CN108678411A - A kind of workshop exempts to tear joist column method open - Google Patents

A kind of workshop exempts to tear joist column method open Download PDF

Info

Publication number
CN108678411A
CN108678411A CN201810576213.7A CN201810576213A CN108678411A CN 108678411 A CN108678411 A CN 108678411A CN 201810576213 A CN201810576213 A CN 201810576213A CN 108678411 A CN108678411 A CN 108678411A
Authority
CN
China
Prior art keywords
joist
column
new
jack
homonymy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810576213.7A
Other languages
Chinese (zh)
Other versions
CN108678411B (en
Inventor
史胜民
于世奎
车蕾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinxing Ductile Iron Pipes Co Ltd
Original Assignee
Xinxing Ductile Iron Pipes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinxing Ductile Iron Pipes Co Ltd filed Critical Xinxing Ductile Iron Pipes Co Ltd
Priority to CN201810576213.7A priority Critical patent/CN108678411B/en
Publication of CN108678411A publication Critical patent/CN108678411A/en
Application granted granted Critical
Publication of CN108678411B publication Critical patent/CN108678411B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3561Extraordinary methods of construction, e.g. lift-slab, jack-block adding living space above existing structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a kind of workshops to exempt to tear joist column method open.Include the following steps:1) the new column span that workshop requires, is measured, the intensity of needs is calculated, draws the part drawing of new joist and new column, make new joist and new column;2) interim column, is fixed on the piston of multiple jack respectively by flange, each jack is separately fixed at workshop homonymy crane girder bracket, and each interim column is withstood on homonymy original joist;3) while each jack is risen, homonymy original joist and homonymy roof truss is jacked up, new joist is placed in the position of former joist with crane, new column is fixed at the both ends of new joist;4) while each jack is fallen, so that homonymy roof truss is fallen on new joist, the two is fixed;5) the intermediate former column, dismantled between each jack, interim column, former joist and new column.Its method is simple, quickly, efficiently, at low cost.

Description

A kind of workshop exempts to tear joist column method open
Technical field
The present invention relates to a kind of beam column method of replacing, especially a kind of workshop exempts to tear joist column method open.
Background technology
Joist column is to spend new carrying column and joist using shifting in the case where main building original agent structure is motionless Grafting formula mode replaces original column and joist, then old column, joist are removed, and to make workshop span increase, reaches enlarging Purpose.Current method is to remove old workshop, builds new workshop again, this not only the construction period it is long and costly.
Invention content
The shortcomings that in order to overcome the prior art, a kind of workshop of present invention offer exempt to tear joist column method open.Its method is simple, Quickly, efficiently, at low cost.
The technical scheme adopted by the invention to solve the technical problem is that:Include the following steps:1), measure what workshop required New column span, calculates the intensity of needs, draws the part drawing of new joist and new column, make new joist and new column;2), more Fix interim column on the piston of a jack respectively by flange, each jack is separately fixed at workshop homonymy crane girder bracket Place, each interim column are withstood on homonymy original joist;3) while each jack is risen, homonymy original joist and homonymy roof truss is jacked up, New joist is placed in the position of former joist with crane, new column is fixed at the both ends of new joist;4) while each jack is fallen, made Homonymy roof truss is fallen on new joist, and the two is fixed;5) in, dismantling between each jack, interim column, former joist and new column Between former column.
The present invention has following advantages:1), method is simple, quickly, efficiently, at low cost;2) 18 meters, are pressed across 100 meter Chang factories Room transform 30 meters as 100 meters of long workshops, if being according to traditional construction method:Old workshop is removed, is built again If new workshop, the construction period is usually 3 to 4 months, and expense is about more than 300 ten thousand yuan.And by joist column technology, remove early period Strange land makes joist and column time, actually dismounts and mounts the transformation duration and can be controlled in 48 hours or so.By comparison it can be seen that support Liang Huanzhu has little influence on the production run in workshop compared with traditional construction, is singly to save construction cost with regard to more than 200 ten thousand yuan.To company The economic benefit that production and operation are brought is even more huge.
Description of the drawings
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is schematic diagram of the present invention;
Fig. 2 is enlarged drawing at the A in Fig. 1 of the present invention.
Specific implementation mode
The present invention includes the following steps:1) the new column span that workshop requires, is measured, the intensity of needs is calculated, is drawn new The part drawing of joist and new column makes new joist and new column;2), solid respectively by flange on the piston of multiple jack 7 Fixed interim column 5, each jack 7 are separately fixed at 8 bracket of workshop homonymy crane girder, and each interim column 5 withstands on homonymy original support On beam 3;3) while each jack 7 is risen, homonymy original joist 3 and homonymy roof truss 1 is jacked up, new joist is placed in original with crane New column is fixed at the both ends of the position of joist 3, new joist;4) while each jack 7 is fallen, homonymy roof truss 1 is made to fall in new joist On, the two is fixed;5) the intermediate former column 4, dismantled between each jack 7, interim column 5, former joist 3 and new column.
Each jack 7 is motor-driven jack, and circuit in parallel uses, it is ensured that the displacement of jack is identical.
Fixed displacement sensor on the former joist 3 monitors the displacement of former joist, it is ensured that safety at any time.
Each jack 7 is fixed on by stiffening ring and positioning pin at 8 bracket of workshop homonymy crane girder respectively, is prevented Each jack run-off the straight dislocation.
The interim column 5 is fixed with both sides original column 2, prevents to tilt dislocation.

Claims (5)

1. a kind of workshop exempts to tear joist column method open, it is characterised in that:Include the following steps:1) the new vertical of workshop requirement, is measured Column span calculates the intensity of needs, draws the part drawing of new joist and new column, makes new joist and new column;2), Duo Geqian Interim column (5) is fixed respectively by flange on the piston on jin top (7), and each jack (7) is separately fixed at workshop homonymy crane At beam (8) bracket, each interim column (5) withstands on homonymy original joist (3);3) while each jack (7) is risen, by homonymy original Joist (3) and homonymy roof truss (1) jack up, and new joist is placed in the position of former joist (3) with crane, and the both ends of new joist are fixed newly Column;4) while each jack (7) is fallen, so that homonymy roof truss (1) is fallen on new joist, the two is fixed;5) it, dismantles each very heavy Intermediate former column (4) between top (7), interim column (5), former joist (3) and new column.
2. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:Each jack (7) is Motor-driven jack, circuit in parallel use, it is ensured that the displacement of jack is identical.
3. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:It is solid on the former joist (3) Displacement sensor is positioned, monitors the displacement of former joist at any time.
4. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:Each jack (7) point It is not fixed at workshop homonymy crane girder (8) bracket by stiffening ring and positioning pin.
5. workshop according to claim 1 exempts to tear joist column method open, it is characterised in that:The interim column (5) with Both sides original column (2) is fixed.
CN201810576213.7A 2018-06-06 2018-06-06 Method for replacing columns of supporting beams without dismantling factory building Active CN108678411B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810576213.7A CN108678411B (en) 2018-06-06 2018-06-06 Method for replacing columns of supporting beams without dismantling factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810576213.7A CN108678411B (en) 2018-06-06 2018-06-06 Method for replacing columns of supporting beams without dismantling factory building

Publications (2)

Publication Number Publication Date
CN108678411A true CN108678411A (en) 2018-10-19
CN108678411B CN108678411B (en) 2020-10-16

Family

ID=63810138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810576213.7A Active CN108678411B (en) 2018-06-06 2018-06-06 Method for replacing columns of supporting beams without dismantling factory building

Country Status (1)

Country Link
CN (1) CN108678411B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610881A (en) * 2018-12-19 2019-04-12 中建三局第建设工程有限责任公司 Prestressed girder underpins disconnected column construction method in a kind of existing tier building transformation
CN115538812A (en) * 2022-12-01 2022-12-30 北京市第三建筑工程有限公司 Joist post insertion transformation method for hoisting newly-added columns in sections and additionally arranging temporary corbels

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476397A (en) * 2009-01-15 2009-07-08 二十三冶建设集团有限公司 Integral jacking method for steel roof frame and concrete column articulated factory house cover
CN102242569A (en) * 2010-05-11 2011-11-16 五冶集团上海有限公司 Method for drawing columns and enlarging distances after replacing beams at high altitude in industrial factory building
CN104863380A (en) * 2015-05-20 2015-08-26 中建三局第二建设工程有限责任公司 Overall replacement system for original building shock-insulation support and construction method
CN105756368A (en) * 2016-04-06 2016-07-13 上海十三冶建设有限公司 Simple construction method for removing columns for bracket girders of heavy-duty industrial workshops
CN106836845A (en) * 2017-04-12 2017-06-13 广州市胜特建筑科技开发有限公司 Beam is dragged to pull out the deformation control method and system that structure is reserved after post

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476397A (en) * 2009-01-15 2009-07-08 二十三冶建设集团有限公司 Integral jacking method for steel roof frame and concrete column articulated factory house cover
CN102242569A (en) * 2010-05-11 2011-11-16 五冶集团上海有限公司 Method for drawing columns and enlarging distances after replacing beams at high altitude in industrial factory building
CN104863380A (en) * 2015-05-20 2015-08-26 中建三局第二建设工程有限责任公司 Overall replacement system for original building shock-insulation support and construction method
CN105756368A (en) * 2016-04-06 2016-07-13 上海十三冶建设有限公司 Simple construction method for removing columns for bracket girders of heavy-duty industrial workshops
CN106836845A (en) * 2017-04-12 2017-06-13 广州市胜特建筑科技开发有限公司 Beam is dragged to pull out the deformation control method and system that structure is reserved after post

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610881A (en) * 2018-12-19 2019-04-12 中建三局第建设工程有限责任公司 Prestressed girder underpins disconnected column construction method in a kind of existing tier building transformation
CN115538812A (en) * 2022-12-01 2022-12-30 北京市第三建筑工程有限公司 Joist post insertion transformation method for hoisting newly-added columns in sections and additionally arranging temporary corbels

Also Published As

Publication number Publication date
CN108678411B (en) 2020-10-16

Similar Documents

Publication Publication Date Title
CN104989114B (en) Sliding construction device and method for large-span arc-shaped roof
CN102912736B (en) Vertical assembling construction method for trussed arch bridge
CN207079729U (en) Steel structure net rack jacking apparatus
CN108678411A (en) A kind of workshop exempts to tear joist column method open
CN104674665B (en) Large-spatial structures vestibule bridge installation method
CN105442705A (en) Large-span steel truss structure and installation method thereof
CN105369891A (en) Construction control method of corridor consisting of large-span trusses different in length
CN108532743A (en) The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method
CN204531469U (en) A kind of steel work overhanging component temporary support of tool-type and discharge mechanism
CN106760561A (en) The assembling method of segmental slipping roof system steel truss
CN104196246A (en) Partial-evacuation in-site lifting construction method for multidirectional stress structure of continuous truss
CN102003078A (en) Assembling method of net rack
CN203213019U (en) Long cantilever bent cap cast-in-place construction support system
CN102877412B (en) Method of pre-assembly in integral erecting way of steel tower
CN103276909B (en) The assembled moulding bed of rack of arch-shaped space truss assembling method and use thereof
CN105155418A (en) Construction method for bridge horizontal movement
CN104612409A (en) Pipe truss structure single pipe supporting sorted unloading tool and using method thereof
CN105421865A (en) Determining method for displacement of power transmission line angle steel tower
CN204401995U (en) Encorbelment support system in a kind of center of installing for dome structure
CN204491429U (en) Adjustable synchronization of jacking up composite steel tunnel support
CN204645706U (en) Super large Steel Cantilever Truss installs supporting apparatus
CN103388405B (en) Large-sized overhang steel structure mounting method
CN204162235U (en) Lift crosshead safety overhauling device
CN107237404A (en) Overhanging steel structure of strip steel pull rod and mounting method thereof
CN207226943U (en) A kind of double crossbeam synchronous hoisting devices

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant