CN108661322A - A kind of novel constructing structure of portable stair step plank sheathing - Google Patents

A kind of novel constructing structure of portable stair step plank sheathing Download PDF

Info

Publication number
CN108661322A
CN108661322A CN201810749412.3A CN201810749412A CN108661322A CN 108661322 A CN108661322 A CN 108661322A CN 201810749412 A CN201810749412 A CN 201810749412A CN 108661322 A CN108661322 A CN 108661322A
Authority
CN
China
Prior art keywords
template
stair
flitch
side template
marking time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810749412.3A
Other languages
Chinese (zh)
Inventor
鞠久如
朱小锋
冯林建
张洁
薛燕飞
田红建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810749412.3A priority Critical patent/CN108661322A/en
Publication of CN108661322A publication Critical patent/CN108661322A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/062Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for stairs or steps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/001Corner fastening or connecting means for forming or stiffening elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements
    • E04G9/04Forming boards or similar elements the form surface being of wood

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Wood Science & Technology (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention discloses a kind of novel constructing structures of portable stair step plank sheathing, the structure includes stair end template, the first stair side template and the second stair side template, and the first stair side template and the second stair side template may be contained within stair end template top;Multigroup template component of marking time, the template component of marking time include at least one piece of first flitch and the template of marking time for being symmetrically disposed on first flitch both sides;The length of first flitch is more than the length of the template of marking time.The measure that structure provided by the present application is combined etc. using flitch with multiple glued layers, forms that stair tread formwork is novel to install constructing structure, and not only at low cost, easy to operate, work efficiency is fast, solves the problems such as adjacent height of stair step is big, tread is not of uniform size.Meanwhile avoid after form removal to mark time chisel, repair the problems such as, ensure that construction quality.

Description

A kind of novel constructing structure of portable stair step plank sheathing
Technical field
The present invention relates to stair technical field of construction equipment, novel more particularly to a kind of portable stair step plank sheathing Constructing structure.
Background technology
With《Concrete structure engineering construction quality and acceptance specification》(GB50204-2015)After formal implementation, cast-in-place Structure subdivisional work further increases stair Forming Quality, that is, using stair it is adjacent mark time height difference measured data as On Quality Evaluation Indicators.
Current construction site, in order to control stair step construction molding quality, each unit in charge of construction is all formulating soon It is prompt, conveniently and can guarantee the stair formwork erecting mode of quality.How selected mold method is led from mould material from the point of view of To use two kinds:First, steel;Second is that traditional wooden model;From making molding mode:First, regularization;Second is that pin-connected panel;Due to each The design drawing in building is different, so a regularization stair step metal form cannot be formed;Thus at present mainly with flitch+more Based on the gang form of layer glued board composition(Abbreviation wooden model);And making, the installation for wooden model of marking time, because each company's scheme difference can It can say that kind is numerous, each has something to recommend him
In the construction of current cast-in-situ stair, template is mainly in the majority with flitch, multi-plywood at present, and traditional stair step wooden model Plate template of marking time with Side shuttering is connect with iron nail, can be poured because of operator's walking, concrete after formwork erection of marking time molding It generates the pressure template that causes to mark time when the process of building is vibrated to be deformed, loosen or displacement with Side shuttering, to adjacent step on occur Walk out of existing height difference, width differs or even the middle part " with tripe " and other issues that occurs marking time.
Invention content
The present invention provides a kind of novel constructing structures of portable stair step plank sheathing.
The present invention provides following schemes:
A kind of novel constructing structure of portable stair step plank sheathing, including:
Stair end template, the first stair side template and the second stair side template, the first stair side template and second building Side of the ladder template may be contained within stair end template top;
Multigroup template component of marking time, the template component of marking time include at least one piece of first flitch and are symmetrically disposed on described the The template of marking time of one flitch both sides;The length of first flitch is more than the length of the template of marking time;The template of marking time Length is equal to the design width of stair bench;
Wherein, symmetrically arranged hole is offered respectively in the first stair side template and the second stair side template, it is described First flitch both ends are located in the hole that the first stair side template and the second stair side template respectively contain;It is described The height at hole is identical as designed stair step height, and width is of same size with first flitch.
Preferably:Further include two the second flitches, two second flitches are respectively arranged at first stair side form The respective upper outside of plate and the second stair side template;Two second flitches are connected by multigroup Horizontal clamp;The water Flat fixture takes institute to for inwardly tightening two second flitches by both sides when inwardly being tightened so as to two second flitches It states the first stair side template and the second stair side template is inwardly tightened, until the first stair side template and the second stair Respectively inside is fitted closely with the template both ends of marking time side template respectively.
Preferably:The Horizontal clamp is step fastener template clamping.
Preferably:The stair end template is set to a plurality of third flitch top;Two second flitches pass through respectively Multigroup vertical clamp is connected with the two on the outermost side third flitches.
Preferably:The vertical clamp is step fastener template clamping.
Preferably:It is fixedly linked on the stair end template there are two the 4th flitch, two the 4th flitches are located at the The respective lower outside of one stair side template and the second stair side template;Two the 4th flitches are for preventing described first building There is horizontal displacement in side of the ladder template and the second stair side template lower part.
Preferably:First flitch is two pieces, and the template of marking time is connected with two pieces of first flitches respectively;Two pieces Respectively both ends are located at the hole that the first stair side template and the second stair side template respectively contain to first flitch In mouthful;The width at the hole combined with two pieces of first flitches after it is of same size.
Preferably:The thickness of the template of marking time is not less than 15 millimeters.
Preferably:The height of the template of marking time is consistent with stair step design height.
Preferably:The stair end template, the first stair side template, the second stair side template and template of marking time are all made of Multi-plywood material is made.
According to specific embodiment provided by the invention, the invention discloses following technique effects:
By the invention it is possible to realize a kind of novel constructing structure of portable stair step plank sheathing, in an implementation mode, The structure may include stair end template, the first stair side template and the second stair side template, the first stair side template And second stair side template may be contained within stair end template top;Multigroup template component of marking time, the template group of marking time Part includes at least one piece of first flitch and the template of marking time for being symmetrically disposed on first flitch both sides;First flitch Length is more than the length of the template of marking time;The length of the template of marking time is equal to the design width of stair bench;Wherein, described Symmetrically arranged hole, first flitch both ends point are offered in first stair side template and the second stair side template respectively It Wei Yu not be in the hole that respectively contains of the first stair side template and the second stair side template;The height at the hole and institute It is highly identical to design stair step, width is of same size with first flitch.Structure provided by the present application using flitch with The measure that multiple glued layers are combined etc., forms that stair tread formwork is novel to install constructing structure, solves and height difference, width occurs Degree differs and other issues, and not only at low cost, easy to operate, work efficiency is fast, while solving that the adjacent height of stair step is big, tread The problems such as not of uniform size, avoid after form removal to mark time chisel, repair the problems such as, ensure that construction quality.
Certainly, it implements any of the products of the present invention and does not necessarily require achieving all the advantages described above at the same time.
Description of the drawings
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the present invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of structural representation of novel constructing structure of portable stair step plank sheathing provided in an embodiment of the present invention Figure;
Fig. 2 is the faces A-A provided in an embodiment of the present invention sectional view;
Fig. 3 is the first structure schematic diagram of template component provided in an embodiment of the present invention of marking time;
Fig. 4 is the second structural schematic diagram of template component provided in an embodiment of the present invention of marking time;
Fig. 5 is the side view of the novel constructing structure of portable stair step plank sheathing provided in an embodiment of the present invention;
Fig. 6 is the structural schematic diagram of the first stair side template provided in an embodiment of the present invention.
In figure:Stair end template 1, the first stair side template 2, the second stair side template 3, the first flitch 4, template of marking time 5, Hole 6, the second flitch 7, Horizontal clamp 8, third flitch 9, the 4th flitch 10, vertical clamp 11.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belong to what the present invention protected Range.
Embodiment
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, for a kind of portable stair step wood provided in an embodiment of the present invention The novel constructing structure of template, shown in as shown in Figure 1, Figure 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, which includes stair end template 1, the first stair Side template 2 and the second stair side template 3, the first stair side template 2 and the second stair side template 3 may be contained within described 1 top of stair end template;
Multigroup template component of marking time, the template component of marking time include at least one piece of first flitch 4 and are symmetrically disposed on described The template 5 of marking time of first flitch, 4 both sides;The length of first flitch 4 is more than the length of the template 5 of marking time;It is described to mark time The length of template 5 is equal to the design width of stair bench;
Wherein, symmetrical hole 6 is offered in the first stair side template 2 and the second stair side template 3 respectively, described One flitch, 4 both ends are located in the hole 6 that the first stair side template 2 and the second stair side template 3 respectively contain;Institute The height for stating hole is identical as designed stair step height, and width is of same size with first flitch.
Further, further include two the second flitches 7, two second flitches 7 are respectively arranged at first stair 3 respective upper outside of side template 2 and the second stair side template;Two second flitches 7 pass through 8 phase of multigroup Horizontal clamp Even;The Horizontal clamp 8 is for inwardly being tightened two second flitches 7 by both sides, so that two second flitches 7 are inside The first stair side template 2 and the second inwardly tightening of stair side template 3 are taken when tightening to, until first stair side form Plate 2 and the second stair side template 3 are respectively fitted closely with 5 both ends of template of marking time inside respectively.The Horizontal clamp 8 is Step fastener template clamping.The stair end template 1 is set to a plurality of 9 top of third flitch;Two second flitches 7 lead to respectively Multigroup vertical clamp 11 is crossed with the two on the outermost side third flitches 9 to be connected.The vertical clamp 11 is step fastener mould Board has.
Further, being fixedly linked on the stair end template 1, there are two the 4th flitch 10, two the 4th flitch 10 difference Positioned at 3 respective lower outside of the first stair side template 2 and the second stair side template;Two the 4th flitches 10 are for placing There is horizontal displacement in the first stair side template 2 and 3 lower part of the second stair side template.
Further, first flitch 4 be two pieces, it is described mark time template 5 respectively with two pieces of 4 phases of the first flitch Even;Respectively both ends are located at the first stair side template 2 and the second stair side template 3 respectively to two pieces of first flitches Including hole 6 in;The width at the hole combined with two pieces of first flitches after it is of same size.The template 5 of marking time Thickness be not less than 15 millimeters.The height of the template 5 of marking time is consistent with stair step design height.The stair end template 1, First stair side template 2, the second stair side template 3 and template 4 of marking time are all made of multi-plywood material and are made.
Structure provided by the present application takes following measures:
1, the template that will mark time adds multi-plywood, the length of glued board to be equal to stair bench and design width using two flitch two sides, It is symmetrical arranged.
2, riser template of marking time in order to prevent generates horizontal displacement, opens a hole on the multi-plywood of side, mouth width with Template of marking time flitch equivalent width, mouth height and stencil design of marking time are highly consistent;The vertical interval and Step design of adjacent existing mouth It is highly consistent, the level interval and Step design equivalent width of adjacent existing mouth;
3, in order to ensure stair bench designs width, symmetrically tighten from both sides with a fixture " step fastener " up to Side shuttering and Multi-plywood both ends closely can in template of marking time;
4, Side shuttering vertical displacement in order to prevent, with a fixture " step fastener " from by flitch on Side shuttering and bench bottom plate Lower flitch clamps just;
5, it is that a flitch is first followed closely on bottom edge to realize that Side shuttering lower part, which prevents horizontal displacement,.
It is in construction process:Preparation of construction(Stair bench bottom surface template, the binding of bench reinforcing bar)The 4th flitch of → installation → Assembled bench Side shuttering, the second flitch → seating side template, mark time template → fastening → examination → form removal, maintenance.
Specifically, carrying out template construct according to stair bench Prototype drawing is formulated.
Two flitch both sides of template of marking time add two multi-plywoods of nail, length and bench equivalent width, highly with design building Terraced riser is highly consistent, and thickness is not less than 15;Flitch length is bench wide+100;Width is riser height -15;Thickness is generally 40;
Bench side template
Due to being oblique fixed when bench side template is installed, the following aspects must be controlled when making:
First, side template height must be over bench plate thickness+riser height;Second is that the position at first starting template hole is necessary Consider multilayer gluing plate thickness;Third, width of cave entrance must be with flitch consistency of thickness in template of marking time;Fourth, the hole bottom water straight angle The thickness of design waist slab is necessary for the bench bed die shortest distance;Hole height must be consistent with stair step design height; Sixth, bench Side shuttering can be made two sections according to ladder length.
The upper and lower flitch of Side shuttering is two, a following flitch(First flitch)It is mainly used for positioning under side panel Portion, section specification, which is used, is less than 40 × 40, and length is equal with bench;Top flitch(Second flitch)(Number is consistent)With pressure It firmly marks time template, stress is larger, and section specification, which is used, is less than 40 × 80, and length is equal with bench;
4th flitch is installed.It is fixed in bench end template with iron nail(Multi-plywood)On, one on one side, two the 4th flitches Spacing is+two multilayer gluing plate thickness of bench width;
Assembled bench Side shuttering, the second flitch.Bench Side shuttering and the second flitch first can be connected in one with iron nail, in this way One can convenience in transport, two can avoid repeatedly remove, assembling cause multi-plywood deformation, damage;
Seating side template, template of marking time.Erection sequence carries out from bottom to top, first installs side Side shuttering, then the mould that will mark time Plate penetrates, and is then again sleeved on other side Side shuttering and marks time in template;Adjust template position of marking time, it is ensured that meet design and want It asks;
Fastening:With Horizontal clamp, two second flitches are clamped from both sides to middle tightening, until the gluing of Side shuttering and template of marking time Until plywood end is close.Vertical clamp is same by the third flitch of bench bottom plate bottom and the second flitch on Side shuttering again Shi Xiangzhong is tightened, until Side shuttering is secured.
It checks and accepts.To template scheme, design drawing, riser height, position, the thickness of waist slab and form joint etc. are tested It receives, until reaching design, code requirement qualification;
Form removal, maintenance.Concreting finishes reach strength of mould stripping after, dismounting is marked time template, sequentially opposite with installation;It removed Cheng Zhong not prized, disorderly be pounded firmly;It conscientiously to be removed after form removable and brush coating plate agent stores classifiedly, for use next time.
The structure small investment.There is no great change, stair bottom plate with original stair tread formwork mold method material Material, erection method do not change, it has only been opened on stair Side shuttering in the corresponding hole for marking time template.Improvement is marked time Template fixing method.The template that will mark time fixed form is changed to be inserted into side by being connected and fixed by iron nail with Side shuttering originally It is fixed on the hole of template;Bench width is controlled by the length of two sides multi-plywood in template of marking time;Riser height is logical It crosses and marks time form height to control;Template branch of marking time can be completed in fixture " step fastener " by tightening vertical, two direction of level If.It is easy to operate.From be fabricated into installation, operator at a glance can, easily-learned easily mastered.Pacify, tear open facilitate it is recycling.All templates It is combination regularization, as long as assembling in sequence;Concreting finishes reach and remove desired strength after, then will install suitable Sequence is inversely removed, and is removed, after brushing stripper plate, next layer is used again;Effect is good.Due to marking time, template uses hole fixed form, Tread run after molding is highly fixed, and overcomes the common fault of template position of marking time over;Convenient material drawing.All material is complete The existing building materials market universal product in portion, it is in liberal supply, it is processed without special ordered.Own wt is light, decomposes transport, manually removes Fortune has enough to meet the need convenient transportation.
In short, the measure that structure provided by the present application is combined etc. using flitch with multiple glued layers, forms stair and steps on Template is novel installs constructing structure for step, solves and height difference occurs, width differs and other issues, not only at low cost, easy to operate, Work efficiency is fast, while solving the problems such as adjacent height of stair step is big, tread is not of uniform size, avoid after form removal to mark time into The problems such as row is chiselled, repaired, ensure that construction quality.
It should be noted that herein, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also include other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that There is also other identical elements in process, method, article or equipment including the element.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the scope of the present invention.It is all Any modification, equivalent replacement, improvement and so within the spirit and principles in the present invention, are all contained in protection scope of the present invention It is interior.

Claims (10)

1. a kind of novel constructing structure of portable stair step plank sheathing, which is characterized in that including:Stair end template, first building Side of the ladder template and the second stair side template, the first stair side template and the second stair side template may be contained within the building Terraced end template top;Multigroup template component of marking time, the template component of marking time include at least one piece of first flitch and symmetrically set It is placed in the template of marking time of first flitch both sides;The length of first flitch is more than the length of the template of marking time;It is described The length for template of marking time is equal to the design width of stair bench;Wherein, the first stair side template and the second stair side form Symmetrically arranged hole is offered on plate respectively, first flitch both ends are located at the first stair side template and In the hole that two stair side templates respectively contain;The height at the hole is identical as designed stair step height, width and institute State the of same size of the first flitch.
2. the novel constructing structure of portable stair step plank sheathing according to claim 1, which is characterized in that further include two A second flitch, two second flitches are respectively arranged at the first stair side template and the second stair side template respectively Upper outside;Two second flitches are connected by multigroup Horizontal clamp;The Horizontal clamp by both sides for inwardly being tightened Two second flitches take the first stair side template and second to when inwardly being tightened so as to two second flitches Stair side template is inwardly tightened, until the first stair side template and the second stair side template respectively on the inside of respectively with it is described Template of marking time both ends fit closely.
3. the novel constructing structure of portable stair step plank sheathing according to claim 2, which is characterized in that the level Fixture is step fastener template clamping.
4. the novel constructing structure of portable stair step plank sheathing according to claim 2, which is characterized in that the stair End template is set to a plurality of third flitch top;Two second flitches by multigroup vertical clamp and are located at outermost respectively Two third flitches be connected.
5. the novel constructing structure of portable stair step plank sheathing according to claim 4, which is characterized in that described vertical Fixture is step fastener template clamping.
6. the novel constructing structure of portable stair step plank sheathing according to claim 1, which is characterized in that the stair It is fixedly linked on end template there are two the 4th flitch, two the 4th flitches are located at the first stair side template and the second stair The respective lower outside of side template;Two the 4th flitches are for preventing the first stair side template and the second stair side form There is horizontal displacement in plate lower part.
7. the novel constructing structure of portable stair step plank sheathing according to claim 1, which is characterized in that described first Flitch is two pieces, and the template of marking time is connected with two pieces of first flitches respectively;Two pieces of first flitches respectively divide by both ends It Wei Yu not be in the hole that respectively contains of the first stair side template and the second stair side template;The width at the hole and two It is of same size after first flitch combination described in block.
8. the novel constructing structure of portable stair step plank sheathing according to claim 7, which is characterized in that described to mark time The thickness of template is not less than 15 millimeters.
9. the novel constructing structure of portable stair step plank sheathing according to claim 7, which is characterized in that described to mark time The height of template is consistent with stair step design height.
10. the novel constructing structure of portable stair step plank sheathing according to claim 1 to 9 any one, feature It is, the stair end template, the first stair side template, the second stair side template and template of marking time are all made of multi-plywood Material is made.
CN201810749412.3A 2018-07-10 2018-07-10 A kind of novel constructing structure of portable stair step plank sheathing Pending CN108661322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810749412.3A CN108661322A (en) 2018-07-10 2018-07-10 A kind of novel constructing structure of portable stair step plank sheathing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810749412.3A CN108661322A (en) 2018-07-10 2018-07-10 A kind of novel constructing structure of portable stair step plank sheathing

Publications (1)

Publication Number Publication Date
CN108661322A true CN108661322A (en) 2018-10-16

Family

ID=63773874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810749412.3A Pending CN108661322A (en) 2018-07-10 2018-07-10 A kind of novel constructing structure of portable stair step plank sheathing

Country Status (1)

Country Link
CN (1) CN108661322A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06173442A (en) * 1992-12-02 1994-06-21 Nagano Kogyo:Kk Concrete form device for stairs and finishing method for stairs
CN204456858U (en) * 2015-02-27 2015-07-08 重庆建工住宅建设有限公司 Just dismounting architectural stair gang form
CN105133833A (en) * 2015-09-15 2015-12-09 成都市第四建筑工程公司 Stair formwork and stair construction method adopting same
CN106088589A (en) * 2016-08-20 2016-11-09 安徽水利开发股份有限公司 Stair concrete-pouring template device and stair concreting method
CN107100366A (en) * 2017-05-09 2017-08-29 中冶天工集团天津有限公司 A kind of construction method for skyscraper reinforced concrete stairs formwork
CN208668944U (en) * 2018-07-10 2019-03-29 江苏南通六建建设集团有限公司 A kind of novel constructing structure of portable stair step plank sheathing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06173442A (en) * 1992-12-02 1994-06-21 Nagano Kogyo:Kk Concrete form device for stairs and finishing method for stairs
CN204456858U (en) * 2015-02-27 2015-07-08 重庆建工住宅建设有限公司 Just dismounting architectural stair gang form
CN105133833A (en) * 2015-09-15 2015-12-09 成都市第四建筑工程公司 Stair formwork and stair construction method adopting same
CN106088589A (en) * 2016-08-20 2016-11-09 安徽水利开发股份有限公司 Stair concrete-pouring template device and stair concreting method
CN107100366A (en) * 2017-05-09 2017-08-29 中冶天工集团天津有限公司 A kind of construction method for skyscraper reinforced concrete stairs formwork
CN208668944U (en) * 2018-07-10 2019-03-29 江苏南通六建建设集团有限公司 A kind of novel constructing structure of portable stair step plank sheathing

Similar Documents

Publication Publication Date Title
Hanna Concrete formwork systems
US6360505B1 (en) Surface panel and associated ICF system for creating decorative and utilitarian surfaces on concrete structures
US20080256894A1 (en) Special and improved configurations for unitized post tension block systems for masonry structures
US20090249725A1 (en) Wall forming system and method thereof
CN104532987A (en) Construction method of bare concrete wall internally provided with heat insulation layer
CN110439265A (en) Bilateral column or wall method for synchronously constructing at a kind of narrow expansion joint
US2627100A (en) Form for progressively molding concrete walls
US7937901B2 (en) Tendon-identifying, post tensioned concrete flat plate slab and method and apparatus for constructing same
CN210396134U (en) Reinforcing tool for controlling horizontal joint quality of shear wall
CN208668944U (en) A kind of novel constructing structure of portable stair step plank sheathing
CN110843123A (en) Adjustable door and window lintel batch prefabricating die and construction method thereof
US1598131A (en) Method of and apparatus for constructing concrete walls
US6401286B1 (en) Bridge deck construction forms
CN111663770B (en) Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN108661322A (en) A kind of novel constructing structure of portable stair step plank sheathing
US20210404176A1 (en) Method and module system for building a wall structure
CN103243912A (en) Multilayer no-board frame structure constructing method
CN110439257A (en) A kind of high turnover rate fashioned iron of sectional-film coating plywood light-type template system construction method
CN212336719U (en) Sinking type toilet hanging mould structure
CN108979137A (en) The assembling and disassembling construction method of Round Concrete column composite wooden template
US2480840A (en) Form for building concrete structures
CN110258890B (en) Construction method of concrete structure with connected broken line type outer wall and roof
JPS5833665A (en) Mold frame plate block and construction thereof
CN109707152B (en) Aluminum alloy formwork system and construction method thereof
CA2520782A1 (en) Spacers for use in masonry wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181016