CN108678411A - A kind of workshop exempts to tear joist column method open - Google Patents
A kind of workshop exempts to tear joist column method open Download PDFInfo
- Publication number
- CN108678411A CN108678411A CN201810576213.7A CN201810576213A CN108678411A CN 108678411 A CN108678411 A CN 108678411A CN 201810576213 A CN201810576213 A CN 201810576213A CN 108678411 A CN108678411 A CN 108678411A
- Authority
- CN
- China
- Prior art keywords
- joist
- column
- new
- jack
- homonymy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0266—Enlarging
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B2001/3561—Extraordinary methods of construction, e.g. lift-slab, jack-block adding living space above existing structures
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to a kind of workshops to exempt to tear joist column method open.Include the following steps:1) the new column span that workshop requires, is measured, the intensity of needs is calculated, draws the part drawing of new joist and new column, make new joist and new column;2) interim column, is fixed on the piston of multiple jack respectively by flange, each jack is separately fixed at workshop homonymy crane girder bracket, and each interim column is withstood on homonymy original joist;3) while each jack is risen, homonymy original joist and homonymy roof truss is jacked up, new joist is placed in the position of former joist with crane, new column is fixed at the both ends of new joist;4) while each jack is fallen, so that homonymy roof truss is fallen on new joist, the two is fixed;5) the intermediate former column, dismantled between each jack, interim column, former joist and new column.Its method is simple, quickly, efficiently, at low cost.
Description
Technical field
The present invention relates to a kind of beam column method of replacing, especially a kind of workshop exempts to tear joist column method open.
Background technology
Joist column is to spend new carrying column and joist using shifting in the case where main building original agent structure is motionless
Grafting formula mode replaces original column and joist, then old column, joist are removed, and to make workshop span increase, reaches enlarging
Purpose.Current method is to remove old workshop, builds new workshop again, this not only the construction period it is long and costly.
Invention content
The shortcomings that in order to overcome the prior art, a kind of workshop of present invention offer exempt to tear joist column method open.Its method is simple,
Quickly, efficiently, at low cost.
The technical scheme adopted by the invention to solve the technical problem is that:Include the following steps:1), measure what workshop required
New column span, calculates the intensity of needs, draws the part drawing of new joist and new column, make new joist and new column;2), more
Fix interim column on the piston of a jack respectively by flange, each jack is separately fixed at workshop homonymy crane girder bracket
Place, each interim column are withstood on homonymy original joist;3) while each jack is risen, homonymy original joist and homonymy roof truss is jacked up,
New joist is placed in the position of former joist with crane, new column is fixed at the both ends of new joist;4) while each jack is fallen, made
Homonymy roof truss is fallen on new joist, and the two is fixed;5) in, dismantling between each jack, interim column, former joist and new column
Between former column.
The present invention has following advantages:1), method is simple, quickly, efficiently, at low cost;2) 18 meters, are pressed across 100 meter Chang factories
Room transform 30 meters as 100 meters of long workshops, if being according to traditional construction method:Old workshop is removed, is built again
If new workshop, the construction period is usually 3 to 4 months, and expense is about more than 300 ten thousand yuan.And by joist column technology, remove early period
Strange land makes joist and column time, actually dismounts and mounts the transformation duration and can be controlled in 48 hours or so.By comparison it can be seen that support
Liang Huanzhu has little influence on the production run in workshop compared with traditional construction, is singly to save construction cost with regard to more than 200 ten thousand yuan.To company
The economic benefit that production and operation are brought is even more huge.
Description of the drawings
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is schematic diagram of the present invention;
Fig. 2 is enlarged drawing at the A in Fig. 1 of the present invention.
Specific implementation mode
The present invention includes the following steps:1) the new column span that workshop requires, is measured, the intensity of needs is calculated, is drawn new
The part drawing of joist and new column makes new joist and new column;2), solid respectively by flange on the piston of multiple jack 7
Fixed interim column 5, each jack 7 are separately fixed at 8 bracket of workshop homonymy crane girder, and each interim column 5 withstands on homonymy original support
On beam 3;3) while each jack 7 is risen, homonymy original joist 3 and homonymy roof truss 1 is jacked up, new joist is placed in original with crane
New column is fixed at the both ends of the position of joist 3, new joist;4) while each jack 7 is fallen, homonymy roof truss 1 is made to fall in new joist
On, the two is fixed;5) the intermediate former column 4, dismantled between each jack 7, interim column 5, former joist 3 and new column.
Each jack 7 is motor-driven jack, and circuit in parallel uses, it is ensured that the displacement of jack is identical.
Fixed displacement sensor on the former joist 3 monitors the displacement of former joist, it is ensured that safety at any time.
Each jack 7 is fixed on by stiffening ring and positioning pin at 8 bracket of workshop homonymy crane girder respectively, is prevented
Each jack run-off the straight dislocation.
The interim column 5 is fixed with both sides original column 2, prevents to tilt dislocation.
Claims (5)
1. a kind of workshop exempts to tear joist column method open, it is characterised in that:Include the following steps:1) the new vertical of workshop requirement, is measured
Column span calculates the intensity of needs, draws the part drawing of new joist and new column, makes new joist and new column;2), Duo Geqian
Interim column (5) is fixed respectively by flange on the piston on jin top (7), and each jack (7) is separately fixed at workshop homonymy crane
At beam (8) bracket, each interim column (5) withstands on homonymy original joist (3);3) while each jack (7) is risen, by homonymy original
Joist (3) and homonymy roof truss (1) jack up, and new joist is placed in the position of former joist (3) with crane, and the both ends of new joist are fixed newly
Column;4) while each jack (7) is fallen, so that homonymy roof truss (1) is fallen on new joist, the two is fixed;5) it, dismantles each very heavy
Intermediate former column (4) between top (7), interim column (5), former joist (3) and new column.
2. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:Each jack (7) is
Motor-driven jack, circuit in parallel use, it is ensured that the displacement of jack is identical.
3. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:It is solid on the former joist (3)
Displacement sensor is positioned, monitors the displacement of former joist at any time.
4. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:Each jack (7) point
It is not fixed at workshop homonymy crane girder (8) bracket by stiffening ring and positioning pin.
5. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:The interim column (5) with
Both sides original column (2) is fixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810576213.7A CN108678411B (en) | 2018-06-06 | 2018-06-06 | Method for replacing columns of supporting beams without dismantling factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810576213.7A CN108678411B (en) | 2018-06-06 | 2018-06-06 | Method for replacing columns of supporting beams without dismantling factory building |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108678411A true CN108678411A (en) | 2018-10-19 |
CN108678411B CN108678411B (en) | 2020-10-16 |
Family
ID=63810138
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810576213.7A Active CN108678411B (en) | 2018-06-06 | 2018-06-06 | Method for replacing columns of supporting beams without dismantling factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108678411B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610881A (en) * | 2018-12-19 | 2019-04-12 | 中建三局第建设工程有限责任公司 | Prestressed girder underpins disconnected column construction method in a kind of existing tier building transformation |
CN115538812A (en) * | 2022-12-01 | 2022-12-30 | 北京市第三建筑工程有限公司 | Joist post insertion transformation method for hoisting newly-added columns in sections and additionally arranging temporary corbels |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101476397A (en) * | 2009-01-15 | 2009-07-08 | 二十三冶建设集团有限公司 | Integral jacking method for steel roof frame and concrete column articulated factory house cover |
CN102242569A (en) * | 2010-05-11 | 2011-11-16 | 五冶集团上海有限公司 | Method for drawing columns and enlarging distances after replacing beams at high altitude in industrial factory building |
CN104863380A (en) * | 2015-05-20 | 2015-08-26 | 中建三局第二建设工程有限责任公司 | Overall replacement system for original building shock-insulation support and construction method |
CN105756368A (en) * | 2016-04-06 | 2016-07-13 | 上海十三冶建设有限公司 | Simple construction method for removing columns for bracket girders of heavy-duty industrial workshops |
CN106836845A (en) * | 2017-04-12 | 2017-06-13 | 广州市胜特建筑科技开发有限公司 | Beam is dragged to pull out the deformation control method and system that structure is reserved after post |
-
2018
- 2018-06-06 CN CN201810576213.7A patent/CN108678411B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101476397A (en) * | 2009-01-15 | 2009-07-08 | 二十三冶建设集团有限公司 | Integral jacking method for steel roof frame and concrete column articulated factory house cover |
CN102242569A (en) * | 2010-05-11 | 2011-11-16 | 五冶集团上海有限公司 | Method for drawing columns and enlarging distances after replacing beams at high altitude in industrial factory building |
CN104863380A (en) * | 2015-05-20 | 2015-08-26 | 中建三局第二建设工程有限责任公司 | Overall replacement system for original building shock-insulation support and construction method |
CN105756368A (en) * | 2016-04-06 | 2016-07-13 | 上海十三冶建设有限公司 | Simple construction method for removing columns for bracket girders of heavy-duty industrial workshops |
CN106836845A (en) * | 2017-04-12 | 2017-06-13 | 广州市胜特建筑科技开发有限公司 | Beam is dragged to pull out the deformation control method and system that structure is reserved after post |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610881A (en) * | 2018-12-19 | 2019-04-12 | 中建三局第建设工程有限责任公司 | Prestressed girder underpins disconnected column construction method in a kind of existing tier building transformation |
CN115538812A (en) * | 2022-12-01 | 2022-12-30 | 北京市第三建筑工程有限公司 | Joist post insertion transformation method for hoisting newly-added columns in sections and additionally arranging temporary corbels |
Also Published As
Publication number | Publication date |
---|---|
CN108678411B (en) | 2020-10-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104989114B (en) | Sliding construction device and method for large-span arc-shaped roof | |
CN102912736B (en) | Vertical assembling construction method for trussed arch bridge | |
CN207079729U (en) | Steel structure net rack jacking apparatus | |
CN108678411A (en) | A kind of workshop exempts to tear joist column method open | |
CN104674665B (en) | Large-spatial structures vestibule bridge installation method | |
CN105442705A (en) | Large-span steel truss structure and installation method thereof | |
CN105369891A (en) | Construction control method of corridor consisting of large-span trusses different in length | |
CN108532743A (en) | The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method | |
CN204531469U (en) | A kind of steel work overhanging component temporary support of tool-type and discharge mechanism | |
CN106760561A (en) | The assembling method of segmental slipping roof system steel truss | |
CN104196246A (en) | Partial-evacuation in-site lifting construction method for multidirectional stress structure of continuous truss | |
CN102003078A (en) | Assembling method of net rack | |
CN203213019U (en) | Long cantilever bent cap cast-in-place construction support system | |
CN102877412B (en) | Method of pre-assembly in integral erecting way of steel tower | |
CN103276909B (en) | The assembled moulding bed of rack of arch-shaped space truss assembling method and use thereof | |
CN105155418A (en) | Construction method for bridge horizontal movement | |
CN104612409A (en) | Pipe truss structure single pipe supporting sorted unloading tool and using method thereof | |
CN105421865A (en) | Determining method for displacement of power transmission line angle steel tower | |
CN204401995U (en) | Encorbelment support system in a kind of center of installing for dome structure | |
CN204491429U (en) | Adjustable synchronization of jacking up composite steel tunnel support | |
CN204645706U (en) | Super large Steel Cantilever Truss installs supporting apparatus | |
CN103388405B (en) | Large-sized overhang steel structure mounting method | |
CN204162235U (en) | Lift crosshead safety overhauling device | |
CN107237404A (en) | Overhanging steel structure of strip steel pull rod and mounting method thereof | |
CN207226943U (en) | A kind of double crossbeam synchronous hoisting devices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |