CN108544655A - The curved beam prefabricated construction method of curved bridge - Google Patents

The curved beam prefabricated construction method of curved bridge Download PDF

Info

Publication number
CN108544655A
CN108544655A CN201810314286.9A CN201810314286A CN108544655A CN 108544655 A CN108544655 A CN 108544655A CN 201810314286 A CN201810314286 A CN 201810314286A CN 108544655 A CN108544655 A CN 108544655A
Authority
CN
China
Prior art keywords
curved
bellows
construction method
concrete
prefabricated construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810314286.9A
Other languages
Chinese (zh)
Inventor
俞宏伟
陈红兵
段景海
范敏
张迟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Bao Xiang Construction Group LLC
Original Assignee
Anhui Bao Xiang Construction Group LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Bao Xiang Construction Group LLC filed Critical Anhui Bao Xiang Construction Group LLC
Priority to CN201810314286.9A priority Critical patent/CN108544655A/en
Publication of CN108544655A publication Critical patent/CN108544655A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • B28B13/06Removing the shaped articles from moulds
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/046Post treatment to obtain pre-stressed articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of curved beam prefabricated construction methods of curved bridge, including:Step a, mounting rail rib and diaphragm plate reinforcing bar;Step b, bellows is installed;Step c, installation form;Step d, slab reinforcement is installed;Step e, hogging moment bellows is installed;Step f, concreting;Step g, maintenance and form removal;Step h, prestressed stretch-draw and mud jacking;Wherein, internal lining pipe is worn in bellows, and tensioning is influenced for mortar leakage prevention.The construction method has broken the common process limitation of curved bridge cast-in-place construction, takes curve song to do technique, meets bridge Horizontal Curve requirement, fully show curved bridge line style.

Description

The curved beam prefabricated construction method of curved bridge
Technical field
The present invention relates to building fields, and in particular, to a kind of curved beam prefabricated construction method of curved bridge.
Background technology
With the development of urban road and highway communication, curved bridge has become Modern Traffic engineering using increasingly extensive In important bridge type.Curved bridge construction method is main or based on cast-in-place, and relatively large radius curved bridge can also be taken pre- Beam blade technolgy processed directly does mode by curve to realize.
Therefore, in order to more fully show curved bridge line style, meet bridge Horizontal Curve requirement, urgent need will provide one The new curved beam prefabricated construction method of curved bridge of kind.
Invention content
The object of the present invention is to provide a kind of curved beam prefabricated construction method of curved bridge, which has broken curved bridge The common process of cast-in-place construction limits to, and takes curve song to do technique, meets bridge Horizontal Curve requirement, fully show curved bridge Line style.
To achieve the goals above, the present invention provides a kind of curved beam prefabricated construction methods of curved bridge, including:
Step a, mounting rail rib and diaphragm plate reinforcing bar;
Step b, bellows is installed;
Step c, installation form;
Step d, slab reinforcement is installed;
Step e, hogging moment bellows is installed;
Step f, concreting;
Step g, maintenance and form removal;
Step h, prestressed stretch-draw and mud jacking;Wherein,
Internal lining pipe is worn in bellows, and tensioning is influenced for mortar leakage prevention.
Preferably, step a includes indicating reinforcement location line on pedestal according to drawing assembling reinforcement, and reinforcing bar is placed by line, And it will be welded and fixed intersection in length and breadth;Wherein,
Ensure that pipeline location is constant and will move reinforcement location at pipeline and reinforcing bar collision.
Preferably, step b includes being fixed according to the coordinate setting bellows on drawing and with spacer bar.
Preferably, step c includes:1, using sizing punching block assembled formwork, wherein plate thickness is more than or equal to 6mm;2, make It will be interconnected and fixed between each template with bolt, wherein embedded fixed type elasticity caulking strip among plate stitch;3, by the side bar edge of a wing Plate working width is processed according to Curve Design parameter maximum width, then mixes adjustable movable edge of a wing edges of boards mould;4, template is marched into the arena It needs to carry out processing of rust removing to template before installation and brushes releasing agent;5, it installs, connect, fixing side form, bed die and end mould.
Preferably, bellows is reserved in form stop when hogging moment area bellows is installed in step e to connect for upper bridging.
Preferably, in step f concrete cast using it is oblique segmentation, horizontal slice continuous placing mode, front and back two layers of concrete Interval time must not exceed the presetting period;
Vibrating for beam body concrete is vibrated using form vibrator, the common cooperation of plug-in type vibrating stick;Horseshoe position concrete When entering mould, corresponding position form vibrator is started, is shaken to concrete compaction;When pouring web and upper limb board concrete, vibrate As a plug based on vibrating head, reinforcing bar is closeer and the intensive place of bellows, cooperation form vibrator vibrate.
Preferably, further include that troweling is carried out to back using wooden float after the completion of beam body concreting in step f, It carries out once receiving slurry processing again before initial set, finally uses steel brush or broom plucking;
During concreting, the bellows internal lining pipe of Liang Leichu need to be twitched manually, before pouring and finishing concrete initial set, Extract internal lining pipe out.
Preferably, maintenance includes being covered using geotextiles after beam piece plucking in step g, and watering, which conserves, prevents surface drying shrinkage from splitting Seam is conserved after form removal using spray, and is subject to hand fit's maintenance;
Form removal, which is included in after beam body concrete strength reaches strength of mould stripping requirement, carries out form removal, wherein is segmented in order when form removal It removes, dabbing is carried out to beam body surface immediately after dismounting.
Preferably, stretch value is recorded in the stretching process in step h, pressure gauge reading is extended using control force and control The dual control method of value carries out cable tensios control;Also, duct must be rinsed well with clear water before mud jacking, front row is clogged after waiting discharge underflow Stomata pressure and fill is starched, and the voltage stabilizing phase equal to 0.6Mpa is remained above, and time voltage stabilizing phase is more than or equal to 2min.
According to above-mentioned technical proposal, the present invention is by changing traditional side bar punching block processing and fabricating mode, by the side bar edge of a wing Plate working width considers according to Curve Design parameter maximum width, then mixes adjustable movable edge of a wing edges of boards mould, to the system of processing Be made it is a set of can meet straight line, Curve requirement universal sideshields beam forms, precast curve side bar, it is beautiful to reach curved bridge line style The effect of sight.It has broken the common process limitation of curved bridge cast-in-place construction, and extend Prestressed T (cored slab) beam applies model It encloses.Also, moulding board of precast beam processing and fabricating is simple, versatile, linear type and shaped form beam piece energy Prefabrication, work of constructing Skill is simple, and quality is guaranteed, is widely used in the curved bridge of radius R >=200m.
Other features and advantages of the present invention will be described in detail in subsequent specific embodiment part.
Description of the drawings
Attached drawing is to be used to provide further understanding of the present invention, an and part for constitution instruction, with following tool Body embodiment is used to explain the present invention together, but is not construed as limiting the invention.In the accompanying drawings:
Fig. 1 is the curved beam side mould template of curve in the present invention;
Fig. 2 is the enlarged drawing of part A in Fig. 1.
Specific implementation mode
The specific implementation mode of the present invention is described in detail below in conjunction with attached drawing.It should be understood that this place is retouched The specific implementation mode stated is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
In the present invention, in the absence of explanation to the contrary, the noun of locality that " inside and outside " etc. is included in the term only represents Orientation of the term under normal service condition, or be those skilled in the art understand that be commonly called as, and be not construed as to the term Limitation.
The present invention provides a kind of curved beam prefabricated construction method of curved bridge, including:
Step a, mounting rail rib and diaphragm plate reinforcing bar;
Step b, bellows is installed;
Step c, installation form;
Step d, slab reinforcement is installed;
Step e, hogging moment bellows is installed;
Step f, concreting;
Step g, maintenance and form removal;
Step h, prestressed stretch-draw and mud jacking;Wherein,
Internal lining pipe is worn in bellows, and tensioning is influenced for mortar leakage prevention.
Steel bar meter is with installation, and reinforcing bar is processed in unified make of reinforcing steel processing shed, in strict accordance with design drawing and specification It is required that test to its model, size, presentation quality, when blanking, pays attention to the reinforcing bar length of side bar curvilinear motion section.
It is strictly bound by drawing when reinforcement installation, reinforcement location line is indicated on pedestal, place reinforcing bar by line, in length and breadth Intersection ensures that framework of steel reinforcement is stable, vertical when necessary using welding.If pipeline collides with reinforcing bar, pipeline should ensure that Position is constant and suitably moves reinforcement location.
Coordinate setting that the installation of wave duct pipe must be provided strictly by design drawing is simultaneously fixed, bellows with spacer bar Junction must be close, and bellows pipe shaft is without breakage, mortar leakage prevention.It, must be more in form stop when hogging moment area bellows is installed Reserve certain length bellows, it is ensured that bellows smoothly connects after upper bridge.It is anti-that internal lining pipe must be worn in bellows in construction Leak-stopping is starched and influences tensioning.
Template is processed with installation:1, select qualified steel construction processing factory to be processed, strictly control blanking, It bends and welding procedure, ensures that each portion structure size of beam body is correct and built-in fitting position is accurate.Template is using bulk sizing steel Mould is assembled, and plate thickness is not less than 6mm, is connected between each template, and embedded fixed type elasticity caulking strip among plate stitch is protected Spillage and beam body be not beautiful for card.
2, the curved beam of curve is pressed side bar flange plate working width by changing traditional side bar punching block processing and fabricating mode Consider according to Curve Design parameter maximum width, then mixes adjustable movable edge of a wing edges of boards mould, it is full to manufacture a set of energy The universal sideshields beam forms that sufficient straight line, Curve require, the wherein curved beam side mould template of curve are as depicted in figs. 1 and 2.
3, processing of rust removing should be carried out after template is marched into the arena to template and brush releasing agent, when installation, requires to accomplish that position is accurate, It is completely embedded, side form and bed die, the end closely connected not spillage of mould.When horizontal slope is arranged in beam piece, beam wing plate must be prefabricated by horizontal slope.It is pre-buried Part is accurately arranged, and whether especially bearing steel plate setting horizontal, upper and lower pull rod and prop up mat piece in template, fastener is not intact It is complete.
In concreting, specifically include:
1, concrete be cast in reinforcing bar and template acceptance(check) after carry out, concrete unifies mixing using mixing plant, sternly Lattice control match ratio and duration of mixing, and the cast of testing crew footman's operation, concrete is poured using oblique segmentation, the continuous of horizontal slice Mode is built, the interval time of front and back two layers of concrete must not exceed the presetting period;
2, vibrating for beam body concrete is vibrated using form vibrator, the common cooperation of plug-in type vibrating stick.Horseshoe position coagulation When soil enters mould, corresponding position form vibrator is started, is shaken to concrete compaction, sky is forbidden to shake template.Pour web and upper limb When board concrete, based on the vibrating head as a plug that vibrates, reinforcing bar is closeer and the intensive place of bellows, cooperation form vibrator shake It smashes.Concrete vibrating is generally no longer sunk with concrete, and no notable bubble rises, and thin layer cement mortar occurs in concrete surface, and Until having uniform appearance and plane;
3, the temperature of concrete mixed material should be no more than 32 ° when hot weather construction, effective cooling should be used to prevent when more than 32 ° Evaporation measure, the template contacted with concrete, reinforcing bar should be reduced to 32 ° or less before cast using effective measures;
4, after the completion of beam body concreting, troweling is carried out to back using wooden float, is carried out again before initial set primary Slurry processing is received, steel brush or broom plucking are finally used;
5, during concreting, the bellows internal lining pipe of Liang Leichu need to be twitched manually, and concrete initial set is finished pouring Before, extract internal lining pipe out;
6, the prefabricated of beam piece will have real curing to give birth to test block, and test block will be placed on beam piece top plate, simultaneously, together with the beam piece Condition health.
It in maintenance and form removal, is covered using geotextiles after beam piece plucking, watering maintenance prevents surface desciccation crack, after form removal It is conserved using special spray, and is subject to hand fit's maintenance, curing time is no less than 7 days, is ensured daily Concrete surface is often in moisture state.When temperature be less than 5 °, answer covering and heat insulating, must not sprinkle water on concrete face.
After beam body concrete strength reaches strength of mould stripping requirement, form removal can be carried out.Dismounting is segmented when form removal in order, it must not There are the templates for loosening or hanging, and forbid to pound firmly or be pushed over mechanical large area, avoid causing template local deformation or damage beam Body concrete corner angle, when handling template, will balance, and prevent damage beam body and adjacent forms.After form removable, immediately to beam body surface into Row dabbing.
In prestressed stretch-draw and mud jacking process, steel strand wires and anchor clamp have a product certificate, and by pass the test after It can use, jack and mating oil pump are demarcated in time.Corresponding elongation and oil meter reading are calculated according to test data.
Tensioning must after T beam strengths reach the 90% of design, and the age of concrete be not less than 10d, can tensioning, and and When mud jacking.Meet design requirement in beam camber, can according to temperature, deposit the factors such as beam time, it is appropriate to shorten concrete Age is drawn, but most short age is no less than 7d.
In stretching process, stretch value, pressure gauge reading, using the dual control of control force and control stretch value are recorded in detail Method carries out cable tensios control, if actual elongation value and theoretic elongation are more than ± 6%, waits ascertaining the reason and after taking measures, can Continue tensioning.
Duct must be rinsed well with clear water before mud jacking, mud jacking carries out with answering slow uniformly continuous, waits discharge underflow rear plug Firmly front-seat stomata pressure and fill slurry, is kept for a voltage stabilizing phase not less than 0.6Mpa, time voltage stabilizing phase are no less than 2min, and without leakage Water, spillage phenomenon make the liquid-tight reality of pipeline entoplasm.
Side bar flange plate is processed by changing traditional side bar punching block processing and fabricating mode according to above-mentioned technical proposal Width considers according to Curve Design parameter maximum width, then mixes adjustable movable edge of a wing edges of boards mould, to manufacture one Set can meet straight line, Curve requirement universal sideshields beam forms, precast curve side bar, reach the effect of curved bridge line style beauty Fruit.It has broken the common process limitation of curved bridge cast-in-place construction, extends the application range of Prestressed T (cored slab) beam.And And moulding board of precast beam processing and fabricating is simple, versatile, linear type and shaped form beam piece energy Prefabrication, construction technology letter Single, quality is guaranteed, is widely used in the curved bridge of radius R >=200m.
The preferred embodiment of the present invention is described in detail above in association with attached drawing, still, the present invention is not limited to above-mentioned realities The detail in mode is applied, within the scope of the technical concept of the present invention, a variety of letters can be carried out to technical scheme of the present invention Monotropic type, these simple variants all belong to the scope of protection of the present invention.
It is further to note that specific technical features described in the above specific embodiments, in not lance In the case of shield, can be combined by any suitable means, in order to avoid unnecessary repetition, the present invention to it is various can The combination of energy no longer separately illustrates.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally The thought of invention, it should also be regarded as the disclosure of the present invention.

Claims (9)

1. a kind of curved beam prefabricated construction method of curved bridge, which is characterized in that including:
Step a, mounting rail rib and diaphragm plate reinforcing bar;
Step b, bellows is installed;
Step c, installation form;
Step d, slab reinforcement is installed;
Step e, hogging moment bellows is installed;
Step f, concreting;
Step g, maintenance and form removal;
Step h, prestressed stretch-draw and mud jacking;Wherein,
Internal lining pipe is worn in bellows, and tensioning is influenced for mortar leakage prevention.
2. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that step a includes according to figure Paper assembling reinforcement indicates reinforcement location line on pedestal, places reinforcing bar by line, and will be welded and fixed intersection in length and breadth;Wherein,
Ensure that pipeline location is constant and will move reinforcement location at pipeline and reinforcing bar collision.
3. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that step b includes according to figure Coordinate setting bellows on paper is simultaneously fixed with spacer bar.
4. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that step c includes:1, it uses Sizing punching block assembled formwork, wherein plate thickness are more than or equal to 6mm;2, it will be interconnected and fixed between each template using bolt, Wherein embedded fixed type elasticity caulking strip among plate stitch;3, side bar flange plate working width is maximum wide according to Curve Design parameter Degree processing, then mix adjustable movable edge of a wing edges of boards mould;4, template marches into the arena and needs to template processing of rust removing and brush before installation Releasing agent;5, it installs, connect, fixing side form, bed die and end mould.
5. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that installed in step e negative curved Bellows is reserved when square area bellows in form stop to connect for upper bridging.
6. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that the cast of concrete in step f Using the continuous placing mode of oblique segmentation, horizontal slice, the interval time of front and back two layers of concrete must not exceed the presetting period;
Vibrating for beam body concrete is vibrated using form vibrator, the common cooperation of plug-in type vibrating stick;Horseshoe position concrete enters mould When, corresponding position form vibrator is started, is shaken to concrete compaction;When pouring web and upper limb board concrete, vibrate to insert Enter based on formula vibrating head, reinforcing bar is closeer and the intensive place of bellows, cooperation form vibrator vibrate.
7. the curved beam prefabricated construction method of curved bridge according to claim 6, which is characterized in that further include in step f After the completion of beam body concreting, troweling is carried out to back using wooden float, carries out once receiving slurry processing again before initial set, finally With steel brush or broom plucking;
During concreting, the bellows internal lining pipe of Liang Leichu need to be twitched manually, before pouring and finishing concrete initial set, extraction Internal lining pipe.
8. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that in step g maintenance include It is covered using geotextiles after beam piece plucking, watering maintenance prevents surface desciccation crack, is carried out using spray maintenance of equipment after form removal Maintenance, and it is subject to hand fit's maintenance;
Form removal, which is included in after beam body concrete strength reaches strength of mould stripping requirement, carries out form removal, wherein dismounting is segmented when form removal in order, Dabbing is carried out to beam body surface immediately after dismounting.
9. the curved beam prefabricated construction method of curved bridge according to claim 1, which is characterized in that the tensioning in step h Stretch value is recorded in journey, pressure gauge reading carries out cable tensios control using the dual control method of control force and control stretch value;Also, it presses Duct must be rinsed well with clear water before slurry, clogs front exhaust hole pressure and fill slurry after waiting discharge underflow, be remained above and be equal to The voltage stabilizing phase of 0.6Mpa, time voltage stabilizing phase are more than or equal to 2min.
CN201810314286.9A 2018-04-10 2018-04-10 The curved beam prefabricated construction method of curved bridge Pending CN108544655A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810314286.9A CN108544655A (en) 2018-04-10 2018-04-10 The curved beam prefabricated construction method of curved bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810314286.9A CN108544655A (en) 2018-04-10 2018-04-10 The curved beam prefabricated construction method of curved bridge

Publications (1)

Publication Number Publication Date
CN108544655A true CN108544655A (en) 2018-09-18

Family

ID=63514546

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810314286.9A Pending CN108544655A (en) 2018-04-10 2018-04-10 The curved beam prefabricated construction method of curved bridge

Country Status (1)

Country Link
CN (1) CN108544655A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820513A (en) * 2019-11-22 2020-02-21 中国电建集团贵阳勘测设计研究院有限公司 Alignment construction method for diaphragm plate of prefabricated concrete T beam of curved bridge
CN111576232A (en) * 2020-05-29 2020-08-25 四川路航建设工程有限责任公司 Linear control construction method for precast beam top plate
CN112342934A (en) * 2020-12-18 2021-02-09 中交三公局第三工程有限公司 Construction method of high-stability curve bridge plate

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040094076A (en) * 2003-05-01 2004-11-09 이형훈 Bridge construction method using precast prestressed concrete beam manufacturing method for straight and curved bridge
CN202187296U (en) * 2011-07-25 2012-04-11 中建七局第三建筑有限公司 Adjustable T beam curb girder template
CN103469734A (en) * 2013-09-25 2013-12-25 中铁十六局集团第三工程有限公司 Negative-bending-moment corrugated pipe duct grouting construction method
CN105345926A (en) * 2015-09-25 2016-02-24 安徽水利开发股份有限公司 Prefabricated construction method for prestressed concrete box girder
CN107090777A (en) * 2017-06-02 2017-08-25 国家电网公司 A kind of T beam manufacture methods for reducing blibbing

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040094076A (en) * 2003-05-01 2004-11-09 이형훈 Bridge construction method using precast prestressed concrete beam manufacturing method for straight and curved bridge
CN202187296U (en) * 2011-07-25 2012-04-11 中建七局第三建筑有限公司 Adjustable T beam curb girder template
CN103469734A (en) * 2013-09-25 2013-12-25 中铁十六局集团第三工程有限公司 Negative-bending-moment corrugated pipe duct grouting construction method
CN105345926A (en) * 2015-09-25 2016-02-24 安徽水利开发股份有限公司 Prefabricated construction method for prestressed concrete box girder
CN107090777A (en) * 2017-06-02 2017-08-25 国家电网公司 A kind of T beam manufacture methods for reducing blibbing

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820513A (en) * 2019-11-22 2020-02-21 中国电建集团贵阳勘测设计研究院有限公司 Alignment construction method for diaphragm plate of prefabricated concrete T beam of curved bridge
CN111576232A (en) * 2020-05-29 2020-08-25 四川路航建设工程有限责任公司 Linear control construction method for precast beam top plate
CN112342934A (en) * 2020-12-18 2021-02-09 中交三公局第三工程有限公司 Construction method of high-stability curve bridge plate
CN112342934B (en) * 2020-12-18 2022-04-19 中交三公局第三工程有限公司 Construction method of high-stability curve bridge plate

Similar Documents

Publication Publication Date Title
CN106284080B (en) Continuous rigid frame aqueduct closes up section constructing method
CN105649197B (en) Rear pouring tape construction method of Afforestation Landscape under the conditions of in advance
CN107268878A (en) The fabrication and installation method of prefabricated sandwich wallboard
CN108544655A (en) The curved beam prefabricated construction method of curved bridge
CN106150523B (en) A kind of Railway Tunnel ditch cable trench integral mold plate construction
CN103899088A (en) Construction method for large-span ultra-thin ultra-long cast-in-situ bare concrete plank
CN107090777A (en) A kind of T beam manufacture methods for reducing blibbing
CN105666687A (en) Construction process for pre-stress reactive powder concrete box girder
CN108532466A (en) A kind of bridge pier over-form construction technique
CN105128131A (en) Method for manufacturing prestressed hollow slab beam through polystyrene foam
CN107476567A (en) It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN110468638A (en) A kind of road bed board concreting and plastering technique
CN108638322B (en) Prefabricated post concreting method in a kind of assembled architecture
CN110306791A (en) Superelevation clear-water concrete independence cylinder construction method
CN106284789A (en) For controlling the construction technology of cast-in-situ floor Forming Quality
JPS6156393B2 (en)
CN106968398A (en) A kind of process that support column is poured below balcony
CN111516096A (en) Precast column concrete pouring method in fabricated building
CN206941968U (en) Reinforcing bar limiting card with the upper oblique bayonet socket being parallel to each other
CN109304796A (en) A kind of construction technology of concrete steel formwork
CN115538316A (en) Pier column construction method
CN106192699B (en) A kind of same phase out-phase road surface cutting method and device
CN109487691A (en) Bridge rectangle variable cross-section hollow pier construction method
CN106638672B (en) A kind of construction method effectively reducing piping lane haunch area concrete formation bubble
CN104234315B (en) Three-back-shaped external wall rod structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180918