CN108625390A - The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation - Google Patents

The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation Download PDF

Info

Publication number
CN108625390A
CN108625390A CN201810604900.5A CN201810604900A CN108625390A CN 108625390 A CN108625390 A CN 108625390A CN 201810604900 A CN201810604900 A CN 201810604900A CN 108625390 A CN108625390 A CN 108625390A
Authority
CN
China
Prior art keywords
foundation
gravity type
concrete
stake
wind turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810604900.5A
Other languages
Chinese (zh)
Inventor
周胡
潘祖兴
姜贞强
吕娜
梁宁
薛寒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201810604900.5A priority Critical patent/CN108625390A/en
Publication of CN108625390A publication Critical patent/CN108625390A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/30Wind power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

A kind of construction process for providing offshore wind turbine foundation of the present invention and the more leg jackets bases of pile foundation gravity type offshore wind turbine height stake, are combined by the cavity gravity type foundation with pile foundation system with the more leg jacket structures of high stake;The present invention can build up the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake safely, in an orderly manner, effectively increase the resistance to tipping moment on basis, the advantages that suffered wave force reduction, simple installation, saving steel, can be applicable in the marine site that more deep water is deep, ground is hard.

Description

The construction process and the more legs of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation are led Pipe support foundation structure
Technical field
The present invention relates to the construction process of offshore wind turbine foundation and Novel pile foundation-more leg conduits of gravity type offshore wind turbine height stake Frame foundation structure belongs to offshore wind farm field of engineering technology.
Background technology
As offshore wind farm is developed from shallow water area to more deep-sea domain, the application of more pile leader frame foundation patterns is more wide It is general.Currently, the wind power plant in foreign countries 20 ~ 50m Intermediate Water Depths marine site has started to apply branch of more pile leader framves as offshore wind turbine Support group plinth is connected by steel-pipe pile with sea bed, provides enough bearing capacity of pile foundation to resist external loads.But more for ground Situations such as hard sand, large-diameter tubular pile is difficult to injection.Although gravity type foundation be it is a kind of be suitable for it is this kind of have it is hard The offshore wind turbine foundation pattern of sand foundation makes wind turbine vertically stand on sea by the dead weight of itself.But this tradition The applicable depth of water of gravity type foundation pattern be limited in scope, be typically only shallow water area, as the depth of water increases, cost can substantially increase Add.Also, since Conventional gravity formula key dimension is huge, prodigious wave force is will produce, the safety of foundation structure is influenced.
Invention content
The first purpose of the invention is to provide a kind of construction process of offshore wind turbine foundation, can build up safely, in an orderly manner The more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake effectively increase the resistance to tipping moment on basis, suffered wave The advantages that power reduction, simple installation, saving steel, can be applicable in the marine site that more deep water is deep, ground is hard.For this purpose, the present invention uses Following technical scheme:
A kind of construction process of offshore wind turbine foundation, it is characterised in that the more leg jacket structures of its processing and fabricating in factory are more Leg jacket structure includes more pile casings, joint steel pipe structure, main cylinder;Pipe casing is connected by joint steel pipe structure and welding It connects and is connected as an entirety with main cylinder;The quantity of pipe casing and position are corresponding with the quantity of pre-buried high stake and position;
Cavity gravity type foundation is rolled in land, the cavity gravity type foundation includes middle part concrete pier base and peripheral coagulation The good pre-buried high pile element of processing and fabricating is put into the corresponding position of concrete pier base by native cavity body according to design quantity and position It sets, pre-buried steel pile protection pipe component is put on the outside of concrete pier base and concrete cavity body bottom according to design quantity and position Corresponding position, then casting concrete, forms the cavity gravity type concrete foundation containing multiple pre-buried high stakes and is conserved, The buoyancy that concrete cavity body is laid in can be such that the cavity gravity type concrete foundation containing multiple pre-buried high stakes floats on Sea;
Wind electric field blower seat in the plane sea bed is arranged, the cavity gravity type concrete containing multiple pre-buried high stakes that will have been conserved Basis is put into the sea, by concrete cavity body from floating, with towboat by the cavity gravity type concrete containing multiple pre-buried high stakes To the corresponding seat in the plane of wind power plant, carrying out sinking to the bottom operation makes cavity gravity type concrete foundation be sink to sea bed for basis haul;Again by steel pipe Stake is put into pre-buried steel pipe casing, carries out pile sinking operation, then pile sinking carries out grouting operation, by steel to being easier in the soil layer of piling Pile pile is connect with pre-buried steel pipe casing, forms pile foundation-gravity type foundation;Then jackstone operation is carried out, by the sky of gravity type foundation Cavity fills up stone;More leg jacket structure hoistings, pipe casing and the top of pre-buried high stake are socketed again, carry out filling waterborne Slurry operation, connection pipe casing and pre-buried high stake, more leg jacket structures are connect to form entirety with gravity type foundation.
It is a further object to provide a kind of more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake, By that there will be the more leg jacket structures of the cavity gravity type foundation of pile foundation system and high stake to be combined, pile foundation-gravity type sea is formed The more leg jacket foundation structures of upper fan height stake, can effectively increase the resistance to tipping moment on basis, and suffered wave force reduces, pacifies The advantages that dress simplicity, saving steel, the marine site that more deep water is deep, ground is hard can be applicable in.For this purpose, the present invention uses following technical side Case:
A kind of more leg jacket bases of pile foundation gravity type offshore wind turbine height stake, it is characterised in that:By the cavity with pile foundation system Gravity type foundation is combined into the more leg jacket structures of high stake;Middle part concrete pier base containing multiple pre-buried high stakes and periphery Concrete cavity body forms cavity gravity type concrete foundation;The peripheral concrete cavity body is provided with several partial cavities It is uniformly arranged multiple pre-buried steel pipe casings respectively on the outside of body, the bottom of the peripheral concrete cavity body and concrete pier base, It drives piles to form steel-pipe pile to sea bed in pre-buried steel pipe casing, is mixed stake with cavity gravity type with casing connection by grouting material Solidifying earth foundation is linked together, and wherein stake is stub;Pipe casing is extrapolated to pre-buried high stake top portion, passes through grouting material and pre-buried high stake Connection;Pipe casing is by joint steel pipe structure and is welded to connect and is connected as an entirety with main cylinder, pre-buried high stake, pipe casing, Joint steel pipe structure forms the high more leg jacket structures of stake, and the gravity type that will have pile foundation system by pre-buried high stake with main cylinder It is basic to hold together with the more leg jacket structures of high stake, as offshore wind turbine foundation, support top blower fan structure, wherein Main cylinder is in center, at pre-buried high stake on the same circumference.
Further, the joint steel pipe structure includes diagonal brace and horizontal brace, each pipe casing by diagonal brace and horizontal brace with Main cylinder is connected as one.
Further, pre-buried high stake is equal diameter steel pipe, and diameter is less than pile protection pipe diameter, and length is longer so that the upper end is revealed Go out the water surface.
Further, pre-buried high stake is corresponding with pipe casing quantity with 3 ~ 4.
Further, between pre-buried high stake consolidation process is carried out with strut.
Further, concrete pier base is reinforced concrete structure, is in cylinder or cone shape;Concrete pier base outer diameter four Week reinforces with concrete cavity body and connects;Raised position is uniformly arranged at least four pre-buried steel pipe casing on the outside of concrete pier base, in advance The center that piling bar casing is buried relative to concrete pier base is on same circumference.
Further, concrete cavity body is reinforced concrete structure, including outer side shield, it is intermediate reinforce baffle, bottom, Several partial cavities are surrounded by outer side shield, intermediate baffle, bottom and the concrete pier base outer wall reinforced;Several parts surrounded Cavity is radially evenly distributed on concrete pier base surrounding;Bottom is uniformly arranged at least four pre-buried steel pipe casing, for driving piles Fixing concrete basis.
Further, stake is equal diameter steel pipe, and diameter is less than pre-buried steel pile protection pipe diameter;Length is shorter, only pile sinking to compared with The preceding several soil layers easily driven piles;Several steel pipe stubs are sink to sea bed bottom, form pile foundation system, fixed gravity type coagulation soil matrix Plinth.
Further, pipe casing is equal diameter steel pipe, and diagonal brace, horizontal brace, main cylinder are reducing steel tube.
Further, main cylinder is in the surface of concrete pier base.
The advantageous effect of patent of the present invention is:
1, to be combined into pile foundation-gravity type offshore wind turbine height stake using pile foundation-gravity type foundation and the more leg jacket structures of high stake more Leg jacket basis, the advantages of having both three kinds of structures, are suitable for 20 ~ 50m Intermediate Water Depths, and suitable for the sea of rigid foundation condition Domain.
2, compared with Conventional gravity formula foundation pattern, the more leg jacket bases of Novel pile foundation-gravity type offshore wind turbine height stake Effective active force is provided for gravity type foundation using piling soil layer is easier to by pile foundation system, greatlys improve gravity type foundation Resistance to capsizing;Upper part rigidity of structure is big, size is small, steel using amount is few, and suffered wave force is small, can support the wind of more capacity Machine is applicable in deeper marine site.
3, compared with the more pile leader frame foundation patterns of tradition, the Novel pile foundation-more leg jackets of gravity type offshore wind turbine height stake It is the high geological conditions of the piling such as hard sand difficulty that basis, which can be applicable in ground, can be carried by pile foundation-gravity type foundation For enough resistance to tipping moment.Due to pre-buried high stake, it is more easy that jacket positions leveling;Meanwhile jacket installation is in the water surface The above position, is grouting waterborne, and installation operation is easy.
Description of the drawings
Fig. 1 is the sectional view of the embodiment of the present invention.
Fig. 2 is the A-A sectional views of Fig. 1.
Fig. 3 is the B-B sectional views of Fig. 1.
Grouting partial views of the Fig. 4 between pipe casing and pre-buried high stake.
Grouting partial views of the Fig. 5 between pre-buried steel pipe casing and stake.
Specific implementation mode
With reference to attached drawing.The more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake provided by the present invention, by having The cavity gravity type foundation and the more leg jacket structures of high stake for having pile foundation system are combined into.
Middle part concrete pier base 2 containing multiple pre-buried high stakes 1 forms cavity gravity type with peripheral concrete cavity body 3 and mixes Solidifying earth foundation;Middle part concrete pier base 2 is in the center of cavity gravity type concrete foundation, peripheral concrete cavity body 3 Around middle part concrete pier base 2.Concrete pier base 2 is reinforced concrete structure, generally in cylinder or cone shape;Concrete pier 2 outer diameter surrounding of platform and concrete cavity body 3 reinforce baffle 3-2 by centre and reinforce connection;2 outside raised position of concrete pier base It is uniformly arranged at least four pre-buried steel pipe casing 4, pre-buried steel pipe casing 4 is in same circumference relative to the center of concrete pier base 2 On.Concrete cavity body 3 is reinforced concrete structure, including outer side shield 3-1, it is intermediate reinforce baffle 3-2, bottom 3-3 and Several partial cavity 3-5 are surrounded by outer side shield 3-1, intermediate baffle 3-2, bottom 3-3 and the concrete pier base outer wall 3-4 of reinforcing; Several partial cavities surrounded are radially evenly distributed on 2 surrounding of concrete pier base;It is pre-buried that bottom is uniformly arranged at least four Piling bar casing 4, for beating 61 fixing concrete of steel-pipe pile basis.
Steel-pipe pile is formed to sea bed piling 6,61 in pre-buried steel pipe casing 4, is connected stake 6 and casing 4 by grouting material 5 It connects and is linked together with cavity gravity type concrete foundation, wherein stake 6 is stub;Stake 6,61 is equal diameter steel pipe, and diameter is less than 4 diameter of pre-buried steel pipe casing;Length is shorter, only pile sinking to the preceding several soil layers for being easier to piling;Several steel pipe stubs are sink to sea Bed bottom forms pile foundation system, fixed gravity type concrete foundation.
Pipe casing 7-1 is extrapolated to 1 top of pre-buried high stake, is connect with pre-buried high stake 1 by grouting material 5;Pipe casing 7-1 is logical It crosses joint steel pipe structure and is welded to connect and be connected as an entirety, pre-buried high stake 1, pipe casing 7-1, connection steel with main cylinder 7-4 Pipe structure forms the high more leg jacket structures of stake, and the gravity type base that will have pile foundation system by pre-buried high stake 1 with main cylinder 7-4 Plinth holds together with the more leg jacket structures of high stake, as offshore wind turbine foundation, supports top blower fan structure.
Main cylinder 7-4 is in center, at pre-buried high stake 1 on the same circumference.Main cylinder 7-4 is in concrete pier base 2 surface is on same center line.
The joint steel pipe structure preferably includes diagonal brace 7-2 and horizontal brace 7-3, each pipe casing 7-1 pass through diagonal brace 7-2 and water It supports 7-3 and main cylinder 7-4 to be connected as one, structure is strong, and easy for installation, weight is relatively lighter.The other knots of joint steel pipe structure Configuration formula combines main cylinder 7-4 and pipe casing 7-1.
Pre-buried high stake 1 is equal diameter steel pipe, and diameter is less than pipe casing 7-1 diameters, and length is longer so that water is exposed in the upper end Face;Pre-buried high stake 1 has 3 ~ 4 pre-buried high stakes 1.
Pipe casing 7-1 is equal diameter steel pipe, and diagonal brace 7-2, horizontal brace 7-3, main cylinder 7-1 are reducing steel tube.
Pre-buried high stake 1, pre-buried steel pipe casing 4, pipe casing 7-1, diagonal brace 7-2, horizontal brace 7-3, main cylinder 7-4 are in factory Processing and fabricating, as needed that consolidation process can be carried out to pre-buried high stake 1 with strut to be applicable in more deep water depth, the steel member that will be made By being welded into leg jacket structure more than one.It is arranged according to the size of gravity type foundation, concrete pier is rolled in land The reinforcing bar that baffle 3-2, outer baffle 3-1 and bottom 3-3 are reinforced among platform 2, cavity body 3, by good pre-buried 1 structure of high stake of processing and fabricating Part is put into 2 corresponding position of concrete pier base, and 4 component of pre-buried steel pipe casing is put into 2 outside of concrete pier base and concrete is empty The corresponding position of cavity bottom 3-3, then casting concrete, forms cavity gravity type concrete foundation and is conserved.To wind Electric field fan seat in the plane sea bed is arranged, and is flattened with rubble 100, and gravity type concrete foundation conserve is put into nautical mile, according to By cavity body from floating, gravity type foundation is hauled into seat in the plane corresponding to wind power plant with towboat, carrying out sinking to the bottom operation makes gravity type foundation It is sink to sea bed.Steel-pipe pile 6 is put into pre-buried steel pipe casing again, carries out pile sinking operation, pile sinking is to being easier in the soil layer of piling, then Grouting operation is carried out, steel-pipe pile 6 is connect with pre-buried steel pipe casing 4, forms pile foundation-gravity type foundation;Then jackstone behaviour is carried out Make, the cavity body 3 of gravity type foundation is filled up into stone 31.More leg jacket structures 7 are lifted again, the top with pre-buried high stake 1 One end is docked, and grouting operation waterborne is carried out, and more leg jacket structures and gravity type foundation are attached to form entirety.
Above is only a specific embodiment of the present invention, but the structure feature of the present invention is not limited thereto, Ren Heben The technical staff in field in the field of the invention, made by changes or modifications all cover among protection scope of the present invention.

Claims (10)

1. a kind of construction process of offshore wind turbine foundation, it is characterised in that the more leg jacket structures of its processing and fabricating in factory, More leg jacket structures include more pile casings(7-1), joint steel pipe structure, main cylinder(7-4);Pipe casing(7-1)Pass through company It connects steel-tube construction and is welded to connect and main cylinder(7-4)It is connected as an entirety;Pipe casing(7-1)Quantity and position with it is pre-buried High stake(1)Quantity and position correspond to;
Cavity gravity type foundation is rolled in land, the cavity gravity type foundation includes middle part concrete pier base(2)With periphery Concrete cavity body(3), by the good pre-buried high stake of processing and fabricating(1)Component is put into concrete pier base according to design quantity and position (2)Corresponding position, by pre-buried steel pipe casing(4)Component is put into concrete pier base according to design quantity and position(2)Outside and Concrete cavity body bottom(3-3)Corresponding position, then casting concrete forms the cavity gravity containing multiple pre-buried high stakes Formula concrete foundation is simultaneously conserved, and the buoyancy that peripheral concrete cavity body is laid in can make described to contain multiple pre-buried high stakes Cavity gravity type concrete foundation float on sea;
Wind electric field blower seat in the plane sea bed is arranged, the cavity gravity type concrete containing multiple pre-buried high stakes that will have been conserved Basis is put into the sea, by peripheral concrete cavity body from floating, is mixed the cavity gravity type containing multiple pre-buried high stakes with towboat Solidifying earth foundation hauls seat in the plane corresponding to wind power plant, and carrying out sinking to the bottom operation makes cavity gravity type concrete foundation be sink to sea bed;Again will Steel-pipe pile(6)It is put into pre-buried steel pipe casing(4), carry out pile sinking operation, pile sinking to be easier to piling soil layer in, be then in the milk Operation, by steel-pipe pile(6)With pre-buried steel pipe casing(4)Connection forms pile foundation-gravity type foundation;Then jackstone operation is carried out, it will The cavity body of gravity type foundation(3)Fill up stone;Again by more leg jacket structure hoistings, pipe casing(7-1)With pre-buried high stake(1) Top be socketed, carry out grouting operation waterborne, connect pipe casing(7-1)With pre-buried high stake(1), by more leg jacket structures It connect to form entirety with gravity type foundation.
2. a kind of more leg jacket bases of pile foundation gravity type offshore wind turbine height stake, it is characterised in that:By the sky with pile foundation system Chamber gravity type foundation is combined into the more leg jacket structures of high stake;Contain multiple pre-buried high stakes(1)Middle part concrete pier base (2)With peripheral concrete cavity body(3)Form cavity gravity type concrete foundation;The peripheral concrete cavity body(3)Setting There are several partial cavities(3-5), the peripheral concrete cavity body(3)Bottom and concrete pier base(2)Outside difference is uniform Multiple pre-buried steel pipe casings are set(4), in pre-buried steel pipe casing(4)It is interior to drive piles to sea bed(6)Steel-pipe pile is formed, injection material is passed through Material(5)By stake(6)With casing(4)It connects and is linked together with cavity gravity type concrete foundation, wherein stake(6)For stub;Stake Casing(7-1)It is extrapolated to pre-buried high stake(1)Top passes through grouting material(5)With pre-buried high stake(1)Connection;Pipe casing(7-1)It is logical It crosses joint steel pipe structure and is welded to connect and main cylinder(7-4)It is connected as an entirety, pre-buried high stake(1), pipe casing(7-1)、 Joint steel pipe structure and main cylinder(7-4)The more leg jacket structures of high stake are formed, and pass through pre-buried high stake(1)There to be pile foundation system Gravity type foundation hold together with the more leg jacket structures of high stake, as offshore wind turbine foundation, support top wind turbine knot Structure, wherein main cylinder(7-4)It is in center, pre-buried high stake(1)Place is on the same circumference.
3. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: The joint steel pipe structure includes diagonal brace(7-2)And horizontal brace(7-3), each pipe casing(7-1)Pass through diagonal brace(7-2)And horizontal brace (7-3)With main cylinder(7-4)It is connected as one.
4. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: Pre-buried high stake(1)For equal diameter steel pipe, diameter is less than pipe casing(7-1)Diameter, length is longer so that the upper end is exposed the surface;In advance Bury high stake(1)With 3 ~ 4.
5. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: Pre-buried high stake(1)Between with strut carry out consolidation process.
6. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: Concrete pier base(2)It is in cylinder or cone shape for reinforced concrete structure;Concrete pier base(2)Outer diameter surrounding and concrete Cavity body(3)Reinforce connection;Concrete pier base(2)Outside raised position is uniformly arranged at least four pre-buried steel pipe casing(4), in advance Bury piling bar casing(4)Relative to concrete pier base(2)Center be on same circumference.
7. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: Concrete cavity body(3)For reinforced concrete structure, including outer side shield(3-1), intermediate reinforce baffle(3-2), bottom(3- 3), by outer side shield(3-1), intermediate reinforce baffle(3-2), bottom(3-3)With concrete pier base outer wall(3-4)Surround several offices Portion's cavity(3-5);Several partial cavities surrounded are radially evenly distributed on concrete pier base(2)Surrounding;Bottom is uniform At least four pre-buried steel pipe casing is set(4), for beating steel-pipe pile(61)Fixing concrete basis.
8. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, it is characterised in that: Stake(6)For equal diameter steel pipe, diameter is less than pre-buried steel pipe casing(4)Diameter;Length is shorter, and only pile sinking is former to being easier to drive piles A soil layer;Several steel pipe stubs are sink to sea bed bottom, form pile foundation system, fixed gravity type concrete foundation.
9. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 3, it is characterised in that: Pipe casing(7-1)For equal diameter steel pipe, diagonal brace(7-2), horizontal brace(7-3), main cylinder(7-1)For reducing steel tube.
10. the more leg jacket bases of a kind of pile foundation gravity type offshore wind turbine height stake according to claim 2, feature exist In:Main cylinder(7-4)It is in concrete pier base(2)Surface.
CN201810604900.5A 2018-06-13 2018-06-13 The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation Pending CN108625390A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810604900.5A CN108625390A (en) 2018-06-13 2018-06-13 The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810604900.5A CN108625390A (en) 2018-06-13 2018-06-13 The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation

Publications (1)

Publication Number Publication Date
CN108625390A true CN108625390A (en) 2018-10-09

Family

ID=63691594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810604900.5A Pending CN108625390A (en) 2018-06-13 2018-06-13 The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation

Country Status (1)

Country Link
CN (1) CN108625390A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080272A (en) * 2019-04-25 2019-08-02 上海交通大学 Offshore wind farm single-pile foundation and offshore wind farm device suitable for greater coasting area
CN110219317A (en) * 2019-04-23 2019-09-10 中交上海港湾工程设计研究院有限公司 A kind of base components for offshore wind power set installation
CN110439018A (en) * 2019-08-02 2019-11-12 中交第四航务工程勘察设计院有限公司 A kind of new plug-in steel cylinder wind power foundation
CN114084302A (en) * 2020-08-24 2022-02-25 上海电气风电集团股份有限公司 Fixed foundation of offshore wind turbine, offshore wind turbine device and transportation and installation method of offshore wind turbine complete machine

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321241A (en) * 2013-06-26 2013-09-25 上海大学 Deepwater open type wharf with combined foundation and method for constructing deepwater open type wharf
CN204676584U (en) * 2015-03-27 2015-09-30 中国电建集团华东勘测设计研究院有限公司 A kind of high stake truss-like offshore wind turbine foundation structure
CN106638659A (en) * 2016-10-27 2017-05-10 中国电建集团华东勘测设计研究院有限公司 Towing truss-gravity type combined offshore wind turbine foundation structure and construction method thereof
CN208563362U (en) * 2018-06-13 2019-03-01 中国电建集团华东勘测设计研究院有限公司 The more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321241A (en) * 2013-06-26 2013-09-25 上海大学 Deepwater open type wharf with combined foundation and method for constructing deepwater open type wharf
CN204676584U (en) * 2015-03-27 2015-09-30 中国电建集团华东勘测设计研究院有限公司 A kind of high stake truss-like offshore wind turbine foundation structure
CN106638659A (en) * 2016-10-27 2017-05-10 中国电建集团华东勘测设计研究院有限公司 Towing truss-gravity type combined offshore wind turbine foundation structure and construction method thereof
CN208563362U (en) * 2018-06-13 2019-03-01 中国电建集团华东勘测设计研究院有限公司 The more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219317A (en) * 2019-04-23 2019-09-10 中交上海港湾工程设计研究院有限公司 A kind of base components for offshore wind power set installation
CN110080272A (en) * 2019-04-25 2019-08-02 上海交通大学 Offshore wind farm single-pile foundation and offshore wind farm device suitable for greater coasting area
CN110439018A (en) * 2019-08-02 2019-11-12 中交第四航务工程勘察设计院有限公司 A kind of new plug-in steel cylinder wind power foundation
CN114084302A (en) * 2020-08-24 2022-02-25 上海电气风电集团股份有限公司 Fixed foundation of offshore wind turbine, offshore wind turbine device and transportation and installation method of offshore wind turbine complete machine

Similar Documents

Publication Publication Date Title
CN108625390A (en) The construction process and the more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake of offshore wind turbine foundation
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
CN104389318B (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN1837511A (en) Double-rowed cofferdam and method for manufacturing the same
CN107653895A (en) Six floating drum buoyancy tank foundation structures and its construction method on a kind of combined type sea
CN103225304B (en) A kind of marine foundation supporting structure and construction method thereof
CN107806108A (en) Three floating drum buoyancy tank foundation structures and its construction method on a kind of combined type sea
CN206928305U (en) A kind of rigid passive area buttress type supporting construction
CN108867684A (en) Offshore wind turbine gravity caisson basis and its installation method
CN108560542A (en) A kind of waste tire cladding builds the two-directed reinforcement and its construction method of slag
CN107740436A (en) A kind of three floating drum buoyancy tank combined type foundation structures of sea and its construction method
CN101838996A (en) Sea gravity type pile foundation combined fan foundation
CN102296629B (en) Tower-drum structure suitable for ocean engineering and installation method thereof
CN207176723U (en) A kind of embedding rock single pile of offshore wind farm and its construction system
CN208563362U (en) The more leg jacket foundation structures of pile foundation gravity type offshore wind turbine height stake
CN211200441U (en) Offshore single-pile foundation with compacted grouting reinforced foundation
KR20220130607A (en) Subsea foundations
CN113718820A (en) Offshore wind power steel pipe pile combined reinforcing device and reinforcing method
CN202559368U (en) Subsidence-reducing pile structure of capped steel pipe of immersed tunnel
CN211172056U (en) Offshore single-pile foundation with high-pressure jet grouting pile reinforced foundation
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN107630462A (en) A kind of six floating drum buoyancy tank combined type foundation structures of sea and its construction method
CN102733407A (en) Two-ring grouted single pile foundation
CN101392521A (en) Rock-socketed steel dock structure and construction method thereof
CN207987950U (en) Four floating drum buoyancy tank foundation structures on a kind of combined type sea

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009