork excavation construction, the drainage system of construction site should be improved as possible, ensure that construction site is drained with extraneous It is unobstructed, and the foundation pit water blocking measure of effect certainly is taken, to prevent the surface water from flowing into foundation pit, for this purpose, completing positioning, putting After line, the work of datum mark pilot measurement, fills and leads up foundation pit surrounding ground and stay outer slope, build by laying bricks or stones and intercept water at the foundation pit structure top ground Brick wall, the brick wall bilateral that intercepts water smears cement mortar, and the slope surface that intercepts water is made on ground on the outside of water stop, and the slope surface that intercepts water is smeared Brick drainage groove is arranged in cement mortar surface, the slope surface top of the slope periphery of intercepting water, and catch pit, collection is arranged in four corners of foundation pit Immersible pump is set in puddle, and above-mentioned working measure can prevent the surface water from flowing into foundation pit.In addition, when blocking water outside progress, answer Synchronous brick or sandstone carry out place mat to the outer slope and detail design traffic route, and external slope is cured, and ensure the Pluvial Carriage way is stablized, and the construction delays brought by Road Factor are prevented.
Wherein, the brick wall thickness that intercepts water is not less than 100mm, by the regional situation of construction, is highly not less than 200mm, draining Groove is 500*500mm, and catch pit hole is deep to be not less than 1000mm, and diameter is more than drainage groove width.
2)When outside block water facility complete, you can carry out pit earthwork excavation construction, it is such as fine in weather, also can same stepping Row.The earthwork should stage excavation, excavation face should make stable side slope from top to bottom in the usual way, synchronous with side slope to the foundation pit Carry out supporting;It when earth excavation to foundation pit bottom, is covered in time, and builds the gutter interconnected in time and catchment Well, sump is interior to be arranged immersible pump.The collecting gutter is by wide 600mm, deep 500~600mm settings, the gutter gradient 1%, distance 0.2~0.3m of foundation pit leftover bits and pieces;The sump is arranged along foundation pit bottom edge angle, diameter 1.5m.The sump bottom is less than Foundation Pit bottom surface 1.5m, setting press bottom, the ponding in sump to be discharged at any time by immersible pump without sand drain pipe, filtrate and rubble.
Wherein, when rainfall, the side slope plastic covering film.
Wherein, when the foundation pit lower part soil body earth excavation Pluvial, example adds 5~10% coagulations in mass ratio in concrete grout Native accelerator carries out whitewashing solidification, is covered to whitewashing position using plastic film after the completion of whitewashing.
Wherein, backwater drainpipe is set at a certain distance in the excavation slope soil.
Wherein, it if foundation pit is not on earth or when the collecting gutter of substrate and sump are fixed, such as heavy showers, is used in foundation pit Slush pump is drained in the rain.In addition, diving pump drainage can also be used in this situation, provisioned draining length of tube, which should meet, can make water Disposable discharge construction site.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the principle of the present invention, several improvement can also be made, these improvement also should be regarded as the present invention's Protection domain.

Claims (7)

1. a kind of rapid construction of pit earthwork at raining season method, which is characterized in that including following construction procedure:
1)Before pit earthwork excavation construction, after completing positioning, unwrapping wire, the work of datum mark pilot measurement, fills and leads up foundation pit surrounding ground and stay Outer slope carries out place mat, in the foundation pit structure top ground with brick or sandstone to the outer slope and detail design traffic route Place builds the brick wall that intercepts water by laying bricks or stones, and the brick wall bilateral that intercepts water smears cement mortar, and the slope surface that intercepts water is made on ground on the outside of water stop, described The slope surface that intercepts water smears cement mortar surface, and the slope surface top of the slope periphery of intercepting water is arranged brick drainage groove, is set in four corners of foundation pit Catch pit is set, immersible pump is set in catch pit;
2)Pit earthwork excavation construction, stage excavation, excavation face should make stable side slope from top to bottom for the earthwork, to the foundation pit and Side slope, which synchronizes, carries out supporting;When earth excavation to foundation pit bottom, covered in time, and build the gutter interconnected in time And sump, sump is interior to be arranged immersible pump.
2. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that described when rainfall Side slope plastic covering film.
3. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that the foundation pit lower part soil body When the earth excavation Pluvial, example adds 5~10% concrete accelerators and carries out whitewashing solidification in mass ratio in concrete grout, whitewashes Whitewashing position is covered using plastic film after the completion.
4. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that on the foundation pit side Backwater drainpipe is set at a certain distance in the soil of slope.
5. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that the collecting gutter is pressed Wide 600mm, deep 500~600mm settings, the gutter gradient 1%, apart from 0.2~0.3m of foundation pit leftover bits and pieces;The sump is described in Foundation pit bottom edge angle is arranged, diameter 1.5m.
6. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that the sump bottom Less than Foundation Pit bottom surface 1.5m, setting presses bottom, the ponding in sump to be arranged at any time by immersible pump without sand drain pipe, filtrate and rubble Go out.
7. a kind of rapid construction of pit earthwork at raining season method according to claim 1, which is characterized in that if foundation pit is not on earth Or the collecting gutter and sump of substrate be when fixing, such as heavy showers, is drained in the rain using slush pump in foundation pit.
CN201810626809.3A 2018-06-19 2018-06-19 A kind of rapid construction of pit earthwork at raining season method Pending CN108755696A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810626809.3A CN108755696A (en) 2018-06-19 2018-06-19 A kind of rapid construction of pit earthwork at raining season method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810626809.3A CN108755696A (en) 2018-06-19 2018-06-19 A kind of rapid construction of pit earthwork at raining season method

Publications (1)

Publication Number Publication Date
CN108755696A true CN108755696A (en) 2018-11-06

Family

ID=63978588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810626809.3A Pending CN108755696A (en) 2018-06-19 2018-06-19 A kind of rapid construction of pit earthwork at raining season method

Country Status (1)

Country Link
CN (1) CN108755696A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology
CN112062443A (en) * 2020-08-10 2020-12-11 安徽科清水环境技术有限公司 Ecological dredging sludge on-site rapid curing process
CN113123360A (en) * 2021-04-28 2021-07-16 上海宝冶集团有限公司 Environment-friendly drainage method for construction of coastal region stone square groove foundation pit in rainy season
CN114232662A (en) * 2021-11-09 2022-03-25 北京城建集团有限责任公司 Building site rain sewage drainage method and system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964973A (en) * 2017-12-27 2018-04-27 中交路桥华南工程有限公司 Anchor ingot drainage of foundation pit system and its construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964973A (en) * 2017-12-27 2018-04-27 中交路桥华南工程有限公司 Anchor ingot drainage of foundation pit system and its construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology
CN112062443A (en) * 2020-08-10 2020-12-11 安徽科清水环境技术有限公司 Ecological dredging sludge on-site rapid curing process
CN113123360A (en) * 2021-04-28 2021-07-16 上海宝冶集团有限公司 Environment-friendly drainage method for construction of coastal region stone square groove foundation pit in rainy season
CN114232662A (en) * 2021-11-09 2022-03-25 北京城建集团有限责任公司 Building site rain sewage drainage method and system
CN114232662B (en) * 2021-11-09 2024-01-09 北京城建集团有限责任公司 Building site rain and sewage drainage method and system

Similar Documents

Publication Publication Date Title
CN108755696A (en) A kind of rapid construction of pit earthwork at raining season method
CN103883328B (en) The dark construction method of half lid half of high steep V-type coombe biased segment is worn under separate tunnel
CN103741714A (en) Full-cover excavation top-down construction method for underground engineering
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN105569058A (en) Expansive soil cutting structure and construction method thereof
CN108842817A (en) A kind of subway station overlays waterproof roll structure and its construction technology
CN208309312U (en) Reinforced earth retaining wall embankment drainage system
CN104847365B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method
CN109372018A (en) Soft base Self-sinking type underground space structure construction and construction technology
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
CN104847375A (en) Supporting method for small-clear-distance four-lane shallow-buried large-span tunnel
CN109914445A (en) A kind of level of ground water alternately changes the construction method of location expensive soil cutting
CN107700497A (en) A kind of building basement pattern foundation pit supporting structure and earth excavation construction method
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN205134481U (en) Highway superelevation excavation highway section hydrocone type drainage system
CN104963348B (en) Soft soil area tower crane foundation construction supporting structure and construction method thereof
CN108661087A (en) The waterproof construction and construction method of tower crane in a kind of basement bottom board
CN204646253U (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel structure
CN109555141A (en) Strong drainage system for ultra-large deep foundation pit and construction method
CN110762286A (en) Drainage pipe network artificial pipe jacking construction process
CN108411785A (en) A kind of method in novel setting gutter
CN109440811A (en) A kind of gully type Dumping Sites loose stone slag blocking wall and surface water channel drainage sunk well technique
CN214363925U (en) Cut water seepage ditch system
CN112302678B (en) Deformation control construction process for shallow tunnel of underpass building
CN210369276U (en) Combined water pump house of underground tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181106