CN108614511A CN201810333465.7A CN201810333465A CN108614511A CN 108614511 A CN108614511 A CN 108614511A CN 201810333465 A CN201810333465 A CN 201810333465A CN 108614511 A CN108614511 A CN 108614511A
Authority
CN
China
Prior art keywords
valve
slot
air
signal
dual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810333465.7A
Other languages
Chinese (zh)
Inventor
李永红
申爽
孙肇伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN EAST INDUSTRIAL TECHNOLOGY CO LTD
Original Assignee
HENAN EAST INDUSTRIAL TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN EAST INDUSTRIAL TECHNOLOGY CO LTD filed Critical HENAN EAST INDUSTRIAL TECHNOLOGY CO LTD
Priority to CN201810333465.7A priority Critical patent/CN108614511A/en
Publication of CN108614511A publication Critical patent/CN108614511A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/05Programmable logic controllers, e.g. simulating logic interconnections of signals according to ladder diagrams or function charts
    • G05B19/054Input/output
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/10Plc systems
    • G05B2219/11Plc I-O input output
    • G05B2219/1103Special, intelligent I-O processor, also plc can only access via processor

Abstract

The invention discloses a kind of advanced absorption slot sequential control algorithms, including hot-blast valve, heater, cold blast sliding valve, fresh windmill, flue gas leading, dirty gas windmill, nitrogen tube, steam pipe, the small valve of steam, rear steam valve, preceding steam valve, nitrogen valve, air bleeding valve, the small valve of the first nitrogen, dirty air valve, fresh air-valve, main valve, the small valve of the second nitrogen, lower distillation air valve, absorption slot, upper distillation air valve, the small valve of distillation gas, soft water mouth, waste water mouth and distillation gas port.The present invention gives full play to the subjective initiative of PLC control devices, abandons the conventional process of logic judgment, and bonding apparatus feature is arranged using time zone, plays time and space feature, understandable using simplicity in equipment, cuts performance stabilization;The a large amount of logic step of original system has been abandoned, application program is enormously simplified, has been convenient for later maintenance, the equipment for also allowing for the later stage is expanded.

Description

A kind of advanced absorption slot sequential control algorithm
Technical field
The present invention relates to a kind of control algolithm, specially a kind of advanced absorption slot sequential control algorithm belongs to waste gas pollution control and treatment Applied technical field.
Background technology
Entire exhaust-gas treatment and recovery control system scheme include waste gas collecting system, exhaust gas purifying treatment system, row Wind system, major function are gas sampling and exhaust gas purifying treatment system.Waste gas collecting system includes mainly hood, Volume damper, pipeline.Exhaust gas purifying treatment system includes mainly deduster, condenser, activated carbon adsorption device.Absorbent is The main coal body of exhaust gas is handled, its property and concentration is matched according to the property of different exhaust gas, and unit-gas is handled Consumption, be the ratio of the molar flow by calculating absorbent and inert gas to determine.
According to technological requirement, the difficult point of this system is more demanding to chain control.What original automatic control system used There are security risks for data collection and control algolithm, and with ageing equipment, process modification, chain function realization is extremely difficult, And there are wretched insufficiency, the maintainability of system is basic to be lost for the visualization of HMI system and operability.
For the safety interlocking of the various dangerous situations in waste gas pollution control and treatment and recycling, new system needs to use advanced control System carries out chain function realization, acts the reliable and person of being conveniently operated in time and watches current chain state.Control system control It makes each absorber and executes adsorption process time, desorption process time and drying process time according to actual needs time-switching And periodic cycle;Robot control system(RCS) combines original and subsequent upgrade equipment mechanical property, research new algorithm, using newly setting Standby, new logic realizes that safety, visualization, operability and the maintainability of automatic control system seem particularly necessary, because This, proposes a kind of advanced absorption slot sequential control algorithm regarding to the issue above.
Invention content
The purpose of the present invention is that solve the above-mentioned problems and provides a kind of advanced absorption slot sequential control algorithm, leads to The mutual overlap joint of PLC software multi-clocks is crossed, and is combined with mechanical location detecting element, is realized between absorbing groove portion step by step Compact combination and effectively connection.
The present invention is achieved through the following technical solutions above-mentioned purpose, a kind of advanced absorption slot, including absorbs slot, the suction The top for receiving slot is connected with air bleeding valve, and is connected with rear steam valve and nitrogen on the absorption slot of the side of the air bleeding valve Valve;Steam valve is connected with the small valve of steam and preceding steam valve after described, and the preceding steam valve is connected with steam pipe;The nitrogen valve It is connected with nitrogen tube;The bottom for absorbing slot is connected with main valve and upper distillation air valve, and the upper distillation air valve is connected with newly Fresh air-valve and the small valve of the second nitrogen;The fresh air-valve is connected with the small valve of the first nitrogen, and the small valve of the first nitrogen is connected with Flue gas leading;The dirt air valve is connected with dirty gas windmill;The fresh air-valve is connected with cold blast sliding valve, and the cold blast sliding valve is parallel with two A heater, hot-blast valve, and connect between the heater and hot-blast valve;One end of the cold blast sliding valve connects fresh windmill;Institute The one end for stating the small valve of the second nitrogen is connected with nitrogen tube;It is connected with distillation air valve between the main valve and the absorption slot, and One end of the upper distillation air valve is connected with lower distillation air valve and the small valve of distillation gas;One end of the small valve of distillation gas is connected with soft The mouth of a river and waste water mouth;The upper distillation air valve is connected with lower distillation air valve, and one end of the lower distillation air valve is connected with distillation Gas port.
A kind of advanced absorption slot sequential control algorithm, includes the following steps:
Step A, it absorbs slot and enters air inlet step:Limit switch signal is fed back to control panel after gear-box positioning, otherwise can stop automatically, Wherein, slot valve position is absorbed:Main valve, dirty air valve, air bleeding valve are opened, fresh air-valve, noble gas valve, dual distillation air valve, dual is closed The signal of steam valve, switch is fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;It closes Main valve compels crowded angle valve, opens the small valve of dual distillation air valve and the small valve of dual steam valve;Each absorption slot is not all chain;Absorb slot gear Case and valve position signal are all correct, and inlet period terminates;
When step B, absorbing slot and changing all valves by air inlet and close step, change step cresset it is bright after, it is then bright to change slot cresset, at this time again Raw lamp can shift to time one slot of registering and execute action;It absorbs slot and enters all valves closings:Limit switch after gear-box positioning, signal feedback To control panel, it otherwise can stop automatically, be shown by alarm and signal lamp;Absorb slot valve position:Close All, signal feedback To control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;It opens main valve and compels crowded angle valve, dual distillation gas The small valve of valve and the small valve of dual steam valve;Each absorption slot is not all chain;It absorbs slot gear-box and valve position signal is all correct, control The fully closed indicator light of moushroom valve is bright, and all valve closing times terminate;
Step C, it when absorption slot shifts to noble gas step by the closing of all valves, changes the bright expression of step lamp and changes step;It absorbs slot and enters noble gas: Limit switch after gear-box positioning, signal are fed back to control panel, otherwise can stop to be shown automatically by alarm and signal lamp; Absorb slot valve position:Noble gas valve, dual distillation air valve are opened, main valve, dirty air valve, air bleeding valve, fresh air-valve, dual steam valve is closed, opens The signal of pass is fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;It opens main valve and compels crowded angle Valve, the small valve of dual steam valve, close the dual small valve of distillation air valve, and evaporator automatic drain valve is opened;Regeneration tank and other slots all connect Lock;Slot is absorbed at this time to start to pour into noble gas, if inert gas pressure is less than lower limit, even if the time terminates still change step, is inhaled It receives slot gear-box and valve position signal is all correct, inert gas pressure is normal, and the noble gas time terminates;
Step D, it when absorption slot is shifted to by noble gas, changes the bright expression of step lamp and changes step;Slot is absorbed to enter:Gear-box positions Limit switch signal is fed back to control panel afterwards, otherwise can stop automatically, to be shown by alarm and signal lamp, evaporator is automatic Drain valve closes;Absorb slot valve position:Open dual distillation air valve, dual steam valve, close main valve, dirty air valve, air bleeding valve, fresh air-valve, Noble gas valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open main valve Compel crowded angle valve, closes the small valve of dual distillation air valve, the small valve of dual steam;Regeneration tank and other slots are all chain;Slot is absorbed at this time to open Beginning pours into steam, and when vapor (steam) temperature or the super lower limit of pressure, main steam valve can be automatically closed, even if the time terminates still change step Suddenly;In going when condenser cooling water temperature over-range, main steam valve can chain closing suspend and go, but timer continues to count When, the time terminates, and will not change step, and the cooling water temperatures such as need, which drop in control parameter, just changes step;Condenser row in going When gas temperature over-range, row's air triple valve can the row's of automatic opening air, main steam valve can chain closing suspend and go, but timer Timing is still will continue to, the time terminates, and will not change step, and the delivery temperatures such as need, which drop in control parameter, just changes step;Remove knot Absorb slot lower layer temperature before beam and require more than the upper limit DEG C, otherwise the time terminate not change step still, continue to ensure completely, To lower layer's temperature up to DEG C or more just restore change step;It absorbs slot gear-box and valve position signal is all correct, control parameter all reaches Mark, goes the time to terminate;
When step E, absorbing slot by removing change release of pressure, changes the bright expression of step signal lamp and change step;It absorbs slot and enters release of pressure:Gear-box After positioning, limit switch signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp;It absorbs Slot valve position:Dual distillation air valve is opened, main valve, dirty air valve, air bleeding valve, fresh air-valve, noble gas valve, dual steam valve, switch letter are closed Number be fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Main valve is opened to compel and angle valve, dual The small valve of steam valve closes the dual small valve of distillation air valve;Regeneration tank is not chain, and other slots are all chain;Fresh windmill starts fortune automatically Turn;It absorbs slot gear-box and valve position signal is all correct, the release of pressure time terminates;
Step F, it when absorption slot shifts to dry by release of pressure, changes the bright expression of step lamp and changes step;It absorbs slot and enters drying:Gear-box positions Afterwards, limit switch;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp;Absorb slot valve Position:Main valve, air bleeding valve, fresh air-valve are opened, dirty air valve, noble gas valve, dual distillation air valve, dual steam valve are closed, switching signal is returned Be fed to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open the small valve of dual distillation air valve, dual The small valve of steam valve closes main valve and compels crowded angle valve;Regeneration tank and other slots be not all chain;Fresh wind radiator valve is opened, cold blast sliding valve is closed; It absorbs slot gear-box and valve position signal is all correct, drying time terminates;
When step G, absorbing slot by drying change cooling, changes the bright expression of step lamp and change step;Absorb slot change cooling:Gear-box is fixed Limit switch behind position;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp;Absorb slot Valve position:Main valve, air bleeding valve, fresh air-valve are opened, dirty air valve, noble gas valve, dual distillation air valve, dual steam valve, switching signal are closed Be fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open the small valve of dual distillation air valve, double The small valve of weight steam valve closes main valve and compels crowded angle valve;Regeneration tank is chain regarding lower layer's temperature setup parameter;Other slots are not chain;Guan Xin Fresh wind radiator valve, opens cold blast sliding valve;Cooling to terminate to absorb slot lower layer temperature not up to lower limit set, then gear-box is chain does not release, Even if terminating cooling time not change step still, continue cooling until temperature just changes step up to lower limit, safety when ensuring air inlet again; It absorbs slot gear-box and valve position signal is all correct, absorb bath temperature degree and reach control parameter standard, terminate cooling time;
Step H, it when absorption slot shifts to exhaust by cooling, changes the bright expression of step lamp and changes step;It absorbs slot and enters exhaust:Gear-box positions Limit switch signal is fed back to control panel afterwards, otherwise can stop automatically, to be shown by alarm and signal lamp;Absorb slot valve Position:Begin to rehearse air valve, closes main valve, dirty air valve, fresh air-valve, noble gas valve, dual distillation air valve, dual steam valve, and switching signal is returned Be fed to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;It opens main valve and compels crowded angle valve, dual distillation The small valve of air valve, the small valve of dual steam valve;Regeneration tank and other slots be not all chain;It absorbs slot gear-box and valve position signal is whole just Really, evacuation time terminates to change to next step:Air inlet;When absorbing slot by exhaust change air inlet, changes the bright expression of step lamp and change step;
Though step I, control panel is stopped automatic reason as regeneration tank gear-box no-fix or is positioned because of the instrument control device number of writing extremely Non- feedback control panel;Gear-box need to be manipulated to positioning or overhauling instrument control device, make signal normal CQI feedback to control panel, Cai Nengzai Cut automatic operating;It has registered rather than regenerated slot, when the non-feedback of gear-box signal, though it will not cause to stop automatic, the slot meeting There is valve dislocation false alarm and cresset;When there are valve bit-errors in the slot registered, and though regeneration tank in what step, all operate to when Between terminate, but do not change step;When there are valve bit-errors in the slot registered, it is necessary to which it is normal to handle the signal made, valve bit-errors message After disappearance, regeneration tank could restore normally to replace step;If can not handle make valve bit-errors message disappear when, which must first move back Go out to register, so that regeneration tank is restored normal and replace step;Regeneration tank stops automatically, and abnormality processing is appropriate and blackout, if again When cutting automatic operating, step switch is changed if you need to touch, then needs to cut next step automatic operating again to the end of this Step Time, It is such as not required to touch and changes step switch, then it can be in cutting automatic operating in this step;
Though step J, regeneration tank valve bit-errors reason is valve position no-fix or positioning because of the non-feedback control of the instrument control device number of writing extremely Disk processed;When valve bit-errors message occurs in regeneration tank, if one minute untreated makes that its signal restores normal, valve bit-errors message disappears Lose, then will produce and stop automatic, shown by alarm and signal lamp, though or Step Time terminate to remain in former step and Next step will not be changed.
The beneficial effects of the invention are as follows:The present invention gives full play to the subjective initiative of PLC control devices, abandons logic judgment Conventional process, bonding apparatus feature is arranged using time zone, plays time and space feature, and easy understandable, cutting property is used in equipment It can stablize;The a large amount of logic step of original system has been abandoned, application program is enormously simplified, has been convenient for later maintenance, also allows for The equipment in later stage is expanded.
Description of the drawings
Fig. 1 is that the present invention absorbs slot structure connection diagram;
Fig. 2 is the logic control chart of the present invention;
Fig. 3 is gear-box time diagram of the present invention;
Fig. 4 is time zone analysis chart of the present invention.
In figure:1, hot-blast valve, 2, heater, 3, cold blast sliding valve, 4, fresh windmill, 5, flue gas leading, 6, dirty gas windmill, 7, nitrogen Pipe, 8, steam pipe, 9, the small valve of steam, 10, rear steam valve, 11, preceding steam valve, 12, nitrogen valve, 13, air bleeding valve, the 14, first nitrogen The small valve of gas, 15, dirty air valve, 16, fresh air-valve, 17, main valve, the 18, second small valve of nitrogen, 19, lower distillation air valve, 20, absorb slot, 21, upper distillation air valve, 22, the small valve of distillation gas, 23, soft water mouth, 24, waste water mouth, 25, distillation gas port.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Refering to Figure 1, a kind of advanced absorption slot, including slot 20 is absorbed, the top for absorbing slot 20 is connected with row Air valve 13, and it is connected with rear steam valve 10 and nitrogen valve 12 on the absorption slot 20 of the side of the air bleeding valve 13;After described Steam valve 10 is connected with the small valve 9 of steam and preceding steam valve 11, and the preceding steam valve 11 is connected with steam pipe 8;The nitrogen valve 12 are connected with nitrogen tube 7;The bottom for absorbing slot 20 is connected with main valve 17 and upper distillation air valve 21, and the upper distillation air valve 21 are connected with fresh air-valve 16 and the small valve of the second nitrogen 18;The fresh air-valve 16 is connected with the small valve 14 of the first nitrogen, and described The small valve of first nitrogen 14 is connected with flue gas leading 5;The dirt air valve 15 is connected with dirty gas windmill 6;The fresh air-valve 16 is connected with Cold blast sliding valve 3, and there are two heater 2, hot-blast valves 1 for 3 parallel connection of the cold blast sliding valve, and gone here and there between the heater 2 and hot-blast valve 1 Connection;One end of the cold blast sliding valve 3 connects fresh windmill 4;One end of the small valve of second nitrogen 18 is connected with nitrogen tube 7;It is described Distillation air valve 21 is connected between main valve 17 and the absorption slot 20, and one end of the upper distillation air valve 21 is connected with lower steaming Evaporate air valve 19 and the small valve of distillation gas 22;One end of the small valve of the distillation gas 22 is connected with soft water mouth 23 and waste water mouth 24;On described Distillation air valve 21 is connected with lower distillation air valve 19, and one end of the lower distillation air valve 19 is connected with distillation gas port 25.
A kind of advanced absorption slot sequential control algorithm, includes the following steps:
Step A, it absorbs slot 20 and enters air inlet step:Limit switch signal is fed back to control panel after gear-box positioning, otherwise can stop certainly It is dynamic, wherein to absorb 20 valve position of slot:Main valve 17, dirty air valve 15, air bleeding valve 13 are opened, fresh air-valve 16, noble gas valve, dual is closed Distill air valve, dual steam valve, the signal of switch is fed back to control panel, otherwise can valve bit-errors, pass through alarm and signal lamp It is shown;It closes main valve 17 and compels crowded angle valve, open the small valve of dual distillation air valve and the small valve of dual steam valve;It is each to absorb slot 20 all It is not chain;It absorbs 20 gear-box of slot and valve position signal is all correct, inlet period terminates;
When step B, absorbing slot 20 and changing all valves by air inlet and close step, change step cresset it is bright after, it is then bright to change slot cresset, at this time Regeneration lamp can shift to time one slot of registering and execute action;It absorbs slot 20 and enters all valves closings:Limit switch after gear-box positioning, signal It is fed back to control panel, otherwise can stop automatically, be shown by alarm and signal lamp;Absorb 20 valve position of slot:Close All, letter Number be fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;It opens main valve 17 and compels crowded angle valve, double The small valve of redistillation air valve and the small valve of dual steam valve;Each absorption slot 20 is not all chain;Absorb 20 gear-box of slot and valve position signal All correct, the control fully closed indicator light of moushroom valve is bright, and all valve closing times terminate;
Step C, it when absorption slot 20 shifts to noble gas step by the closing of all valves, changes the bright expression of step lamp and changes step;Slot 20 is absorbed to enter Noble gas:Limit switch after gear-box positioning, signal are fed back to control panel, otherwise can stop to carry out automatically by alarm and signal lamp Display;Absorb 20 valve position of slot:Noble gas valve, dual distillation air valve are opened, main valve 17, dirty air valve 15, air bleeding valve 13, fresh air-valve are closed 16, the signal of dual steam valve, switch is fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp Show;It opens main valve 17 and compels crowded angle valve, the small valve of dual steam valve, close the dual small valve of distillation air valve, evaporator automatic drain valve is opened;Regeneration Slot and other slots are all chain;It absorbs slot 20 at this time to start to pour into noble gas, if inert gas pressure is less than lower limit, even if the time ties Beam will not still change step, absorb 20 gear-box of slot and valve position signal is all correct, inert gas pressure is normal, and the noble gas time terminates;
Step D, it when absorption slot 20 is shifted to by noble gas, changes the bright expression of step lamp and changes step;Slot 20 is absorbed to enter:Gear-box Limit switch signal is fed back to control panel after positioning, otherwise can stop automatically, to be shown by alarm and signal lamp, evaporator Automatic drain valve closes;Absorb 20 valve position of slot:Dual distillation air valve, dual steam valve are opened, main valve 17, dirty air valve 15, air bleeding valve are closed 13, fresh air-valve 16, noble gas valve, switching signal are fed back to control panel, otherwise can valve bit-errors, by alarm and signal lamp into Row display;It opens main valve 17 and compels crowded angle valve, close the small valve of the small valve of dual distillation air valve, dual steam 9;Regeneration tank and other slots all connect Lock;Slot 20 is absorbed at this time starts to pour into steam, when vapor (steam) temperature or the super lower limit of pressure, main steam valve can be automatically closed, even if when Between terminate still change step;In going when condenser cooling water temperature over-range, main steam valve can chain closing suspend and go, but Timer continues to timing, and the time terminates, and will not change step, and the cooling water temperatures such as need, which drop in control parameter, just changes step; In going when condenser exhaust gas temperature over-range, row's air triple valve can the row's of automatic opening air, main steam valve chain can close temporarily Stop, but timer still will continue to timing, the time terminates, and will not change step, and the delivery temperatures such as need drop in control parameter Just change step;Go terminate before absorb 20 lower layer's temperature of slot require more than 105 DEG C of the upper limit, otherwise the time terminate not change step still, after It is continuous to go to ensure completely, until lower layer's temperature is just restored to change step up to 105 DEG C or more;Absorb 20 gear-box of slot and valve position letter Number whole is correct, and control parameter is all up to standard, and the time is gone to terminate;
When step E, absorbing slot 20 by removing change release of pressure, changes the bright expression of step signal lamp and change step;It absorbs slot 20 and enters release of pressure:Tooth After roller box positioning, limit switch signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp; Absorb 20 valve position of slot:It opens dual distillation air valve, closes main valve 17, dirty air valve 15, air bleeding valve 13, fresh air-valve 16, noble gas valve, dual Steam valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open main valve 17 urgent and angle valve, the small valves of dual steam valve, close the dual small valve of distillation air valve;Regeneration tank is not chain, and other slots are all chain;It is fresh Windmill 4 starts operating automatically;It absorbs 20 gear-box of slot and valve position signal is all correct, the release of pressure time terminates;
Step F, it when absorption slot 20 shifts to dry by release of pressure, changes the bright expression of step lamp and changes step;It absorbs slot 20 and enters drying:Gear-box After positioning, limit switch;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp;It absorbs 20 valve position of slot:Main valve 17, air bleeding valve 13, fresh air-valve 16 are opened, dirty air valve 15, noble gas valve, dual distillation air valve, dual steam are closed Valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open dual distillation The small valve of air valve, the small valve of dual steam valve close main valve 17 and compel crowded angle valve;Regeneration tank and other slots be not all chain;Fresh wind is opened to add 2 valve of hot device closes cold blast sliding valve 3;It absorbs 20 gear-box of slot and valve position signal is all correct, drying time terminates;
When step G, absorbing slot 20 by dry change cooling, changes the bright expression of step lamp and change step;Absorb the change cooling of slot 20:Gear Limit switch after case positioning;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp;It inhales Receive 20 valve position of slot:Main valve 17, air bleeding valve 13, fresh air-valve 16 are opened, dirty air valve 15, noble gas valve, dual distillation air valve, dual steaming are closed Steam valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open dual steaming The small valve of air valve, the small valve of dual steam valve are evaporated, main valve 17 is closed and compels crowded angle valve;Regeneration tank is chain regarding lower layer's temperature setup parameter;Its Its slot is not chain;Fresh 2 valve of wind heater is closed, cold blast sliding valve 3 is opened;The cooling 20 lower layer's temperature of absorption slot that terminates does not reach lower limit set, Then gear-box is chain does not release, even if terminating cooling time not change step still, continues cooling until temperature just changes step up to lower limit, It is safe when ensuring air inlet again;It absorbs 20 gear-box of slot and valve position signal is all correct, absorb 20 temperature of slot and reach control parameter mark Standard, cooling time terminate;
Step H, it when absorption slot 20 shifts to exhaust by cooling, changes the bright expression of step lamp and changes step;It absorbs slot 20 and enters exhaust:Gear-box Limit switch signal is fed back to control panel after positioning, otherwise can stop automatically, to be shown by alarm and signal lamp;Absorb slot 20 valve positions:Begin to rehearse air valve 13, closes main valve 17, dirty air valve 15, fresh air-valve 16, noble gas valve, dual distillation air valve, dual steam Valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Main valve 17 is opened to compel Squeeze angle valve, the small valve of dual distillation air valve, the small valve of dual steam valve;Regeneration tank and other slots be not all chain;Absorb 20 gear of slot Case and valve position signal are all correct, and evacuation time terminates to change to next step:Air inlet;When absorbing slot 20 by exhaust change air inlet, It changes the bright expression of step lamp and changes step;
Though step I, control panel is stopped automatic reason as regeneration tank gear-box no-fix or is positioned because of the instrument control device number of writing extremely Non- feedback control panel;Gear-box need to be manipulated to positioning or overhauling instrument control device, make signal normal CQI feedback to control panel, Cai Nengzai Cut automatic operating;It has registered rather than regenerated slot, when the non-feedback of gear-box signal, though it will not cause to stop automatic, the slot meeting There is valve dislocation false alarm and cresset;When there are valve bit-errors in the slot registered, and though regeneration tank in what step, all operate to when Between terminate, but do not change step;When there are valve bit-errors in the slot registered, it is necessary to which it is normal to handle the signal made, valve bit-errors message After disappearance, regeneration tank could restore normally to replace step;If can not handle make valve bit-errors message disappear when, which must first move back Go out to register, so that regeneration tank is restored normal and replace step;Regeneration tank stops automatically, and abnormality processing is appropriate and blackout, if again When cutting automatic operating, step switch is changed if you need to touch, then needs to cut next step automatic operating again to the end of this Step Time, It is such as not required to touch and changes step switch, then it can be in cutting automatic operating in this step;
Though step J, regeneration tank valve bit-errors reason is valve position no-fix or positioning because of the non-feedback control of the instrument control device number of writing extremely Disk processed;When valve bit-errors message occurs in regeneration tank, if one minute untreated makes that its signal restores normal, valve bit-errors message disappears Lose, then will produce and stop automatic, shown by alarm and signal lamp, though or Step Time terminate to remain in former step and Next step will not be changed.
Embodiment:
Control logic compact to design is needed, is main logic control figure below:As shown in Figure 2:According to design, gear is first set Case rotates a circle, that is, absorbs the time that eight step handoff procedure of slot needs in total, as shown in Figure 3.
According to this roller box feature, the position feed back signal often walked is determined, according to position feed back signal, calculate and absorb slot every Time zone residing for the handoff procedure of step, and decomposed, limited, as shown in Figure 4.
After each step is run, setting steps complete position.After the completion of step, this roller box is unlocked, is driven Moving electromagnetic valve, gear-box rotation, band hydrodynamic circuit drive the hydraulic valve of next step, in place after the completion of signal, switch step It completes.
The present invention plays the subjective initiative of PLC control system according to hydraulic gear box feature, and design time algorithm is protected Demonstrate,prove the stable operation of hydraulic test.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiment being appreciated that.

Claims (2)

1. a kind of advanced absorption slot, including absorb slot(20), it is characterised in that:The absorption slot(20)Top be connected with exhaust Valve(13), and the air bleeding valve(13)Side the absorption slot(20)On be connected with rear steam valve(10)And nitrogen valve (12);Steam valve after described(10)It is connected with the small valve of steam(9)With preceding steam valve(11), and the preceding steam valve(11)It is connected with Steam pipe(8);The nitrogen valve(12)It is connected with nitrogen tube(7);
The absorption slot(20)Bottom be connected with main valve(17)With upper distillation air valve(21), and the upper distillation air valve(21)Even It is connected to fresh air-valve(16)With the small valve of the second nitrogen(18);The fresh air-valve(16)It is connected with the small valve of the first nitrogen(14), and The small valve of first nitrogen(14)It is connected with flue gas leading(5);The dirt air valve(15)It is connected with dirty gas windmill(6);It is described fresh Air-valve(16)It is connected with cold blast sliding valve(3), and the cold blast sliding valve(3)It is in parallel that there are two heaters(2), hot-blast valve(1), and it is described plus Hot device(2)With hot-blast valve(1)Between connect;The cold blast sliding valve(3)One end connect fresh windmill(4);Second nitrogen is small Valve(18)One end be connected with nitrogen tube(7);The main valve(17)With the absorption slot(20)Between be connected with distillation air valve (21), and the upper distillation air valve(21)One end be connected with lower distillation air valve(19)With the small valve of distillation gas(22);The distillation The small valve of gas(22)One end be connected with soft water mouth(23)With waste water mouth(24);The upper distillation air valve(21)It is connected with lower distillation gas Valve(19), and the lower distillation air valve(19)One end be connected with distillation gas port(25).
2. a kind of advanced absorption slot sequential control algorithm, it is characterised in that:Include the following steps:
Step A, slot is absorbed(20)Enter air inlet step:Limit switch signal is fed back to control panel after gear-box positioning, otherwise can stop Automatically, wherein absorb slot(20)Valve position:Open main valve(17), dirty air valve(15), air bleeding valve(13), close fresh air-valve(16)、 Noble gas valve, dual distillation air valve, dual steam valve, the signal of switch are fed back to control panel, otherwise can valve bit-errors, pass through alarm And signal lamp is shown;Close main valve(17)Compel crowded angle valve, opens the small valve of dual distillation air valve and the small valve of dual steam valve;Respectively Absorb slot(20)It is all not chain;Absorb slot(20)Gear-box and valve position signal are all correct, and inlet period terminates;
Step B, slot is absorbed(20)When changing all valves by air inlet and closing step, change step cresset it is bright after, it is then bright to change slot cresset, this Shi Zaisheng lamps can shift to time one slot of registering and execute action;Absorb slot(20)Enter all valves to close:Limit switch after gear-box positioning, Signal is fed back to control panel, otherwise can stop automatically, be shown by alarm and signal lamp;Absorb slot(20)Valve position:All Close, signal is fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp;Open main valve(17)Compel Squeeze angle valve, the small valve of dual distillation air valve and the small valve of dual steam valve;It is each to absorb slot(20)It is all not chain;Absorb slot(20)Gear Case and valve position signal are all correct, and the control fully closed indicator light of moushroom valve is bright, and all valve closing times terminate;
Step C, slot is absorbed(20)When shifting to noble gas step by the closing of all valves, changes the bright expression of step lamp and change step;Absorb slot (20)Enter noble gas:Limit switch after gear-box positioning, signal are fed back to control panel, otherwise can stop automatically by alarm and signal Lamp is shown;Absorb slot(20)Valve position:Noble gas valve, dual distillation air valve are opened, main valve is closed(17), dirty air valve(15), air bleeding valve (13), fresh air-valve(16), dual steam valve, the signal of switch is fed back to control panel, otherwise can valve bit-errors, by alarm with And signal lamp is shown;Open main valve(17)Compel crowded angle valve, the small valve of dual steam valve, closes the dual small valve of distillation air valve, evaporator Automatic drain valve is opened;Regeneration tank and other slots are all chain;Slot is absorbed at this time(20)Start to pour into noble gas, if inert gas pressure is low When lower limit, even if the time terminates still change step, slot is absorbed(20)Gear-box and valve position signal are all correct, inert gas pressure Normally, the noble gas time terminates;
Step D, slot is absorbed(20)When being shifted to by noble gas, changes the bright expression of step lamp and change step;Absorb slot(20)Enter:Tooth Limit switch signal is fed back to control panel after roller box positioning, otherwise can stop automatically, to be shown by alarm and signal lamp, steam Tank automatic drain valve is sent out to close;Absorb slot(20)Valve position:Dual distillation air valve, dual steam valve are opened, main valve is closed(17), dirty air valve (15), air bleeding valve(13), fresh air-valve(16), noble gas valve, switching signal is fed back to control panel, otherwise can valve bit-errors, pass through Alarm and signal lamp are shown;Open main valve(17)Compel crowded angle valve, closes the small valve of dual distillation air valve, the small valve of dual steam(9); Regeneration tank and other slots are all chain;Slot is absorbed at this time(20)Start to pour into steam, when vapor (steam) temperature or the super lower limit of pressure, main steaming Steam valve can be automatically closed, even if the time terminates still change step;In going when condenser cooling water temperature over-range, main steam valve Understand chain closing pause to go, but timer continues to timing, the time terminates, and will not change step, and the cooling water temperatures such as need decline Step is just changed in control parameter;In going when condenser exhaust gas temperature over-range, row's air triple valve can the row's of automatic opening air, Main steam valve can chain closing pause go, but timer still will continue to timing, and the time terminates, and will not change step, the exhausts such as need Temperature, which drops in control parameter, just changes step;It goes to absorb slot before terminating(20)Lower layer's temperature requires more than 105 DEG C of the upper limit, otherwise Time terminates not change step still, continues to ensure completely, until lower layer's temperature is just restored to change step up to 105 DEG C or more; Absorb slot(20)Gear-box and valve position signal are all correct, and control parameter is all up to standard, and the time is gone to terminate;
Step E, slot is absorbed(20)When by removing change release of pressure, changing the bright expression of step signal lamp and changing step;Absorb slot(20)Enter to release Pressure:After gear-box positioning, limit switch signal is fed back to control panel, otherwise can stop automatically, to pass through alarm and signal lamp carries out Display;Absorb slot(20)Valve position:Dual distillation air valve is opened, main valve is closed(17), dirty air valve(15), air bleeding valve(13), fresh air-valve (16), noble gas valve, dual steam valve, switching signal is fed back to control panel, otherwise can valve bit-errors, pass through alarm and signal lamp It is shown;Open main valve(17)Urgent and angle valve, the small valve of dual steam valve, close the dual small valve of distillation air valve;Regeneration tank is not chain, Its slot is all chain;Fresh windmill(4)It is automatic to start operating;Absorb slot(20)Gear-box and valve position signal are all correct, release of pressure Time terminates;
Step F, slot is absorbed(20)When shifting to dry by release of pressure, changes the bright expression of step lamp and change step;Absorb slot(20)Enter drying:Tooth After roller box positioning, limit switch;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp; Absorb slot(20)Valve position:Open main valve(17), air bleeding valve(13), fresh air-valve(16), close dirty air valve(15), noble gas valve, dual steaming Evaporate air valve, dual steam valve, switching signal is fed back to control panel, otherwise can valve bit-errors, pass through alarm and signal lamp and carry out Display;The small valve of dual distillation air valve, the small valve of dual steam valve are opened, main valve is closed(17)Compel crowded angle valve;Regeneration tank and other slots are whole It is not chain;Open fresh wind heater(2)Valve closes cold blast sliding valve(3);Absorb slot(20)Gear-box and valve position signal are all correct, do The dry time terminates;
Step G, slot is absorbed(20)When cooling by dry change, change the bright expression of step lamp and change step;Absorb slot(20)Change cooling: Limit switch after gear-box positioning;Signal is fed back to control panel, otherwise can stop automatically, to be shown by alarm and signal lamp Show;Absorb slot(20)Valve position:Open main valve(17), air bleeding valve(13), fresh air-valve(16), close dirty air valve(15), it is noble gas valve, dual Distill air valve, dual steam valve, switching signal is fed back to control panel, otherwise can valve bit-errors, by alarm and signal lamp into Row display;The small valve of dual distillation air valve, the small valve of dual steam valve are opened, main valve is closed(17)Compel crowded angle valve;Regeneration tank regards lower layer's temperature Setup parameter and it is chain;Other slots are not chain;Close fresh wind heater(2)Valve opens cold blast sliding valve(3);It is cooling to terminate to absorb slot (20)Lower layer's temperature does not reach lower limit set, then gear-box is chain does not release, even if terminating cooling time not change step still, continues cold But safe when ensuring air inlet again until temperature just changes step up to lower limit;Absorb slot(20)Gear-box and valve position signal are whole just Really, slot is absorbed(20)Temperature reaches control parameter standard, terminates cooling time;
Step H, slot is absorbed(20)When shifting to exhaust by cooling, changes the bright expression of step lamp and change step;Absorb slot(20)Enter exhaust:Tooth Limit switch signal is fed back to control panel after roller box positioning, otherwise can stop automatically, to be shown by alarm and signal lamp;It inhales Receive slot(20)Valve position:Begin to rehearse air valve(13), close main valve(17), dirty air valve(15), fresh air-valve(16), noble gas valve, dual distillation Air valve, dual steam valve, switching signal are fed back to control panel, otherwise can valve bit-errors, shown by alarm and signal lamp Show;Open main valve(17)Compel crowded angle valve, the small valve of dual distillation air valve, the small valve of dual steam valve;Regeneration tank and other slots do not connect all Lock;Absorb slot(20)Gear-box and valve position signal are all correct, and evacuation time terminates to change to next step:Air inlet;Absorb slot (20)When changing to air inlet by exhaust, changes the bright expression of step lamp and change step;
Though step I, control panel is stopped automatic reason as regeneration tank gear-box no-fix or is positioned because of the instrument control device number of writing extremely Non- feedback control panel;Gear-box need to be manipulated to positioning or overhauling instrument control device, make signal normal CQI feedback to control panel, Cai Nengzai Cut automatic operating;It has registered rather than regenerated slot, when the non-feedback of gear-box signal, though it will not cause to stop automatic, the slot meeting There is valve dislocation false alarm and cresset;When there are valve bit-errors in the slot registered, and though regeneration tank in what step, all operate to when Between terminate, but do not change step;When there are valve bit-errors in the slot registered, it is necessary to which it is normal to handle the signal made, valve bit-errors message After disappearance, regeneration tank could restore normally to replace step;If can not handle make valve bit-errors message disappear when, which must first move back Go out to register, so that regeneration tank is restored normal and replace step;Regeneration tank stops automatically, and abnormality processing is appropriate and blackout, if again When cutting automatic operating, step switch is changed if you need to touch, then needs to cut next step automatic operating again to the end of this Step Time, It is such as not required to touch and changes step switch, then it can be in cutting automatic operating in this step;
Though step J, regeneration tank valve bit-errors reason is valve position no-fix or positioning because of the non-feedback control of the instrument control device number of writing extremely Disk processed;When valve bit-errors message occurs in regeneration tank, if one minute untreated makes that its signal restores normal, valve bit-errors message disappears Lose, then will produce and stop automatic, shown by alarm and signal lamp, though or Step Time terminate to remain in former step and Next step will not be changed.
CN201810333465.7A 2018-08-16 2018-08-16 A kind of advanced absorption slot sequential control algorithm Pending CN108614511A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810333465.7A CN108614511A (en) 2018-08-16 2018-08-16 A kind of advanced absorption slot sequential control algorithm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810333465.7A CN108614511A (en) 2018-08-16 2018-08-16 A kind of advanced absorption slot sequential control algorithm

Publications (1)

Publication Number Publication Date
CN108614511A true CN108614511A (en) 2018-10-02

Family

ID=63660196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810333465.7A Pending CN108614511A (en) 2018-08-16 2018-08-16 A kind of advanced absorption slot sequential control algorithm

Country Status (1)

Country Link
CN (1) CN108614511A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101219319A (en) * 2007-09-30 2008-07-16 泉州市天龙环境工程有限公司 Device for recovering viscose fiber production exhaust-gas with soda washing-adsorption condensing method
CN101825878A (en) * 2010-04-02 2010-09-08 杭州奥通科技有限公司 Viscose fiber waste gas treatment control system
CN103007681A (en) * 2012-12-18 2013-04-03 中冶长天国际工程有限责任公司 Activated carbon flue gas desulfurization and regeneration device and method
CN104759187A (en) * 2015-03-23 2015-07-08 湖北吴城环保科技有限公司 Organic exhaust gas concentration adjusting system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101219319A (en) * 2007-09-30 2008-07-16 泉州市天龙环境工程有限公司 Device for recovering viscose fiber production exhaust-gas with soda washing-adsorption condensing method
CN101825878A (en) * 2010-04-02 2010-09-08 杭州奥通科技有限公司 Viscose fiber waste gas treatment control system
CN103007681A (en) * 2012-12-18 2013-04-03 中冶长天国际工程有限责任公司 Activated carbon flue gas desulfurization and regeneration device and method
CN104759187A (en) * 2015-03-23 2015-07-08 湖北吴城环保科技有限公司 Organic exhaust gas concentration adjusting system

Similar Documents

Publication Publication Date Title
CN205323477U (en) Organic solvent's device is retrieved to energy -conserving nitrogen gas desorption
CN201684613U (en) Microwave activated carbon regenerating device
CN103585854A (en) Technology for recovering and processing organic exhaust gas by activated carbon adsorption and N2 desorption
JP2001317307A (en) Method of removing carbon dioxide from exhaust gas of gas turbine plant and device for carrying out the method
CN206905338U (en) A kind of fume afterheat depth recovery system based on Absorption heat-transformer
CN105921139B (en) A kind of mercury absorbent and its preparation method and application
CN103816765B (en) Organic exhaust gas adsorption desorption purification integrated machine
CN106178817A (en) A kind of extensive carbon dioxide capture system and capture method
CN104119946B (en) A kind of catalytic cracking flue gas desulfurization and Acidic Gas Treating technique
CN108614511A (en) A kind of advanced absorption slot sequential control algorithm
CN106582200A (en) Flue gas carbon capturing system for temperature swing adsorption power plant by virtue of intermediate steam extraction
CN111023076A (en) Full-open type absorption heat pump for flue gas waste heat full-heat gradient depth recovery
CN108671687A (en) A kind of dry-method dust-removal device and its technique for the aqueous flue dust of slag
JP6642590B2 (en) Carbon dioxide separation and capture device, combustion system and thermal power generation system using the same, and carbon dioxide separation and capture method
CN107238227A (en) A kind of fume afterheat depth recovery system based on Absorption heat-transformer
JP2016059917A (en) Material for carbon dioxide recovery, method for producing material for carbon dioxide recovery, and recovery method of carbon dioxide
CN208694613U (en) A kind of nitrogen desorption condensate recycling device
CN106693605A (en) Adsorptive regeneration device with solid-liquid phase change matters and adsorptive regeneration process
CN109876594A (en) Air adsorption purification system in air separation unit
CN105126533A (en) Method, apparatus and system for controlling natural gas adsorption column, and purification system
CN101825878B (en) Viscose fiber waste gas treatment control system
CN210874699U (en) Contain three jar two-stage adsorption's organic waste gas treatment system
CN208032225U (en) A kind of caching absorber absorption organic waste gas recycling system
JPH0483509A (en) Continuously adsorbing and reproducing-type carbon dioxide separating and removing apparatus
CN203790798U (en) Purification treatment system for waste gas produced in production process of furfural

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002