CN108660885A - A kind of road structure and its construction method - Google Patents
A kind of road structure and its construction method Download PDFInfo
- Publication number
- CN108660885A CN108660885A CN201810383858.9A CN201810383858A CN108660885A CN 108660885 A CN108660885 A CN 108660885A CN 201810383858 A CN201810383858 A CN 201810383858A CN 108660885 A CN108660885 A CN 108660885A
- Authority
- CN
- China
- Prior art keywords
- roadbed
- rhone
- drainpipe
- ground
- filter plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/02—Arrangement of sewer pipe-lines or pipe-line systems
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/14—Devices for separating liquid or solid substances from sewage, e.g. sand or sludge traps, rakes or grates
Landscapes
- Engineering & Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a kind of road structure and its construction methods, belong to technical field of road construction, the road structure include positioned at ground and it is overhead between combination roadbed, it is to be obliquely installed in conjunction with roadbed, filter plate is installed in conjunction with the upper surface of roadbed, filter plate bottom is provided with permeable formation, permeable formation bottom is provided with rhone, rhone is along combining the length direction of roadbed to be arranged, and rhone is equipped with drainpipe in the connection close to ground one end, and drainpipe extends downward into ground and is connected to the drainage system on ground;Construction method include drainpipe installation with connect and roadbed is combined to build, solve the problems, such as that overhead and ground junction drainage effect is poor, can rapidly drain rainwater, the water accumulating volume inside reduction roadbed, reduction traffic accident.
Description
Technical field
The present invention relates to technical field of road construction, more specifically, it relates to a kind of road structure and its construction method.
Background technology
Roadbed refers to requiring the banded structure object as road bed of build according to route allocation and certain technology, is
The basis of railway and highway.
In order to preferably comply with geographical environment, economize the land resource, be conducive to traffic administration, it will usually build it is overhead, due to
The overhead side of resting on the ground, therefore when building overhead, it will usually artificially increase ground, to improve road grade.
Overhead and building for ground bound fraction is very important, the method for prior art generally use embankment, load-bearing
Although effect is preferable, drainage performance is poor, and when encountering heavy rain weather, rainwater will be along the gradient to flowing down so that ground
The full rainwater of product influences the normally travel of vehicle to increase the burden of surface road drainage system.
Invention content
In view of the deficiencies of the prior art, the present invention intends to provide a kind of road structure and its construction method,
Which solve overhead and ground junction drainage effect difference problems.
To achieve the above object, the present invention provides following technical solutions:
A kind of road structure, include positioned at ground and it is overhead between combination roadbed, the combination roadbed be obliquely installed,
The upper surface of the combination roadbed is equipped with filter plate, and the filter plate bottom is provided with permeable formation, and the permeable formation bottom is provided with
Rhone, the rhone are arranged along the length direction of the combination roadbed, and the rhone connects close to described ground one end
Logical to be equipped with drainpipe, the drainpipe extends downward into the ground and is connected to the drainage system on the ground.
Through the above technical solutions, when raining, rainwater will be along combining the slope surface of roadbed to flowing down, due to combining roadbed
Upper surface is equipped with filter plate, therefore rainwater will flow through filter plate, and is penetrated into rhone by permeable formation.Since rhone passes through row
Water pipe is connected to the drainage system on ground, therefore the rainwater in rhone will be flowed to all in drainage system, be convenient for concentrating
Processing, can rapidly drain rainwater, reduce traffic accident, while can reduce the water accumulating volume inside roadbed, prevent
Lead to road surface integral strength and stability reduction and freezing season pavement structure frost heaving failure because ponding is more.
Further preferably:The filter plate is arranged along the width direction of the combination roadbed.
Through the above technical solutions, flow through filter plate convenient for more rainwater, hence into in drainage system.
Further preferably:The filter plate is equipped with multiple and is spaced set.
Through the above technical solutions, flow through filter plate convenient for more rainwater, hence into in drainage system.
Further preferably:The bottom of the combination roadbed is arranged for embankment.
Through the above technical solutions, load-bearing property is good, convenient for improving integral strength and stability in conjunction with roadbed.
A kind of construction method of road structure, includes the following steps:
(1) installation and connection of drainpipe:When building ground roadbed, the drainage system need to be mounted under earth's surface, together
When reserve embedded hole, so that the drainpipe bottom end is connect with the drainage system;
(2) building for roadbed is combined:Embankment construction is above the ground carried out described, and according to construction requirements, makes its upper table
Towards being tilted close to described drainpipe one end, after embankment is good, then carries out pouring processing, while opening up out the rhone, install
The good permeable formation and filter plate, the upper end of the drainpipe need to be plugged in the rhone, the drainpipe and the draining
Slot junction need to be sealed processing using fluid sealant.
Through the above technical solutions, it is simple for process, convenient for construction.
In conclusion the invention has the advantages that:When raining, rainwater will be downward along the slope surface of combination roadbed
Stream, due to combining the upper surface of roadbed to be equipped with filter plate, rainwater will flow through filter plate, and penetrate into rhone by permeable formation
It is interior.Since rhone is connected to by drainpipe with the drainage system on ground, the rainwater in rhone will all flow to draining
It in system, is convenient for focusing on, can rapidly drain rainwater, reduce traffic accident, while road can be reduced
Water accumulating volume inside base prevents from leading to road surface integral strength and stability reduction and freezing season pavement structure because ponding is more
Frost heaving failure.It is good and simple for process in conjunction with roadbed load-bearing property, it is easy for construction.
Description of the drawings
Fig. 1 is the schematic cross-sectional view of embodiment, is mainly used for embodying the structure in conjunction with roadbed.
In figure, 1, ground;2, overhead;3, in conjunction with roadbed;4, drainage system;5, drainpipe;6, rhone;7, filter plate;8、
Permeable formation.
Specific implementation mode
With reference to the accompanying drawings and examples, the present invention will be described in detail.
Embodiment:A kind of road structure and its construction method, as shown in Figure 1, including ground 1, overhead 2 and being located at ground
Combination roadbed 3 between 1 and overhead 2 is to be obliquely installed in conjunction with roadbed 3.In conjunction with roadbed 3 be from top to bottom disposed with filter plate 7,
Permeable formation 8 and rhone 6 are arranged in conjunction with the bottom of roadbed 3 for embankment.Filter plate 7 is located at the upper surface in conjunction with roadbed 3 and along combination
The width direction of roadbed 3 is arranged, and filter plate 7 is equipped with multiple and is spaced set.Permeable formation 8 is used to flow through the rainwater of filter plate 7
It penetrates into rhone 6, rhone 6 is along the length direction setting for combining roadbed 3.Rhone 6 is set in the connection close to 1 one end of ground
There are drainpipe 5, drainpipe 5 to extend downwardly, 1 lower section of ground is equipped with drainage system 4, and lower end and the drainage system 4 of drainpipe 5 connect
It connects.
Drainage procedure and principle:When raining, rainwater will be along combining the slope surface of roadbed 3 to flowing down, due to combining roadbed 3
Upper surface is equipped with filter plate 7, therefore rainwater will flow through filter plate 7, and is penetrated into rhone 6 by permeable formation 8.Due to rhone 6
Be connected to the drainage system 4 on ground 1 by drainpipe 5, thus the rainwater in rhone 6 will all flow in drainage system 4 into
Row centralized processing and discharge.
Construction method:
(1) installation and connection of drainpipe 5:When building 1 roadbed of ground, drainage system 4 need to be mounted under earth's surface, simultaneously
Embedded hole is reserved, 5 bottom end of drainpipe is made to be connect with drainage system 4;
(2) building for roadbed 3 is combined:Embankment construction is carried out above ground 1, and according to construction requirements, makes its upper surface
It is tilted to close to 5 one end of drainpipe, after embankment is good, then carries out pouring processing, while opening up out rhone 6, install permeable formation 8
It need to be plugged in rhone 6 with the upper end of filter plate 7, drainpipe 5, drainpipe 5 need to be carried out with 6 junction of rhone using fluid sealant
Encapsulation process.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art
Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvement and modification
It should be regarded as protection scope of the present invention.
Claims (5)
1. a kind of road structure, include positioned at ground and it is overhead between combination roadbed, the combination roadbed is to be obliquely installed,
It is characterized in that:The upper surface of the combination roadbed is equipped with filter plate, and the filter plate bottom is provided with permeable formation, the permeable formation bottom
Portion is provided with rhone, and the rhone is arranged along the length direction of the combination roadbed, and the rhone is close to described
The connection of face one end is equipped with drainpipe, and the drainpipe extends downward into the ground and is connected to the drainage system on the ground.
2. a kind of road structure according to claim 1, it is characterised in that:Width of the filter plate along the combination roadbed
Direction is arranged.
3. a kind of road structure according to claim 1, it is characterised in that:The filter plate is equipped with multiple and is equidistantly to set
It sets.
4. a kind of road structure according to claim 1, it is characterised in that:The bottom of the combination roadbed sets for embankment
It sets.
5. the construction method of any one of the claim 1-4 road structures, it is characterised in that:Include the following steps:
(1) installation and connection of drainpipe:When building ground roadbed, the drainage system need to be mounted under earth's surface, be stayed simultaneously
Go out embedded hole, the drainpipe bottom end is made to be connect with the drainage system;
(2) building for roadbed is combined:Above the ground carry out embankment construction described, and according to construction requirements, make its upper surface to
It is tilted close to described drainpipe one end, after embankment is good, then carries out pouring processing, while opening up out the rhone, install institute
Permeable formation and filter plate are stated, the upper end of the drainpipe need to be plugged in the rhone, the drainpipe and the rhone knot
It need to be sealed processing using fluid sealant at conjunction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810383858.9A CN108660885A (en) | 2018-04-26 | 2018-04-26 | A kind of road structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810383858.9A CN108660885A (en) | 2018-04-26 | 2018-04-26 | A kind of road structure and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108660885A true CN108660885A (en) | 2018-10-16 |
Family
ID=63781214
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810383858.9A Pending CN108660885A (en) | 2018-04-26 | 2018-04-26 | A kind of road structure and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108660885A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20110016158A (en) * | 2009-08-11 | 2011-02-17 | 함미영 | L-type road side gutter having drainage hole equipped with water conduit |
CN103669145A (en) * | 2013-12-31 | 2014-03-26 | 北京东方园林股份有限公司 | Pavement method of permeable pavement structure |
CN105275076A (en) * | 2014-06-28 | 2016-01-27 | 冷庆林 | Road surface paving method |
CN205676740U (en) * | 2016-05-26 | 2016-11-09 | 丁权福 | A kind of permeable road structure |
CN206173824U (en) * | 2016-11-17 | 2017-05-17 | 唐山东方自来水安装有限公司 | Road bed buries water tube unit |
-
2018
- 2018-04-26 CN CN201810383858.9A patent/CN108660885A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20110016158A (en) * | 2009-08-11 | 2011-02-17 | 함미영 | L-type road side gutter having drainage hole equipped with water conduit |
CN103669145A (en) * | 2013-12-31 | 2014-03-26 | 北京东方园林股份有限公司 | Pavement method of permeable pavement structure |
CN105275076A (en) * | 2014-06-28 | 2016-01-27 | 冷庆林 | Road surface paving method |
CN205676740U (en) * | 2016-05-26 | 2016-11-09 | 丁权福 | A kind of permeable road structure |
CN206173824U (en) * | 2016-11-17 | 2017-05-17 | 唐山东方自来水安装有限公司 | Road bed buries water tube unit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105648873B (en) | A kind of cabin storage formula kerbstone | |
CN106320433A (en) | Urban road rainwater collection structure | |
CN102383373B (en) | Be applied to elevated bridge invisible rainwater collecting system and the method to set up thereof of flat slope | |
CN209652669U (en) | A kind of subgrade drainage structure | |
CN106869239A (en) | A kind of elevated bridge rain water collecting system for being applied to flat slope | |
CN207017093U (en) | New-old concrete bond widens seam-line removal structure | |
CN203475267U (en) | Curb for water-permeable asphalt greenway pavement | |
CN206521696U (en) | A kind of bridge drainage system | |
CN209584768U (en) | A kind of permeable integral type water drainage curb | |
CN108660885A (en) | A kind of road structure and its construction method | |
CN204265530U (en) | A kind of road green belt water purification structure | |
CN209243482U (en) | A kind of town road for receiving water function with face formula | |
CN212641083U (en) | Large-gap drainage asphalt pavement structure | |
CN107237255A (en) | A kind of bridge pier type road construction concentrates discharge structure with rainwater | |
CN201801811U (en) | Invisible rainwater collecting device applied to viaduct with flat slope | |
CN205529776U (en) | Infiltration structure of waterproof road in road surface | |
CN212834837U (en) | Town road with drainage function | |
CN213740415U (en) | Porous permeable pavement system | |
CN205443854U (en) | Notch cuttype curb | |
CN208685362U (en) | The arragement construction of city non-motorized lane | |
CN208136651U (en) | A kind of road structure for ground and overhead junction | |
CN209537975U (en) | A kind of urban road drainage system | |
CN210507035U (en) | Modular sponge city footpath that permeates water | |
CN208362846U (en) | Bituminous highway discharge structure | |
CN207701171U (en) | A kind of french drain formula tunnel arch angle drainage system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181016 |
|
RJ01 | Rejection of invention patent application after publication |