CN108596374A - Construction schedule optimizes preparation method - Google Patents

Construction schedule optimizes preparation method Download PDF

Info

Publication number
CN108596374A
CN108596374A CN201810320264.3A CN201810320264A CN108596374A CN 108596374 A CN108596374 A CN 108596374A CN 201810320264 A CN201810320264 A CN 201810320264A CN 108596374 A CN108596374 A CN 108596374A
Authority
CN
China
Prior art keywords
construction schedule
bim
construction
bim models
schedule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810320264.3A
Other languages
Chinese (zh)
Inventor
王代兵
张学伟
姜化强
于航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201810320264.3A priority Critical patent/CN108596374A/en
Publication of CN108596374A publication Critical patent/CN108596374A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of construction schedules to optimize preparation method, includes the following steps:It establishes corresponding BIM models according to construction drawing and carries out light-weight technologg;BIM models are imported into BIM progress control softwares and are integrated;Time parameter is assigned to each component in the BIM models according to construction schedule in the BIM progress controls software, to which the BIM models is associated with the construction schedule;D visualized simulation is carried out using the BIM progress controls software pair BIM models associated with the construction schedule, the reasonability that the construction schedule is examined by visual Simulation optimizes unreasonable place the construction schedule to form optimization and the BIM models associated there;And the construction schedule of format needed for export.The D visualized simulation to construction schedule can be achieved in the present invention, and the modification of construction schedule is easy to adjust quick.

Description

Construction schedule optimizes preparation method
Technical field
The present invention relates to building Construction of Civil Engineering fields, refer in particular to a kind of construction schedule optimization preparation method.
Background technology
With the development of building civil engineering construction, construction industry Construction management is also constantly being sent out with method, technology Exhibition progress.
During building cost management, to the way to manages such as progress, quality, cost, safety, method also continuous Innovation.In the management process of construction speed, the construction schedule for working out engineering project is one of construction project time management Major tasks.
Traditional schedule preparation method uses in general, according to construction drawing on the basis of construction experience The software of project etc carries out the authorized strength work of construction schedule.The method, there are a large amount of defects, such as:It is worked out Construction schedule can not meet practice of construction demand;In terms of largely construction schedule is there are working procedure Wrong, missing, touch, lack the problems such as.In addition to this, worked out construction schedule can not be simulated visually, and into The adjustment work for spending plan is inconvenient.
Invention content
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of construction schedule optimization preparation method is provided, Solve existing preparation method there are in terms of working procedure defect problem, visual Simulation and adjustment inconvenience etc. can not be carried out The problem of.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides a kind of construction schedules to optimize preparation method, includes the following steps:
Corresponding BIM models are established according to construction drawing;
Light-weight technologg is carried out to the BIM models established;
BIM models through light-weight technologg are imported into BIM progress control softwares and are integrated;
Each component in the BIM models is assigned according to construction schedule in the BIM progress controls software Time parameter, to which the BIM models is associated with the construction schedule;
Carrying out three-dimensional using the BIM progress controls software pair BIM models associated with the construction schedule can It is simulated depending on changing, the reasonability of the construction schedule is examined by visual Simulation, shape is optimized to unreasonable place Construction schedule at optimization and the BIM models associated there;And
The construction schedule that required format is exported by the BIM progress controls software, to complete construction speed meter The establishment drawn.
The present invention work out construction schedule in such a way that BIM models and construction schedule are associated, it can be achieved that To the D visualized simulation of construction schedule, and the modification of construction schedule is easy to adjust quick, construction schedule It is associated with the component in BIM models so that when instructing practice of construction according to construction schedule, BIM models can be passed through Intuitive display construction work progress, has stronger intuitive.The present invention using BIM technology be construction schedule establishment with Optimization Work brings innovation, provides new mode and method.
Construction schedule of the present invention optimization preparation method further improvement lies in that, established according to construction drawing corresponding BIM models, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.
Construction schedule of the present invention optimization preparation method further improvement lies in that, to each in the BIM models Before a component assigns time parameter, further include:
According to arrangement and method for construction work out construction schedule, and by the construction schedule worked out be input to the BIM into It spends in management software.
Construction schedule of the present invention optimization preparation method further improvement lies in that, in the BIM progress controls software It is interior to assign time parameter to each component in the BIM models according to construction schedule, including:
The component in the BIM models is chosen, and the component to being chosen adds time parameter, until to the BIM moulds Until all components add deadline parameter in type;
The segmentum intercalaris when time parameter added on the BIM models is linked to corresponding in the construction schedule Point, so as to complete the operation associated of the BIM models and the construction schedule.
Construction schedule of the present invention optimization preparation method further improvement lies in that, examined by visual Simulation described in The reasonability of construction schedule, including:
During visual Simulation, the time that each component in the BIM models is completed is examined according to working procedure Whether sequence is reasonable, indicates reasonable if the time sequencing that the component is completed is consistent with the working procedure, if described Component complete time sequencing be not consistent with the working procedure, indicate unreasonable.
Construction schedule of the present invention optimization preparation method further improvement lies in that, unreasonable place is optimized The construction schedule of optimization and the BIM models associated there are formed, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node that unreasonable place is corresponded in the construction schedule is changed, by modified timing node chain It is connected on the time parameter after adjustment, to complete optimization operation.
Construction schedule of the present invention optimization preparation method further improvement lies in that, the BIM progress controls software is adopted With Autodesk navisworks.
Description of the drawings
Fig. 1 is the flow chart that construction schedule of the present invention optimizes preparation method.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
Refering to fig. 1, the present invention provides a kind of construction schedules to optimize preparation method, for solving existing construction speed Plan cannot meet practice of construction demand, there are working procedure in terms of Wrong, missing, touch, lack the problems such as, construction schedule can not Visually simulated, it is inconvenient to the adjustment work of schedule.BIM technology is utilized in the preparation method of the present invention, will apply Work schedule is associated with BIM models, so that construction schedule can carry out D visualized simulation by software, from And construction schedule can be optimized, and facilitate adjustment and modification.The construction schedule can also provide after export Intuitive three-dimensional display, preparation method of the invention are that construction schedule authorized strength work brings innovation, provide new side Formula and method.Construction schedule of the present invention optimization preparation method is illustrated below in conjunction with the accompanying drawings.
Refering to fig. 1, it is shown that the flow chart of construction schedule optimization preparation method of the present invention.With reference to Fig. 1, to this Invention construction schedule optimization preparation method illustrates.
As shown in Figure 1, a kind of construction schedule of the present invention optimizes preparation method, include the following steps:
Step S101 is executed, corresponding BIM models are established according to construction drawing;Then step S102 is executed.
Step S102 is executed, light-weight technologg is carried out to BIM models;Then step S103 is executed.
Step S103 is executed, the BIM models of light-weight technologg are imported into BIM progress control softwares, BIM progresses are utilized Management software integrates the BIM models of importing;Then step S104 is executed.
Step S104 is executed, BIM models is associated with construction schedule, and foundation is applied in BIM progress control softwares Work schedule assigns time parameter to each component in BIM models, to which BIM models is related to construction schedule Connection;Then step S105 is executed.
Step S105 is executed, a pair BIM models associated with construction schedule carry out D visualized simulation, utilize BIM progress controls software pair BIM models associated with construction schedule carry out D visualized simulation, by visualizing mould The quasi- reasonability for examining construction schedule, unreasonable place is optimized the construction schedule to form optimization and and its Associated BIM models;Then step S106 is executed.
Step S106 is executed, the construction schedule of required format is exported, passes through BIM progress control softwares and exports required lattice The construction schedule of formula, to complete the establishment of construction schedule.
The present invention work out construction schedule in such a way that BIM models and construction schedule are associated, it can be achieved that To the D visualized simulation of construction schedule, and the modification of construction schedule is easy to adjust quick, construction schedule It is associated with the component in BIM models so that when instructing practice of construction according to construction schedule, BIM models can be passed through Intuitive display construction work progress, has stronger intuitive.The present invention using BIM technology be construction schedule establishment with Optimization Work brings innovation, provides new mode and method.
As the better embodiment of the present invention, corresponding BIM models are established according to construction drawing, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.In each project under construction, include Multiple professional classifications, for example include that electromechanical speciality and building structure are professional for the project under construction that one is built, it is corresponding to build When vertical BIM models, the BIM models of the BIM models and building structure profession of electromechanical speciality are established.
For professional difference, different software can be flexibly selected to establish BIM models so that modeling is convenient and efficient.It selects soft When part, it is contemplated that the Data Integration of each BIM models requires and required precision.
It when establishing BIM models, is required according to arrangement and method for construction, selects the BIM models of corresponding fining degree, foundation The accuracy class of BIM models should meet the requirement of construction schedule establishment time fining degree.
By the BIM models of each profession according to the requirement of computer software, light-weight technologg is carried out, by the number of BIM models Reduced according to capacity, it is made to meet the requirement of computer computation ability.
As another better embodiment of the present invention, the BIM models of each profession through light-weight technologg are imported into During being integrated in BIM progress control softwares, it is to be ensured that the compatibility and integrality of each BIM model datas.Compared with Goodly, BIM progress controls software uses Autodesk navisworks.Certainly, BIM progress controls software is not limited to Autodesk navisworks can also select other software.
As the another better embodiment of the present invention, before assigning time parameter to each component in BIM models, Further include:
Construction schedule is worked out according to arrangement and method for construction, and the construction schedule worked out is input to BIM progress pipes It manages in software.Construction schedule is generally formulated with arrangement and method for construction together, and designing both can be by the construction after construction schedule Schedule is input in BIM progress control softwares, or the directly edit session schedule in BIM progress control softwares.
Further, each component in BIM models is assigned according to construction schedule in BIM progress control softwares Time parameter, including:
The component in BIM models is chosen, and the component to being chosen adds time parameter, until to owning in BIM models Until component adds deadline parameter;
The time parameter added on BIM models is linked into corresponding timing node in construction schedule, to complete BIM models and construction schedule it is operation associated.
Timing node of the selection of time parameter in construction schedule, so time parameter is opposite with timing node Answer, after choosing time parameter, time parameter accordingly added for each component, and by time parameter with it is corresponding construct into The timing node of degree in the works is linked, so as to check corresponding BIM models by the timing node in construction schedule Component.
Further, the reasonability of construction schedule is examined by visual Simulation, including:
During visual Simulation, the time sequencing that each component in BIM models is completed is examined according to working procedure Whether rationally, if the time sequencing completed of component be consistent with working procedure if indicate reasonable, if component completion time Sequence is not consistent with working procedure, indicates unreasonable.
For building structure profession and electromechanical speciality, in the construction of each component have certain sequence, visual Change in simulation process, can intuitively and significantly check out the component for not meeting working procedure, this does not meet the component of working procedure As unreasonable place provides tune to provide the visual test mode of construction schedule for construction schedule The possibility changed is rebuild, and optimizes and changes and facilitate.
Further, the construction schedule to form optimization and associated there is optimized to unreasonable place BIM models, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node that unreasonable place is corresponded in modification construction schedule, modified timing node is linked to On time parameter after adjustment, to complete optimization operation.
The present invention preparation method required according to arrangement and method for construction in BIM progress control softwares, pair with construction speed meter The simulation that associated BIM models carry out three-dimensional visualization is drawn, easily and efficiently modifies, optimize to actual progress plan.And In BIM progress control softwares, the time parameter of the BIM models after simulation, modification, optimization is adjusted, while modification is applied Work schedule.By BIM progress control softwares, construction schedule editor is arranged, different-format is exported by software Construction schedule completes the establishment of construction schedule.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (7)

1. a kind of construction schedule optimizes preparation method, which is characterized in that include the following steps:
Corresponding BIM models are established according to construction drawing;
Light-weight technologg is carried out to the BIM models established;
BIM models through light-weight technologg are imported into BIM progress control softwares and are integrated;
In the BIM progress controls software time is assigned to each component in the BIM models according to construction schedule Parameter, to which the BIM models is associated with the construction schedule;
Three-dimensional visualization is carried out using the BIM progress controls software pair BIM models associated with the construction schedule Simulation, the reasonability of the construction schedule is examined by visual Simulation, unreasonable place is optimized to be formed it is excellent The construction schedule of change and the BIM models associated there;And
The construction schedule that required format is exported by the BIM progress controls software, to complete construction schedule Establishment.
2. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that according to construction drawing foundation pair The BIM models answered, including:
The BIM models of corresponding profession are established according to professional classification in arrangement and method for construction.
3. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that in the BIM models Each component assign time parameter before, further include:
Construction schedule is worked out according to arrangement and method for construction, and the construction schedule worked out is input to the BIM progresses pipe It manages in software.
4. the construction schedule as described in claim 1 or 3 optimizes preparation method, which is characterized in that in the BIM progresses pipe It manages in software and assigns time parameter to each component in the BIM models according to construction schedule, including:
The component in the BIM models is chosen, and the component to being chosen adds time parameter, until in the BIM models Until all components add deadline parameter;
The time parameter added on the BIM models is linked into corresponding timing node in the construction schedule, So as to complete the operation associated of the BIM models and the construction schedule.
5. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that examined by visual Simulation The reasonability of the construction schedule, including:
During visual Simulation, the time sequencing that each component in the BIM models is completed is examined according to working procedure Whether rationally, indicate reasonable if the time sequencing that the component is completed is consistent with the working procedure, if the structure The time sequencing that part is completed is not consistent with the working procedure, indicates unreasonable.
6. construction schedule as claimed in claim 5 optimizes preparation method, which is characterized in that carried out to unreasonable place Optimization forms the construction schedule of optimization and the BIM models associated there, including:
Adjust the unreasonable corresponding time parameter in place;
The timing node for corresponding to unreasonable place in the construction schedule is changed, modified timing node is linked to On time parameter after adjustment, to complete optimization operation.
7. construction schedule as described in claim 1 optimizes preparation method, which is characterized in that the BIM progress controls are soft Part uses Autodesk navisworks.
CN201810320264.3A 2018-04-11 2018-04-11 Construction schedule optimizes preparation method Pending CN108596374A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810320264.3A CN108596374A (en) 2018-04-11 2018-04-11 Construction schedule optimizes preparation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810320264.3A CN108596374A (en) 2018-04-11 2018-04-11 Construction schedule optimizes preparation method

Publications (1)

Publication Number Publication Date
CN108596374A true CN108596374A (en) 2018-09-28

Family

ID=63621629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810320264.3A Pending CN108596374A (en) 2018-04-11 2018-04-11 Construction schedule optimizes preparation method

Country Status (1)

Country Link
CN (1) CN108596374A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN111047098A (en) * 2019-12-16 2020-04-21 四川众合广汇企业管理咨询有限公司 Construction progress and cost management system, computer equipment and computer readable storage medium
CN111783270A (en) * 2020-03-17 2020-10-16 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN112307548A (en) * 2020-11-02 2021-02-02 中国电建集团华东勘测设计研究院有限公司 BIM-based rail transit construction visualization progress management method and system
CN112465390A (en) * 2020-12-10 2021-03-09 中铁一局集团第二工程有限公司 BIM-based subway station construction progress management method
CN112950303A (en) * 2019-12-10 2021-06-11 阿里巴巴集团控股有限公司 Order processing method and device, electronic equipment and storage medium
CN113792370A (en) * 2021-09-22 2021-12-14 中国电建集团华东勘测设计研究院有限公司 4D simulation and optimization method, device, storage medium and equipment for old power station transformation construction
CN115860499A (en) * 2023-02-28 2023-03-28 安徽智享云科技有限公司 Multi-professional work-type coordination construction management system based on BIM technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107480370A (en) * 2017-08-10 2017-12-15 嘉兴恒创电力设计研究院有限公司 A kind of construction speed Forecasting Methodology and system based on BIM models

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107480370A (en) * 2017-08-10 2017-12-15 嘉兴恒创电力设计研究院有限公司 A kind of construction speed Forecasting Methodology and system based on BIM models

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN112950303A (en) * 2019-12-10 2021-06-11 阿里巴巴集团控股有限公司 Order processing method and device, electronic equipment and storage medium
CN111047098A (en) * 2019-12-16 2020-04-21 四川众合广汇企业管理咨询有限公司 Construction progress and cost management system, computer equipment and computer readable storage medium
CN111783270A (en) * 2020-03-17 2020-10-16 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN111783270B (en) * 2020-03-17 2021-09-03 江西武大扬帆科技有限公司 Construction progress digital simulation method based on BIM technology
CN112307548A (en) * 2020-11-02 2021-02-02 中国电建集团华东勘测设计研究院有限公司 BIM-based rail transit construction visualization progress management method and system
CN112465390A (en) * 2020-12-10 2021-03-09 中铁一局集团第二工程有限公司 BIM-based subway station construction progress management method
CN113792370A (en) * 2021-09-22 2021-12-14 中国电建集团华东勘测设计研究院有限公司 4D simulation and optimization method, device, storage medium and equipment for old power station transformation construction
CN115860499A (en) * 2023-02-28 2023-03-28 安徽智享云科技有限公司 Multi-professional work-type coordination construction management system based on BIM technology
CN115860499B (en) * 2023-02-28 2023-05-05 安徽智享云科技有限公司 BIM technology-based multi-specialty work coordination construction management system

Similar Documents

Publication Publication Date Title
CN108596374A (en) Construction schedule optimizes preparation method
CN106022523B (en) A kind of automatic production line Optimization Design based on integrated emulation
US20190205484A1 (en) Systems and methods for construction planning
CN103765334B (en) Method and system for simulating a working process on a machine tool
CN109377066A (en) A kind of live Schedule monitoring system and method based on threedimensional model
Castro-Lacouture et al. Construction project scheduling with time, cost, and material restrictions using fuzzy mathematical models and critical path method
CN104407576B (en) A kind of implementation method and control system of universal manufacturing unit
Su et al. Life cycle approach to construction workspace modeling and planning
CN110363852A (en) A kind of 3-dimensional digital Liang Chang, construction method, computer equipment and storage medium
CN105787229B (en) A kind of design of automatic production line and operation combined optimization method
CN107229777A (en) A kind of acceptance of concealed work method based on mixed reality technology
Bley et al. Integration of product design and assembly planning in the digital factory
CN113609550A (en) BIM-based construction process planning management method and system
Havard et al. Collaborative virtual reality decision tool for planning industrial shop floor layouts
EP2110762A1 (en) Digital plant structure method and system thereof
CN115187039A (en) Construction progress management method and system based on BIM
CN101655884B (en) Method for automatically drawing trimming line of stamping die
Corbett Human centred advanced manufacturing systems: From rhetoric to reality
CN112654943A (en) Manufacturing system design assistance device
JP2002355724A (en) Assembly-disassembly process design support device
Wörner et al. Visual Analysis of Advanced Manufacturing Simulations.
CN107730103A (en) Spatial data handling flow control method
CN100465888C (en) Method for automatically establishing procedure body
US8090812B2 (en) CAE analysis progress management system
US20220374802A1 (en) Automated analysis of objects for construction planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928

RJ01 Rejection of invention patent application after publication