CN108596374A - Construction schedule optimizes preparation method - Google Patents
Construction schedule optimizes preparation method Download PDFInfo
- Publication number
- CN108596374A CN108596374A CN201810320264.3A CN201810320264A CN108596374A CN 108596374 A CN108596374 A CN 108596374A CN 201810320264 A CN201810320264 A CN 201810320264A CN 108596374 A CN108596374 A CN 108596374A
- Authority
- CN
- China
- Prior art keywords
- construction schedule
- bim
- construction
- bim models
- schedule
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 147
- 238000002360 preparation method Methods 0.000 title claims abstract description 30
- 238000005457 optimization Methods 0.000 claims abstract description 24
- 238000004088 simulation Methods 0.000 claims abstract description 21
- 230000000007 visual effect Effects 0.000 claims abstract description 12
- 238000000034 method Methods 0.000 claims description 31
- 238000012163 sequencing technique Methods 0.000 claims description 7
- 238000012800 visualization Methods 0.000 claims description 2
- 238000012986 modification Methods 0.000 abstract description 7
- 230000004048 modification Effects 0.000 abstract description 7
- 238000005516 engineering process Methods 0.000 description 6
- 230000007547 defect Effects 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- General Health & Medical Sciences (AREA)
- Educational Administration (AREA)
- Biodiversity & Conservation Biology (AREA)
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to a kind of construction schedules to optimize preparation method, includes the following steps:It establishes corresponding BIM models according to construction drawing and carries out light-weight technologg;BIM models are imported into BIM progress control softwares and are integrated;Time parameter is assigned to each component in the BIM models according to construction schedule in the BIM progress controls software, to which the BIM models is associated with the construction schedule;D visualized simulation is carried out using the BIM progress controls software pair BIM models associated with the construction schedule, the reasonability that the construction schedule is examined by visual Simulation optimizes unreasonable place the construction schedule to form optimization and the BIM models associated there;And the construction schedule of format needed for export.The D visualized simulation to construction schedule can be achieved in the present invention, and the modification of construction schedule is easy to adjust quick.
Description
Technical field
The present invention relates to building Construction of Civil Engineering fields, refer in particular to a kind of construction schedule optimization preparation method.
Background technology
With the development of building civil engineering construction, construction industry Construction management is also constantly being sent out with method, technology
Exhibition progress.
During building cost management, to the way to manages such as progress, quality, cost, safety, method also continuous
Innovation.In the management process of construction speed, the construction schedule for working out engineering project is one of construction project time management
Major tasks.
Traditional schedule preparation method uses in general, according to construction drawing on the basis of construction experience
The software of project etc carries out the authorized strength work of construction schedule.The method, there are a large amount of defects, such as:It is worked out
Construction schedule can not meet practice of construction demand;In terms of largely construction schedule is there are working procedure
Wrong, missing, touch, lack the problems such as.In addition to this, worked out construction schedule can not be simulated visually, and into
The adjustment work for spending plan is inconvenient.
Invention content
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of construction schedule optimization preparation method is provided,
Solve existing preparation method there are in terms of working procedure defect problem, visual Simulation and adjustment inconvenience etc. can not be carried out
The problem of.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides a kind of construction schedules to optimize preparation method, includes the following steps:
Corresponding BIM models are established according to construction drawing;
Light-weight technologg is carried out to the BIM models established;
BIM models through light-weight technologg are imported into BIM progress control softwares and are integrated;
Each component in the BIM models is assigned according to construction schedule in the BIM progress controls software
Time parameter, to which the BIM models is associated with the construction schedule;
Carrying out three-dimensional using the BIM progress controls software pair BIM models associated with the construction schedule can
It is simulated depending on changing, the reasonability of the construction schedule is examined by visual Simulation, shape is optimized to unreasonable place
Construction schedule at optimization and the BIM models associated there;And
The construction schedule that required format is exported by the BIM progress controls software, to complete construction speed meter
The establishment drawn.
The present invention work out construction schedule in such a way that BIM models and construction schedule are associated, it can be achieved that
To the D visualized simulation of construction schedule, and the modification of construction schedule is easy to adjust quick, construction schedule
It is associated with the component in BIM models so that when instructing practice of construction according to construction schedule, BIM models can be passed through
Intuitive display construction work progress, has stronger intuitive.The present invention using BIM technology be construction schedule establishment with
Optimization Work brings innovation, provides new mode and method.
Construction schedule of the present invention optimization preparation method further improvement lies in that, established according to construction drawing corresponding
BIM models, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.
Construction schedule of the present invention optimization preparation method further improvement lies in that, to each in the BIM models
Before a component assigns time parameter, further include:
According to arrangement and method for construction work out construction schedule, and by the construction schedule worked out be input to the BIM into
It spends in management software.
Construction schedule of the present invention optimization preparation method further improvement lies in that, in the BIM progress controls software
It is interior to assign time parameter to each component in the BIM models according to construction schedule, including:
The component in the BIM models is chosen, and the component to being chosen adds time parameter, until to the BIM moulds
Until all components add deadline parameter in type;
The segmentum intercalaris when time parameter added on the BIM models is linked to corresponding in the construction schedule
Point, so as to complete the operation associated of the BIM models and the construction schedule.
Construction schedule of the present invention optimization preparation method further improvement lies in that, examined by visual Simulation described in
The reasonability of construction schedule, including:
During visual Simulation, the time that each component in the BIM models is completed is examined according to working procedure
Whether sequence is reasonable, indicates reasonable if the time sequencing that the component is completed is consistent with the working procedure, if described
Component complete time sequencing be not consistent with the working procedure, indicate unreasonable.
Construction schedule of the present invention optimization preparation method further improvement lies in that, unreasonable place is optimized
The construction schedule of optimization and the BIM models associated there are formed, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node that unreasonable place is corresponded in the construction schedule is changed, by modified timing node chain
It is connected on the time parameter after adjustment, to complete optimization operation.
Construction schedule of the present invention optimization preparation method further improvement lies in that, the BIM progress controls software is adopted
With Autodesk navisworks.
Description of the drawings
Fig. 1 is the flow chart that construction schedule of the present invention optimizes preparation method.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
Refering to fig. 1, the present invention provides a kind of construction schedules to optimize preparation method, for solving existing construction speed
Plan cannot meet practice of construction demand, there are working procedure in terms of Wrong, missing, touch, lack the problems such as, construction schedule can not
Visually simulated, it is inconvenient to the adjustment work of schedule.BIM technology is utilized in the preparation method of the present invention, will apply
Work schedule is associated with BIM models, so that construction schedule can carry out D visualized simulation by software, from
And construction schedule can be optimized, and facilitate adjustment and modification.The construction schedule can also provide after export
Intuitive three-dimensional display, preparation method of the invention are that construction schedule authorized strength work brings innovation, provide new side
Formula and method.Construction schedule of the present invention optimization preparation method is illustrated below in conjunction with the accompanying drawings.
Refering to fig. 1, it is shown that the flow chart of construction schedule optimization preparation method of the present invention.With reference to Fig. 1, to this
Invention construction schedule optimization preparation method illustrates.
As shown in Figure 1, a kind of construction schedule of the present invention optimizes preparation method, include the following steps:
Step S101 is executed, corresponding BIM models are established according to construction drawing;Then step S102 is executed.
Step S102 is executed, light-weight technologg is carried out to BIM models;Then step S103 is executed.
Step S103 is executed, the BIM models of light-weight technologg are imported into BIM progress control softwares, BIM progresses are utilized
Management software integrates the BIM models of importing;Then step S104 is executed.
Step S104 is executed, BIM models is associated with construction schedule, and foundation is applied in BIM progress control softwares
Work schedule assigns time parameter to each component in BIM models, to which BIM models is related to construction schedule
Connection;Then step S105 is executed.
Step S105 is executed, a pair BIM models associated with construction schedule carry out D visualized simulation, utilize
BIM progress controls software pair BIM models associated with construction schedule carry out D visualized simulation, by visualizing mould
The quasi- reasonability for examining construction schedule, unreasonable place is optimized the construction schedule to form optimization and and its
Associated BIM models;Then step S106 is executed.
Step S106 is executed, the construction schedule of required format is exported, passes through BIM progress control softwares and exports required lattice
The construction schedule of formula, to complete the establishment of construction schedule.
The present invention work out construction schedule in such a way that BIM models and construction schedule are associated, it can be achieved that
To the D visualized simulation of construction schedule, and the modification of construction schedule is easy to adjust quick, construction schedule
It is associated with the component in BIM models so that when instructing practice of construction according to construction schedule, BIM models can be passed through
Intuitive display construction work progress, has stronger intuitive.The present invention using BIM technology be construction schedule establishment with
Optimization Work brings innovation, provides new mode and method.
As the better embodiment of the present invention, corresponding BIM models are established according to construction drawing, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.In each project under construction, include
Multiple professional classifications, for example include that electromechanical speciality and building structure are professional for the project under construction that one is built, it is corresponding to build
When vertical BIM models, the BIM models of the BIM models and building structure profession of electromechanical speciality are established.
For professional difference, different software can be flexibly selected to establish BIM models so that modeling is convenient and efficient.It selects soft
When part, it is contemplated that the Data Integration of each BIM models requires and required precision.
It when establishing BIM models, is required according to arrangement and method for construction, selects the BIM models of corresponding fining degree, foundation
The accuracy class of BIM models should meet the requirement of construction schedule establishment time fining degree.
By the BIM models of each profession according to the requirement of computer software, light-weight technologg is carried out, by the number of BIM models
Reduced according to capacity, it is made to meet the requirement of computer computation ability.
As another better embodiment of the present invention, the BIM models of each profession through light-weight technologg are imported into
During being integrated in BIM progress control softwares, it is to be ensured that the compatibility and integrality of each BIM model datas.Compared with
Goodly, BIM progress controls software uses Autodesk navisworks.Certainly, BIM progress controls software is not limited to
Autodesk navisworks can also select other software.
As the another better embodiment of the present invention, before assigning time parameter to each component in BIM models,
Further include:
Construction schedule is worked out according to arrangement and method for construction, and the construction schedule worked out is input to BIM progress pipes
It manages in software.Construction schedule is generally formulated with arrangement and method for construction together, and designing both can be by the construction after construction schedule
Schedule is input in BIM progress control softwares, or the directly edit session schedule in BIM progress control softwares.
Further, each component in BIM models is assigned according to construction schedule in BIM progress control softwares
Time parameter, including:
The component in BIM models is chosen, and the component to being chosen adds time parameter, until to owning in BIM models
Until component adds deadline parameter;
The time parameter added on BIM models is linked into corresponding timing node in construction schedule, to complete
BIM models and construction schedule it is operation associated.
Timing node of the selection of time parameter in construction schedule, so time parameter is opposite with timing node
Answer, after choosing time parameter, time parameter accordingly added for each component, and by time parameter with it is corresponding construct into
The timing node of degree in the works is linked, so as to check corresponding BIM models by the timing node in construction schedule
Component.
Further, the reasonability of construction schedule is examined by visual Simulation, including:
During visual Simulation, the time sequencing that each component in BIM models is completed is examined according to working procedure
Whether rationally, if the time sequencing completed of component be consistent with working procedure if indicate reasonable, if component completion time
Sequence is not consistent with working procedure, indicates unreasonable.
For building structure profession and electromechanical speciality, in the construction of each component have certain sequence, visual
Change in simulation process, can intuitively and significantly check out the component for not meeting working procedure, this does not meet the component of working procedure
As unreasonable place provides tune to provide the visual test mode of construction schedule for construction schedule
The possibility changed is rebuild, and optimizes and changes and facilitate.
Further, the construction schedule to form optimization and associated there is optimized to unreasonable place
BIM models, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node that unreasonable place is corresponded in modification construction schedule, modified timing node is linked to
On time parameter after adjustment, to complete optimization operation.
The present invention preparation method required according to arrangement and method for construction in BIM progress control softwares, pair with construction speed meter
The simulation that associated BIM models carry out three-dimensional visualization is drawn, easily and efficiently modifies, optimize to actual progress plan.And
In BIM progress control softwares, the time parameter of the BIM models after simulation, modification, optimization is adjusted, while modification is applied
Work schedule.By BIM progress control softwares, construction schedule editor is arranged, different-format is exported by software
Construction schedule completes the establishment of construction schedule.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper
It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this
Invention will be using the range that the appended claims define as protection scope of the present invention.
Claims (7)
1. a kind of construction schedule optimizes preparation method, which is characterized in that include the following steps:
Corresponding BIM models are established according to construction drawing;
Light-weight technologg is carried out to the BIM models established;
BIM models through light-weight technologg are imported into BIM progress control softwares and are integrated;
In the BIM progress controls software time is assigned to each component in the BIM models according to construction schedule
Parameter, to which the BIM models is associated with the construction schedule;
Three-dimensional visualization is carried out using the BIM progress controls software pair BIM models associated with the construction schedule
Simulation, the reasonability of the construction schedule is examined by visual Simulation, unreasonable place is optimized to be formed it is excellent
The construction schedule of change and the BIM models associated there;And
The construction schedule that required format is exported by the BIM progress controls software, to complete construction schedule
Establishment.
2. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that according to construction drawing foundation pair
The BIM models answered, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.
3. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that in the BIM models
Each component assign time parameter before, further include:
Construction schedule is worked out according to arrangement and method for construction, and the construction schedule worked out is input to the BIM progresses pipe
It manages in software.
4. the construction schedule as described in claim 1 or 3 optimizes preparation method, which is characterized in that in the BIM progresses pipe
It manages in software and assigns time parameter to each component in the BIM models according to construction schedule, including:
The component in the BIM models is chosen, and the component to being chosen adds time parameter, until in the BIM models
Until all components add deadline parameter;
The time parameter added on the BIM models is linked into corresponding timing node in the construction schedule,
So as to complete the operation associated of the BIM models and the construction schedule.
5. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that examined by visual Simulation
The reasonability of the construction schedule, including:
During visual Simulation, the time sequencing that each component in the BIM models is completed is examined according to working procedure
Whether rationally, indicate reasonable if the time sequencing that the component is completed is consistent with the working procedure, if the structure
The time sequencing that part is completed is not consistent with the working procedure, indicates unreasonable.
6. construction schedule as claimed in claim 5 optimizes preparation method, which is characterized in that carried out to unreasonable place
Optimization forms the construction schedule of optimization and the BIM models associated there, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node for corresponding to unreasonable place in the construction schedule is changed, modified timing node is linked to
On time parameter after adjustment, to complete optimization operation.
7. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that the BIM progress controls are soft
Part uses Autodesk navisworks.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810320264.3A CN108596374A (en) | 2018-04-11 | 2018-04-11 | Construction schedule optimizes preparation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810320264.3A CN108596374A (en) | 2018-04-11 | 2018-04-11 | Construction schedule optimizes preparation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108596374A true CN108596374A (en) | 2018-09-28 |
Family
ID=63621629
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810320264.3A Pending CN108596374A (en) | 2018-04-11 | 2018-04-11 | Construction schedule optimizes preparation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108596374A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN111047098A (en) * | 2019-12-16 | 2020-04-21 | 四川众合广汇企业管理咨询有限公司 | Construction progress and cost management system, computer equipment and computer readable storage medium |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN112307548A (en) * | 2020-11-02 | 2021-02-02 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based rail transit construction visualization progress management method and system |
CN112465390A (en) * | 2020-12-10 | 2021-03-09 | 中铁一局集团第二工程有限公司 | BIM-based subway station construction progress management method |
CN112950303A (en) * | 2019-12-10 | 2021-06-11 | 阿里巴巴集团控股有限公司 | Order processing method and device, electronic equipment and storage medium |
CN113792370A (en) * | 2021-09-22 | 2021-12-14 | 中国电建集团华东勘测设计研究院有限公司 | 4D simulation and optimization method, device, storage medium and equipment for old power station transformation construction |
CN115860499A (en) * | 2023-02-28 | 2023-03-28 | 安徽智享云科技有限公司 | Multi-professional work-type coordination construction management system based on BIM technology |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106202723A (en) * | 2016-07-10 | 2016-12-07 | 北京工业大学 | A kind of BIM subway work method |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
-
2018
- 2018-04-11 CN CN201810320264.3A patent/CN108596374A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106202723A (en) * | 2016-07-10 | 2016-12-07 | 北京工业大学 | A kind of BIM subway work method |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN112950303A (en) * | 2019-12-10 | 2021-06-11 | 阿里巴巴集团控股有限公司 | Order processing method and device, electronic equipment and storage medium |
CN111047098A (en) * | 2019-12-16 | 2020-04-21 | 四川众合广汇企业管理咨询有限公司 | Construction progress and cost management system, computer equipment and computer readable storage medium |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111783270B (en) * | 2020-03-17 | 2021-09-03 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN112307548A (en) * | 2020-11-02 | 2021-02-02 | 中国电建集团华东勘测设计研究院有限公司 | BIM-based rail transit construction visualization progress management method and system |
CN112465390A (en) * | 2020-12-10 | 2021-03-09 | 中铁一局集团第二工程有限公司 | BIM-based subway station construction progress management method |
CN113792370A (en) * | 2021-09-22 | 2021-12-14 | 中国电建集团华东勘测设计研究院有限公司 | 4D simulation and optimization method, device, storage medium and equipment for old power station transformation construction |
CN115860499A (en) * | 2023-02-28 | 2023-03-28 | 安徽智享云科技有限公司 | Multi-professional work-type coordination construction management system based on BIM technology |
CN115860499B (en) * | 2023-02-28 | 2023-05-05 | 安徽智享云科技有限公司 | BIM technology-based multi-specialty work coordination construction management system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108596374A (en) | Construction schedule optimizes preparation method | |
CN106022523B (en) | A kind of automatic production line Optimization Design based on integrated emulation | |
US20190205484A1 (en) | Systems and methods for construction planning | |
CN103765334B (en) | Method and system for simulating a working process on a machine tool | |
CN109377066A (en) | A kind of live Schedule monitoring system and method based on threedimensional model | |
Castro-Lacouture et al. | Construction project scheduling with time, cost, and material restrictions using fuzzy mathematical models and critical path method | |
CN104407576B (en) | A kind of implementation method and control system of universal manufacturing unit | |
Su et al. | Life cycle approach to construction workspace modeling and planning | |
CN110363852A (en) | A kind of 3-dimensional digital Liang Chang, construction method, computer equipment and storage medium | |
CN105787229B (en) | A kind of design of automatic production line and operation combined optimization method | |
CN107229777A (en) | A kind of acceptance of concealed work method based on mixed reality technology | |
Bley et al. | Integration of product design and assembly planning in the digital factory | |
CN113609550A (en) | BIM-based construction process planning management method and system | |
Havard et al. | Collaborative virtual reality decision tool for planning industrial shop floor layouts | |
EP2110762A1 (en) | Digital plant structure method and system thereof | |
CN115187039A (en) | Construction progress management method and system based on BIM | |
CN101655884B (en) | Method for automatically drawing trimming line of stamping die | |
Corbett | Human centred advanced manufacturing systems: From rhetoric to reality | |
CN112654943A (en) | Manufacturing system design assistance device | |
JP2002355724A (en) | Assembly-disassembly process design support device | |
Wörner et al. | Visual Analysis of Advanced Manufacturing Simulations. | |
CN107730103A (en) | Spatial data handling flow control method | |
CN100465888C (en) | Method for automatically establishing procedure body | |
US8090812B2 (en) | CAE analysis progress management system | |
US20220374802A1 (en) | Automated analysis of objects for construction planning |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180928 |
|
RJ01 | Rejection of invention patent application after publication |